Back to District of Columbia

CA26-0005 • 2025

Proposed Contract with Capitol Paving of DC, Inc., to Contract No. DCKA-2024-C-0073

Proposed Contract with Capitol Paving of DC, Inc., to Contract No. DCKA-2024-C-0073

Active

The official status still shows this bill as active or still awaiting another formal step.

Sponsor
at the request of the Mayor
Last action
2025-01-02
Official status
Deemed Approved
Effective date
Not listed

Plain English Breakdown

The official source material does not specify how residents will be informed about construction details or include information on potential environmental impacts of the project.

Proposed Contract with Capitol Paving

The bill proposes a contract between the District of Columbia and Capitol Paving of DC, Inc., to construct parts of the DC Power Line Undergrounding Program.

What This Bill Does

  • Creates a contract for Capitol Paving of DC, Inc. to build feeders 14702 and 118 as part of the DC Power Line Undergrounding Program.
  • Sets the total cost of the project at no more than $11,096,337.50.
  • Specifies that Capitol Paving will provide all labor, materials, and equipment needed for the construction over a period of 570 days from when work starts.

Who It Names or Affects

  • The District of Columbia government
  • Capitol Paving of DC, Inc.

Terms To Know

Certified Business Enterprise (CBE)
A business that meets certain criteria to help support local economic development.
Not-to-Exceed Amount
The maximum amount the contract can cost, set by the government before work starts.

Limits and Unknowns

  • Does not specify how residents will be informed about construction details.
  • Does not include information on potential environmental impacts of the project.
  • Does not provide a timeline for when the Council will vote on this contract.

Bill History

  1. 2025-01-02 Council of the District of Columbia LIMS

    CA26-0005 Introduced by Chairman Mendelson at Office of the Secretary

  2. 2025-01-02 Council of the District of Columbia LIMS

    Retained by the Council with comments from the Committee on Transportation and the Environment

Official Summary Text

Proposed Contract with Capitol Paving of DC, Inc., to Contract No. DCKA-2024-C-0073

Current Bill Text

Read the full stored bill text
MURIELBOWSERMAYOR
January2,2025
The Honorable PhilMendelson
Chairman,Councilof theDistrictof Columbia
1350PennsylvaniaAvenueNW, Suite504
Washington,DC 20004
Dear Chairman Mendelson:
Pursuantto section451 of the Districtof Columbia Home Rule Act (D.C. OfficialCode § 1-
204.51)and section202ofthe ProcurementPracticesReform Act of 2010 (D.C.OfficialCode §
2-352.02),enclosedforconsiderationand approvalby theCouncilof theDistrictof Columbia is
proposedContractNo. DCKA-2024-C-0073 withCapitolPavingof DC, Inc.,inthenot-to-exceed
amountof$11,096,337.50.The contract'speriodofperformance is570 consecutivecalendardays
from thedateof theNoticetoProceed.
Undertheproposedcontract,CapitolPavingofDC,Inc.,shallprovidealllabor,materials,and
equipmentforthecivilconstructionoffeeders14702and118fortheDC PowerLine
UndergroundingProgram.
My administrationisavailabletodiscussanyquestionsyoumayhaveregardingtheproposedcontract.Inordertofacilitatearesponsetoanyquestionsyoumayhave,pleasehaveyourstaffcontactMareScott,ChiefOperatingOfficer,OfficeofContractingandProcurement,at(202)724-
8759.
Ilook forwardto theCouncil'sfavorableconsiderationof thiscontract.
Singerely,
1

GOVERNMENT OF THE DISTRICT OF COLUMBIA
Office of Contracting and Procurement

Pursuant to section 202(c) of the Procurement Practices Reform Act of 2010, as amended, D.C.
Official Code § 2-352.02(c), the following contract summary is provided:

COUNCIL CONTRACT SUMMARY
(Standard)

(A) Contract Number: DCKA-2024-C-0073

Proposed Contractor: Capitol Paving of DC, Inc.

Proposed Contractor’s Principals: President: Francisco R. Neto
Secretary: Luis M. Neto
Treasurer: Randolph B. Panizo

Contract Amount (Base Period): Not-to-Exceed (NTE) $11,096,337.50

Unit and Method of Compensation: Fixed Unit Prices

Term of Contract: 570 consecutive calendar days from date of the Notice to
Proceed

Type of Contract: Fixed Unit Price

Source Selection Method: Competitive Sealed Bidding/Invitation for Bid (IFB)

(B) For a contract containing option periods, the contract amount for the base period and for
each option period. If the contract amount for one or more of the option periods differs from
the amount for the base period, provide an explanation of the reason for the difference:

Not Applicable

(C) The goods or services to be provided, the methods of delivering goods or services, and any
significant program changes reflected in the proposed contract:

The contractor shall provide all labor, material and equipment to construct feeders 14702 and 118
for the DC Power Line Undergrounding (DC PLUG) Program as shown on the plans and as directed
by the engineer.

2

(D) The selection process, including the number of offerors, the evaluation criteria, and the
evaluation results, including price, technical or quality, and past performance components:

The IFB was advertised on July 5, 2024, and two bids were received by the due date. After bid
tabulation, the applicable Certified Business Enterprise (CBE) preference point reductions were
applied resulting in the total evaluated price. Capitol Paving of DC, Inc. (Capitol Paving) was
determined to be the lowest responsive and responsible bidder.

(E) A description of any bid protest related to the award of the contract, including whether the
protest was resolved through litigation, withdrawal of the protest by the protestor, or
voluntary corrective action by the District. Include the identity of the protestor, the grounds
alleged in the protest, and any deficiencies identified by the District as a result of the protest:

None

(F) A description of any other contracts the proposed contractor is currently seeking or holds
with the District:

DCKA-2022-C-0036 DC Plug 15009 Construction
DCKA-2022-C-0068 DC Plug 14008 Construction
DCKA-2023-C-0042 DC Plug 15001 Construction
DCKA-2023-C-0019 DC Plug 15166 Construction

(G) The background and qualifications of the proposed contractor, including its organization,
financial stability, personnel, and performance on past or current government or private
sector contracts with requirements similar to those of the proposed contract:

Capitol Paving is a leading utility and infrastructure firm that has been in business for nearly 36
years. Capitol Paving offers a range of construction services including bridges, dry and wet
utilities, and green infrastructure. In addition, Capitol Paving also has a record of satisfactory
performance on previous District Department of Transportation (DDOT) projects and has
completed a number of other projects for the District of Columbia and neighboring states.

(H) A summary of the subcontracting plan required under section 2346 of the Small, Local, and
Disadvantaged Business Enterprise Development and Assistance Act of 2005, as amended,
D.C. Official Code § 2-218.01 et seq. (“Act”), including a certification that the subcontracting
plan meets the minimum requirements of the Act and the dollar volume of the portion of the
contract to be subcontracted, expressed both in total dollars and as a percentage of the total
contract amount:

The proposed contractor is a CBE and will self-perform 92.5% of the contract’s total dollar volume
of the contract. The total value of this contract is $11,096,337.50 and the total that will be
subcontracted out to another CBE will be $832,580.00, totaling 7.5%.

(I) Performance standards and the expected outcome of the proposed contract:
3

At the direction of the DDOT contract administrator, the awardee will perform the required
construction services related to DC PLUG feeders 14702 and 118 in accordance with the
terms of the contract.

(J) The amount and date of any expenditure of funds by the District pursuant to the contract
prior to its submission to the Council for approval:

None

(K) A certification that the proposed contract is within the appropriated budget authority for the
agency for the fiscal year and is consistent with the financial plan and budget adopted in
accordance with D.C. Official Code §§ 47-392.01 and 47-392.02:

On October 31, 2024, the Agency Fiscal Officer certified that $11,096,337.50 in available in local
capital funds for the Contract and the amount of funding is consistent with the financial plan.

(L) A certification that the contract is legally sufficient, including whether the proposed
contractor has any pending legal claims against the District:

The Office of the Attorney General has reviewed and approved the proposed contract for legal
sufficiency. The proposed contractor has no pending legal claims against the District.

(M) A certification that Citywide Clean Hands database indicates that the proposed contractor is
current with its District taxes. If the Citywide Clean Hands Database indicates that the
proposed contractor is not current with its District taxes, either: (1) a certification that the
contractor has worked out and is current with a payment schedule approved by the District;
or (2) a certification that the contractor will be current with its District taxes after the District
recovers any outstanding debt as provided under D.C. Official Code § 2-353.01(b):

The contractor is current with its District taxes per the Clean Hands certification dated October 30,
2024.

(N) A certification from the proposed contractor that it is current with its federal taxes, or has
worked out and is current with a payment schedule approved by the federal government:

The proposed contractor is current with its federal taxes per the System for Award Management
validation performed October 30, 2024.

(O) A certification that the proposed contractor has been determined not to violate section 334a of
the Board of Ethics and Government Accountability Establishment and Comprehensive
Ethics Reform Amendment Act of 2011, D.C. Official Code § 1-1163.34a; and (2) A
certification from the proposed contractor that it currently is not and will not be in violation
of section 334a of the Board of Ethics and Government Accountability Establishment and
Comprehensive Ethics Reform Amendment Act of 2011, D.C. Official Code § 1-1163.34a:

4

The proposed contractor signed the Contractor Self Certification on November 18, 2024. That he
currently is not and will not be in violation of section 334a of the Board of Ethics and Government
Accountability Establishment and Comprehensive Ethics Reform Amendment Act of 2011, D.C.
Official Code § 1-1163.34a.

(P) The status of the proposed contractor as a certified local, small, or disadvantaged business
enterprise as defined in the Small, Local, and Disadvantaged Business Enterprise
Development and Assistance Act of 2005, as amended; D.C. Official Code § 2-218.01 et seq.:

Capitol Paving is a CBE.

(Q) Other aspects of the proposed contract that the Chief Procurement Officer considers
significant:

None

(R) A statement indicating whether the proposed contractor is currently debarred from providing
services or goods to the District or federal government, the dates of the debarment, and the
reasons for debarment:

The proposed contractor is not debarred or an excluded party on the District or Federal
listings per the validations dated October 30, 2024.

(S) Any determination and findings issues relating to the contract’s formation, including any
determination and findings made under D.C. Official Code § 2-352.05 (privatization
contracts):

Determination and Findings for Price Reasonableness
Determination and Findings for Contractor Responsibility

(T) Where the contract, and any amendments or modifications, if executed, will be made
available online:

OCP.DC.GOV

(U) Where the original solicitation, and any amendments or modifications, will be made available
online:

OCP.DC.GOV

*
*
* GovernmentoftheDistrictofColumbia

Emm OfficeoftheChiefFinancialOfficer 110144Street,SWGm OfficeofTaxandRevenue ‘Washington,DC20024
DateofNotice:October30,2024 NoticeNumber:10012781022 =
CAPITOLPAVINGOFDCINC2211CHANNINGSTNE
WASHINGTONDC 20018-2127 LEA!

[AND
AsreportedintheCleanHandssystem,theabovereferencedindividual/entityhasnooutstandingliabilitywiththeDistrictofColumbiaOfficeofTaxandRevenueortheDepartmentofEmploymentServices.Asofthedateabove,theindividual/entityhascompliedwithDC Code§47-2862,therefore
thisCertificateofCleanHandsisissued.
TITLE 47. TAXATION, LICENSING, PERMITS, ASSESSMENTS, AND FEES
CHAPTER28GENERALLICENSESUBCHAPTERII.CLEANHANDSBEFORERECEIVINGA LICENSEOR PERMIT
D.C.CODE§47-2862(2006)§ 47-2862 PROHIBITION AGAINST ISSUANCE OF LICENSE OR PERMIT

AuthorizedBy Melinda Jenkins
Branch Chief,Collectionand Enforcement Administration
Tovalidatethiscertificate,pleasevisitMyTax.DC.gov.OntheMyTaxDChomepage,clickthe“Validate a Certificateof Clean Hands” hyperlink under the Clean Hands section.

111014thStreetSW,SuiteW270,Washington,DC20024/Phone:(202)724-S045/MyTax.DC.g0v
250 M Street, S.E., Washington, DC 20003 Telephone: (202) 671-2300
GOVERNMENT OF THE DISTRICT OF COLUMBIA
OFFICE OF THE CHIEF FINANCIAL OFFICER

Government Services Cluster

FINANCIAL PLAN AND BUDGET CERTIFICATION

Contract No.: DCKA-2024-C-0073
Contract Name: District of Columbia Power Undergrounding (DC PLUG)
Feeder 14702 and 118

Contractor: Capitol Paving of DC INC
Contract Ceiling Amount: $11,096,337.50

Current Available Amount: $11,096,337.50

Contract Period of Service: 10/31/2024 to 5/24/2026

Organization Code: KA0
Requisition Number: RK292671

DIFS Project #: 100592 (LMG09C) and 100595 (LMG13C)

==============================================================================

I, Calvin Skinner, Agency Fiscal Officer, OCFO, hereby certify that the amount of $11,096,337.50
is available for the above referenced contract and that the service is within the appropriate
budget authority for the agency for FY 20 25 and is consistent with the applicable approved
financial plan and budget. Future orders above the available funding are contingent upon the
identification of additional funding.

____________________________________ _________________
Calvin Skinner Date
Agency Fiscal Officer, OCFO

10/31/24
400 6th Street NW, Suite 9100, Washington, DC 20001 (202) 727-3400

GOVERNMENT OF THE DISTRICT OF COLUMBIA
Office of the Attorney General

ATTORNEY GENERAL
BRIAN L. SCHWALB

Commercial Division
Government Contract Section

MEMORANDUM

TO: Tomás Talamante
Director, Mayor’s Office of Policy and Legislative Affairs

FROM: Robert Schildkraut
Section Chief

DATE: December 12, 2024

SUBJECT: Legal Sufficiency Review of DDOT Construction Contract for Feeder
14701/118 of the DC PLUG Program
Contract No. DCKA-2024-C-0073
Contractor: Capitol Paving of D.C., Inc.
Proposed Contract Not-to-Exceed (NTE) Amount: $11,096,337.50

This is to Certify that this Office has reviewed the above-referenced Contract and that we have
found it to be legally sufficient subject to the following condition:
1. Receipt by the District, prior to contract award, of a Certificate(s) of Insurance that meets
all of the insurance requirements in the Contract.

If you have any questions in this regard, please do not hesitate to call me at (202) 724-4018.

______________________________
Robert Schildkraut
P.P.
Page 1 of 60DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
A. SOLICITATION, OFFER, AND AWARD
1. Caption
District of Columbia Power Line Undergrounding (DC
Plug) 14702/118
Page of Pages
1 of 62
2. Contract Number
DCKA-2024-C-0073
3. Solicitation Number
DCKA-2024-B-0073
4. Type of Solicitation
5. Date
Issued
7/5/2024
6. Type of Market
X Sealed Bid (IFB) x Open
Sealed Proposals (RFP) Set Aside
Sole Source Open with Sub-
Contracting Set
AsideHuman Care Agreements
Emergency
7. Issued By:
District Department of Transportation Office of
Contracting and Procurement 55 M Street, SE
Suite 700
Washington, DC 20003
8. AddressOffer to:
Department of Transportation
Office of Contracting and Procurement 250 M
Street, SE Suite 700
Washington, DC 20003
NOTE: In sealed bid solicitations "offer" and offeror" means "bid" and "bidder"
SOLICITATION
9. Sealed offers in original and 1 copy for furnishing the supplies or services in the Schedule will be received at address in 8 above until
local time on for electronic submission refer to Section L of the Solicitation.
CAUTION: Late Submissions, Modifications and Withdrawals: See 27 DCMR chapters 15 & 16 as applicable. All offers are subject to all terms &
conditions contained in this solicitation.
10. ForInformation Contact:
A. Name
District of Columbia Power Line
Undergrounding (DC Plug) Feeder
B. Telephone C. E-mail Address
(Area Code) (Number) (Ext)
Rickie.spivey@dc.gov
11. Table of Contents
(X) Section Description Page No. (X) Section Description Page
No.
PART I - THE SCHEDULE PART II - CONTRACT CLAUSES
X A Solicitation/ContractForm 1 X H Contract Clauses 26
X B Contract Type, Supplies or Services
and Price/Cost 2 PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER
ATTACHMENTS
X C Specifications/WorkStatement 10 X J List of Attachments 51
x D Packaging and Marking 15 PART IV - REPRESENTATIONS AND INSTRUCTIONS
X E Inspection and Acceptance 16 Representations, Certifications, and Other
Statements of OfferorsX F Period of Performance and
Deliverables 19
X G Special Contract Requirements 20 Instructions, Conditions, and Notices to
Offerors
Evaluation Factors
OFFER
12. In compliance with the above, the undersigned agrees, if this offer is accepted within330 calendar days from the date for receipt of offers specified above, to furnish
any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified herein.
13Not Applicable
14. Acknowledgement of Amendments (The
offeror acknowledges receipt of amendments
to the SOLICITATION) [In case there is more
than three amendments attach separate sheet
with acknowledgements):
Amendment Number Date Amendment
Number Date
Amendment 1 7/17/2024 Amendment 4 8/14/2024
Amendment 2 7/30/2024 Amendment 5 8/15/2024
Amendment 3 8/2/2024
15A. Name and Address of Offeror
Capitol Paving of DC Inc,
2211 Channing Street NW
Washing DC 20018
16. Name and Title of Person Authorized to Sign Offer
Randolph B. Panizo - Vice President
15B. Telephone 15 C. Check if remittance
address is different from above -
Refer to Section G
17. Signature 18. Offer Date
(Area Code)
202
(Number)
529-7225
(Ext)
AWARD(TOBE COMPLETEDBY GOVERNMENT)
19. Accepted as to Items Numbered 20. Amount
$11,096,337.50
21. Accounting and Appropriation
22. Name of Contracting Officer (Type or Print) 23. Signature of Contracting Officer (District of
Columbia)
24. Award Date
Government of the District of Columbia Office of Contracting & Procurement
12/10/2024
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 2 of 60
SECTION B: CONTRACT TYPE AND PRICE/COST
B.1 SUMMARY
The District of Columbia Office of Contracting and Procurement (“OCP”), on behalf of the District
Department of Transportation (“DDOT” or “Department”), is seeking a contractor to provide
Construction of for the District of Columbia Power Line Underground (DC PLUG) Feeder
14702/118 (the “Project”) in accordance with the Contract Documents, as defined herein.
B.2 TYPE OF CONTRACT
In accordance with 27 DCMR 2402.2 the contract (“the Contract”) awarded under this Invitation
for Bids (“IFB” or “Solicitation”) shall be a fixed unit price contract with a not to exceed amount
(ceiling) equal to the Contract award amount.

B.4 NOTICE OF SUBCONTRACTING REQUIREMENTS
For contracts in excess of $250,000, at least 35% of the dollar volume of the Contract shall be
subcontracted in accordance with section H.9.1. Bids responding to this IFB shall be deemed
nonresponsive and shall be rejected if the bidder fails to submit a subcontracting plan that is
required by law.
A CBE/SBE offeror that intends to self -perform 100% of the work must submit a subcontracting
plan form with its bid or proposal in which the offeror attests to its intent to self -perform all
work. A bid or proposal that does not include a subcontracting plan form shall be deemed
nonresponsive and rejected.
The Subcontracting Plan form is available at:
https://dslbd.dc.gov/sites/default/files/dc/sites/dslbd/SBE_Subcontracting_Plan_Revised_11_2
1_14.doc.
B.5 PRICE SCHEDULE
Note to bidders: The price schedule is attached at Section J.7. The price schedule of the selected
awardee will be included here in the executed contract.
Page 3 of 77
District Department of Transportation

District Department of Transportation
PROPOSAL FOR

Letting ID: 20240073
08/05/2024 02:00:00 PM

Contract ID: KA20240073
Call: 005

BID TYPE:
(Enter a Bid Type, otherwise bid will be considered Regular)
Submitted by
Capitol Paving of D.C., Inc.
2211 Channing Street NE
Washington D.C., DC 20018
Page 4 of 77
District Department of Transportation

Line Number Item Number Quantity Unit Unit Price Extension Price

Section 0001
DC PLUG 14702/118
3.000 EACH $56,553.00000 $169,659.00
Unassigned Special Item -EACH - Construct Cast in Place MH for Primary Splice
Boxes (4.5'x6' all depth)

8.000 EACH $56,553.00000 $452,424.00
Unassigned Special Item -EACH - Construct Cast in Place MH for Secondary Splice
Boxes (4.5'x6' all depth)

3.000 EACH $84,147.00000 $252,441.00
Unassigned Special Item -EACH - Construct Cast In Place MH Over Existing Duct
(4.5x6' all depth)

0020 000506 4.000 EACH $750.00000 $3,000.00
Unassigned Special Item -EACH - Install 2 Way Concrete Encased Fiberglass Pole
Bends

0025 000506 71.000 EACH $750.00000 $53,250.00
Unassigned Special Item -EACH - Install 2 Way Concrete Encased PVC Pole Bends

0030 000506 66.000 EACH $9,000.00000 $594,000.00
Unassigned Special Item -EACH - Install Precast Roadway MH (4.5x6' all depths)

0035 000506 8.000 EACH $23,000.00000 $184,000.00
Unassigned Special Item -EACH - Install Precast Roadway MH (6x12' all depths)

0040 000506 2.000 EACH $25,000.00000 $50,000.00
Unassigned Special Item -EACH - Install Precast Sidewalk MH (6'x12' all depths)

0045 000506 3.000 EACH $37,000.00000 $111,000.00
Unassigned Special Item -EACH - Install Precast Sidwalk UG Switch MH (6x18 all
depths)

0050 000506 44.000 EACH $2,700.00000 $118,800.00
Unassigned Special Item -EACH - Install Precast Taphole (3.5L x 3.5'C x 4' H)

0055 000506 63.000 EACH $3,000.00000 $189,000.00
Unassigned Special Item -EACH - Install Precast Transformer Enclosure
( 48"x72")

0060 000506 9.000 EACH $24,505.00000 $220,545.00
Unassigned Special Item -EACH - Install Precast Transformer MH Sidewalk Type
(6'x 14' all depths)

0065 000509 424.000 LF $195.00000 $82,680.00
Unassigned Special Item -LF - Install 10 Way Conduit - 4" PVC (all depths)

0070 000509 50.000 LF $725.00000 $36,250.00
Unassigned Special Item -LF - Install 10 Way Conduit - 5" FB & 4 Way Conduit -
4" PVC (all depth)

0075 000509 83.000 LF $220.00000 $18,260.00
Unassigned Special Item -LF - Install 10 Way Conduit - 5"FB (all depths)

0080 000509 296.000 LF $228.00000 $67,488.00
Unassigned Special Item -LF - Install 12 Way Conduit - 4" PVC (all depths)
0085 000509 28.000 LF $450.00000 $12,600.00
Unassigned Special Item -LF - Install 16 Way Conduit - 5" Fiberglass (all
depths)
0090 000509 5124.000 LF $117.00000 $599,508.00
Unassigned Special Item -LF - Install 2 Way Conduit - 4" PVC (all depths)
0095 000509 97.000 LF $130.00000 $12,610.00
Unassigned Special Item -LF - Install 2 Way Conduit - 5" Fiberglass (all
depths)
0100 000509 11950.000 LF $127.00000 $1,517,650.00
0005 000506
0010 000506
0015 000506

Page 5 of 77

Unassigned
District Department of Transportation

Special Item -LF - Install 4 Way

Conduit - 4" PVC (all depths)
0105 000509 317.000 LF $132.00000 $41,844.00
Unassigned
depths)
Special Item -LF - Install 4 Way Conduit - 5" Fiberglass (all
0110 000509 1863.000 LF $135.00000 $251,505.00
Unassigned Special Item -LF - Install 6 Way Conduit - 4" PVC (all depths)
0115 000509 174.000 LF $140.00000 $24,360.00
Unassigned
depths)
Special Item -LF - Install 6 Way Conduit - 5" Fiberglass (all
0120 000509 2710.000 LF $150.00000 $406,500.00
Unassigned Special Item -LF - Install 8 Way Conduit - 4" PVC (all depths)
0125 000509 212.000 LF $190.00000 $40,280.00
Unassigned Special Item -LF
4" PVC (all depths)
- Install 8 Way Conduit - 5" FB & 2 Way Conduit -
0130 000509 392.000 LF $250.00000 $98,000.00
Unassigned Special Item -LF
4" PVC (all depths)
- Install 8 Way Conduit - 5" FB & 4 Way Conduit -
0135 000509 145.000 LF $350.00000 $50,750.00
Unassigned Special Item -LF
4" PVC (all depths)
- Install 8 Way Conduit - 5" FB & 6 Way Conduit -
0140 000509 211.000 LF $400.00000 $84,400.00
Unassigned Special Item -LF
4" PVC (all depths)
- Install 8 Way Conduit - 5" FB & 8 Way Conduit -
0145 000509 1385.000 LF $155.00000 $214,675.00
Unassigned Special Item -LF - Install 8 Way Conduit - 5" Fiberglass (all
depths)
0150 000516 360.000 TON $200.00000 $72,000.00
Unassigned Special Item -TON - Speed Hump
0155 108002 1.000 LS $443,000.00000 $443,000.00
Mobilization
0160 108004 1.000 LS $15,000.00000 $15,000.00
Progress Photographs
0165 108006 1.000 LS $15,000.00000 $15,000.00
Record Drawings and As-Built Drawings
0170 108012 1.000 LS $164,000.00000 $164,000.00
Engineer's Field Facilities
0175 108016 1.000 LS $60,000.00000 $60,000.00
Field Layout
0180 200005 400.000 CY $100.00000 $40,000.00
Earthwork and Excavation Special
Construction
Item - CY - Rock Excavation for PEPCO Facility
0185 201002 1.000 LS $22,500.00000 $22,500.00
Clear and Grub
0190 202002 300.000 CY $70.00000 $21,000.00
Common Excavation
0195 202004 1507.000 CY $70.00000 $105,490.00
Hard Surface Pavement Excavation

0200 207008 1750.000 CY $40.00000 $70,000.00
Borrow Trench Backfill

0205 209002 1505.000 CY $95.00000 $142,975.00
Aggregate Base Course

Page 6 of 60
District Department of Transportation

0210 212991 100.000 EACH
Test Pit Special Item - EACH -
$450.00000 $45,000.00
0215 402002 500.000 TON
HMA Base Course, 19 mm
$220.00000 $110,000.00
0220 402010 4003.000 TON
HMA Surface Course, 12.5 mm
$140.00000 $560,420.00
0225 403002 27330.000 SY
Tack Coat
$1.50000 $40,995.00
0230 405016 361.000 TON
Temporary AC, HMA Surface Course,

12.5

mm
$100.00000 $36,100.00
0235 410002 27330.000 SY $8.00000 $218,640.00
Pavement Profiling (Milling)
0240 501030
High Early

Strength
1700.000
Portland
BAGS
Cement
$10.00000 $17,000.00
0245 501034
Additional

Standard
600.000
Portland
BAGS
Cement
$10.00000 $6,000.00
0250 502004 3200.000 CY $570.00000 $1,824,000.00
PCC Base for Utility Cuts
0255 503006 30.000 SY $190.00000 $5,700.00
Reinforced PCC Alley, 8 Inch
0260 504006 20.000
PCC Driveway-Alley Entrance,
CY
7 Inch
$700.00000 $14,000.00
0265 505002 495.000 SY $145.00000 $71,775.00
Replace PCC Pavement, 8 Inch
0270 505032 30.000 CY $625.00000 $18,750.00
Repair PCC Pavement
0275 507010 3.000 CY $2,300.00000 $6,900.00
Standard PCC Coping
0280 507012 3.000 CY $2,900.00000 $8,700.00
Special PCC Coping
0285 600011 2.000 EACH $2,500.00000 $5,000.00
Incidental Construction Special Item - EACH - Furnish and Install Bike Rack and
Buffer

0290 600021 1.000 LS $9,000.00000 $9,000.00
Incidental Construction Special Item - LS - Replace wooden retaining wall with
equivalent or better material

0295 605006 1933.000 SY $85.00000 $164,305.00
PCC Sidewalk, 4 Inch
0300 605050 2.000
Remove Bike Rack
EACH $937.00000 $1,874.00
0305 606002 3428.000
PCC Curb
LF $42.00000 $143,976.00
0310 606004 4112.000
PCC Curb and/or Gutter
LF $50.00000 $205,600.00
0315 606102 12.000
PCC Wheelchair/Bicycle Ramp
EACH $2,981.00000 $35,772.00
0320 607004 1690.000
Seed with 4 Inch Topsoil
SY $27.00000 $45,630.00
0325 608072 398.000 EACH $175.00000 $69,650.00
Page 7 of 60
District Department of Transportation

Tree Protection and Replacement Tree Protection and Replacement
0330 612008 16134.000 SF
Remove Lane Markings
$3.00000 $48,402.00
0335 612054
Thermoplastic
1231.000 LF
Pavement Marking, 4

Inch
$3.50000 $4,308.50
0340 612056
Thermoplastic
327.000 LF
Pavement Marking, 4

Inch

Dash
$4.00000 $1,308.00
0345 612058
Thermoplastic
4170.000 LF
Pavement Marking, 6

Inch
$6.00000 $25,020.00
0350 612064
Thermoplastic
1784.000 LF
Pavement Marking, 12

Inch
$8.50000 $15,164.00
0355 612066
Thermoplastic
7062.000 LF
Pavement Marking, 24

Inch
$13.50000 $95,337.00
0360 612068
Thermoplastic
13.000 EACH
Pavement Letter
$335.00000 $4,355.00
0365 612070
Thermoplastic
2.000 EACH
Pavement Arrow
$820.00000 $1,640.00
0370 612076
Thermoplastic
2.000 EACH
Pavement Bicycle Marking,

8

Foot
$670.00000 $1,340.00
0375 612078 45.000 EACH
Flexible Delineators for Bicycle Lane
$180.00000 $8,100.00
0380 612092 6.000 EACH
Truck Mounted Attenuator
$1,000.00000 $6,000.00
0385 612100 6.000 EACH
Portable Changeable Message Sign
$1,000.00000 $6,000.00
0390 612110 7512.000 LF
Preformed Pavement Markings, Lines

Temporary
$5.00000
traffic control
$37,560.00
0395 612997
Traffic Control
4452.000 LF
Special Item - LF

-

612

995
$4.00000
Construction Fence
$17,808.00
0400 614056 24.000 EACH $768.50000 $18,444.00
Root Pruning
0405 616014 240.000 LF
Metal Sign Posts, 2.00 Pounds per

Foot
$21.50000 $5,160.00
0410 616022 80.000 SF
Traffic Sign Panels
$52.00000 $4,160.00
0415 616036 80.000 SF $37.50000 $3,000.00
Remove Existing Ground Mounted Sign

Section 0001 Total $11,096,337.50

Item Total $11,096,337.50

DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 8 of 60
B.6 SCOPE OF PAYMENT
In accordance with Standard Specifications Section 109.02:
A. The Contractor shall receive and accept compensation in accordance with the Price Schedule
as full payment for furnishing all materials and for performing all of the Work in a complete
and satisfactory manner including all labor, Plant, as defined herein, and incidentals needed,
and for all risk, loss, damage or expense of whatever nature arising from the Work and its
prosecution, subject to the terms of the Contract.
B. If work under one Contract Line Item (“CLIN”) includes compensation for any work or
material accessory to that CLIN, the amount of such work or material will not be measured,
nor will payment be made under, any other CLIN.
C. Where two or more Contract Line -Item areas overlap either by discrepancy in definition or
by the intricate nature of the work, payment will be made at the lowest Contract unit price
of overlapping Contract Line Items involved.
D. The phrases “Work includes” and “as part of the Work” are sometimes used to clarify that
referenced requirements shall be included as part of the Contract Line Item involved; no
separate or additional payment will be made.
E. The phrase “at Contractor expense” means the Contractor shall meet requirements as its
sole expense with neither liability nor expense to the District.
B.7. NONPROFIT FAIR COMPENSATION ACT OF 2020, D.C. Code § 2-222.01 et seq.
B.7.1 Nonprofit organizations, as defined in the Act, shall include in their rates the indirect
costs incurred in provision of goods or performance of services under this contract
pursuant to the nonprofit organization's unexpired Negotiated Indirect Cost Rate
Agreement (NICRA). If a nonprofit organization does not have an unexpired NICRA, the
nonprofit organization may elect to instead include in its rates its indirect costs:
(1) As calculated using a de minimis rate of 10% of all direct costs under this contract;
(2) By negotiating a new percentage indirect cost rate with the awarding agency;
(3) As calculated with the same percentage indirect cost rate as the nonprofit organization
negotiated with any District agency within the past 2 years; however, a nonprofit
organization may request to renegotiate indirect costs rates in accordance with B.8.2; or
(4) As calculated with a percentage rate and base amount, determined by a certified public
accountant, as defined in the Act, using the nonprofit organization's audited financial
statements from the immediately preceding fiscal year, pursuant to the OMB Uniform
Guidance, and certified in writing by the certified public accountant.
B.7.2 If this contract is funded by a federal agency, indirect costs shall be consistent with the
requirements for pass-through entities in 2 C.F.R. § 200.331, or any successor
regulations.
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 9 of 60
B.7.3 The Contractor shall pay its subcontractors which are nonprofit organizations the same
indirect cost rates as the nonprofit organization subcontractors would have received as
a prime contractor.
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 10 of 60
SECTION C: DESCRIPTION/SPECIFICATIONS/ STATEMENT OF WORK
C.1 STATEMENT OF WORK
The Contractor shall provide all labor, materials, and equipment for the construction of the
Project in accordance with the Contract Documents (“the Work”). Work under this Contract
consists of the civil construction for PEPCO feeder 14702/118 of the DC Power Line
Undergrounding (DC PLUG) Program, located in Ward 7 and bound by 19th St SE, Minnesota Ave
SE, Anacostia Rd SE, 31st St SE, 38th St SE, Texas Ave SE, and S St SE as shown on the contract plans,
indicated in the specifications / Special Provisions (J.8), and as directed by the DDOT Engineer.

The specifications in this document and related Contract Drawings cover the work which
includes, but is not limited to the following:

• The removal and disposal of existing roadway pavement, curb, gutter, and
sidewalks to the extents shown on plans or as necessary for access to trench
excavation.
• The installation of PEPCO supplied materials such as PVC and fiberglass conduits,
precast manholes, precast tapholes, precast transformer enclosures, and other
related items and components.
• The furnishing and installation of pea gravel concrete for ductbank encasement.
• The furnishing and installation of thermal fill for ductbank encasement at
transmission feeder crossings.
• The furnishing and installation of concrete and reinforcing steel for cast-in-place
manhole construction.
• Excavation and backfilling of all utility cuts.
• Temporary restoration of all utility cuts.
• Permanent restoration of all utility cuts.
• Restoration of all pavement markings disturbed by the utility cut and pavement
restoration work. Upgrade crosswalks to the high visibility type at all intersections
within the project limits.
• Pavement profiling (milling) and overlay (approximately 2 inches) of utility cuts
and per plan in accordance with DDOT standards.
• Installation of topsoil, seed, and mulch on all disturbed earth and grass areas.
• Installation of replacement curb (in-kind), curb and gutter (in-kind), and sidewalk
(in-kind) sections.
• The installation and use of erosion and sediment control measures meeting
DDOT/DOEE standards and per plan.
• Dust control during pavement sawcutting and excavation operations.
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 11 of 60
• Mobilization and demobilization, completion of field layout, provision and
maintenance of engineer's field facilities, progress photographs, and rodent
control.
• Maintain vehicular, bicycle and pedestrian traffic per DDOT Standard
Specifications Section 612 and Attachment J.14 or as directed by the Engineer.
Maintain access to residential, institutional and commercial establishments using
appropriate means as approved by the Engineer.
• Maintain service of all existing utilities during construction.
• Work includes the disposal of all unsalvageable materials and all labor, materials,
tools, equipment and incidentals necessary to obtain a complete and finished
product.
• The Contractor shall be fully responsible for protection against damages for the
duration of the Contract of all the utility structures within the Contract limits and
adjacent thereto. The utilities include but are not limited to public and/or private
water, sewer, electricity, gas and communications lines. No separate
measurement or payment will be made. Cost of this protective work shall be
reflected and distributed among the Contract pay items.
• Work also includes all incidentals needed to complete the project as shown on the
Contract Drawings and within the Special Provisions

C.2 APPLICABLE DOCUMENTS INCORPORATED BY REFERENCE
The following documents are applicable to this procurement and are hereby incorporated by this
reference:

Title Link
DDOT Standard Specifications for Highways and
Structures
https://wiki.ddot.dc.gov/pages/relea
seview.action?pageId=204112538#
StandardsandManuals(New)-
StandardsandSpecificationsforHigh
waysandStructures
DDOT Standard Drawings https://wiki.ddot.dc.gov/pages/relea
seview.action?pageId=204112538#
StandardsandManuals(New)-
StandardsandSpecificationsforHigh
waysandStructures
Equal Employment Opportunity Employer
Information Report and Mayor’s Order 85-85
OHR's EEO Packet_7.21.2023.pdf
(dc.gov)
Way to Work Amendment Act of 2024 – Living
Wage Notice
https://ocp.dc.gov/sites/default/files
/dc/sites/ocp/publication/attachment
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 12 of 60
s/2024%20Living%20Wage%20No
tice.pdf
Way to Work Amendment Act of 2024 – Living
Wage Fact Sheet
https://ocp.dc.gov/sites/default/files
/dc/sites/ocp/publication/attachment
s/2024%20Living%20Wage%20Fa
ct%20Sheet%20.pdf
Subcontracting Plan Form District Agency Compliance | dslbd
(dc.gov)
DOES First Source Employment Program https://does.dc.gov/page/first-
source-employment-program-

C.3 DEFINITIONS
The definitions at Section 101.03 of the Standard Specifications apply to this Contract except to
the extent specifically stated herein.
For the convenience of the bidders, the following definitions from Section 101.03 are specified
below. To the extent that the definitions below modify and supplement Section 101.03, such
modified and supplemented definitions supersede the corresponding definitions at Section
101.03.
Contract – The entire, integrated agreement between the District and the Contractor for the
Project. The Contract is made of the Contract Documents, and supersedes prior negotiations,
representations or agreements.
Contract Documents – The Contract documents consist of the Solicitation sections A -K (the
“Contract Form”), addenda issued prior to execution of the Contract, the price schedule,
performance and payment bonds, specifications, contract drawings, and other documents
listed in this contract form, and modifications issued after execution of the Contract.
Final Acceptance – The occurrence of all the events and satisfaction of all the conditions with
respect to the Work for completion of all aspects of the Contract as set forth in Standard
Specifications Section 108.09.
Plant – All physical resources, facilities, machinery, equipment, staging, forms, tools, work
and storage space other than provided by the Contract, together with subsidiary essentials
and necessary maintenance for proper construction and acceptable completion of the
Project.
Project – The title of the Contract, and also the entire Work to be completed under the
Contract.
Work – The furnishing of all labor, materials, equipment, and incidentals necessary or
convenient to the successful completion of the Project and the carrying out of the duties
and obligations imposed by the Contract.
In addition, these terms are defined as follows:
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 13 of 60
C.4 DELIVERABLES
In addition to any deliverables required elsewhere in the Contract Documents, as defined herein,
the Contractor shall submit the following deliverables in accordance with the Contract.
Item Description Schedule Contract Reference
1. Subcontractor Payment Form Monthly G.3
2. Subcontractor Approval Request Form As Needed I.5
3. Schedule Update Monthly G.1.B
4.. Certified Payrolls and Statement of Compliance Weekly H.2

C.5 CONTRACTOR’S RESPONSIBILITY FOR WORK
A. Until Final Acceptance of the Project by the District, the Contractor shall be responsible for
the Project and shall take every precaution against injury, or damage to any part thereof,
whether arising from the execution or from the non-execution of the Project. The Contractor
shall rebuild, repair, restore, and bare the expense of such injury or damage before Final
Acceptance except to the extent that such injury or damage is due to unforeseeable cause
beyond the control, and without the fault or negligence, of the Contractor or subcontractor.
B. In case of suspension of all or any portion of the Work from any cause whatever, the
Contractor shall be responsible for the Project and shall 1 ) take such precautions as may
be necessary to prevent damage to the Project, 2) provide for normal drainage and 3) erect
any necessary temporary structures, signs, or other facilities. In addition, during such period
of suspension, the Contractor shall properly and continuously maintain, in an acceptable
growing condition, all living material in newly established plantings, seeding, and sodding
furnished under the Contract, and shall take necessary precautions to protect new tree
growth and other important vegetative growth against injury.
C.6 BRAND NAME OR EQUAL
A. If items called for by the Solicitation have been identified by a brand name description, such
identification is intended to be descriptive, but not restrictive, and is to indicate the quality
and characteristics of products that will be satisfactory. The District will consider alternate
products to be equal if the Contract Administrator determines them to be equal in all material
respects to the brand name products referenced in the Solicitation.
B. The Contractor must provide all descriptive material (such as cuts, illustrations, drawings, or
other information) necessary for the District to (i) determine whether the product offered
meets the requirements of the Contract. In making the determination as to equality of a
product the District will consider information furnished by the Contractor. The District may,
but is not obligated to, also consider information reasonably available to the District.
C.7 SUPPLEMENTARY SPECIFICATIONS (also referred to as “Special Provisions”)
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 14 of 60
Supplementary Specifications (also referred to as “Special Provisions”) are attached to the
Contract at Section J.8.
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 15 of 60
SECTION D: PACKAGING AND MARKING

Not Applicable.
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 16 of 60
SECTION E: INSPECTION AND ACCEPTANCE
E.1 INSPECTION
The inspection and acceptance requirements for this Contract shall be governed by Standard
Specification Section 103.01, Article 12, “Inspection and Acceptance,” and Section 105.13,
“Inspection-Acceptance.”
A. The Contractor shall allow the District, and any entity defined in subparagraph D below, to
test and inspect materials and workmanship. at reasonable times and at the Site of the Work,
unless the Engineer notifies the Contractor that inspection or testing of a material to be
incorporated in the Work will be made at the place of production, manufacture, or shipment
(“off-site”) of such material.
1. To the extent specified in the Engineer’s notification to the Contractor of off -site
inspection or testing, such inspection or test shall be conclusive as to whether the material
involved conforms to Contract requirements.
2. Such off -site inspection or test shall not relieve the Contractor of responsibility for
damage to, or loss of, the material prior to incorporation into the Work, nor in any way
affect the rights of the District under the terms of this Article, except as herein above
provided.
B. The District will endeavor to perform such inspections and testing in such manner as not
unnecessarily to delay the Work. Special, full size, and performance tests shall be performed
as described in the Contract.
C. The Contractor shall furnish promptly, without additional cost to the District, all facilities,
labor, equipment and material, including access and traffic control devices, needed for
performing safe and convenient inspection and testing in accordance with subparagraph A
and D of this clause. If off-site material and workmanship are not ready for inspection at the
time specified by the District, the Contractor shall be responsible for any additional cost of
tests and inspection.
D. When a unit of government other than the District, a utility company, or a railroad has an
interest in or is affected by the Contract, its respective representatives shall have the right to
inspect such portion of the Work. Such inspection shall not make any government unit, utility
company, or railroad a party to the Contract nor interfere with the rights of the District or the
Contractor.
E. The Contractor shall, at its own expense, replace any material and correct any workmanship
determined by the District not to conform to the Contract requirements, as directed by the
District. If, however, the District determines that acceptance of such work is in the public
interest, the District may accept such material or workmanship and make an appropriate
downward adjustment in the Contract price. The Contractor shall promptly segregate and
remove rejected material from the premises at Contractor’s expense. Costs associated with
inspection services will not be permitted in claims nor as a basis of claims except as specifically
provided herein.
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 17 of 60
F. Failure of the District to inspect or reject workmanship or material shall not in any way imply
acceptance, nor prevent the District from later rejecting the work. Inspection and acceptance
by the District in no way relieves the Contractor of its responsibility to meet the requirements
of the Contract Documents.
G. If the Contractor does not promptly replace rejected material or correct rejected
workmanship, the District:
1. May, by Contract or otherwise, replace such material and correct such workmanship and
charge the cost thereof to the Contractor, or
2. May terminate the Contractor’s Right to Proceed in accordance with Standard
Specifications Section 103.01 Article 5, “Termination-Delays.”
H. Should the Engineer determine that it is necessary to make an examination of any part or all
of the Work by removing or tearing out same, the Contractor shall, upon request, promptly
furnish all necessary facilities, labor and material to do same. If such work is found to be
defective or nonconforming, in any material respect, due to the fault of the Contractor or its
Subcontractors, the Contractor shall be responsible for the expenses of such removal and
tearing out of the work, examination, and of satisfactory reconstruction of the work. If,
however, such work is found to meet the requirements of the Contract, the District will make
an equitable adjustment in the Contract Price to compensate the Contractor for the additional
services involved in such removal or tearing out of such work, examination and
reconstruction. If completion of the Work has been delayed thereby, the District will, in
addition, make an equitable extension of time.
E.2 ACCEPTANCE
This clause supersedes Standard Specifications Section 105.13, “Inspection – Acceptance.”
A. PARTIAL ACCEPTANCE - When the Contractor completes a suitable unit or portion of the
Project, the Engineer may make, or the Contractor may request, final inspection of that unit.
If the Engineer determines that such unit or portion is complete and meets Contract
requirements, he or she may accept in writing that unit or portion as complete, which written
acceptance shall include a description of specific work accepted, and the Contractor may be
relieved of further responsibility for the accepted unit or portion subject to the requirements
of the Contract. Such partial acceptance shall not void or alter any Contract provision.
B. FINAL INSPECTION AND ACCEPTANCE
1. Within thirty (30) consecutive Calendar Days after receipt of written notice from the
Contractor that Contract work is complete, and the Project area cleaned up, the Engineer
will make a final inspection of the Project. The Contractor shall promptly correct all
deficiencies identified by the Engineer. Once the Contractor has satisfactorily completed
all of the requirements at Section 108.09, “Substantial Completion and Acceptance,” the
Engineer will certify in writing Final Acceptance of the Project.
2. Unless otherwise provided in the Contract, Final Acceptance by the District will be made
as promptly as practicable after inspection of the Work and shall be final and conclusive
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 18 of 60
except with regard to latent defects, fraud, or such gross mistakes as may amount to
fraud, or with regard to the District’s rights under any warranty or guaranty.
3. The Project will not be accepted until the Contractor has met all Contract requirements.
The Contractor remains responsible for the correction of any deficient or non -compliant
aspects of the Work until Final Acceptance, even if discovered after Final Acceptance.
C. The warranty of workmanship for the Work shall commence at Substantial Completion and
continue for a period of 2 years. If the Department declares partial Substantial Completion on
any portion of the Work in advance of Substantial Completion for the entire Project, the
warranty period for such portion shall commence on the date of partial Substantial
Completion and continue for a period of 2 years.
D. The Department, at any time during the warranty period, may conduct an inspection of the
Work in order to determine conformance to the Contract. If the Department reasonably
determines that defective work of any nature is present and is the responsibility of the
Contractor, the Contractor shall immediately make corrective action to bring the defective
Work into compliance with the Contract, or to the satisfaction of the Department, and at no
expense of the Department.
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 19 of 60
SECTION F: PERIOD OF PERFORMANCE AND DELIVERABLES
F.1 PERIOD OF PERFORMANCE
For the purposes of the Contract “Period of Performance” means “Contract Time” as defined in
Standard Specification Section 108.08, Determination of Contract Time and Partial Performance.
In accordance with Section 108.09, “Substantial Completion and Final Acceptance,” the following
periods of performance apply to this Contract:
A. Substantial Completion Date. Unless the Contract specifies a different time, Substantial
Completion is 30 Calendar Days before Final Acceptance.
B Final Acceptance Date. The Final Acceptance Date is 570 consecutive calendar days from the
date of Notice to Proceed.
F.2 DELIVERABLES
A. The Contractor shall perform the activities required to successfully complete the District’s
requirements and submit each deliverable to the Contract Administrator.
B. In addition to all deliverables required by the Contract, the Contractor shall submit to the
District, as a deliverable, all reports required by First Source Employment Agreement (see
H.5.E). If the Contractor does not submit the report as part of the deliverables, the District
shall not make final payment to the Contractor pursuant to section G.3.B.
F.3 FAILURE TO COMPLETE ON TIME
Standard Specifications Section 108.09(C), “Liquidated Damages,” applies to the Contract.
F.4 ROAD USERS - Not applicable.
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 20 of 60

SECTION G:

G.1 INVOICE PAYMENT
This clause supplements and modifies Standard Specifications Section 103.01 Article 9,
“Payments to Contractor,” and Section 109.05, “Progress Payments,” as follows:
A. Monthly Invoices (also be referred to as “applications for payment”). On a monthly basis, the
Contractor shall submit a proper invoice, in accordance with paragraph G.2(B) below, for
completed work. The Contractor shall submit evidence of timely payments to all
subcontractors, in accordance with paragraph G.2, below.
The District will make progress payments to the Contractor for work satisfactorily performed,
less any retainage, discounts, allowances or adjustments provided for in this Contract, on or
before the 30 th day after approval of an invoice for payment. Progress payments do not
constitute final acceptance of the work for which payments are made.
B. In the event that the Contractor fails to submit to the CO, at the time of its invoice submittal,
evidence of timely payment to subcontractors for work under the previous invoice and a
performance schedule update, the District will withhold progress payments.
C. Retainage.
The District may retain up to 5% of each progress payment. If, however, the Contractor has
been notified in writing of its failure to meet Contract requirements, the District may withhold
retainage up to 10% of each subsequent progress payment.
G.2 INVOICE SUBMITTAL
A. The Contractor shall create and submit payment requests in an electronic format through the
DC Vendor Portal, https://vendorportal.dc.gov.
B. Unless otherwise specified in the Contract, the Contractor shall submit proper invoices on a
monthly basis.
C. To constitute a proper invoice, the Contractor shall enter all required information into the
Portal after selecting the applicable purchase order number, which is listed on the
Contractor’s profile.
D. At the time of each invoice, the Contractor shall submit to the CA all deliverables required
under the Contract.
G.3 THE QUICK PAYMENT ACT (Feb 2019)
This clause supplements and modifies Standard Specifications Section 109.06, “Payment to
Subcontractors and Suppliers Certificate,” as follows:
A. Interest Penalties to Contractors
1. The District will pay interest penalties on amounts due to the Contractor under the Quick
Special Contract Requirements
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 21 of 60
Payment Act, D.C. Official Code § 2 -221.01 et seq., as amended, for the period beginning on
the day after the required payment date and ending on the date on which payment of the
amount is made. Interest shall be calculated at the rate of at least 1% per month. No interest
penalty shall be paid if payment for the completed delivery of the item of property or service
is made on or before the required payment date. The required payment date shall be:
a. The date on which payment is due under the terms of this contract;
b. Not later than 7 calendar days, excluding legal holidays, after the date of delivery of
meat or meat food products;
c. Not later than 10 calendar days, excluding legal holidays, after the date of delivery
of a perishable agricultural commodity; or
d. 30 calendar days, excluding legal holidays, after receipt of a proper invoice for the
amount of the payment due.
2. No interest penalty shall be due to the Contractor if payment for the completed delivery
of goods or services is made on or before:
a. 3rd day after the required payment date for meat or a meat product;
b. 5th day after the required payment date for an agricultural commodity; or
c. 15th day after any other required payment date.
3. Any amount of an interest penalty which remains unpaid at the end of any 30-day period
shall be added to the principal amount of the debt and thereafter interest penalties shall
accrue on the added amount.
B. Payments to Subcontractors
1. The Contractor shall take one of the following actions within seven (7) days of receipt of
any amount paid to the Contractor by the District for work performed by any
subcontractor under the contract:
a. Pay the subcontractor(s) for the proportionate share of the total payment received
from the District that is attributable to the subcontractor(s) for work performed under
the Contract; or
b. Notify the CO and the subcontractor(s), in writing, of the Contractor’s intention to
withhold all or part of the subcontractor’s payment and state the reason for the
nonpayment.
2. The Contractor shall pay subcontractors or suppliers interest penalties on amounts due
to the subcontractor or supplier beginning on the day after the payment is due and
ending on the date on which the payment is made. Interest shall be calculated at the rate
of at least 1% per month. No interest penalty shall be paid on the following if payment
for the completed delivery of the item of property or service is made on or before the:
a. 3rd day after the required payment date for meat or a meat product;
b. 5th day after the required payment date for an agricultural commodity; or
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 22 of 60
c. 15th day after any other required payment date.
3. Any amount of an interest penalty which remains unpaid by the Contractor at the end
of any 30 -day period shall be added to the principal amount of the debt to the
subcontractor and thereafter interest penalties shall accrue on the added amount.
4. A dispute between the Contractor and subcontractor relating to the amounts or
entitlement of a subcontractor to a payment or a late payment interest penalty under the
Quick Payment Act does not constitute a dispute to which the District is a party. The District
may not be interpleaded in any judicial or administrative proceeding involving such a
dispute.
C. Subcontract requirements
1. The Contractor shall include in each subcontract under this contract a provision requiring
the subcontractor to include in its contract with any lower-tier subcontractor or supplier
the payment and interest clauses required under paragraphs (1) and (2) of D.C. Official
Code § 2-221.02(d).
2. The Contractor shall include in each subcontract under this contract a provision that obligates
the Contractor, at the election of the subcontractor, to participate in negotiation or
mediation as an alternative to administrative or judicial resolution of a dispute between
them.

G.4 ASSIGNMENT OF CONTRACT PAYMENTS
A. In accordance with 27 DCMR 3250, the Contractor may assign to a bank, trust company, or
other financing institution funds due or to become due as a result of the performance of this
contract.
B. Any assignment shall cover all unpaid amounts payable under this contract, and shall not be
made to more than one party.
C. Notwithstanding an assignment of contract payments, the Contractor, not the assignee, is
required to prepare invoices. Where such an assignment has been made, the original copy
of the invoice must refer to the assignment and must show that payment of the invoice is to
be made directly to the assignee as follows: “Pursuant to the instrument of assignment dated
, make payment of this invoice to (name and address of assignee).”
G.5 FINAL PAYMENT
This clause supersedes Standard Specification Section 109.08, “Acceptance and Final Payment.”
A. Acceptance means “Final Acceptance,” as defined in Standard Specification Section
108.08(B). When the Project has been accepted in accordance Standard Specification Section
101.08(B), the Contractor shall prepare, and submit to the CA, the final estimate for the Work
performed for approval by the District. If the District approves the final estimate without
exception to the quantities, the Contractor may file an invoice for final payment. The amount
of the final payment will be the entire sum found to be due after deducting all previous
DCKA-2024-C3-0073
DC Power Line Underground (Feeder 14702/118)
Page 23 of 60
payments and all amounts to be retained or deducted under the provisions of the Contract.
All prior partial estimates and progress payments shall be subject to correction in the final
estimate and payment.
B. In addition to its invoice for final payment, the Contractor must submit to the Contracting
Officer:
1. A release of all claims against the District arising from or relating to this Contract;
2. Proof of payment of all subcontractors; and
3. All required product warranties, as -built drawings, operating manuals, material
certifications, and other items as specified in the Contract.
The District shall not make final payment to the Contractor unless and until all required
documentation is received.
C. All release forms must bear an original signature of an individual authorized to sign on behalf
of the Contractor and must be affixed with the Contractor’s corporate seal o
D. Notwithstanding the provisions of B.1 above, the Contractor may reserve from the release
specific claims only if such claims have been submitted in accordance with the Disputes clause
of the Contract. In such event, the District will make final payment pending resolution of the
claim. Upon final adjudication
G.6 FIRST SOURCE AGREEMENT REQUEST FOR FINAL PAYMENT
A. For contracts subject to the 51% District Residents New Hires Requirements and/or First
Source Employment Agreement requirements, final request for payment must be
accompanied by the compliance report or a waiver of compliance.
B. The District may impose monetary fines for willful breach of the employment agreement or
failure to submit the compliance report.
G.7 CONTRACTING OFFICER (CO)
Contracts will be entered into and signed on behalf of the District only by contracting officers.
The contact information for the Contracting Officer is:

Carol Hessler
Office of Contracting and Procurement
250 M Street, SE, 7th Floor.
Telephone: 202524-8136
E-mail: carol.hessler@dc.gov

G.8 AUTHORIZED CHANGES BY THE CONTRACTING OFFICER (“CO”)
A. The CO is the only person authorized to approve changes in any of the requirements of the
Contract.
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 24 of 60
B. The Contractor shall not comply with any order, directive or request that changes or modifies
the requirements of the Contract, unless issued in writing and signed by the CO.
C. In the event the Contractor effects any change at the instruction or request of any person
other than the CO, the change will be considered to have been made without authority and
no adjustment will be made in the Contract price to cover any cost increase incurred as a
result thereof.
D. The Contractor will be fully responsible for any changes not authorized in advance, in writing,
by the CO; may be denied compensation or other relief for any additional work performed that
is not so authorized; and may also be required, at no additional cost to the District, to take all
corrective action necessitated by reason of the unauthorized changes.

G.9 CONTRACT ADMINSTRATOR (CA)
A. The address and telephone number of the Contract Administrator (CA) is: TBD
B. For the purposes of the Contract, “Contract Administrator” or “CA” are synonymous with
“Engineer.” The CA is responsible for general administration of the Contract and advising the
CO as to the Contractor’s compliance or noncompliance with the Contract . The CA has the
responsibility of ensuring the work conforms to the requirements of the Contract and such
other responsibilities and authorities as may be specified in the Contract. The CA will act as
the CO’s representative on technical matters, providing technical clarifications, as necessary,
with respect to the Specifications or Statement of Work, and monitoring the progress and
quality of the Contractor’s performance. Other responsibilities include:
1. Keeping the CO fully informed of any technical or contractual difficulties encountered
during the performance period and advising the CO of any potential problem areas under
the Contract;
2. Coordinating site entry for Contractor personnel, if applicable;
3. Reviewing and approving invoices for completed work if the Contractor’s costs are
consistent with the negotiated amounts and progress is satisfactory and commensurate
with the rate of expenditure;
4. Reviewing and approving invoices for deliverables to ensure receipt of goods and services.
This includes the timely processing of invoices and vouchers in accordance with the
District’s payment provisions;
5. Inspecting and accepting/rejecting all deliverables under the Contract; and
6. Maintaining a file that includes all Contract correspondence, modifications, records of
inspections (site, data, equipment, etc.) and invoice or vouchers.
C. The CA shall NOT have the authority to:
1. Award, agree to, or sign any contract, delivery order or task order. Only the CO shall make
contractual agreements, commitments or modifications;
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 25 of 60
2. Grant deviations from or waive any of the terms and conditions of the Contract;
3. Increase the dollar limit of the contract or authorize work beyond the dollar limit of the
Contract,
4. Authorize the expenditure of funds by the Contractor;
5. Change the period of performance;
6. Substitute key personnel without CO approval; or
7. Authorize the use of District property, except as specified under the Contract.
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 26 of 60
SECTION H: Contract Clauses
H.1 HIRING OF DISTRICT RESIDENTS AS APPRENTICES AND TRAINEES
A. For all new employment resulting from this contract or subcontracts hereto, as defined in
First Source Employment Agreement Act of 1984, as amended, D.C. Official Code § 2-219.01
et seq. (First Source Act), the Contractor shall use its best efforts to comply with the following
basic goal and objectives for utilization of bona fide residents of the District of Columbia in
each project’s labor force:
1. At least fifty-one (51) percent of apprentices and trainees employed shall be residents of
the District of Columbia registered in programs approved by the District of Columbia
Apprenticeship Council.
B. The Contractor shall negotiate an Employment Agreement with the Department of
Employment Services (DOES) for jobs created as a result of this contract. The DOES shall be
the Contractor’s first source of referral for qualified apprentices and trainees in the
implementation of employment goals contained in this clause.
H.2 DEPARTMENT OF LABOR WAGE DETERMINATIONS
A. Section 103.02(A) of the Standard Specifications is modified and supplemented as
follows:
In accordance with applicable provisions of 29 CFR Part 1 which require that the correct wage
determination and the appropriate wage rates therein be incorporated into this contract.
General Wage Decision No. DC20240001, Dated 05/31/2024 is bound herein and contains
the specific applicable wage rate(s) which is for: Heavy and Highway.
B. Further, as set forth in 29 CFR Part 1, Section 1.6(c)(3)(iv), if the intent to award letter is not
issued within ninety (90) days of bid opening, all intervening modifications, notice of which
are published on the US Department of Labor website, are made a part of this Contract.
The Contractor will be reimbursed this added labor cost.
C. Within 7 days after the regular payment date of the Contractor’s payroll period, the
Contractor shall submit all certified payrolls and the accompanying Statement of Compliance
electronically using LCPTracker, the DDOT electronic labor compliance software. DDOT will
provide information regarding registration for LCPTracker at the pre -construction
conference. More information regarding these requirements is in the Davis Bacon
Compliance Requirements, attached at J.4.
H.3 PREGNANT WORKERS FAIRNESS
The Contractor shall comply with the Protecting Pregnant Workers Fairness Act of 2016 , D.C.
Official Code § 32-1231.01 et seq.
A. The Contractor shall not:
1. Refuse to make reasonable accommodations to the known limitations related to
pregnancy, childbirth, related medical conditions, or breastfeeding for an employee,
unless the Contractor can demonstrate that the accommodation would impose an undue
hardship;
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 27 of 60
2. Take an adverse action against an employee who requests or uses a reasonable
accommodation in regard to the employee's conditions or privileges of employment,
including failing to reinstate the employee when the need for reasonable
accommodations ceases to the employee's original job or to an equivalent position with
equivalent:
a. Pay;
b. Accumulated seniority and retirement;
c. Benefits; and
d. Other applicable service credits;
3. Deny employment opportunities to an employee, or a job applicant, if the denial is based
on the need of the employer to make reasonable accommodations to the known
limitations related to pregnancy, childbirth, related medical conditions, or breastfeeding;
4. Require an employee affected by pregnancy, childbirth, related medical conditions, or
breastfeeding to accept an accommodation that the employee chooses not to accept if
the employee does not have a known limitation related to pregnancy, childbirth, related
medical conditions, or breastfeeding or the accommodation is not necessary for the
employee to perform her duties;
5. Require an employee to take leave if a reasonable accommodation can be provided; or
6. Take adverse action against an employee who has been absent from work as a result of a
pregnancy-related condition, including a pre-birth complication.
B. The Contractor shall post and maintain in a conspicuous place a notice of rights in both English
and Spanish and provide written notice of an employee's right to a needed reasonable
accommodation related to pregnancy, childbirth, related medical conditions, or
breastfeeding pursuant to the PPWF Act to:
1. New employees at the commencement of employment;
2. Existing employees; and
3. An employee who notifies the employer of her pregnancy, or other condition covered
by the PPWF Act, within 10 days of the notification.
C. The Contractor shall provide an accurate written translation of the notice of rights to any
non-English or non-Spanish speaking employee.
D. Violations of the PPWF Act shall be subject to civil penalties as described in the Act.
H.4 UNEMPLOYED ANTI-DISCRIMINATION
A. The Contractor shall comply with the Unemployed Anti-Discrimination Act of 2012, D.C.
Official Code § 32-1361 et seq.
B. The Contractor shall not:
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 28 of 60
1. Fail or refuse to consider for employment, or fail or refuse to hire, an individual as an
employee because of the individual's status as unemployed; or
2. Publish, in print, on the Internet, or in any other medium, an advertisement or
announcement for any vacancy in a job for employment that includes:
a. Any provision stating or indicating that an individual's status as unemployed
disqualifies the individual for the job; or
b. Any provision stating or indicating that an employment agency will not consider or
hire an individual for employment based on that individual's status as unemployed.
C. Violations of the Unemployed Anti-Discrimination Act shall be subject to civil penalties as
described in the Act.
H.5 51% DISTRICT RESIDENTS NEW HIRES REQUIREMENTS AND FIRST SOURCE
EMPLOYMENT AGREEMENT
A. The Contractor shall comply with the First Source Employment Agreement Act of 1984, as
amended, D.C. Official Code § 2-219.01 et seq. (First Source Act).
B. The Contractor shall enter into and maintain during the term of the contract, a First Source
Employment Agreement (Employment Agreement) with the District of Columbia
Department of Employment Services (DOES), in which the Contractor shall agree that:
1. The first source for finding employees to fill all jobs created in order to perform the
contract shall be the First Source Register; and
2. The first source for finding employees to fill any vacancy occurring in all jobs covered by
the Employment Agreement shall be the First Source Register.
C. The Contractor shall not begin performance of the contract until its Employment Agreement
has been accepted by DOES. Once approved, the Employment Agreement shall not be
amended except with the approval of DOES.
D. The Contractor agrees that at least 51% of the new employees hired to perform the contract
shall be District residents if the awarded contract has a value totaling between $300,000
and $5,000,000. If the award contract has a value totaling $5 million or more, the
Contractor agrees that:
1. At least 20% of journey workers by trade shall be performed by District resident;
2. At least 60% of apprentice hours by trade shall be performed by District resident;
3. At least 51% of the skilled laborer hours by trade shall be performed by District
resident; and
4. At least 70% of common laborer hours shall be performed by District residents.
E. The Contractor’s hiring and reporting requirements under the First Source Act and any rules
promulgated thereunder shall continue for the term of the contract.
F. The CO may impose penalties, including monetary fines of 5% of the total amount of the
direct and indirect labor costs of the contract, for a willful breach of the Employment
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 29 of 60
Agreement, failure to submit the required hiring compliance reports, or deliberate
submission of falsified data.
G. If the Contractor does not receive a good faith waiver, the CO may also impose an additional
penalty equal to 1/8 of 1% of the total amount of the direct and indirect labor costs of the
contract for each percentage by which the Contractor fails to meet its hiring requirements.
H. Any contractor which violates, more than once within a 10 -year timeframe, the hiring or
reporting requirements of the First Source Act shall be referred for debarment for not more
than five (5) years.
I. The contractor may appeal any decision of the CO pursuant to this clause to the D.C. Contract
Appeals Board as provided in the Disputes clause in the Contract.
J. The provisions of the First Source Act do not apply to nonprofit organizations which employ
50 employees or less.
H.6 WAY TO WORK AMENDMENT ACT OF 2006
A. Except as described in section (h) of this clause, the Contractor shall comply with Title I of the
Way to Work Amendment Act of 2006, D.C. Law 16-118, D.C. Official Code §2-220.01 et seq.
("Living Wage Act of 2006"), for contracts in the amount of $100,000 or more in a 12-month
period.
B. The Contractor shall pay its employees and subcontractors who perform services under the
contract no less than the current living wage published on the OCP website at
www.ocp.dc.gov.
C. The Contractor shall include in any subcontract for $15,000 or more a provision requiring the
subcontractor to pay its employees who perform services under the contract no less than the
current living wage rate.
D. The DOES may adjust the living wage annually and the OCP will publish the current living wage
rate on its website at www.ocp.dc.gov.
E. The Contractor shall provide a copy of the Fact Sheet attached to the contract to each
employee and subcontractor who performs services under the contract. The Contractor shall
also post the Notice attached to the contract in a conspicuous place in its place of business.
The Contractor shall include in any subcontract for $15,000 or more a provision requiring the
subcontractor to post the Notice in a conspicuous place in its place of business.
F. The Contractor shall maintain its payroll records under the contract in the regular course of
business for a period of at least three (3) years from the payroll date, and shall include this
requirement in its subcontracts for $15,000 or more under the contract.
G. The payment of wages required under the Living Wage Act of 2006 shall be consistent with
and subject to the provisions of D.C. Official Code §32-1301 et seq.
H. The requirements of the Living Wage Act of 2006 do not apply to:
1. Contracts or other agreements that are subject to higher wage level determinations
required by federal law;
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 30 of 60

2. Existing and future collective bargaining agreements, provided, that the future collective
bargaining agreement results in the employee being paid no less than the established
living wage;
3. Contracts for electricity , telephone, water , sewer or other services provided by a
regulated utility;
4. Contracts for services needed immediately to prevent or respond to a disaster or eminent
threat to public health or safety declared by the Mayor;
5. Contracts or other agreements that provide trainees with additional services including,
but not limited to, case management and job readiness services; provided that the
trainees do not replace employees subject to the Living Wage Act of 2006;
6. An employee under 22 years of age employed during a school vacation period, or enrolled
as a full-time student, as defined by the respective institution, who is in high school or at
an accredited institution of higher education and who works less than 25 hours per week;
provided that he or she does not replace employees subject to the Living Wage Act of
2006;
7. Tenants or retail establishments that occupy property constructed or improved by
receipt of government assistance from the District of Columbia; provided, that the tenant
or retail establishment did not receive direct government assistance from the District;
8. Employees of nonprofit organizations that employ not more than 50 individuals and
qualify for taxation exemption pursuant to section 501(c)(3) of the Internal Revenue Code
of 1954, approved August 16, 1954 (68A Stat. 163; 26 U.S.C. § 501(c)(3));
9. Medicaid provider agreements for direct care services to Medicaid recipients, provided,
that the direct care service is not provided through a home care agency, a community
residence facility, or a group home for mentally retarded persons as those terms are
defined in section 2 of the Health -Care and Community Residence Facility , Hospice, and
Home Care Licensure Act of 1983, effective February 24, 1984 (D.C. Law 5-48; D.C. Official
Code§ 44-501); and
10. Contracts or other agreements between managed care organizations and the Health Care
Safety Net Administration or the Medicaid Assistance Administration to provide health
services.
I. The Mayor may exempt a contractor from the requirements of the Living Wage Act of 2006,
subject to the approval of Council, in accordance with the provisions of Section 109 of the
Living Wage Act of 2006.
H.7 SECTION 504 OF THE REHABILITATION ACT OF 1973, AS AMENDED
During the performance of the Contract, the Contractor and its subcontractors shall comply
with Section 504 of the Rehabilitation Act of l973, as amended. This Act prohibits
discrimination against disabled people in federally funded programs and activities. See 29
U.S.C. § 794 et seq.
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 31 of 60
H.8 AMERICANS WITH DISABILITIES ACT OF 1990 (ADA)
During the performance of this contract, the Contractor and its subcontractors shall comply
with the ADA. The ADA makes it unlawful to discriminate in employment against a qualified
individual with a disability. See 42 U.S.C. § 12101 et seq.
H.9 SUBCONTRACTING REQUIREMENTS
A. Mandatory Subcontracting Requirements

1. For all contracts in excess of $250,000, at least 35% of the dollar volume of the Contract
shall be subcontracted to qualified small business enterprises (SBEs).
2. If there are insufficient SBEs to completely fulfill the requirement of paragraph H.9.A.1,
the Contractor may satisfy the requirement by subcontracting 35% of the dollar volume
to any qualified certified business enterprises (CBEs); provided, however, that all
reasonable efforts shall be made to ensure that SBEs are significant participants in the
overall subcontracting work.
3. A prime contractor that is certified by DSLBD as a small, local, or disadvantaged business
enterprise shall not be required to comply with the provisions of sections H.9.A.1 and
H.9.A.2.
4. Except as provided in H.9.A.5 and H.9.A.7, a prime contractor that is a CBE and has been
granted a bid preference pursuant to D.C. Official Code § 2-218.43, or is selected through
a set -aside program, shall perform at least 35% of the contracting effort with its own
organization and resources and, if it subcontracts, 35% of the subcontracting effort shall
be with CBEs. A CBE prime contractor that performs less than 35% of the contracting
effort shall be subject to enforcement actions under D.C. Official Code § 2-218.63.
5. If the prime contractor is a certified joint venture and has been granted a bid preference
pursuant to D.C. Official Code § 2-218.43, or is selected through a set-aside program, the
CBE member of the certified joint venture shall perform at least 50% of the contracting
effort with its own organization and resources and, if it subcontracts, 35% of the
subcontracting effort shall be with CBEs. A certified joint venture prime contractor that
performs less than 50% of the contracting effort shall be subject to enforcement actions
under D.C. Official Code § 2-218.63.
6. Each CBE utilized to meet these subcontracting requirements shall perform at least 35%
of its contracting effort with its own organization and resources.
7. A prime contractor that is a CBE and has been granted a bid preference pursuant to D.C.
Official Code § 2-218.43, or is selected through a set-aside program, shall perform at least
50% of the on -site work with its own organization and resources if the contract is $1
million or less.
B. Subcontracting Plan
If the prime contractor is required to subcontract under the contract, it shall submit a
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 32 of 60
subcontracting plan as part of the bid, which may only be amended after award with the prior
written approval of the CO and the Director of DSLBD. Any reduction in the dollar volume of the
subcontracted portion resulting from an amendment of the plan after award shall inure to the
benefit of the District.
Each subcontracting plan shall include the following:
1. The name and address of each subcontractor;
2. A current certification number of the small or certified business enterprise;
3. The scope of work to be performed by each subcontractor; and
4. The price that the prime contractor will pay each subcontractor.
C. Copies of Subcontracts
Within twenty-one (21) days of the date of award, the Contractor shall provide fully executed
copies of all subcontracts identified in the subcontracting plan to the CO, CA, District of Columbia
Auditor and the Director of DSLBD.

Auditor DSLBD
Office of the District of Columbia Auditor
717 14th Street, NW, Suite 900
Washington, DC 20005
Director - DSLBD
441 4th Street, NW, Suite 850 North
Washington, DC 20001
D. Subcontracting Plan Compliance Reporting
1. The Contractor shall submit a quarterly report to the CO, CA, District of Columbia Auditor
and the Director of DSLBD. The quarterly report shall include the following information
for each subcontract identified in the subcontracting plan:
a. The price that the prime contractor will pay each subcontractor under the
subcontract;
b. A description of the goods procured or the services subcontracted for;
c. The amount paid by the prime contractor under the subcontract; and
d. A copy of the fully executed subcontract, if it was not provided with an earlier
quarterly report.
2. If the fully executed subcontract is not provided with the quarterly report, the prime
contractor will not receive credit toward its subcontracting requirements for that
subcontract.
E. Annual Meetings
Upon at least 30-days written notice provided by DSLBD, the Contractor shall meet annually with
the CO, CA, District of Columbia Auditor and the Director of DSLBD to provide an update on its
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 33 of 60
subcontracting plan.
F. Notices
The Contractor shall provide written notice to the DSLBD and the District of Columbia Auditor
upon commencement of the Contract and when the Contract is completed.
G. Enforcement and Penalties for Breach of Subcontracting Plan
1. A contractor shall be deemed to have breached a subcontracting plan required by law, if
the contractor (i) fails to submit subcontracting plan monitoring or compliance reports or
other required subcontracting information in a reasonably timely manner; (ii) submits
and monitoring or compliance report or other required subcontracting information containing a
materially false statement; or (iii) fails to meet its subcontracting requirements.
2. A contractor that is found to have breached its subcontracting plan for utilization of CBEs
in the performance of a contract shall be subject to the imposition of penalties, including
monetary fines in accordance with D.C. Official Code § 2-218.63.
3. If the CO determines the Contractor’s failure to be a material breach of the contract, the
CO shall have cause to terminate the contract under the default provisions in Clause 8 of
the Standard Contract Provisions for Supplies and Services, which is incorporated into the
Contract by reference.
H.10 FAIR CRIMINAL RECORD SCREENING
A. The Contractor shall comply with the provisions of the Fair Criminal Record Screening
Amendment Act of 2014, effective December 17, 2014 (D.C. Law 20 -152) (“Act” as used in
this section). This section applies to any employment, including employment on a temporary
or contractual basis, where the physical location of the employment is in whole or substantial
part within the District of Columbia.

B. Prior to making a conditional offer of employment, the Contractor shall not require an
applicant for employment, or a person who has requested consideration for employment by
the Contractor, to reveal or disclose an arrest or criminal accusation that is not then pending
or did not result in a criminal conviction.

C. After making a conditional offer of employment, the Contractor may require an applicant to
disclose or reveal a criminal conviction.
D. The Contractor may only withdraw a conditional offer of employment, or take adverse action
against an applicant, for a legitimate business reason as described in the Act.
E. This section and the provisions of the Act shall not apply:
1. Where a federal or District law or regulation requires the consideration of an applicant’s
criminal history for the purposes of employment;
2. To a position designated by the employer as part of a federal or District government
program or obligation that is designed to encourage the employment of those with
criminal histories;
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 34 of 60
3. To any facility or employer that provides programs, services, or direct care to, children,
youth, or vulnerable adults; or
4. To employers that employ less than 11 employees.
F. A person claiming to be aggrieved by a violation of the Act may file an administrative
complaint with the District of Columbia Office of Human Rights, and the Commission on
Human Rights may impose monetary penalties against the Contractor.

H.11 EQUAL EMPLOYMENT OPPORTUNITY
In accordance with the District of Columbia Administrative Issuance System, Mayor’s Order
85- 85 dated June 10, 1985, the forms for completion of the Equal Employment Opportunity
Information Report are incorporated herein as Section J.3. An award cannot be made to any
bidder who has not satisfied the equal employment requirements.
H.12 RESERVED
H.13 PRE-AWARD APPROVAL
The award and enforceability of this contract is contingent upon approval of the Council of the
District of Columbia. In accordance with D.C. Official Code §2 -352.02 and §1 -204.51(c), the
Council of the District of Columbia must approve an award of any contract for over $1,000,000.00
or that has a term extending beyond 12 months. No contract in excess of $l,000,000.00 or that
is for a term extending beyond 12 months shall be binding or give rise to any claim or demand
against the District until approved by the Council of the District of Columbia and signed by the
CO.
H.14 BUY AMERICA REQUIREMENTS
This clause supersedes Standard Specifications Section 103.01, Article 24, “Buy American.”
In accordance with OMB Memo M -22-11, dated April 18, 2022, and the Build America Buy
America Act, Pub. L. No. 117 -58 §§ 70901-52 (the “Act”), bidders are hereby notified that none
of the funds provided under the resultant award may be used for a project for infrastructure
unless:
(1) all iron and steel used in the project are produced in the United States --this means
all manufacturing processes, from the initial melting stage through the application of
coatings, occurred in the United States;
(2) all manufactured products used in the project are produced in the United States —
this means the manufactured product was manufactured in the United States; and the
cost of the components of the manufactured product that are mined, produced, or
manufactured in the United States is greater than 55 percent of the total cost of all
components of the manufactured product, unless another standard for determining the
minimum amount of domestic content of the manufactured product has been
established under applicable law or regulation; and
(3) all construction materials are manufactured in the United States —this means that all
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 35 of 60
manufacturing processes for the construction material occurred in the United States.
The Buy America preference only applies to articles, materials, and supplies that are consumed
in, incorporated into, or affixed to an infrastructure project. As such, it does not apply to tools,
equipment, and supplies, such as temporary scaffolding, brought to the construction site and
removed at or before the completion of the infrastructure project. Nor does a Buy America
preference apply to equipment and furnishings, such as movable chairs, desks, and portable
computer equipment, that are used at or within the finished infrastructure project but are not
an integral part of the structure or permanently affixed to the infrastructure project.
For purposes of this section, an article, material, or supply should only be classified into one of
the following categories:
(1) iron or steel,
(2) a manufactured product, or
(3) a construction material.
For ease of administration, an article, material, or supply should not be considered to fall into
multiple categories. The iron and steel test should be applied to items that are predominantly
iron or steel, unless another standard applies under law or regulation. When necessary, waivers
from these requirements may be available from FHWA.
When FHWA has made a determination that one of the following exceptions applies, then the
application of the domestic content procurement preference may be waived in any case in which
FHWA determines that:
(1) applying the domestic content procurement preference would be inconsistent with the
public interest;
(2) the types of iron, steel, manufactured products, or construction materials are not
produced in the United States in sufficient and reasonably available quantities or of a
satisfactory quality; or
(3) the inclusion of iron, steel, manufactured products, or construction materials produced in
the United States will increase the cost of the overall project by more than 25 percent.
Waiver requests are subject to public comment periods of no less than 15 days, except in
unforeseen and exigent circumstances, and must be approved by FHWA and reviewed by the Made
in America Office. There may be instances where an award qualifies, in whole or in part, for an
existing waiver.
Definitions:
“Construction Materials” includes an article, material, or supply —other than an item of primarily
iron or steel; a manufactured product; cement and cementitious materials; aggregates such as
stone, sand, or gravel; or aggregate binding agents or additives—that is or consists primarily of:
1. non-ferrous metals;
2. plastic and polymer -based products (including polyvinylchloride, composite building
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 36 of 60
materials, and polymers used in fiber optic cables);
3. glass (including optic glass);
4. lumber; or
5. drywall.
See the Act § 70911(5) for further information about the definition of Construction Materials. “All
Manufacturing Processes” as defined in the Standards at 2 CFR 184.6 For additional information,
refer to OMB Memo M-24-02.
H.15 CONSTRUCTION WAGE RATE REQUIREMENTS (DAVIS BACON ACT)
a) Definition.
1. “Site of the work” is defined as:
a. The primary site of the work. The physical place or places where the construction
called for in the contract.
b. Contractor may have to utilize multiple shifts and/or overtime work (including
Saturdays, Sundays and Holidays) if granted.
c. The cost of multiple shifts and/or overtime work shall be included in the bid process
for the various items of work on the project and no additional compensation will be
allowed.
d. In developing the plan, the Contractor shall consider time lost due to inclement
weather. The District will not consider any requests for partial suspension or time
extension for time lost due to inclement weather.
2. Schedule requirements and updates

a. The Contractor shall provide schedule data files to the CA and the CM upon
request.
b. The Contractor shall have monthly reconciliation meetings with the CA/CM to
agree on actual completion percentages.
c. The Contractor shall use the agreed completion percentages for monthly schedule
updates.
d. The Contractor shall not change the schedule logic (relationships between
activities, key constraints, predecessors/successors) without the CA/CM’s
approval.
e. Although the construction Critical Path Method (CPM) schedule is the master path
for the completion of the work, the day -to-day installation of the work by the
Contractor should be managed by short term schedules. These short -term
schedules should cover periods from one to four weeks with two-week lookahead
schedules. The Contractor shall extract the lookahead schedules form the
construction CPM schedule. The Contractor’s lookahead activities shall follow the
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 37 of 60
latest approved construction CPM schedule.
f. An evaluation of progress is to be completed after each 10 percent increment of
the contract time that has elapsed. Whenever performance falls behind the
approved plans schedule by 10 percent of more, the Contractor shall, within 15
calendar says, submit to the CA/CM for review a revised plan for completing the
project within the remaining time.
The Contractor must be aware that part of the work may include coordination with various
Government agencies, National Park Service and Utility Companies. Delay by any outside sources
will not constitute grounds for waiving this provision.
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 38 of 60
SECTION I: CONTRACT CLAUSES
I.1 APPLICABILITY OF STANDARD CONTRACT PROVISIONS
Except to the extent supplemented and modified, or superseded, by the terms of the Contract,
Standard Specifications for Highways and Structures (2013) (“Standard Specifications”) applies to
this Contract. The Standard Specifications may be found at: http://ddot.dc.gov/page/standard-
specifications-highways-and-structures.
I.2 CONTRACTS THAT CROSS FISCAL YEARS
The District’s obligation for performance of the Contract beyond the fiscal year is contingent
upon the availability of appropriated funds from which payment for contract purposes can be
made. No legal liability on the part of District for any payment may arise for performance under
the Contract beyond the end of the fiscal year in which the Contract was awarded, until funds
are made available to the Contracting Officer for performance and until the Contractor receives
notice of availability, to be confirmed in writing by the Contracting Officer
I.3 CONFIDENTIALITY OF INFORMATION
The Contractor shall keep all information relating to the Project in absolute confidence, shall
comply with the District and federal laws governing the confidentiality of records, and shall not
use the information in connection with any other matters.
I.4 PUBLICITY
The Contractor shall at all times obtain the prior written approval from the CO before the
Contractor, any of its officers, agents, employees or subcontractors, either during the term of the
Contract or after expiration or termination of the Contract, make any statement, or issue any
material, for publication through any medium of communication, bearing on the work performed
or data collected under the Contract.
I.5 SUBCONTRACTING
This paragraph supersedes Standard Specifications Section 108.01, “Subletting of Contract.”
A. The Contractor hereunder shall not subcontract any of the Work to any subcontractor without
the prior written consent of the CO. If the CO consents, any work so subcontracted shall be
performed pursuant to a subcontract agreement, which the District will have the right to
review and approve prior to its execution by the Contractor. Any such subcontract shall
specify that the Contractor and the subcontractor shall be subject to every provision of the
Contract. Notwithstanding any work that is subcontracted, the Contractor shall remain liable
to the District for all of the Work.
B. The Contractor shall use the Subcontractor Approval Request Form (DDOT Form 120 -KA),
attached at J.3, to request approval of subcontractors on this Project. The form should be
completed for each subcontractor requested for approval and submitted to the Contracting
Officer.
C. The Contractor shall make copies of subcontracts available for review at any time by
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 39 of 60
representatives of the District and, for FAHP contracts, the FHWA.
The Contractor shall ensure that all subcontractors meet the General Standards of Responsibility
as set forth in 27 DCMR 2200.4. The Contracting Officer may, but is under no obligation to,
request that the Contractor provide written evidence of a subcontractor’s responsibility. Such
action on the part of the Contracting Officer in no way limits the Contractor’s responsibility under
this subparagraph D.
I.6 TIME
Time, if stated as number of days, will include Saturdays, Sundays, and holidays, unless otherwise
stated herein.
I.7 FREEDOM OF INFORMATION ACT
The District of Columbia Freedom of Information Act, at D.C. Official Code §2-532 (a-3), requires
the District to make available for inspection and copying any record produced or collected
pursuant to a District contract with a private contractor to perform a public function, to the same
extent as if the record were maintained by the agency on whose behalf the contract is made. If
the Contractor receives a request for such information, the Contractor shall immediately send
the request to the CA who will provide the request to the DDOT Freedom of Information Act
(FOIA) Officer in accordance with the D.C. Freedom of Information Act. If DDOT receives a request
for a record maintained by the Contractor pursuant to the Contract, the CA will forward a copy
to the Contractor. In either event, the Contractor is required by law to provide all responsive
records to the CA within the timeframe designated by the CA. The DDOT FOIA Officer will
determine whether the records are releasable. The District will reimburse the Contractor for the
costs of searching and copying the records in accordance with D.C. Official Code §2 -532 and
Chapter 4 of Title 1 of the D.C. Municipal Regulations.
I.8 INSURANCE
A. GENERAL REQUIREMENTS. The Contractor at its sole expense shall procure and
maintain, during the entire period of performance under this contract, the types of
insurance specified below. The Contractor shall submit a Certificate of Insurance to the
Contracting Officer (CO) giving evidence of the required coverage prior to commencing
performance under this contract. In no event shall any work be performed until the
required Certificates of Insurance signed by an authorized representative of the
insurer(s) have been provided to, and accepted by, the CO.

The Government of the District of Columbia shall be included in all policies, where
applicable and allowable by law, required hereunder to be maintained by the Contractor
and its subcontractors (except for workers’ compensation and professional liability
insurance) as an additional insureds for claims against The Government of the District of
Columbia relating to this contract, with the understanding that any affirmative
obligation imposed upon the insured Contractor or its subcontractors (including without
limitation the liability to pay premiums) shall be the sole obligation of the Contractor or
its subcontractors, and not the additional insured. The additional insured status under
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 40 of 60
the Contractor’s and its subcontractors’ Commercial General Liability insurance policies
shall be effected using the ISO Additional Insured Endorsement form CG 20 10 11 85 (or
CG 20 10 07 04 and CG 20 37 07 04) or such other endorsement or combination of
endorsements providing coverage at least as broad and approved by the CO in writing.
All of the Contractor’s and its subcontractors’ liability policies (except for workers’
compensation and professional liability insurance) shall be endorsed using ISO form CG
20 01 04 13 or its equivalent so as to indicate that such policies provide primary
coverage (without any right of contribution by any other insurance, reinsurance or self-
insurance, including any deductible or retention, maintained by an Additional Insured)
for all claims against the additional insured arising out of the performance of this
Statement of Work by the Contractor or its subcontractors, or anyone for whom the
Contractor or its subcontractors may be liable. These policies shall include a separation
of insureds clause applicable to the additional insured.

If the Contractor and/or its subcontractors maintain broader coverage and/or higher
limits than the minimums shown below, the District requires and shall be entitled to the
broader coverage and/or the higher limits maintained by the Contractor and
subcontractors.

B. INSURANCE REQUIREMENTS
1. Commercial General Liability Insurance (“CGL”) - The Contractor shall provide evidence
satisfactory to the CO with respect to the services performed that it carries a CGL policy,
written on an occurrence (not claims-made) basis, on Insurance Services Office, Inc.
(“ISO”) form CG 00 01 04 13 (or another occurrence-based form with coverage at least
as broad and approved by the CO in writing), covering liability for all ongoing and
completed operations of the Contractor and under all subcontracts, covering claims for
bodily injury, including without limitation sickness, disease or death and mental anguish
of any persons, broad form property damage, including loss of use resulting therefrom,
personal and advertising injury, and including coverage for liability arising out of an
Insured Contract (including the tort liability of another assumed in a contract) and acts of
terrorism (whether caused by a foreign or domestic source). Such coverage shall have
limits of liability of not less than $1,000,000 for each occurrence, and a $2,000,000
general aggregate.

The Commercial General Liability shall be further endorsed to:
a) To the fullest extent permitted by law, provide additional insured coverage
using ISO form CG 2015 0413 (or its equivalent) to The Government of the
District of Columbia
b) Coverage available to the additional insureds shall apply on a primary and
non-contributing basis as respects any other insurance, deductibles, or self-
insurance available to the additional insureds
c) A waiver of subrogation in favor of The Government of the District of
Columbia
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 41 of 60
d) Any Annual Aggregate shall apply on a per location or per project basis
(where applicable)
e) Defense costs shall be in addition to and not erode the limits of liability

2. Automobile Liability Insurance - The Contractor shall provide evidence satisfactory to
the CO of commercial (business) automobile liability insurance written on ISO form CA
00 01 10 13 (or another form with coverage at least as broad and approved by the CO in
writing) including coverage for all owned, hired, borrowed and non-owned vehicles and
equipment used by the Contractor in connection with work under this agreement, with
a minimum combined single limit of $1,000,000 for bodily injury or death and property
damage, including loss of use thereof. Such policy or policies of automobile liability
insurance shall be written on an "occurrence" (as opposed to a "claims made") basis.

Auto Physical Damage Coverage - The Contractor shall provide auto physical damage
insurance to cover "loss" to a covered "auto" or its equipment:
a) Comprehensive - Fire, lightning or explosion; theft; windstorm, hail or
earthquake; flood; mischief or vandalism; or the sinking, burning, collision or
derailment of any conveyance transporting the covered "auto".
b) Collision Coverage - Caused by: The covered "auto's" collision with another
object or the covered "auto's" overturn.

The Commercial Auto Liability policy shall be further endorsed to:
a) To the fullest extent permitted by law, provide additional insured coverage
to The Government of the District of Columbia
b) Coverage available to the additional insureds shall apply on a primary and
non-contributing basis as respects any other insurance, deductibles, or self-
insurance available to the additional insureds
c) A waiver of subrogation in favor of The Government of the District of
Columbia
d) Defense costs shall be in addition to and not erode the limits of liability
e) If applicable, include Form CA 99 48 03 06 Pollution Liability - Broadened
Coverage for Covered Autos - Business Auto, Motor Carrier, and Truckers (or
its equivalent)

3. Workers’ Compensation Insurance - The Contractor shall provide evidence satisfactory
to the CO of Workers’ Compensation insurance in accordance with the statutory
mandates of the District of Columbia or the jurisdiction in which the contract is
performed.

Employer’s Liability Insurance - The Contractor shall provide evidence satisfactory to the
CO of employer’s liability insurance as follows: $500,000 per accident for injury;
$500,000 per employee for disease; and $500,000 for policy disease limit.
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 42 of 60
The Workers Compensation and Employers Liability shall be further endorsed to:
a) Include a Waiver of Subrogation in favor of The Government of the District of
Columbia.
b) Where applicable, include United States Longshore and Harbor Workers
Compensation Act (USL&H)
c) Where applicable, include Jones Act Coverage for seamen or crew members on
an “if any” basis.
4. Network Security/Privacy (Cyber) Liability Insurance covering acts, errors, omissions,
breach of contract, and violation of any consumer protection laws arising out of
Contractor’s operations or services with a limit of $2,000,000 per claim and in the
aggregate. Such coverage shall include but not be limited to, third party and first party
coverage for loss or disclosure of any data, including personally identifiable information
and payment card information, network security failure, violation of any consumer
protection laws, unauthorized access and/or use or other intrusions, infringement of
any intellectual property rights (except patent), unintentional breach of contract,
negligence or breach of duty to use reasonable care, breach of any duty of
confidentiality, invasion of privacy, or violations of any other legal protections for
personal information, defamation, libel, slander, commercial disparagement, negligent
transmission of computer virus, or use of computer networks in connection with denial
of service attacks. Such coverage shall include regulatory defense and fines/penalties in
any jurisdiction anywhere in the world. Such coverage shall include contractual privacy
coverage for data breach response and crisis management costs that would be incurred
by Contractor on behalf of The Government of the District of Columbia in the event of a
data breach including legal and forensic expenses, notification costs, credit monitoring
costs, and costs to operate a call center. Contractor shall maintain coverage in force
during the term of this Agreement and for an extended reporting period of not less than
two (2) years after.

5. Professional Liability Insurance (Errors & Omissions) - The Contractor shall provide
Professional Liability Insurance (Errors and Omissions) to cover liability resulting from
any error or omission in the performance of professional services under this Contract.
The policy shall provide limits of $1,000,000 per claim or per occurrence for each
wrongful act and $2,000,000 annual aggregate. The Contractor warrants that any
applicable retroactive date precedes the date the Contractor first performed any
professional services for the Government of the District of Columbia and that
continuous coverage will be maintained or an extended reporting period will be
exercised for a period of at least ten years after the completion of the professional
services. Limits may not be shared with other lines of coverage.

6. Commercial Umbrella or Excess Liability - The Contractor shall provide evidence
satisfactory to the CO of commercial umbrella or excess liability insurance with
minimum limits of $5,000,000 per occurrence and $5,000,000 in the annual aggregate,
following the form and in excess of all liability policies. All liability coverages must be
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 43 of 60
scheduled under the umbrella and/or excess policy. The insurance required under this
paragraph shall be written in a form that annually reinstates all required limits.
Coverage shall be primary to any insurance, self-insurance or reinsurance maintained by
The Government of the District of Columbia and the “other insurance” provision must
be amended in accordance with this requirement and principles of vertical exhaustion.

7. Environmental Liability/Contractors Pollution Liability Insurance - The Contractor shall
provide evidence satisfactory to the CO of environmental liability insurance covering
losses caused by pollution or other hazardous conditions arising from ongoing or
completed operations of the Contractor. Such insurance shall apply to bodily injury,
property damage (including loss of use of damaged property or of property that has
been physically injured), clean-up costs, transit and non-owned disposal sites. Coverage
shall extend to defense costs and expenses incurred in the investigation, civil fines,
penalties and damages or settlements. There shall be neither an exclusion nor a
sublimit for mold or fungus-related claims. The minimum limits required under this
paragraph shall be $2,000,000 per occurrence and $2,000,000 in the annual aggregate.
If such coverage is written on a claims-made basis, the Contractor warrants that any
retroactive date applicable to coverages under the policy precedes the Contractor’s
performance of any work under the Contract and that continuous completed operations
coverage will be maintained for at least ten (10) years or an extended reporting period
shall be purchased for no less than ten (10) years after completion.

The Contractor also must furnish to the CO Owner certificates of insurance
evidencing environmental liability insurance maintained by third party
transportation and disposal site operators(s) used by the Contractor for losses
arising from facility(ies) accepting, storing or disposing hazardous materials or other
waste as a result of the Contractor’s operations. Such coverages must be
maintained with limits of at least the amounts set forth above.

The Environmental Liability policy shall be further endorsed to include The
Government of the District of Columbia as an Additional Insured.

8. Installation-Floater Insurance - For projects not involving structural alterations, the
contractor shall provide an installation floater policy with a limit equal to the Property
values being installed as part of the project. The policy shall cover property while
located at the project site, at temporary locations, or in transit; deductibles will be the
sole responsibility of the contractor.
C. PRIMARY AND NONCONTRIBUTORY INSURANCE
The insurance required herein shall be primary to and will not seek contribution from any
other insurance, reinsurance or self -insurance including any deductible or retention,
maintained by the Government of the District of Columbia.
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 44 of 60
D. DURATION. The Contractor shall carry all required insurance until all contract work is
accepted by The Government of the District of Columbia and shall carry listed coverages
for ten years for construction projects following final acceptance of the work performed
under this contract and two years for non-construction related contracts.

E. LIABILITY. These are the required minimum insurance requirements established by The
Government of the District of Columbia. However, it is understood that The
Government of the District of Columbia does not in any way represent that the
insurance or the limits of insurance specified herein are sufficient or adequate to
protect your interests or liabilities and will not in any way limit the contractor’s liability
under this contract.

F. CONTRACTOR’S PROPERTY. Contractor and subcontractors are solely responsible for
any loss or damage to their personal property, including but not limited to tools and
equipment, scaffolding, and temporary structures, rented machinery, or owned and
leased equipment. A waiver of subrogation shall apply in favor of The Government of
the District of Columbia.

G. MEASURE OF PAYMENT. The Government of the District of Columbia shall not make
any separate measure or payment for the cost of insurance and bonds. The Contractor
shall include all of the costs of insurance and bonds in the contract price.
H. NOTIFICATION. The Contractor shall ensure that all policies provide that the CO shall
be given thirty (30) days prior written notice in the event of cancellation, non-renewal,
or material changes to the extent such cancellation or material changes results in
Contractor no long complying with the above requirements. The Contractor shall
provide the CO with ten (10) days’ prior written notice in the event of non-payment of
premium. The Contractor will also provide the CO with an updated Certificate of
Insurance should its insurance coverages renew during the contract. The Government of
the District of Columbia may reasonably change the above insurance coverage
requirements during the Term by giving Contractor at least 30 days’ notice of the
change. Contractor must comply, at your expense, and deliver to the CO evidence of
compliance before the change becomes effective.

I. CERTIFICATES OF INSURANCE. The Contractor must send to CO, at least 10 days after
execution of this Agreement, certificates of insurance evidencing the required insurance
coverage and endorsements required herein. Contractor must also provide us with
evidence of renewal before the expiration date of each insurance policy. Contractor is
responsible for providing us with 30 days advanced written notice if the certificate of
insurance by the insurer has been canceled, reduced in coverage, or otherwise altered.
Certificates of insurance must reference the corresponding contract number. Evidence
of insurance shall be submitted by e mail to:
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 45 of 60
The Government of the District of Columbia
Office of Contracting and Procurement at DDOT
and mailed to the attention of:
Carol Hessler, Contracting Officer
250 M Street S.E., 7th Floor, Washington D.C. 20003
Carol.hessler@dc.gov
The CO may request and the Contractor shall promptly deliver updated certificates of
insurance, endorsements indicating the required coverages, and/or certified copies of
the insurance policies. If the insurance initially obtained by the Contractor expires prior
to completion of the contract, renewal certificates of insurance and additional insured
and other endorsements shall be furnished to the CO prior to the date of expiration of
all such initial insurance. For all coverage required to be maintained after completion,
an additional certificate of insurance evidencing such coverage shall be submitted to the
CO on an annual basis as the coverage is renewed (or replaced).
J. DISCLOSURE OF INFORMATION. The Contractor agrees that The Government of the
District of Columbia may disclose the name and contact information of its insurers to
any third party which presents a claim against The Government of the District of
Columbia for any damages or claims resulting from or arising out of work performed by
the Contractor, its agents, employees, servants or subcontractors in the performance of
this contract.

K. CARRIER RATINGS. All Contractor’s and its subcontractors’ insurance required in
connection with this contract shall be written by insurance companies with an A.M. Best
Insurance Guide rating of at least A- VII or better (or the equivalent by any other rating
agency) and licensed in the District of Columbia.
L. WARRANTIES. When applicable, the Contractor should be named as an additional
insured on the applicable manufacturer’s/distributer’s Commercial General Liability
policy using Insurance Services Office, Inc. (“ISO”) form CG 20 15 04 13 (or another
occurrence-based form with coverage at least as broad). CO should collect, review for
accuracy, and maintain all warranties for goods and services.
I.9 DISPUTES
This clause supersedes Standard Specifications Section 103.01 Article 7, “Disputes.”
All disputes arising under or relating to the contract shall be resolved as provided herein, except,
for Federal Aid Highway Program (FAHP) contracts only , disputes arising out of the labor
standards provisions of the Contract are governed by the requirements at H.10.A.9.
(a) Claims by the Contractor against the District: Claim, as used in paragraph (a) of this clause,
means a written assertion by the Contractor seeking, as a matter of right, the payment of
money in a sum certain, the adjustment or interpretation of contract terms, or other relief
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 46 of 60
arising under or relating to the Contract. A claim arising under a contract, unlike a claim
relating to that contract, is a claim that can be resolved under a contract clause that
provides for the relief sought by the claimant
(1) All claims by a Contractor against the District arising under or relating to a contract
shall be in writing and shall be submitted to the CO for a decision. The Contractor’s
claim shall contain at least the following:
(i) A description of the claim and the amount in dispute;
(ii) Data or other information in support of the claim;
(iii) A brief description of the Contractor’s efforts to resolve the dispute prior to filing
the claim; and
(iv) The Contractor’s request for relief or other action by the CO.
(2) The CO may meet with the Contractor in a further attempt to resolve the claim by
agreement.
(3) The CO shall issue a decision on any claim within 120 calendar days after receipt of
the claim. Whenever possible, the CO shall take into account factors such as the size
and complexity of the claim and the adequacy of the information in support of the
claim provided by the Contractor.
(4) The CO’s written decision shall do the following:
(i) Provide a description of the claim or dispute;
(ii) Refer to the pertinent contract terms;
(iii) State the factual areas of agreement and disagreement;
(iv) State the reasons for the decision, including any specific findings of fact, although
specific findings of fact are not required and, if made, shall not be binding in any
subsequent proceeding;
(v) If all or any part of the claim is determined to be valid, determine the amount of
monetary settlement, the contract adjustment to be made, or other relief to be
granted;
(vi) Indicate that the written document is the CO’s final decision; and
(vii) Inform the Contractor of the right to seek further redress by appealing the
decision to the Contract Appeals Board.
(5) Failure by the CO to issue a decision on a contract claim within 120 days of receipt of
the claim will be deemed to be a denial of the claim, and will authorize the
commencement of an appeal to the Contract Appeals Board as provided by D.C.
Official Code § 2-360.04.
(6) If a contractor is unable to support any part of its claim and it is determined that the
inability is attributable to a material misrepresentation of fact or fraud on the part of
the Contractor, the Contractor shall be liable to the District for an amount equal to
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 47 of 60
the unsupported part of the claim in addition to all costs to the District attributable to
the cost of reviewing that part of the Contractor’s claim. Liability under this paragraph
(a)(6) shall be determined within six (6) years of the commission of the
misrepresentation of fact or fraud.
(7) Pending final decision of an appeal, action, or final settlement, the Contractor shall
proceed diligently with performance of the Contract in accordance with the decision
of the CO.
(b) Claims by the District against the Contractor: Claim as used in paragraph (b) of this clause,
means a written demand or written assertion by the District seeking, as a matter of right,
the payment of money in a sum certain, the adjustment of contract terms, or other relief
arising under or relating to the Contract. A claim arising under a contract, unlike a claim
relating to that contract, is a claim that can be resolved under a contract clause that
provides for the relief sought by the claimant.
(1) The CO shall decide all claims by the District against a contractor arising under or
relating to a contract.
(2) The CO shall send written notice of the claim to the Contractor. The CO’s written
decision shall do the following:
(i) Provide a description of the claim or dispute;
(ii) Refer to the pertinent contract terms;
(iii) State the factual areas of agreement and disagreement;
(iv) State the reasons for the decision, including any specific findings of fact,
although specific findings of fact are not required and, if made, shall not be binding
in any subsequent proceeding;
(v) If all or any part of the claim is determined to be valid, determine the amount of
monetary settlement, the contract adjustment to be made, or other relief to be
granted;
(vi) Indicate that the written document is the CO’s final decision; and
(vii) Inform the Contractor of the right to seek further redress by appealing the
decision to the Contract Appeals Board.
(3) The CO shall support the decision by reasons and shall inform the Contractor of its
rights as provided herein.
(4) Before or after issuing the decision, the CO may meet with the Contractor to attempt
to resolve the claim by agreement.
(5) The authority contained in this paragraph (b) shall not apply to a claim or dispute for
penalties or forfeitures prescribed by statute or regulation which another District
agency is specifically authorized to administer, settle or determine.
(6) This clause shall not authorize the CO to settle, compromise, pay, or otherwise adjust
any claim involving fraud.
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 48 of 60
(c) Decisions of the CO shall be final and not subject to review unless the Contractor timely
commences an administrative appeal for review of the decision, by filing a complaint with
the Contract Appeals Board, as authorized by D.C. Official Code § 2-360.04.
(d) Pending final decision of an appeal, action, or final settlement, the Contractor shall
proceed diligently with performance of the Contract in accordance with the decision of
the CO.
I.10 PERFORMANCE AND PAYMENT SECURITY
Standard Specifications Section 102.01, Article 12(B), (C) and (D) apply to the Contract.
In the event the Contract is terminated for default, the Contractor is liable for any cost of
acquiring the remaining work that exceeds the amount of its bid, and the performance bond is
available to offset the difference.
I.11 GOVERNING LAW
This Contract, and any disputes arising out of or related to this Contract, shall be governed by,
and construed in accordance with, the laws of the District of Columbia.
I.12 SITE INVESTIGATION – CONSTRUCTION
A. The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the
nature and location of the Work, and that it has investigated and satisfied itself as to the
general and local conditions which can affect the Work or its cost, including but not limited
to:
1. conditions bearing upon transportation, disposal, handling, and storage of materials;
2. the availability of labor, water, electric power, and roads;
3. uncertainties of weather, river stages, tides, or similar physical conditions at the site;
4. the conformation and conditions of the ground;
5. the character of equipment and facilities needed preliminary to and during the
performance of the Work; and
6. all conditions related to site access, required permits, utilities coordination, and District
requirements.
B. The Contractor also acknowledges that it has satisfied itself as to the character, quality, and
quantity of surface and subsurface materials or obstacles to be encountered insofar as
this information is reasonably ascertainable from an inspection of the site, including all
exploratory work done by the District, as well as from the Drawings and Specifications made a
part of the Contract. Any failure of the Contractor to take the actions described and
acknowledged in this clause shall not relieve the Contractor from responsibility for estimating
properly the difficulty and cost of successfully performing the Work, or for proceeding to
successfully perform the Work without additional expense to the District.
C. The Contractor is solely responsible for any conclusions or interpretations made by the
Contractor based on the information made available by the District. The District assumes no
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 49 of 60
responsibility for, and Contractor is solely responsible for, any understanding based upon,
any representation made by any District officers or agents before the execution of the
Contract, unless that understanding or representation is expressly stated in the Contract.
I.13 DC HUMAN RIGHTS ACT ANTI-DISCRIMINATION CLAUSE
During the performance of the Contract, the Contractor shall comply with the DC Human Rights
Act of 1977, D.C. Official Code § 2-1401 et. seq., as amended. The Contractor shall ensure that all
subcontracts contain this requirement.
I.14 AMERICANS WITH DISABILITIES ACT REQUIREMENTS
This clause supersedes Standard Specification Section 102.10, “Employment of the Handicapped.”
Pursuant to the Rehabilitation Act of 1973, 29 U.S.C. § 701, as amended, the DC Human Rights
Act of 1977, and the Americans With Disabilities Act, the Contractor and all Subcontractors agree
not to discriminate against any person with disabilities who is qualified to perform the job. The
Contractor also agrees to take Affirmative Action to hire, advance, and treat persons with
disabilities without discrimination.
I.15 ORDER OF PRECEDENCE
This paragraph supersedes Standard Specifications Section 103.01 Article 2 “Order of
Precedence.”
The Contract Documents are complimentary, and different requirements within the Contract
Documents shall only be deemed in conflict if compliance with both cannot be achieved. In the
event of a conflict between the terms of the Contract, the Contract Documents apply in the
following order of precedence:
1. Task Orders and Modifications
2. The Contract
3. Contract Attachments, including Supplementary Specifications, Special Provisions and
Contract Drawings
4. Standard Specifications for Highways and Structures (2013)
5. Other DDOT Standard Specifications
6. Utility Standard Specifications
In addition:
7. Original scaled drawings and details have priority over other different scale drawings and de
tails; and
8. Large scale drawings and details have priority over small scale drawings and details.
I.16 STANDARD TERMS AND CONDITIONS
The following sections of the Standard Specifications, Division 100, are incorporated into this
Contract by reference. These references are not intended to be an exhaustive list of Division 100
requirements and are included simply for the convenience of the Contractor.
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 50 of 60
Section 103.01
Article 3 Changes
Article 5 Termination – Delays
Article 6 Termination – Convenience of the District
Article 10 Transfer or Assignment
Article 11 Material and Workmanship
Article 13 Superintendence by Contractor
Article 14 Permits and Responsibilities
Article 15 Indemnification
Article 16 Protection Against Trespass
Article 17 Conditions Affecting the Work
Article 19 Patent Indemnity
Article 20 Covenant Against Contingent Fees
Article 21 Appointment of Attorney
Article 22 Officials Not to Benefit
Article 23 Waiver
Article 25 Taxes
Article 26 Suspension of Work
Article 27 Safety Program
Article 28 Retention of Records
Section 107.15 Contractor’s Responsibility for the Work
Section 108.01 Subletting of Contract
Section 108.02 Notice to Proceed
Section 109.03 Extra and Force Account Work
Section 109.04 Eliminated Items
Section 109.07 Payment for Stockpiled Materials
DCKA-2024-C-0073
DC Power Line Underground (Feeder 14702/118)
Page 51 of 60
SECTION J: ATTACHMENTS
The following attachments are incorporated into the Solicitation.

Attachment
Number Document

J.1
U.S. Department of Labor Wage Determination DC20240001, Dated May 31,
2024, All wage categories in the Wage Determination apply to this contract
including Heavy Construction, Sewer and Water Lines, Paving and Incidental.
J.2 Subcontractor Approval Request Form (DDOT Form 120-KA)
J.3 Equal Employment Opportunity Information Report
J.4 DDOT Davis Bacon Compliance Requirements, Certified Payroll, And Weekly
Compliance
J.5 DDOT Monthly Equal Employment Opportunity Utilization Report
J.6 Subcontractor Payment Form
J.7 Price Schedule

TECHNICAL REQUIREMENTS
J.8 Supplementary Specifications (also referred to as “Special Provisions”)
J.9 Project Drawings
J.10 Pepco Standard Details and Drawings
J.11 Duct Certification Procedures
J.12 Duct Certification Form
J.13 DC PLUG Typical MOT Drawings
Page 70 of 77
AMENDMENT TO SOLICITATION / MODIFICATION OF
CONTRACT
1. Contract Number Page of Pages
1 1
2. Amendment/Modification Number
Amendment 001
3. Effective Date
See Box 16 C
4. Requisition/Purchase
Request No.
5. Solicitation Caption
District of Columbia Power
Underground (DC Plug Feeder
14702 and 118)
6. Issued by: Code 7. Administered by (If other than line 6)
Office of Contracting and Procurement
441 4th Street, N.W., Suite 700 South
Washington, D.C. 20001

District Department of Transportation
8. Name and Address of Contractor (No. street, city, county, state and zip
code)
9A. Amendment of Solicitation No.
DCKA-2024-B-0073
9B. Dated (See Item 11)
July 5, 2024
10A. Modification of Contractor/Order No.
Code

Facility
10B. Dated (See Item 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended. is not
extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning one (1) copy of the amendment: (b) By acknowledging receipt of this amendment on each copy of the offer
submitted; or (c) BY separate letter or fax which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGMENT
TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such may be made by letter or fax, provided
each letter or telegram makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting and Appropriation Data (If Required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTORS/ORDERS ,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14
A. This change order is issued pursuant to (Specify Authority): 27 DCMR, Chapter 36, Section 3601.2(b)
The changes set forth in Item 14 are made in the contract/order no. in item 10A.
B. The above numbered contract/order is modified to reflect the administrative changes (such as changes in paying office, appropriation
data etc.) set forth in item 14, pursuant to the authority of:
C. This supplemental agreement is entered into pursuant to authority of: 27 DCMR, Chapter 36, Section 3601.2 and mutual agreement of
the parties.
D. Other (Specify type of modification and authority):
E. IMPORTANT: Contractor is not is required to sign this document and return ( ) copy to the issuing office.
14. Description of Amendment/Modification (Organized by UCF Section headings, including solicitation/contract subject matter where feasible.)

Solicition DCKA-2024-B-0073 is hereby amended to include the following:

1. Section B.4 Notice of Subcontracting Requirements has been updated.
2. Pre-bid slides and attendee sheet has been
Except as provided herein, all terms and conditions of the document is referenced in Item 9A or 10A remain unchanged and in full force and effect.
15A. Name and Title of Signer (Type or print) 16A. Approved:
Carol Hessler
15B. Name of Contractor
(Signature of person authorized to sign)
15C. Date Signed 16B. District of Columbia

(Signature)
16C. Date Signed

7/17/2024

Page71 of 77
PreBid Meeting Attendees

Sarah Kamins - DC PLUG PMC
James G. Gittens, DC PLUG PMC
Mike Hillard, Anchor Construction
Kathy Poole, DC PLUG PMC
Ronald Williams, DDOT
Cesar Barreto, DDOT
Joseph McElwee - Anchor Construction
Jose Cambronero, Capitol paving
James Payne MCKINC PMC
Carol Hessler
Rickie Spivey
Page 72 of 77
AMENDMENT TO SOLICITATION / MODIFICATION OF
CONTRACT
1. Contract Number Page of Pages
1 1
2. Amendment/Modification Number
Amendment 002
3. Effective Date
See Box 16 C
4. Requisition/Purchase
Request No.
5. Solicitation Caption
District of Columbia Power
Underground (DC Plug Feeder
14702 and 118)
6. Issued by: Code 7. Administered by (If other than line 6)
Office of Contracting and Procurement
441 4th Street, N.W., Suite 700 South
Washington, D.C. 20001

District Department of Transportation
8. Name and Address of Contractor (No. street, city, county, state and zip
code)
9A. Amendment of Solicitation No.
DCKA-2024-B-0073
9B. Dated (See Item 11)
July 5, 2024
10A. Modification of Contractor/Order No.
Code

Facility
10B. Dated (See Item 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended. is not
extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning one (1) copy of the amendment: (b) By acknowledging receipt of this amendment on each copy of the offer
submitted; or (c) BY separate letter or fax which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGMENT
TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such may be made by letter or fax, provided
each letter or telegram makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting and Appropriation Data (If Required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTORS/ORDERS ,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14
A. This change order is issued pursuant to (Specify Authority): 27 DCMR, Chapter 36, Section 3601.2(b)
The changes set forth in Item 14 are made in the contract/order no. in item 10A.
B. The above numbered contract/order is modified to reflect the administrative changes (such as changes in paying office, appropriation
data etc.) set forth in item 14, pursuant to the authority of:
C. This supplemental agreement is entered into pursuant to authority of: 27 DCMR, Chapter 36, Section 3601.2 and mutual agreement of
the parties.
D. Other (Specify type of modification and authority):
E. IMPORTANT: Contractor is not is required to sign this document and return ( ) copy to the issuing office.
14. Description of Amendment/Modification (Organized by UCF Section headings, including solicitation/contract subject matter where feasible.)

Solicition DCKA-2024-B-0073 is hereby amended to include the following:

1. All bid are due 2 PM on August 5, 2024.
2. Bid opening will be at 3 PM on August 5, 2024.
Except as provided herein, all terms and conditions of the document is referenced in Item 9A or 10A remain unchanged and in full force and effect.
15A. Name and Title of Signer (Type or print) 16A. Approved:
Carol Hessler
15B. Name of Contractor
(Signature of person authorized to sign)
15C. Date Signed 16B. District of Columbia

(Signature)
16C. Date Signed

07/30/24

Page 73 of 77
AMENDMENT TO SOLICITATION / MODIFICATION OF
CONTRACT
1. Contract Number Page of Pages
1 1
2. Amendment/Modification Number
Amendment 003
3. Effective Date
See Box 16 C
4. Requisition/Purchase
Request No.
5. Solicitation Caption
District of Columbia Power
Underground (DC Plug Feeder
14702 and 118)
6. Issued by: Code 7. Administered by (If other than line 6)
Office of Contracting and Procurement
441 4th Street, N.W., Suite 700 South
Washington, D.C. 20001

District Department of Transportation
8. Name and Address of Contractor (No. street, city, county, state and zip
code)
9A. Amendment of Solicitation No.
DCKA-2024-B-0073
9B. Dated (See Item 11)
July 5, 2024
10A. Modification of Contractor/Order No.
Code

Facility
10B. Dated (See Item 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended. is not
extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning one (1) copy of the amendment: (b) By acknowledging receipt of this amendment on each copy of the offer
submitted; or (c) BY separate letter or fax which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGMENT
TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such may be made by letter or fax, provided
each letter or telegram makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting and Appropriation Data (If Required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTORS/ORDERS ,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14
A. This change order is issued pursuant to (Specify Authority): 27 DCMR, Chapter 36, Section 3601.2(b)
The changes set forth in Item 14 are made in the contract/order no. in item 10A.
B. The above numbered contract/order is modified to reflect the administrative changes (such as changes in paying office, appropriation
data etc.) set forth in item 14, pursuant to the authority of:
C. This supplemental agreement is entered into pursuant to authority of: 27 DCMR, Chapter 36, Section 3601.2 and mutual agreement of
the parties.
D. Other (Specify type of modification and authority):
E. IMPORTANT: Contractor is not is required to sign this document and return ( ) copy to the issuing office.
14. Description of Amendment/Modification (Organized by UCF Section headings, including solicitation/contract subject matter where feasible.)

Solicition DCKA-2024-B-0073 is hereby amended to include the following:

1. To extend the bid opening to August 16, 2024, bids are due at 2PM bid opening will be at 3PM.
2. To Clarify the following items {see attached)
Except as provided herein, all terms and conditions of the document is referenced in Item 9A or 10A remain unchanged and in full force and effect.
15A. Name and Title of Signer (Type or print) 16A. Approved: signing for:
Carol Hessler
15B. Name of Contractor
(Signature of person authorized to sign)
15C. Date Signed 16B. District of Columbia

(Signature)
16C. Date Signed

8/2/2024

Page 74 of 77
1. No product information is provided for bike racks item #285. And please
provide detail of the buffer as required by the item description.
Item #285 is for the reinstallation of existing bike racks and buffer. The buffer refers to the
existing wheel stops around the bike racks. The line item shall be revised to read “Incidental
Construction Special Item - EACH - Reinstall Salvaged Bike Rack and Buffer” for clarity.
Details for reinstallation is in the Gold Book.

2. No detail, plan or special provision provided for the replacement of the
wooden retaining wall bid item #290. Please provide details and location.
The location of the wall is on sheet HD-29. Additional detail for wall replacement will be
provided.

3. Supplementary specification is provided for Stone/Granite Pavers (J.38) and
Remove and replace chain link fence (J.39) but no bid items are listed on the bid
form. Are these two items required for this project?
Stone/Granite Pavers and the removal and replacement of chain link fence are not required
for this project.
Page 75 of 77
AMENDMENT TO SOLICITATION / MODIFICATION OF
CONTRACT
1. Contract Number Page of Pages
1 1
2. Amendment/Modification Number
Amendment 005
3. Effective Date
See Box 16 C
4. Requisition/Purchase
Request No.
5. Solicitation Caption
District of Columbia Power
Underground (DC Plug Feeder
14702 and 118)
6. Issued by: Code 7. Administered by (If other than line 6)
Office of Contracting and Procurement
441 4th Street, N.W., Suite 700 South
Washington, D.C. 20001

District Department of Transportation
8. Name and Address of Contractor (No. street, city, county, state and zip
code)
9A. Amendment of Solicitation No.
DCKA-2024-B-0073
9B. Dated (See Item 11)
July 5, 2024
10A. Modification of Contractor/Order No.
Code

Facility
10B. Dated (See Item 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended. is not
extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning one (1) copy of the amendment: (b) By acknowledging receipt of this amendment on each copy of the offer
submitted; or (c) BY separate letter or fax which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGMENT
TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such may be made by letter or fax, provided
each letter or telegram makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting and Appropriation Data (If Required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTORS/ORDERS ,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14
A. This change order is issued pursuant to (Specify Authority): 27 DCMR, Chapter 36, Section 3601.2(b)
The changes set forth in Item 14 are made in the contract/order no. in item 10A.
B. The above numbered contract/order is modified to reflect the administrative changes (such as changes in paying office, appropriation
data etc.) set forth in item 14, pursuant to the authority of:
C. This supplemental agreement is entered into pursuant to authority of: 27 DCMR, Chapter 36, Section 3601.2 and mutual agreement of
the parties.
D. Other (Specify type of modification and authority):
E. IMPORTANT: Contractor is not is required to sign this document and return ( ) copy to the issuing office.
14. Description of Amendment/Modification (Organized by UCF Section headings, including solicitation/contract subject matter where feasible.)

Solicition DCKA-2024-B-0073 is hereby amended to include the following:

1. Clarify detail in response to bidder question #2 regarding the replacement of the existing wall found on sheet HD-29. (See
attached)
Except as provided herein, all terms and conditions of the document is referenced in Item 9A or 10A remain unchanged and in full force and effect.
15A. Name and Title of Signer (Type or print) 16A. Approved:
Carol Hessler
15B. Name of Contractor
(Signature of person authorized to sign)
15C. Date Signed 16B. District of Columbia

(Signature)
16C. Date Signed

8/15/24

-----------FENCE, SEE NOTE 1
R;1" R;1" 6" LR;l"
R ;1 " 1/2" PREFORMED
XPANSION JOINT
3 SEE NOTE 4 1 /2" PREFORMED
Ll
.
EXPANSION JOINT
'b8c3S " SEE NOTE 4
goaoc):;i
X / SIQ,EWAL <(
:::,
ffi7Jtn ' 0u o« o00
------. _IJ//// ///;/(Wi \«< Ll " o c;i I
0
BI ORE TENT I 0 •
FACILITY //_ •
va , /"<'« " " /\,l ' • --+
DB0 );1515S0'1:lro o a 'b80S 'b80S 'b8c5S 'b8c5S(
cilgo c//,DoD8 ooD0uo\? Cll'OS' ----f goCJoCJC) goC)o\\C) goC)o\\C) goC)o\\( ,
¢5Q)3a o()Y 'b0o QgoaoCJ( - IB
0 9go
!
Ogc5'.go ogo;go Ogc5'. "'
0
«««IB«««'i GfB?J GfB?i ' ---- '-
B E N C H1 ?c:@»,/v?}f§!,}J§)FPOIB es;,dQO?f!iFf,P-' >«};§§;§'\
, «;f'C«""'-VY -------' ,v('</0-'­
'' )/;v« 20' ">V' 18'
SEE NOTE 4 SEE NOTE 4

L-WALL (FLUSH) L-WALL (WITH REVEAL)

NOTES:
/. WHEN FLUSH WALLS ARE SELECTED, TYPICALLY IN HIGH-VOLUME PEDESTRIAN AREAS,
PROVIDE RAILING OR FENCE PER PLAN.

2. WHEN WALLS WITH REVEALS ARE USED, TYPICALLY IN LOY-VOLUME PEDESTRIAN AREAS,
PROVIDE BREAKS IN REVEAL AS SHOWN ON PLANS TO ALLOW FOR SIDEWALK RUNOFF INTO
STORMWATER MANAGEMENT FACILITY.

3. CONCRETE SHALL BE CLASS E: FINISH ALL EXPOSED CONCRETE SURFACES.

4. BASE MAY BE REDUCED TO 15' WIDTH IF CONCRETE 15 USED IN THE HATCHED AREA.

5. REFER TO DESIGN AND ENGINEERING MANUAL SECTION '33.14.5.6 SAFETY AND ACCESS'
FOR PEDESTRIAN SAFETY DESIGN REQUIREMENTS.

6. EXPANSION JOINTS SHALL BE PLACED AT MAXIMUM 90
FOOT INTERVAL. CONTRACTION JOINTS SHALL BE FORMED
OR SAWED AT 30 FOOT MAXIMUM INTERVAL BETWEEN EXPANSION JOINTS. WHERE ADJACENT
TO CURB, SIDEWALK OR CONCRETE PAVEMENT, JOINTS SHALL LINE UP.

RECOMMENDED:

DEPUTY CHIEF ENGINEER
BIORETENTION FACILITY
SIDEWALK SIDE EDGE
TREATMENT
DISTRICT OF COLUMBIA
DEPARTMENT OF TRANSPORTATION

DWG. NO. 621.32

DATE APPR,
APPROVED:

CHIEF TRANSPORTATION ENGINEER
REVISED
ISSUED:
REFERENCE
Page 76 of 77

AMENDMENT TO SOLICITATION / MODIFICATION OF
CONTRACT
1. Contract Number Page of Pages
1 1
2. Amendment/Modification Number
Amendment 004
3. Effective Date
See Box 16 C
4. Requisition/Purchase
Request No.
5. Solicitation Caption
District of Columbia Power
Underground (DC Plug Feeder
14702 and 118)
6. Issued by: Code 7. Administered by (If other than line 6)
Office of Contracting and Procurement
441 4th Street, N.W., Suite 700 South
Washington, D.C. 20001

District Department of Transportation
8. Name and Address of Contractor (No. street, city, county, state and zip
code)
9A. Amendment of Solicitation No.
DCKA-2024-B-0073
9B. Dated (See Item 11)
July 5, 2024
10A. Modification of Contractor/Order No.
Code

Facility
10B. Dated (See Item 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended. is not
extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning one (1) copy of the amendment: (b) By acknowledging receipt of this amendment on each copy of the offer
submitted; or (c) BY separate letter or fax which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGMENT
TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such may be made by letter or fax, provided
each letter or telegram makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting and Appropriation Data (If Required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTORS/ORDERS ,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14
A. This change order is issued pursuant to (Specify Authority): 27 DCMR, Chapter 36, Section 3601.2(b)
The changes set forth in Item 14 are made in the contract/order no. in item 10A.
B. The above numbered contract/order is modified to reflect the administrative changes (such as changes in paying office, appropriation
data etc.) set forth in item 14, pursuant to the authority of:
C. This supplemental agreement is entered into pursuant to authority of: 27 DCMR, Chapter 36, Section 3601.2 and mutual agreement of
the parties.
D. Other (Specify type of modification and authority):
E. IMPORTANT: Contractor is not is required to sign this document and return ( ) copy to the issuing office.
14. Description of Amendment/Modification (Organized by UCF Section headings, including solicitation/contract subject matter where feasible.)
Solicition DCKA-2024-B-0073 is hereby amended to include the following:

1. To extend the bid opening to August 22, 2024, bids are due at 2PM bid opening will be at 3PM.
Except as provided herein, all terms and conditions of the document is referenced in Item 9A or 10A remain unchanged and in full force and effect.
15A. Name and Title of Signer (Type or print) 16A. Approved:
Carol Hessler
15B. Name of Contractor
(Signature of person authorized to sign)
15C. Date Signed 16B. District of Columbia

(Signature)
16C. Date Signed

8/14/24