Proposed Contract with Smoot Construction Company of Washington, DC to Contract No. DCAM-23-CS-RFP-0016

Proposed Contract with Smoot Construction Company of Washington, DC to Contract No. DCAM-23-CS-RFP-0016

Budget Education
Active

The official status still shows this bill as active or still awaiting another formal step.

Sponsor
at the request of the Mayor
Last action
2025-12-02
Official status
Deemed Approved
Effective date
Not listed

Plain English Breakdown

The candidate explanation included details about students and staff at Brent Elementary School being affected, which is not directly supported by the provided official source material.

Proposed Contract with Smoot Construction Company

This bill proposes to modify an existing contract between the District of Columbia and Smoot Construction Company for modernizing Brent Elementary School, increasing the budget from $14,208,101 to $87,495,111.

What This Bill Does

  • Increases the total amount of money available in the contract from $14,208,101 to $87,495,111.
  • Extends services under the contract to include design-build work for both renovation and new construction at Brent Elementary School.
  • Sets a completion date of July 15, 2027, for the project.

Who It Names or Affects

  • The District of Columbia government
  • Smoot Construction Company

Terms To Know

Design-Build Services
A process where one company is responsible for both designing and building a project.
Guaranteed Maximum Price (GMP)
The maximum amount the contractor can charge for completing the work, agreed upon in advance.

Limits and Unknowns

  • It is unclear if there are any potential delays or issues that could affect the completion date.

Bill History

  1. 2025-12-02 Council of the District of Columbia LIMS

    Retained by the Council with comments from the Committee on Facilities

  2. 2025-12-01 Council of the District of Columbia LIMS

    CA26-0516 Introduced by Chairman Mendelson at Office of the Secretary

Official Summary Text

Proposed Contract with Smoot Construction Company of Washington, DC to Contract No. DCAM-23-CS-RFP-0016

Current Bill Text

Read the full stored bill text
MURIEL BOWSER
MAYOR

December 1, 2025

The Honorable Phil Mendelson
Chairman
Council of the District of Columbia
John A. Wilson Building
1350 Pennsylvania Avenue, NW, Suite 504
Washington, DC 20004

Dear Chairman Mendelson:

Pursuant to section 451 of the District of Columbia Home Rule Act (D.C. Official Code § 1 -
204.51) and section 202 of the Procurement Practices Reform Act of 2010 (D.C. Official Code §
2-352.02), enclosed for consideration and approval by the Council of the District of Columbia is
proposed Modification No. 3 to Contract No. DCAM-23-CS-RFP-0016 with Smoot Construction
Company of Washington, DC (“Smoot”). If approved, Modification No. 3 will increase the
contract’s not-to-exceed amount by $73,287,010, from $14,208,101 to $87,495,111.

The underlying contract was deemed approved by Council on May 3, 2024, as CA25 -0692, as an
early start agreement to complete a preliminary scope of work including design and permitting for
the modernization of Brent Elementary School.

Under proposed Modification No. 3, Smoot will provide design-build services for both renovation
and new construction of the existing facility to increase the square footage required to bring the
property in line with District of Columbia Public Schools spe cifications. The substantial
completion date for the project is July 15, 2027.

My administration is available to discuss any questions you may have regarding the proposed
modification. In order to facilitate a response to any questions you may have, please contact Delano
Hunter, Director, Department of General Services (“DGS”), or ha ve your staff contact Xavier
Beltran, Interim Chief Procurement Officer, DGS, at (202) 727-2800.

I look forward to the Council’s favorable consideration of this contract modification.

Sincerely,

Muriel Bowser

Department of General Services 3924 Minnesota Avenue, NE, Washington D.C. 20019
Contracts & Procurement

Pursuant to section 202(c) of the Procurement Practices Reform Act of 2010, as amended, D.C.
Official Code § 2-352.02(c), the following contract summary is provided:

COUNCIL CONTRACT SUMMARY
(Standard)

Modification No. 3 to Design-Build Agreement for Brent Elementary School Modernization

(A) Contract Number: DCAM-23-CS-RFP-0016
Modification No. 3

Contractor: SMOOT Construction Company of Washington,
DC

Proposed Increased Contract Amount
via Modification No. 3: $73,287,010.00

Total Contract Amount (Final
Guaranteed Maximum
Price (“GMP”)): $87,495,111.00

Unit and Method of Compensation: Progress payments on a monthly basis

Term of Contract: December 8, 2023 (date of execution of the Letter
Contract by the Department) through July 15,
2027 (“Substantial Completion Date”) with an
Administrative Term of March 15, 2028.

Type of Contract: Cost Plus Fixed Fee with a GMP

Source Selection Method: Competitive Request for Proposals

(B) For a contract containing option periods, the contract amount for the base period and for
each option period. If the contract amount for one or more of the option periods differs
from the amount for the base period, provide an explanation of the reason for the
difference:

Not applicable.

(C) The goods or services to be provided, the methods of delivering goods or services, and any
significant program changes reflected in the proposed contract:
DCAM-23-CS-RFP-0016
Brent Elementary School Modernization
Page 2 of 7

Department of General Services 3924 Minnesota Avenue, NE, Washington D.C. 20019

The Department of General Services (the “Department”) engaged SMOOT Construction
Company of Washington, DC (the “Contractor”) to provide design- build services required for
an approximately 94,000 square f oot school facility for Brent Elementary School. The
Contractor shall design and construct a combination of renovation of the existing facility and
new construction to increase the existing footprint to accommodate the square footage required
to bring the property in line with District of Columbia Public Schools (“DCPS”) specifications.
The Project shall be designed in such a way as to incorporate, at a minimum, LEED for Schools
– Gold principles and achieve net zero strategies. The substantial completion of the Project shall
occur on or by July 15, 2027.

The underlying Contract was deemed approved by the Council on May 3, 2024, as CA25- 0692
with a Not -to-Exceed (“NTE”) amount of $5,940,809.00. Modification No. 1 was a $0
modification to replace key personnel. Modification No. 2 to the Contract was deemed approved
by the Council on February 14, 2025, as CA26- 0039, as an early start agreement No. 2 (“ESA
2”) to fund the foundation to trade grade activities, including structural concrete, helical piles,
site work, demolition, and underground site utilities. The ESA 2 funding also includes general
conditions, insurance, performance and payment bonds, partial funding for long lead items, and
the balance amounts for phase one playground construction. Modification No. 2 increased the
Contract’s NTE amount by $8,267,292.00, from $5,940,809.00 to $14,208,101.00.

The Department now seeks Council approval to execute the proposed modification to establish
the Guaranteed Maximum Price (“GMP”). If approved, Modification No. 3 will establish the
final GMP of $87,495,111.00, thereby increasing the Contract’s value by $73,287.010.00 (from
$14,208,101.00 to $87,495,111.00), with a GMP of $ 87,495,111.00. As the proposed
Modification No. 3 would increase the Contract value by more than $1 million, Council approval
is required for this contract action.

(D) The selection process, including the number of offerors, the evaluation criteria, and the
evaluation results, including price, technical or quality, and past performance
components:

The underlying Contract was competitively bid and previously submitted to and approved by the
Council as (CA25-0692) on May 3, 2024.

(E) A description of any bid protest related to the award of the contract, including whether
the protest was resolved through litigation, withdrawal of the protest by the protestor, or
voluntary corrective action by the District. Include the identity of the protestor, the
grounds alleged in the protest, and any deficiencies identified by the District as a result of
the protest:

The award of the Contract was not protested.

DCAM-23-CS-RFP-0016
Brent Elementary School Modernization
Page 3 of 7

Department of General Services 3924 Minnesota Avenue, NE, Washington D.C. 20019
(F) A description of any other contracts the proposed contractor is currently seeking or
holds with the District:

The Contractor is currently involved in several District projects and is in pursuit of many other
District projects. The list of projects is provided as Exhibit A.

(G) The background and qualifications of the proposed contractor, including its organization,
financial stability, personnel, and performance on past or current government or private
sector contracts with requirements similar to those of the proposed contract:

The Contractor is based in Washington, DC, and is a CBE and a general contractor specializing
in construction management, general contracting, and design- build services. The Contractor
has successfully completed multiple school modernization projects for DGS, including:

1. Dunbar Senior High School Modernization (DGS/DCPS);
2. Roosevelt High School Modernization (DGS/DCPS);
3. Marie Reed Elementary School and Community Center (DGS/DCPS);
4. H.D. Cooke Elementary School (DGS/DCPS); and
5. Kramer Middle School (DGS/DCPS).

The Contractor possesses the financial stability to successfully perform the Project and has
provided a staffing plan for the Project, which has been reviewed and approved by the
Department. The Contractor has been determined responsible in accordance with 27 DCMR
4706.1.

(H) A summary of the subcontracting plan required under section 2346 of the Small, Local,
and Disadvantaged Business Enterprise Development and Assistance Act of 2005, as
amended, D.C. Official Code § 2-218.01 et seq. (“Act”), including a certification that the
subcontracting plan meets the minimum requirements of the Act and the dollar volume
of the portion of the contract to be subcontracted, expressed both in total dollars and as a
percentage of the total contract amount:

The Contractor is a certified business enterprise in accordance with the Act (CBE Number:
LXR20781062027). Pursuant to D.C. Official Code § 2- 218.46(d-1), the Contractor shall
submit a detailed subcontracting plan to DSLBD that meets the requirements of D.C. Official
Code § 2-218.46(d), before entering into a guaranteed maximum price:

Contract’s NTE Dollar Value: $87,495,111.00
Subcontracting Requirement %: 35%
CBE Self-Performed Amount: $5,249,706.66
Subcontracting Plan Required Dollar Value $28,785,891.52
Subcontracting Plan Actual Dollar Value $33,564,229.00

DCAM-23-CS-RFP-0016
Brent Elementary School Modernization
Page 4 of 7

Department of General Services 3924 Minnesota Avenue, NE, Washington D.C. 20019
(I) Performance standards and the expected outcome of the proposed contract:

The Contractor is required to provide all design, preconstruction, and construction services, as
well as all other services necessary to substantially complete the Project no later than July 15,
2027. In general, the Contractor must perform the requirements contained in the Contract and
meet or exceed the performance standards therein. The Contractor is subject to liquidated
damages of $2,500 per day of delay for failure to timely achieve substantial completion of the
Project. The Contract also provides a disincentive fee of $25,000 for the replacement of key
personnel without the Department’s prior approval and not as a penalty, to reimburse the
Department for its administrative costs arising from the Contractor’s failure to provide the key
personnel.

(J) The amount and date of any expenditure of funds by the District pursuant to the contract
prior to its submission to the Council for approval:

Not applicable.

(K) A certification that the proposed contract is within the appropriated budget authority for
the agency for the fiscal year and is consistent with the financial plan and budget adopted
in accordance with D.C. Official Code §§ 47-392.01 and 47-392.02:

The Office of the Chief Financial Officer has certified that the proposed Contract’s GMP and
NTE amounts are consistent with the Department’s budget and that adequate funds are available
in the Department’s budget in accordance with D.C. Official Code §§ 47-392.01 and 47-392.02.
The applicable Fiscal Sufficiency certification accompanies this Council Package.

(L) A certification that the contract is legally sufficient, including whether the proposed
contractor has any pending legal claims against the District:

The proposed Modification No. 3 has been deemed legally sufficient by the Department’s
Office of the General Counsel, and the Contractor does not appear to have any current pending
legal claims against the District.

(M) A certification that the Citywide Clean Hands database indicates that the proposed
contractor is current with its District taxes. If the Citywide Clean Hands Database
indicates that the proposed contractor is not current with its District taxes, either: (1) a
certification that the contractor has worked out and is current with a payment schedule
approved by the District; or (2) a certification that the contractor will be current with its
District taxes after the District recovers any outstanding debt as provided under D.C.
Official Code § 2-353.01(b):

The Citywide Clean Hands database indicates that the Contractor is in compliance with the
Government of the District of Columbia tax laws and regulations. The applicable Clean Hands
certification for the Contractor accompanies this Council Package.
DCAM-23-CS-RFP-0016
Brent Elementary School Modernization
Page 5 of 7

Department of General Services 3924 Minnesota Avenue, NE, Washington D.C. 20019

(N) A certification from the proposed contractor that it is current with its federal taxes, or has
worked out and is current with a payment schedule approved by the federal government:

The Contractor has certified that it is current with its federal tax laws.

(O) The status of the proposed contractor as a certified local, small, or disadvantaged business
enterprise as defined in the Small, Local, and Disadvantaged Business Enterprise
Development and Assistance Act of 2005, as amended; D.C. Official Code § 2-218.01 et
seq.:

According to the DSLBD website, the Contractor is a certified Local Business Enterprise and
Resident Owned Business. The Contractor’s CBE Number is LXR20781062027, with an
expiration date of June 13, 2027.

(P) Other aspects of the proposed contract that the Chief Procurement Officer considers
significant:

None.

(Q) A statement indicating whether the proposed contractor is currently debarred from
providing services or goods to the District or federal government, the dates of the
debarment, and the reasons for debarment:

The Contractor is not debarred from providing services to the Government of the District of
Columbia or the Federal Government according to the Office of Contracts & Procurement’s
Excluded Parties List and the Federal Government’s Excluded Parties List.

(R) Any determination and findings issues relating to the contract’s formation, including any
determination and findings made under D.C. Official Code § 2-352.05 (privatization
contracts):

Not applicable.

(S) Where the contract, and any amendments or modifications, if executed, will be made
available online:

The Contract award and the Contract are available on the Department’s website. A copy of the
proposed modification will be made available on the Department’s website upon approval.

(T) Where the original solicitation, and any amendments or modifications, will be made
available online:

The original solicitation and any amendments were posted on the Department’s website.
DCAM-23-CS-RFP-0016
Brent Elementary School Modernization
Page 6 of 7

Department of General Services 3924 Minnesota Avenue, NE, Washington D.C. 20019

(U) (1) A certification that the proposed contractor has been determined not to be in violation
of section 334a of the Board of Ethics and Government Accountability Establishment and
Comprehensive Ethics Reform Amendment Act of 2011, D.C. Official Code § 1-1163.34a;
and (2) A certification from the proposed contractor that it currently is not and will not
be in violation of section 334a of the Board of Ethics and Government Accountability
Establishment and Comprehensive Ethics Reform Amendment Act of 2011, D.C. Official
Code § 1-1163.34a:

Based upon a certification from the Contractor, the Contractor has been determined not to be
in violation of D.C. Official Code § 1-1163.34a; and will not be in violation of D.C. Official
Code § 1-1163.34a.

Department of General Services 3924 Minnesota Avenue, NE, Washington D.C. 20019

Exhibit A

Contracts that SMOOT Construction Company of Washington, DC, Currently Holds with The
District Agency:

Contract Number Project Caption Project Value
1. DCAM-22-CS-RFP-0019 CMAR Services for DC Infrastructure Academy at
Spingarn High School
$55,000,000.00
2. DCAM-23-CS-RFP-0003 DB for Thomas ES Modernization $72,000,000.00
3. DCAM-21-CS-RFP-0002 CMAR Services for Joy Evans Therapeutic
Recreation Center and Pool
$38,644,206.00
4. DCAM-21-CS-RFP-0007 CMAR Services for Fort DuPont Ice Arena $33,593,674.00
5. DCAM-23-CS-RFP-0016 DB Brent ES Modernization $82,000,000.00
6. GF-2023-R-0029 DB Lamond Riggs Community College
Modernization
$36,200,000.00

Projects that SMOOT Construction Company of Washington, DC is Currently Seeking with
The District Agency:

Contract Number Project Caption Project Value
NA NA NA

1101 4th Street, SW
Washington, DC 20024
Date of Notice: November 19, 2025 L0015231253Notice Number:
FEIN: **-***4741
Case ID: 18780372

Government of the District of Columbia
Office of the Chief Financial Officer
Office of Tax and Revenue
SMOOT CONSTRUCTION COMPANY OF WASHINGTON DC
3939 WISCONSIN AVENUE NW
WASHINGTON DC 20016

Branch Chief, Collection and Enforcement Administration
Authorized By Melinda Jenkins
To validate this certificate, please visit MyTax.DC.gov. On the MyTax DC homepage, click the
“Validate a Certificate of Clean Hands” hyperlink under the Clean Hands section.
CERTIFICATE OF CLEAN HANDS
As reported in the Clean Hands system, the above referenced individual/entity has no outstanding
liability with the District of Columbia Office of Tax and Revenue or the Department of Employment
Services. As of the date above, the individual/entity has complied with DC Code § 47-2862, therefore
this Certificate of Clean Hands is issued.
TITLE 47. TAXATION, LICENSING, PERMITS, ASSESSMENTS, AND FEES
CHAPTER 28 GENERAL LICENSE
SUBCHAPTER II. CLEAN HANDS BEFORE RECEIVING A LICENSE OR PERMIT
D.C. CODE § 47-2862 (2006)
§ 47-2862 PROHIBITION AGAINST ISSUANCE OF LICENSE OR PERMIT
1101 4th Street SW, Suite W270, Washington, DC 20024/Phone: (202) 724-5045/MyTax.DC.gov

COPY

Department of General Services 3924 Minnesota Avenue, NE, Washington D.C. 20019

Contracts & Procurement

Memorandum

To: Delano Hunter
Director

From: Antoinette Hudson - Beckham
Agency Fiscal Officer

Reference: Proposed Modification No. 3 to Contract No. DCAM-23-CS-RFP-0016
Design-Build Services for Brent Elementary School Modernization

Date: November 17, 2025

Subject: Fiscal Sufficiency Review

In my capacity as the Agency Fiscal Officer of the Department of General Services (the “Department”), I hereby state that
Modification No. 3 (GMP Amendment) to the Agreement for Design -Build Services for Brent Elementary School
Modernization (DCAM-23-CS-RFP-0016), with SMOOT Construction of Company of Washington, DC, in the amount
of $87,495,111.00, is consistent with the Department’s current budget and that adequate funds are available in the budget
for the expenditure.

Per the Department of General Services Contracts & Procurement (“C&P”) team, the underlying Contract was deemed
approved by the Council on May 3, 2024, as CA25 -692, with an initial Not -to-Exceed amount of $5,940,809.00
($995,000.00 Letter Contract amount + $4,945,809.00 Early Start Agreement #1). Additionally, Modification No. 2, for
additional early release work, was deemed approved by the Council on February 14, 2025, as CA26-0039, and increased
the Not-to-Exceed amount by $8,267,292.00 to $14,208,101.00 ($5,940,809.00+$8,267,292.00) as Early Start Agreement
#2.

The proposed Modification No. 3 in the amount of $73,287,010.00 would establish the guaranteed maximum price (the
“GMP”), increasing the Contract NTE amount to $87,495,111.00 ($14,208,101.00+$73,287,010.00).

While funding in the amount of $87,495,111.00 is being approved for capital-eligible items only, there is an ineligible
amount of $1,377,447.88 listed in Exhibit H of the Contract. See the FY27 Non-Capital column and associated items.
These items are ineligible for capital expenditure, per the District Guidelines. The goods/services are needed for
FY2027. There should be no purchases, commitments and expenditures for these items, until operating funds are
available via a purchase order for the same amount. In no event shall the Contractor be entitled to perform any work
against these items unless authorized in advance and in writing by a duly authorized DGS Contracting Officer through
a modification of the contract. Unless and until such modification is exec uted by a duly authorized DGS Contracting
Officer, the Contractor will be limited to capital-funded purchase orders (“POs”) in the amount of $86,117,663.12 for
the capital eligible work authorized by this contract modification. For the avoidance of confusi on, if the Contractor
performs any work with the ineligible items in the amount of $1,377,447.88, as outlined in Exhibit H, without express
written authorization by a duly authorized DGS Contracting Officer, the Contractor does so at its own risk.
DCAM-23-CS-RFP-0016
Brent Elementary School Modernization

Page 2 of 10

Department of General Services 3924 Minnesota Avenue, NE, Washington D.C. 20019
The Department of General Services (DGS – Implementing AGY) has $87,495,111.00 in the District of Columbia Public
Schools (DCPS – Owner AGY) cumulative capital budget authority balance. $57,208,101.00 is funded through FY2026.
$30,287,010.00 is pending the FY2027 capital budget load for the Brent ES Modernization project - 100246. Per the
approved FY2026 – FY2031 CIP, Brent ES Modernization capital project will receive $34,253,523.00 in FY2027.

The SOAR/PASS information is attached/below.

________________________________

Antoinette Hudson Beckham
Agency Fiscal Officer
Department of General Services

Project Name Project
Number
Fund
Detail AY Imp
AGY
Owner
AGY RQ/PO Amount Comments
AM0.TB137C.BRENT ES
MODERNIZATION 100246 3030300 n/a AM0 GA0 PO700998 $995,000.00 Letter Contract
AM0.TB137C.BRENT ES
MODERNIZATION 100246 3030300 n/a AM0 GA0 PO707742 $4,945,809.00 ESA #1
AM0.TB137C.BRENT ES
MODERNIZATION 100246 3030300 n/a AM0 GA0 PO722880 $8,267,292.00 ESA #2
AM0.TB137C.BRENT ES
MODERNIZATION 100246 3030300 n/a AM0 GA0 RK316064 $43,000,000.00
Proposed Mod #3
FY26 Capital
Portion of
$73,287,010.00
AM0.TB137C.BRENT ES
MODERNIZATION 100246 3030300 n/a AM0 GA0 RK316068 $28,909,562.12
Proposed Mod #3
FY27 Capital
Portion of
$73,287,010.00
AM0.TB137C.BRENT ES
MODERNIZATION
100246 3030300 n/a AM0 GA0 RK316069 $1,377,447.88
Proposed Mod #3
FY27 Non-Capital
Portion of
$73,287,010.00.
Pending the
approval of a
reverse capital
paygo to operating
repro in FY27.
TOTAL $87,495,111.00
for AHB

Department of General Services 3924 Minnesota Avenue, NE, Washington D.C. 20019
Contracts & Procurement

OFFICE OF THE GENERAL COUNSEL

MEMORANDUM

TO: Tomás Talamante
Director, Office of Policy and Legislative Affairs

FROM: Kristen Walp
Senior Assistant General Counsel

SUBJECT: Legal Sufficiency Certification

Proposed Modification No. 3 to the Design- Build Services Agreement for Brent
Elementary School Modernization
Contract Number: DCAM-23-CS-RFP-0016
Contractor: SMOOT Construction Company of Washington, DC

DATE: November 18, 2025

This is to certify that this Office has reviewed the above-referenced proposed Modification
No. 3 and has found it to be legally sufficient, subject to submission of: (i) any required
materials and Council approval; (ii) Council’s approval of the same; and (iii) a Fiscal
Certification issued by the Department of General Services’ Agency Fiscal Officer.

Please feel free to contact me at (202) 727-2800 with any questions.

_______________________
Kristen Walp
Senior Assistant General Counsel

X
1
2
3
Peter Henry Lyonga
14. Description of amendment/modification (Organized by UCF Section headings, including solicitation/contract subject matter where feasible.)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
Contract No. DCAM-23-CS-RFP-0016 to provide Design-Build Services for Brent Elementary School is hereby modified as follows:
copies of the amendment: (b) By acknowledging receipt of this
copy to the issuing office.E. IMPORTANT:
an offer already submitted, such change may be made by letter or fax, provided each letter or telegram makes reference to the
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14
The changes set forth in Item 14 are made in the contract/order no. in item 10A.
amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS
PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change
Guaranteed Maximum Price. The Contract No. DCAM-23-CS-RFP-0016 Design Build Services for Brent Elementary School
Modernization is modified to establish the Contract's Guaranteed Maximum Price ("GMP") in the amount of Eighty-Seven Million
Four Hundred Ninety-FiveThousand One Hundred Eleven Dollars ($87,495,111.00) per the terms of Attachment A (GMP
amendment) hereto. The Contract value is therefore increased by $73,287,010.00 from $14,208,101.00 to $87,495,111.00. Pre-
approval by the Department is required to use the owner allowance listed in Exhibit B of the GMP amendment.
While funding in the amount of $87,495,111.00 is being approved for capital-eligible items only, there is an ineligible amount of
$1,377,447.88 listed in Exhibit H of the Contract. See the FY27 Non-Capital column and associated items. These items are
ineligible for capital expenditure, per the District Guidelines. The goods/services are needed for FY2027. There should be no
purchases, commitments and expenditures for these items, until operating funds are available via a purchase order for the same
amount. In no event shall the Contractor be entitled to perform any work against these items unless authorized in advance and in
writing by a duly authorized DGS Contracting Officer through a modification of the contract. Unless and until such modification is
executed by a duly authorized DGS Contracting Officer, the Contractor will be limited to capital-funded purchase orders (“POs”) in
the amount of $86,117,663.12 for the capital eligible work authorized by this contract modification. For the avoidance of confusion, if
the Contractor performs any work with the ineligible items in the amount of $1,377,447.88, as outlined in Exhibit H,
without express
written authorization by a duly authorized DGS Contracting Officer, the Contractor does so at its own risk.
Release: It is mutually agreed that in exchange for this Modification and other considerations, the Contractor hereby releases,
waives, settles, and holds the Department harmless from any and all actual or potential claims or demands for delays, disruptions,
additional work, additional time, additional cost, contract extensions, compensations or liability under any theory, whether known or
unknown, that the Contractor may have now or in the future against the Department arising from or out of, as a consequence or
result of, relating to or in any manner connected with this Modification, the above-referenced Project, and the Contract Work.
Terms & Conditions: All other Terms and Conditions remain unchanged.
X D. Other (Specify type of modification and authority) Title 27 DCMR Section 4728 and Contract DCAM-23-CS-RFP-0016
1
B. The above numbered contract/order is modified to reflect the administrative changes (such as changes in paying office, appropriation
date, etc.) set forth in item 14.
C. This supplemental agreement is entered into pursuant to authority of:
A. This change order is issued pursuant to: (Specify Authority)
Pamela Murray Johnson
SMOOT Construction Company of Washington, DC
8. Name and Address of Contractor (No. Street, city, country, state and ZIP Code) 9A. Amendment of Solicitation No.
(Signature of person authorized to sign) (Signature of Contracting Officer)
solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting and Appropriation Data (If Required)
15B. SMOOT Construction Company of
Washington, DC 15C. Date Signed 16B. District of Columbia 16C. Date Signed
15A. Name and Title of Signer (Type or print) 16A. Name of Contracting Officer
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the
Contractor is not, is required to sign this document and return
amendment on each copy of the offer submitted; or (c) By separate letter or fax which includes a reference to the solicitation and
following methods: (a) By completing Items 8 and 15, and returning 1
1. Contract Number
MODIFICATION OF CONTRACT Page of Pages
DCAM-23-CS-RFP-0016 1 2
7. Administered By (If other than line 6)
Department of General Services
6. Issued By:
3. Effective Date 4. Requisition/Purchase Request No. 5. Caption
Modification No. 3-DCAM-23-CS-RFP-0016 See Block 16C PR-010472 Design-Build Services Brent
Elementary School Modernization
2. Modification Number
Washington, DC 20016
Contracts and Procurement Division
3924 Minnesota Avenue, NE, 5th Floor
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
DCAM-23-CS-RFP-0016/Mod No. 3
9B. Dated (See Item 11)
May 14, 2024
X
10A. Modification of Contract/Task Order No.
3939 Wisconsin Avenue NW, 2nd Floor
Washingtong, DC 20015
pmjohnson@smootbuilds.com
10B. Dated (See Item 13)
Vice President
11/19/2025
(Continuation)
Contract Number Page of Pages
DCAM-23-CS-RFP-0016 2 of 2
6. Contract Recap:
NTP Letter Contract Executed: December 8, 2023 995,000.00$
Contract (ESA1) Executed: May 14,2024 4,945,809.00$
Mod No.1 (Key Personnal Change) Execute: January 28, 2025 -$
Mod No. 2 (ESA2) Execute: February 27, 2025 8,267,292.00$
Mod No. 3 (GMP) Execute: 73,287,010.00$
Total Price 87,495,111.00$
Modification No.
Modification No. 3-DCAM-23-CS-RFP-0016
ATTACHMENT A

GUARANTEED MAXIMUM PRICE AMENDMENT
DESIGN-BUILD AGREEMENT
BRENT ELEMENTARY SCHOOL MODERNIZATION
THIS GUARANTEED MAXIMUM PRICE AMENDMENT (“Amendment”) is
entered into by and between the DISTRICT OF COLUMBIA GOVERNMENT , acting by
and through its DEPARTMENT OF GENERAL SERVICES (the “Department”) and
SMOOT Construction Company of Washington, DC , (the “Design -Builder”) pursuant to
the Agreement, dated May 14, 2024, between the District of Columbia government, by and
through the Department and the Design -Builder, for design-build work at the BRENT
ELEMENTARY SCHOOL MODERNIZATION and to establish a GMP and Contract Time
for the Work as set forth below.
ARTICLE 1
GUARANTEED MAXIMUM PRICE
Section 1.1 Guaranteed Maximum Price . Subject to additions and deductions
which may be made only in accordance with the Agreement, the Design -Builder represents,
warrants and guarantees to the Department that the total maximum cost to be paid by the
Department for Design-Builder’s complete performance under the Agreement, including, but
not limited to, Final Completion of all Work, all services of Design -Builder under the
Agreement, and all fees, compensation and reimbursements to Design-Builder, shall not exceed
the total amount of Eighty-Seven Million Four Hundred Ninety-Five Thousand One Hundred
Eleven Dollars ($87,495,111.00) (“Guaranteed Maximum Price ” or “GMP” ). The GMP
includes capital ineligible items per Section 1.8 of this GMP Amendment and Exhibit H in the
amount of $1,367,447.88. Costs which would cause the GMP (as may be adjusted pursuant to
the Contract Project Documents) to be exceeded shall be paid by the Design-Builder without
reimbursement by the Department.
Section 1.2 Guaranteed Maximum Price Components . The GMP is comprised of
the maximum amount payable by the Department for:
1.2.1 the Cost of the Work for full and complete performance of the Work in strict
accordance with the Contract Project Documents;
1.2.2 a Preconstruction Fee for the Design-Builder, as defined in the Agreement, in
the amount of $184,500.00.
1.2.3 a Design Fee as defined in the Agreement, in the amount of $4,315,500.00.
1.2.4 a Design-Build Fee for the Design-Builder, as defined in the Agreement, in the
amount of $2,050,000.00.
1.2.5 a Lump Sum General Conditions Cost, as defined in the Agreement, in the
amount of $2,806,963.00.
1.2.6 The GMP is further broken down into line items and categories on the Exhibits
attached hereto.

Section 1.3 Basis for the GMP. The GMP is for the performance of the Work in
accordance with the Contract Project Documents listed and attached to this Amendment and
marked Exhibits A through I, as follows:

1.3.1 Exhibit A: List of Drawings, Specifications, addenda and General,
Supplementary and other Conditions of the Agreement on which the GMP is based.
1.3.2 Exhibit B: A list of Allowances.
1.3.3 Exhibit C: Assumptions and clarifications made in preparing the GMP
Proposal, noting, in particular, any exclusions. The assumptions and clarifications shall take
precedence over the drawings and specifications.
1.3.4 Exhibit D: The proposed GMP, including a statement of the detailed cost
estimate organized by trade categories, allowances, contingency, and other items and the fee
that comprise the GMP.
1.3.5 Exhibit E: An update to the Project’s schedule to which the Design-Builder will
agree to be bound. This update shall be prepared in the same level of detail and in the same
manner as the Baseline Schedule, and without any change, to the Substantial and Final
Completion Dates unless approved by the Department’s Contracting Officer.
1.3.6 Exhibit F: A subcontracting plan setting forth the names and estimated dollar
volume of the work that will be performed by LSBDEs, as certified by the Department of Small
and Local Business Development, upon which the GMP is based.
1.3.7 Exhibit G: First Source Agreement and Employment Plan.
1.3.8 Exhibit H: A summary of Capital Cost vs Operating Cost Eligibility.
1.3.9 Exhibit I: Capital eligibility guideline.
1.3.10 Exhibit J: A list of additive alternates or deductive alternates with defined
executable dates, if any.
Section 1.4 Incomplete Drawings and Specifications. Design-Builder and the
Department acknowledge that the Drawings and Specifications are not complete and, as of the
date hereof, that such Drawings and Specifications have reached the level of approximately
100% complete design development Project Documents. The Design-Builder, however, has
been actively involved in the design process and hereby represents that it has a sufficient
understanding of the Project to agree to a GMP to Fully Complete the Project. T he Design-
Builder hereby acknowledges that the GMP Basis Project Documents provides sufficient detail
and information to provide a firm GMP and that the GMP proposed therein is intended to
represent the Design -Builder’s offer to Fully Complete the Project. The Design-Builder and
the Department agree to work together to complete the Drawings and Specifications as
provided in this Agreement, consistent with the GMP premises and assumptions and Project
Schedule.
Section 1.5 Design Intent; Inferable Work. Design-Builder agrees that the GMP
is based on the current state of the design, which represents approximately 100% percent
complete design development Project Documents. The GMP Basis Project Documents will
include various clarifications and assumptions that are intended to further define the scope of
Work that will be required to complete design. The Design -Builder has included within the
GMP sufficient amounts to cover aspects of the Work that are not shown on the GMP Basis

Project Documents. If the Department does not approve any such scope increase, the Design-
Builder shall cause the Design-Builder’s Architect to develop a design that is consistent with
the original design intent and shall complete the Work for an amount that does not exceed the
GMP.
Section 1.6 Cost Overruns. Subject to additions or deductions which may be made
in accordance with the Agreement, the Design -Builder shall be solely liable and responsible
for and shall pay any and all costs, fees and other expenditures in excess of the GMP for and/or
relating to the Work, without entitlement to reimbursement from the Department. Design -
Builder shall not be entitled to any fee, payment, compensation or reimbursement under this
Agreement or relating to the Work or Project other than as expr essly provided in the
Agreement.
Section 1.7 Allowances. The GMP includes specific "Unit Price Allowance
Amounts" for certain items as shown on the Schedule of Values and budgeted in the GMP
("Allowance Items"). The only Allowance Items shall be those specifically identified as such
in the Schedule of Values and in the GMP. The Allowance Amounts represent all Costs of the
Work of the Allowance Items, including, without limitation, costs of materials, labor, handling,
transportation, loading and unloading and installation, as determined by Design-Builder.
Section 1.8 Capital Eligibility. While funding in the amount of $87,495,111.00 is being
approved for capital-eligible items only, there is an ineligible amount of $1,377,447.88 listed
in Exhibit H of the Contract. See the FY27 Non-Capital column and associated items. These
items are ineligible for capital expenditure, per the District Guidelines. The goods/services are
needed for FY2027. There should be no purchases, commitments and expenditures for these
items, until operating funds are available via a purchase order for the same amount. In no event
shall the Contractor be entitled to perform any work against these items unless authorized in
advance and in writing by a duly authorized DGS Contracting Officer through a modification
of the contract. Unless and until such modification is exec uted by a duly authorized DGS
Contracting Officer, the Contractor will be limited to capital -funded purchase orders (“POs”)
in the amount of $86,117,663.12 for the capital eligible work authorized by this contract
modification. For the avoidance of confusi on, if the Contractor performs any work with the
ineligible items in the amount of $1,377,447.88, as outlined in Exhibit H, without express
written authorization by a duly authorized DGS Contracting Officer, the Contractor does so at
its own risk.

Section 1.9 Shared Savings. In the event there are GMP savings, excluding any Owner
Allowances and Owner Contingency, the GMP savings shall be split 60/40, with 60% allocated
to the Department and 40% allocated to the Design -Builder. The maximum allocation to the
Design-Builder shall be $1,000,000.00.

ARTICLE 2
INTENT, INTERPRETATION AND CORRELATION
Section 2.1 Intent of the Agreement . The intent of the Agreement is for the
Design-Builder to perform and supply, and the Department hereby engages Design-Builder to
and Design-Builder hereby agrees to perform and supply, the Work, including all necessary
design services, scheduling, pro curement, supervision, construction, and construction
management services and supply all necessary labor, materials, equipment and related work
and services necessary to fully complete the Work and obtain the intended results of the
Contract Project Docum ents, including, but not limited to the requirements of the Project
Schedule and the GMP requirements set forth in Article 1 above. The enumeration of particular
items in the Specifications and/or Drawings shall not be construed to exclude other items. The
Contract Project Documents are complementary, and what is required by any one of the
Contract Project Documents (including either a Drawing or Specification) as being necessary
to produce the intended results shall be binding and required as a part of the Work as if required
by all Contract Project Documents.
Section 2.2 Design-Builder’s Compliance with Contract Project Documents .
Design-Builder agrees, accepts and assumes that the Department's decision will require
implementation of the most stringent requirements among any conflicting provisions of the
Contract Project Documents as being part of the Work. The Design-Builder agrees to be bound
by all decisions by the Department to implement the most stringent of any conflicting
requirements within the Contract Project Documents. Any failure by Design -Builder to seek
such clarifications shall in no way limit the Department's ability to require implementation,
including replacement of installed Work at a later date at Design -Builder's sole expense, to
achieve compliance with the more stringent requirements. Without limiting the generality of
the foregoing, the Design-Builder hereby agrees as follows:
Section 2.2.1 The failure of the Department to insist in any one or more instances upon
a strict compliance with any provision of this Agreement, or to exercise any option herein
conferred, shall not be construed as a waiver or relinquishment of the Department's right
thereafter to require compliance with such provision of this Agreement, or as being a waiver
of the Department's right thereafter to exercise such option, and such provision or option will
remain in full force and effect.
Section 2.2.2 If there is any inconsistency in the Drawings or any conflict between the
Drawings and Specifications, Design-Builder shall provide the better quality or greater quantity
of Work or materials, as applicable, unless the Department directs otherwise in writing.
Section 2.2.3 Design-Builder shall be responsible for dividing the Work among the
appropriate Subcontractors and Vendors. No claim will be entertained by the Department based
upon the organization or arrangement of the Specifications and/or the Drawings into areas,
sections, subsections or trade disciplines.
Section 2.2.4 Detail drawings shall take precedence over scale drawings, and figured
dimensions on the Drawings shall govern the setting out of the Work.
Section 2.2.5 Unless the Specifications expressly state otherwise, references to
documents and standards of professional organizations shall mean the latest editions published

prior to the Effective Date.
Section 2.2.6 Technical words, abbreviations and acronyms in the Contract Project
Documents shall be used and interpreted in accordance with customary usage in the
construction industry.
Section 2.2.7 Whenever consent, permission or approval is required from any party
pursuant to the provisions of the Contract Project Documents , such consent, permission or
approval shall, unless expressly provided otherwise in this Agreement, be given or obtained,
as applicable, in writing.

ARTICLE 3
[INTENTIONALLY OMITTED]

ARTICLE 4
OTHER PROVISIONS
Section 4.1 Design-Builder’s Responsibilities. The Design-Builder also expressly
acknowledges that this Project and the Work will proceed on a "fast -track" method of
construction, i.e., construction will commence without final Drawings and Specifications in
place. More specifically, while Drawings and Specifications are complete for certain portions
of Work, the design process will continue for other portions during construction based on the
GMP premises and assumptions. The Design -Builder has been, and will continue to be, an
active participant in the design process. Given such participation, the Design-Builder represents
that it is familiar with the scope and quality of those aspects of the Pr oject that have not yet
been fully designed, and has taken such scope and quality matters into consideration in
preparing each component of the GMP. The Design -Builder agrees to work with the
Department in managing the construction and design work to complete the design process. The
Design-Builder shall manage the Project, including coordinating redesign or value engineering
necessary or advisable for certain aspects of the Project at any stage of the design process in
order to bring the cost of such Work within or below, but not in excess of, the respective
allowances or the budgeted or allocated amounts for other items contained in the GMP. Once
the Drawings and Specifications are complete, it is recognized by the Design -Builder and the
Department that th e scope of the GMP may include Work not expressly indicated on the
Contract Project Documents , but which is reasonably inferable from the Contract Project
Documents, and such Work shall be performed without any increase in the GMP or extension
of Contract Time, except if and to the extent otherwise expressly provided in this Agreement.

ARTICLE 5
MISCELLANEOUS PROVISIONS
Section5.1 PriorAgreementUnaffected.Exceptasexpresslyagreedtoherein,all
oftheterms,conditions,representationsandwarrantiessetforthintheAgreementshallremain
unaffectedandinfullforceandaffect.
Section5.2 IntegratedAgreement.ThisAmendmentandanyattachmentheretosetforththeentireagreementandunderstandingofthepartiesregardingthetransactionscontemplatedherebyandsupersedeallpriororalandwrittenagreements,arrangementsandunderstandingsrelatingtothesubjectmatterhereof.Therearenooralorwrittenagreements
orunderstandings,representationsorwarrantiesamongthepartiesotherthanthosesetforth
herein
Section5.3 Counterparts.ThisAmendmentmaybeexecutedinoneormorecounterparts,eachofwhichshallbedeemedtobeanoriginal,butallofwhichshallbeconsideredoneandthesameinstrument.
Section5.4 Construction.ThisAgreementshallbeconstruedfairlyastoallpartiesandnotinfavoroforagainstanyparty,regardlessofwhichpartypreparedtheAgreement,
IN WITNESS WHEREOF, each of the partiesto thisAmendment to Agreement
(DCAM-23-CS-RFP-0016)hascausedittobeexecutedbyitsdulyauthorizedrepresentativeonthedatessetforthbelow.
DISTRICT OF COLUMBIA GOVERNMENT, by and through its
DEPARTMENT OF GENERAL SERVICES
By:

SMOOT CONS" i ’OF WASHINGTON, DC
Name: _ PamelaMurrayJohnson
Its: Vice President
Date: 11/19/2025
g and Specifications
Exhibit A
List of Drawing and Specifications

BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
G0001 COVER SHEET GMP SET 4/24/2025
CP0001 BUILDING USE ANALYSIS GMP SET 4/24/2025
CP0101 LEVEL 0, LEVEL 1 - CODE PLAN GMP SET 4/24/2025
CP0102 LEVEL 2, LEVEL 3 - CODE PLAN GMP SET 4/24/2025
CIVIL
CIV0001 NOTES, LEGEND AND ABBREVIATIONS ADD 2 5/15/2025
CIV0101 EXISITING CONDITIONS ADD 2 5/15/2025
CIV0102 DEMOLITION PLAN ADD 2 5/15/2025
CIV0103 EROSION AND SEDIMENT CONTROL PLAN ADD 2 5/15/2025
CIV0104 EROSION AND SEDIMENT CONTROL NOTES ADD 2 5/15/2025
CIV0105 SITE PLAN ADD 2 5/15/2025
CIV0106 UTILITY PLAN ADD 2 5/15/2025
CIV0107 GRADING PLAN ADD 2 5/15/2025
CIV0301 UTILITY PROFILE ADD 2 5/15/2025
CIV0302 UTILITY PROFILE ADD 2 5/15/2025
CIV0501 EROSION AND SEDIMENT CONTROL DETAILS ADD 2 5/15/2025
CIV0502 SITE DETAILS ADD 2 5/15/2025
CIV0503 UTILITY DETAILS ADD 2 5/15/2025
CIV0504 UTILITY DETAILS ADD 2 5/15/2025
CIV0701 STORM WATER MANAGEMENT PLAN - EXISITING DRAINAGE DIVIDES ADD 2 5/15/2025
CIV0702 STORM WATER MANAGEMENT PLAN - PROPOSED DRAINAGE DIVIDES ADD 2 5/15/2025
CIV0703 STORM WATER MANAGEMENT PLAN ADD 2 5/15/2025
CIV0704 STORM WATER MANAGEMENT PLAN - BIORETENTION ADD 2 5/15/2025
CIV0705 STORM WATER MANAGEMENT PLAN - GREEN ROOF ADD 2 5/15/2025
ARCHITECTURAL GENERAL
GENERAL
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS

BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
CIV0706 STORM WATER MANAGEMENT PLAN - PERMEABLE PAVEMENT ADD 2 5/15/2025
CIV0707 STORM WATER MANAGEMENT PLAN - INFILTRATION TRENCH ADD 2 5/15/2025
CIV0708 STORM WATER MANAGEMENT PLAN - STORM SEPARATOR ADD 2 5/15/2025
CIV0709 STORM WATER MANAGEMENT PLAN - CALCULATIONS ADD 2 5/15/2025
LANDSCAPE
L001 COVER SHEET ADD 2 5/15/2025
L003 BASIC TREE PRESERVATION PLAN ADD 2 5/15/2025
L100 OVERALL MATERIALS PLAN ADD 2 5/15/2025
L110 MATERIALS ENLARGEMENT NORTH ADD 2 5/15/2025
L111 MATERIALS ENLARGEMENT SOUTH ADD 2 5/15/2025
L120 PLAYGROUND A - DESIGN CONCEPT ADD 2 5/15/2025
L121 PLAYGROUND B - DESIGN CONCEPT ADD 2 5/15/2025
L122 PLAYGROUND TRAFFIC GARDEN LAYOUT ADD 2 5/15/2025
L400 TREE PLANTING PLAN ADD 2 5/15/2025
L410 UNDERSTORY PLANTING PLAN NORTH ADD 2 5/15/2025
L411 UNDERSTORY PLANTING PLAN SOUTH ADD 2 5/15/2025
L430 PLANTING SCHEDULE AND NOTES ADD 2 5/15/2025
L440 PLANTING DETAILS ADD 2 5/15/2025
L500 PRODUCT INFORMATION ADD 2 5/15/2025
L501 PRODUCT INFORMATION ADD 2 5/15/2025
L510 PAVING AND EDGE DETAILS ADD 2 5/15/2025
L520 WALL AND STAIR DETAILS ADD 2 5/15/2025
ARCHITECTURAL
A0001 GENERAL NOTES , ARCHITECHTUAL SYMBOLS & ABBREVIATIONS ADD 2 5/15/2025
AS0101 ARCHITECTURAL SITE PLAN ADD 2 5/15/2025
A0010 FLOOR PLAN - LEVEL 0 ADD 2 5/15/2025
A0011 FLOOR PLAN - LEVEL 1 ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
A0012 FLOOR PLAN -LEVEL 2 ADD 2 5/15/2025
A0013 FLOOR PLAN - LEVEL 3 ADD 2 5/15/2025
A0014 ROOF PLAN ADD 2 5/15/2025
A0200 ENLARGED VIEWS - RESTROOMS ADD 2 5/15/2025
A0201 ENLARGED VIEWS - RESTROOMS ADD 2 5/15/2025
A0202 ENLARGED VIEWS - RESTROOMS ADD 2 5/15/2025
A0203 ENLARGED VIEWS - MUSIC ADD 2 5/15/2025
A0204 ENLARGED VIEWS - GYMNASIUM ADD 2 5/15/2025
A0205 ENLARGED VIEWS - GYMNASIUM ADD 2 5/15/2025
A0206 ENLARGED VIEWS - ENTRY ADD 2 5/15/2025
A0207 ENLARGED VIEWS - STUDENT DINING ADD 2 5/15/2025
A0208 ENLARGED VIEWS - STUDENT DINING ADD 2 5/15/2025
A0209 ENLARGED VIEWS - LIBRARY ADD 2 5/15/2025
A0210 ENLARGED VIEWS - LIBRARY ADD 2 5/15/2025
A0211 ENLARGED VIEWS - L2 SPECIALS ADD 2 5/15/2025
A0212 ENLARGED VIEWS - L3 SPECIALS ADD 2 5/15/2025
A0213 ENLARGED VIEWS - ART LAB ADD 2 5/15/2025
A0214 ENLARGED VIEWS - L2 DISCOVERY COMMONS ADD 2 5/15/2025
A0215 ENLARGED VIEWS - L3 DISCOVERY COMMONS ADD 2 5/15/2025
A0216 ENLARGED VIEWS - L3 DISCOVERY COMMONS ADD 2 5/15/2025
A0217 ENLARGED VIEWS - TYPE A PK CLASSROOMS ADD 2 5/15/2025
A0218 ENLARGED VIEWS - TYPE A KINDERGARTEN, 1ST GRADE CLASSROOMS ADD 2 5/15/2025
A0219 ENLARGED VIEWS - TYPE B KINDERGARTEN, 1ST GRADE CLASSROOMS ADD 2 5/15/2025
A0220 ENLARGED VIEWS - TYPE A 2-5 CLASSROOMS ADD 2 5/15/2025
A0221 ENLARGED VIEWS - TYPE B 2-5 CLASSROOMS ADD 2 5/15/2025
A0222 ENLARGED VIEWS - TYPE C 2-5 CLASSROOMS ADD 2 5/15/2025
A0300 REFLECTED CEILING PLAN - LEVEL 0 ADD 2 5/15/2025
A0301 REFLECTED CEILING PLAN - LEVEL 1 ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
A0302 REFLECTED CEILING PLAN - LEVEL 2 ADD 2 5/15/2025
A0303 REFLECTED CEILING PLAN - LEVEL 3 ADD 2 5/15/2025
A0400 EXTERIOR ELEVATIONS ADD 2 5/15/2025
A0401 EXTERIOR ELEVATIONS ADD 2 5/15/2025
A0402 EXTERIOR ELEVATIONS ADD 2 5/15/2025
A0500 BUILDING SECTIONS ADD 2 5/15/2025
A0501 BUILDING SECTIONS ADD 2 5/15/2025
A0600 WALL SECTIONS ADD 2 5/15/2025
A0601 WALL SECTIONS ADD 2 5/15/2025
A0700 STAIR B PLANS & SECTIONS ADD 2 5/15/2025
A0701 STAIR C PLANS & SECTIONS ADD 2 5/15/2025
A0702 STAIR D PLANS & SECTIONS ADD 2 5/15/2025
A0703 STAIR A PLANS & SECTIONS ADD 2 5/15/2025
A0704 STAIR & RAILING DETAILS ADD 2 5/15/2025
A0720 RAMP & ELEVATOR VIEWS ADD 2 5/15/2025
A0800 PARTITION TYPES ADD 2 5/15/2025
A0820 DOOR & FRAME TYPE & SCHEDULE ADD 2 5/15/2025
A0830 EXTERIOR WINDOWS TYPES & SCHEDULES ADD 2 5/15/2025
A0831 INTERIOR WINDOWS TYPES & SCHEDULES ADD 2 5/15/2025
A0900 EXTERIOR DETAILS ADD 2 5/15/2025
A0901 EXTERIOR DETAILS ADD 2 5/15/2025
A0902 EXTERIOR DETAILS ADD 2 5/15/2025
A0903 EXTERIOR DETAILS ADD 2 5/15/2025
A1000 INTERIOR ELEVATIONS ADD 2 5/15/2025
A1001 INTERIOR ELEVATIONS ADD 2 5/15/2025
A1002 INTERIOR ELEVATIONS ADD 2 5/15/2025
A1003 INTERIOR ELEVATIONS ADD 2 5/15/2025
A1004 INTERIOR ELEVATIONS ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
A1100 HM DOOR & WINDOW FRAME DETAILS ADD 2 5/15/2025
A1101 INTERIOR DETAILS ADD 2 5/15/2025
A1102 INTERIOR DETAILS ADD 2 5/15/2025
A1103 CEILING DETAILS ADD 2 5/15/2025
A1200 FINISH PLAN - LEVEL 0 ADD 2 5/15/2025
A1201 FINISH PLAN - LEVEL 1 ADD 2 5/15/2025
A1202 FINISH PLAN - LEVEL 2 ADD 2 5/15/2025
A1203 FINISH PLAN - LEVEL 3 ADD 2 5/15/2025
A1204 FINISH AND APPLIANCE SCHEDULES ADD 2 5/15/2025
INTERIORS
IN030 FURNITURE COORDINATION PLAN - LEVEL 0 ADD 2 5/15/2025
IN031 FURNITURE COORDINATION PLAN - LEVEL 1 ADD 2 5/15/2025
IN032 FURNITURE COORDINATION PLAN - LEVEL 2 ADD 2 5/15/2025
IN033 FURNITURE COORDINATION PLAN - LEVEL 3 ADD 2 5/15/2025
FOOD SERVICES
K-001 COVER SHEET GMP SET 4/24/2025
K-101 KITCHEN EQUIPMENT PLAN GMP SET 4/24/2025
K-102 KITCHEN EQUIPMENT SCHEDULE GMP SET 4/24/2025
K-200 BUILDING CONDITIONS & VENTILATION PLAN GMP SET 4/24/2025
K-201 VENTILATION SCHEDULE DETAILS GMP SET 4/24/2025
K-300 PLUMBING ROUGH-IN PLAN GMP SET 4/24/2025
K-301 PLUMBING SCHEDULE AND DETIALS GMP SET 4/24/2025
K-400 ELECTRICAL ROUGH-IN PLAN GMP SET 4/24/2025
K-401 ELECTRICAL SCHEDULE AND DETIALS GMP SET 4/24/2025
K-500 FABRICATIONS GMP SET 4/24/2025
K-501 FABRICATIONS & DETIALS GMP SET 4/24/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
K-510 EXHAUST CANOPY DETAILS GMP SET 4/24/2025
K-511 VENTILATOR WIRING DIAGRAM GMP SET 4/24/2025
STRUCTURAL
S001 GENERAL STRUCTURAL NOTES ADD 2 5/15/2025
S002 GENERAL STRUCTURAL NOTES ADD 2 5/15/2025
S010 LEVEL 00 - FOUNDATION PLAN ADD 2 5/15/2025
S011 LEVEL 01 FLOOR FRAMING / FOUNDATION PLAN ADD 2 5/15/2025
S012 LEVEL 02 - FLOOR FRAMING PLAN ADD 2 5/15/2025
S013 LEVEL 03 - FLOOR FRAMING PLAN ADD 2 5/15/2025
S014 LEVEL 04 - ROOF FRAMING PLAN ADD 2 5/15/2025
S015 LEVEL 05 - HIGH ROOF FRAMING PLAN ADD 2 5/15/2025
S021 BUILDING / WALL SECTIONS ADD 2 5/15/2025
S022 BUILDING / WALL SECTIONS ADD 2 5/15/2025
S023 BUILDING / WALL SECTIONS ADD 2 5/15/2025
S031 TYPICAL FOUNDATION DETAILS ADD 2 5/15/2025
S032 TYPICAL FOUNDATION DETAILS ADD 2 5/15/2025
S033 TYPICAL FOUNDATION DETAILS ADD 2 5/15/2025
S034 FOUNDATION SECTIONS AND DETAILS ADD 2 5/15/2025
S041 TYPICAL MASONRY DETIALS ADD 2 5/15/2025
S042 TYPICAL MASONRY DETIALS ADD 2 5/15/2025
S051 STEEL COLUMN SCHEDULE AND TYPICAL BASE DETAILS ADD 2 5/15/2025
S052 TYPICAL STEEL FRAMING DETIALS ADD 2 5/15/2025
S053 TYPICAL STEEL FRAMING DETIALS ADD 2 5/15/2025
S054 FLOOR SECTIONS AND DETAILS ADD 2 5/15/2025
S055 ROOF SECTIONS AND DETAILS ADD 2 5/15/2025
S056 ROOF SECTIONS AND DETAILS ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
FIRE PROTECTION
FP0001 FIRE PROTECTION SYMBOLS AND ABBREVIATIONS ADD 2 5/15/2025
FP0100 FIRE PROTECTION PLAN - LEVEL 0 ADD 2 5/15/2025
FP0101 FIRE PROTECTION PLAN - LEVEL 1 ADD 2 5/15/2025
FP0102 FIRE PROTECTION PLAN - LEVEL 2 ADD 2 5/15/2025
FP0103 FIRE PROTECTION PLAN - LEVEL 3 ADD 2 5/15/2025
FP0104 FIRE PROTECTION PLAN - ROOF ADD 2 5/15/2025
FP0300 FIRE PROTECTION DETAILS ADD 2 5/15/2025
PLUMBING
P0001 PLUMBING GENERAL NOTES & SYMBOLS ADD 2 5/15/2025
P0002 PLUMBING ABBREVIATIONS ADD 2 5/15/2025
PS0101 PLUMBING SITE PLAN ADD 2 5/15/2025
P0010 LEVEL 00 - UNDERGROUND PLUMBING PLAN ADD 2 5/15/2025
P0011 LEVEL 01 - UNDERGROUND PLUMBING PLAN ADD 2 5/15/2025
P0100 PLUMBING PLAN - LEVEL 0 ADD 2 5/15/2025
P0101 PLUMBING PLAN - LEVEL 1 ADD 2 5/15/2025
P0102 PLUMBING PLAN - LEVEL 2 ADD 2 5/15/2025
P0103 PLUMBING PLAN - LEVEL 3 ADD 2 5/15/2025
P0104 PLUMBING PLAN - ROOF ADD 2 5/15/2025
P0300 ENLARGED PLUMBING PLANS - LEVEL 0 ADD 2 5/15/2025
P0301 ENLARGED PLUMBING PLANS - LEVEL 1 ADD 2 5/15/2025
P0302 ENLARGED PLUMBING PLANS - LEVEL 2 ADD 2 5/15/2025
P0303 ENLARGED PLUMBING PLANS - LEVEL 3 ADD 2 5/15/2025
P0400 WASTE & VENT RISER DIAGRAMS ADD 2 5/15/2025
P0401 WASTE & VENT RISER DIAGRAMS ADD 2 5/15/2025
P0402 DOMESTIC RISER DIAGRAMS ADD 2 5/15/2025
P0403 DOMESTIC RISER DIAGRAMS ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
P0404 STORM RISER DIAGRAM ADD 2 5/15/2025
P0500 PLUMBING DETAILS ADD 2 5/15/2025
P0501 PLUMBING DETAILS ADD 2 5/15/2025
P0502 PLUMBING DETAILS ADD 2 5/15/2025
P0600 PLUMBING SCHEDULES ADD 2 5/15/2025
P0601 PLUMBING SCHEDULES ADD 2 5/15/2025
MECHANICAL
M0001 MECHANICAL SYMBOLS, ABBREVIATIONS & NOTES ADD 2 5/15/2025
M0002 MECHANICAL ABBREVIATIONS ADD 2 5/15/2025
MS0101 MECHANICAL SITE PLAN ADD 2 5/15/2025
M0100 HVAC PLAN - LEVEL 0 ADD 2 5/15/2025
M0101 HVAC PLAN - LEVEL 1 ADD 2 5/15/2025
M0102 HVAC PLAN - LEVEL 2 ADD 2 5/15/2025
M0103 HVAC PLAN - LEVEL 3 ADD 2 5/15/2025
M0104 HVAC PLAN - ROOF ADD 2 5/15/2025
M0200 PIPING PLAN - LEVEL 0 ADD 2 5/15/2025
M0201 PIPING PLAN - LEVEL 1 ADD 2 5/15/2025
M0202 PIPING PLAN - LEVEL 2 ADD 2 5/15/2025
M0203 PIPING PLAN - LEVEL 3 ADD 2 5/15/2025
M0204 PIPING PLAN - LEVEL ROOF ADD 2 5/15/2025
M0300 ENLARGED HVAC PLANS ADD 2 5/15/2025
M0301 ENLARGED MECHANICAL PIPING PLANS ADD 2 5/15/2025
M0400 MECHANICAL SECTIONS ADD 2 5/15/2025
M0500 CONTROLS DIAGRAMS ADD 2 5/15/2025
M0501 CONTROLS DIAGRAMS ADD 2 5/15/2025
M0502 CONTROLS DIAGRAMS ADD 2 5/15/2025
M0503 CONTROLS DIAGRAMS ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
M0504 CONTROLS DIAGRAMS ADD 2 5/15/2025
M0600 DUCT RISER DIAGRAM ADD 2 5/15/2025
M0601 HYDRONIC RISER DIAGRAM ADD 2 5/15/2025
M0700 MECHANICAL DETAILS ADD 2 5/15/2025
M0701 MECHANICAL DETAILS ADD 2 5/15/2025
M0800 MECHANICAL SCHEDULES ADD 2 5/15/2025
M0801 MECHANICAL SCHEDULES ADD 2 5/15/2025
M0802 MECHANICAL SCHEDULES ADD 2 5/15/2025
M0803 MECHANICAL SCHEDULES ADD 2 5/15/2025
M0804 MECHANICAL SCHEDULES ADD 2 5/15/2025
M0900 ZONING PLAN - LEVEL 0 ADD 2 5/15/2025
M0901 ZONING PLAN - LEVEL 1 ADD 2 5/15/2025
M0902 ZONING PLAN - LEVEL 2 ADD 2 5/15/2025
M0903 ZONING PLAN - LEVEL 3 ADD 2 5/15/2025
ELECTRICAL
E001 ELECTRICAL SYMBOLS, ABBREVIATIONS & NOTES
ES101 LEVEL 01 - SITE PLAN ADD 2 5/15/2025
E100 BASEMENT LIGHTING PLAN ADD 2 5/15/2025
E101 LEVEL 01 - LIGHTING PLAN ADD 2 5/15/2025
E102 LEVEL 02- LIGHTING PLAN ADD 2 5/15/2025
E103 LEVEL 03 - LIGHTING PLAN ADD 2 5/15/2025
E104 ROOF - LIGHTING PLAN ADD 2 5/15/2025
E200 BASEMENT - POWER PLAN ADD 2 5/15/2025
E201 LEVEL 01 - POWER PLAN ADD 2 5/15/2025
E202 LEVEL 02 - POWER PLAN ADD 2 5/15/2025
E203 LEVEL 03 - POWER PLAN ADD 2 5/15/2025
E204 ROOF - POWER PLAN ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
E300 BASEMENT - SPECIAL SYSTEMS PLAN ADD 2 5/15/2025
E301 LEVEL 01 - SPECIAL SYSTEMS PLAN ADD 2 5/15/2025
E302 LEVEL 02 - SPECIAL SYSTEMS PLAN ADD 2 5/15/2025
E303 LEVEL 03 - SPECIAL SYSTEMS PLAN ADD 2 5/15/2025
E304 ROOF - SPECIAL SYSTEMS PLAN ADD 2 5/15/2025
E401 ENLARGED ELECTRICAL PLANS ADD 2 5/15/2025
E402 ENLARGED KITCHEN PLAN ADD 2 5/15/2025
E403 ENLARGED PLANS - TYPE A CLASSROOMS ADD 2 5/15/2025
E404 ENLARGED PLANS - TYPE B CLASSROOMS ADD 2 5/15/2025
E405 ENLARGED PLANS - TYPE C CLASSROOMS ADD 2 5/15/2025
E406 ENLARGED PLANS - SPECIALS AND ART LAB ADD 2 5/15/2025
E501 ELECTRICAL DIAGRAMS ADD 2 5/15/2025
E601 ELECTRICAL DETAILS - GROUNDING ADD 2 5/15/2025
E602 ELECTRICAL DETAILS ADD 2 5/15/2025
E603 ELECTRICAL DETAILS - ELEVATORS ADD 2 5/15/2025
E701 ELECTRICAL SCHEDULES ADD 2 5/15/2025
E702 ELECTRICAL LIGHTING SCHEDULES ADD 2 5/15/2025
E703 ELECTRICAL LIGHTING SCHEDULES ADD 2 5/15/2025
E704 ELECTRICAL SCHEDULES - BASEMENT ADD 2 5/15/2025
E705 ELECTRICAL SCHEDULES - LEVEL 01 & BASEMENT ADD 2 5/15/2025
E706 ELECTRICAL SCHEDULES - LEVEL 02 ADD 2 5/15/2025
E707 ELECTRICAL SCHEDULES - LEVEL 03 ADD 2 5/15/2025
E708 ELECTRICAL SCHEDULES - EMERGENCY ADD 2 5/15/2025
TELECOM
TE001 TELECOM GENERAL NOTES, SYMBOLS & ABBREVIATIONS ADD 2 5/15/2025
TE002 TELECOM SECURITY SITE PLAN ADD 2 5/15/2025
TE100 BASEMENT FLOOR TELECOM & SECURITY PLAN ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
TE101 FIRST FLOOR TELECOM AND SECURITY PLAN ADD 2 5/15/2025
TE102 SECOND FLOOR TELECOM/ & SECURITY PLAN ADD 2 5/15/2025
TE103 THIRD FLOOR TELECOM/ & SECURITY PLAN ADD 2 5/15/2025
TE200 BASEMENT FLOOR TELECOM / SECURITY RCP ADD 2 5/15/2025
TE201 OVERALL FIRST FLOOR TELECOM / SECURITY RCP ADD 2 5/15/2025
TE202 OVERALL SECOND FLOOR TELECOM / SECURITY RCP ADD 2 5/15/2025
TE203 OVERALL THIRD FLOOR TELECOM / SECURITY RCP ADD 2 5/15/2025
TE301 TELECOM ENLARGED PLANS ADD 2 5/15/2025
TE501 TELECOM ONE-LINE ADD 2 5/15/2025
TE601 TELECOM DETAILS ADD 2 5/15/2025
TE602 TELECOM DETAILS ADD 2 5/15/2025
TE701 TELECOM SCHEDULES ADD 2 5/15/2025
AUDIOVISUAL
TA001 AUDIOVISUAL GENERAL NOTES ADD 2 5/15/2025
TA002 AUDIOVISUAL GENERAL DETAILS ADD 2 5/15/2025
TA101 LEVEL 01- OVERALL FLOOR PLAN ADD 2 5/15/2025
TA102 LEVEL 02- OVERALL FLOOR PLAN ADD 2 5/15/2025
TA201 LEVEL 01 - OVERALL REFELECTED CIELING PLAN ADD 2 5/15/2025
TA202 LEVEL 02 - OVERALL REFELECTED CIELING PLAN ADD 2 5/15/2025
TA301 AV PLANS - GYNASIUM ADD 2 5/15/2025
TA302 AV PLANS - DINING AND VESTIBULE ADD 2 5/15/2025
TA303 AV PLANS - LEARNING CENTER ADD 2 5/15/2025
TA401 ELEVATIONS , SECTIOS AND 3D VIEWS ADD 2 5/15/2025
TA651 AUDIOVISUAL WIRING DEVICE DETAILS ADD 2 5/15/2025
TA701 AUDIOVISUAL SCHEDULES
FF&E
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
FFE0 FF&E SCHEDULES GMP SET 4/24/2025
FFE1 FLOOR PLAN - LEVEL 0 GMP SET 4/24/2025
FFE2 FLOOR PLAN - LEVEL 1 GMP SET 4/24/2025
FFE3 FLOOR PLAN - LEVEL 2 GMP SET 4/24/2025
FFE4 FLOOR PLAN - LEVEL 3 GMP SET 4/24/2025
SPECIFICATIONS DLR GROUP
VOLUME I
DIVISION 00 - PROCUREMENT AND CONYTRACTING REQUIREMENTS
000000 COVER PAGE VOLUME I ADD 2 5/15/2025
000000 COVER PAGE VOLUME II ADD 2 5/15/2025
000110 TABLE OF CONTENTS VOLUME I ADD 2 5/15/2025
000110 TABLE OF CONTENTS VOLUME II ADD 2 5/15/2025
DIVISION 01 - GENERAL REQUIREMENTS
011000 SUMMARY ADD 2 5/15/2025
013100 PROJECT MANAGEMENT AND COORDINATION ADD 2 5/15/2025
013200 CONSTRUCTION PROGRESS DOCUMENTATION ADD 2 5/15/2025
013233 PHOTOGRAPHIC DOCUMENTATION ADD 2 5/15/2025
013300 SUBMITTAL PROCEDURES ADD 2 5/15/2025
016000 PRODUCT REQUIREMENTS ADD 2 5/15/2025
017300 EXECUTION ADD 2 5/15/2025
017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL ADD 2 5/15/2025
017700 CLOSEOUT PROCEDURES ADD 2 5/15/2025
017823 OPERATION AND MAINTENANCE DATA ADD 2 5/15/2025
017839 PROJECT RECORDS DOCUMENTS ADD 2 5/15/2025
017900 DEMONSTRATION AND TRAINING ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
018113.23 SUSTAINABLE DESIGN REQUIREMENTS - LEED V4.1 BD+C SCHOOLS ADD 2 5/15/2025
018113.90 LEED SCORECARD ADD 2 5/15/2025
019113 GENERAL COMMISSIONING REQUIREMENTS ADD 2 5/15/2025
DIVISION 02 - EXISITING CONDITIONS
024116 STRUCTURE DEMOLITION ADD 2 5/15/2025
DIVISION 03 - CONCRETE
031000 CONCRETE FORMING AND ACCESSORIES ADD 2 5/15/2025
032000 CONCRETE REINFORCING ADD 2 5/15/2025
033000 CAST-IN-PLACE CONCRETE ADD 2 5/15/2025
035413 GYPSUM CEMENT UNDERLAYMENT ADD 2 5/15/2025
DIVISION 04 - MASONRY ADD 2 5/15/2025
042000 UNIT MASONRY ADD 2 5/15/2025
042613 MASONRY VENEER ADD 2 5/15/2025
DIVISION 05 - METALS
051200 STRUCTURAL STEEL FRAMING ADD 2 5/15/2025
053100 STEEL DECKING ADD 2 5/15/2025
054000 COLD-FORMED METAL FRAMING ADD 2 5/15/2025
055000 METAL FABRICATIONS ADD 2 5/15/2025
051113 METAL PAN STAIRS ADD 2 5/15/2025
055213 PIPE AND TUBE RAILINGS ADD 2 5/15/2025
055313 BAR GRATINGS ADD 2 5/15/2025
055813 COLUMN COVERS ADD 2 5/15/2025
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
061000 ROUGH CARPENTRY ADD 2 5/15/2025
061600 SHEATHING ADD 2 5/15/2025
062023 INTERIOR FINISH CARPENTRY ADD 2 5/15/2025
064023 INTERIOR ARCHITECTUAL WOODWORK ADD 2 5/15/2025
064116 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS ADD 2 5/15/2025
064219 PLASTIC-LAMINATE-FACED WOOD PANELING ADD 2 5/15/2025
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
071326 SELF-ADHERING SHEET WATERPROOFING ADD 2 5/15/2025
072100 THERMAL INSULATION ADD 2 5/15/2025
072726 FLUID-APPLIED MEMBRANE AIR BARRIERS ADD 2 5/15/2025
074210.11 COMPOSITE FRAMING SUPPORT (CFS) SYSTEM ADD 2 5/15/2025
074213.23 METAL COMPOSITE MATERIAL WALL PANELS ADD 2 5/15/2025
074247 HIGH PERFORMANCE CONCRETE FAÇADE PANELS ADD 2 5/15/2025
074293 SOFFIT PANELS ADD 2 5/15/2025
075419 POLYVINYL-CHLORIDE (PVC) ROOFING ADD 2 5/15/2025
076200 SHEET METAL FLASHING AND TRIM ADD 2 5/15/2025
077200 ROOF ACCESSORIES ADD 2 5/15/2025
077273 VEGETATED ROOF SYSTEMS ADD 2 5/15/2025
078413 PENETRATION FIRESTOPPING ADD 2 5/15/2025
079200 JOINT SEALANTS ADD 2 5/15/2025
079219 ACOUSTICAL JOINT SEALANTS ADD 2 5/15/2025
DIVISION 08 - OPENINGS
081113 HOLLOW METAL DOORS AND FRAMES ADD 2 5/15/2025
081113A HOLLOW METAL DOORS AND FRAMES INDEX ADD 2 5/15/2025
081116.13 INTERIOR ALUMINUM DOORS AND FRAMES ADD 2 5/15/2025
081316.13 ALUMINUM TERRACE DOORS ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
081416 FLUSH WOOD DOORS ADD 2 5/15/2025
083113 ACCESS DOORS AND FRAMES ADD 2 5/15/2025
083323 OVERHEAD COILING DOORS ADD 2 5/15/2025
84313 ALUMINUM-FRAMED STOREFRONTS ADD 2 5/15/2025
084413 GLAZED ALUMINUM CURTAIN WALLS ADD 2 5/15/2025
85113 ALUMINUM WINDOWS ADD 2 5/15/2025
087100 DOOR HARDWARE ADD 2 5/15/2025
087100A DOOR HARDWARE SETS ADD 2 5/15/2025
087113 POWER DOOR OPERATORS ADD 2 5/15/2025
088000 GLAZING ADD 2 5/15/2025
088113 DECORATIVE GLASS GLAZING ADD 2 5/15/2025
088300 MIRRORS ADD 2 5/15/2025
089119 FIXED LOUVERS ADD 2 5/15/2025
DIVISION 09 - FINISHES
092116.23 GYPSUM BOARD SHAFT WALL ASSEMBLIES ADD 2 5/15/2025
092216 NON-STRUCTURAL METAL FRAMING ADD 2 5/15/2025
092900 GYPSUM BOARD ADD 2 5/15/2025
093013 CERAMIC TILING ADD 2 5/15/2025
095113 ACOUSTICAL METAL PANEL CEILINGS ADD 2 5/15/2025
095426 SUSPENDED WOOD CEILINGS ADD 2 5/15/2025
096513 RESILIENT BASE AND ACCESSORIES ADD 2 5/15/2025
096519 RESILIENT TILE FLOORING ADD 2 5/15/2025
096566 RESILIENT ATHLETIC FLOORING ADD 2 5/15/2025
096623 RESINOUS MATRIX TERRAZZO FLOORING ADD 2 5/15/2025
096723 RESINOUS FLOORING ADD 2 5/15/2025
097200 WALL COVERINGS ADD 2 5/15/2025
097723 FABRIC-WRAPPED WALL PANELS ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
98400 ACOUSTIC ROOM COMPONENTS ADD 2 5/15/2025
099113 EXTERIOR PAINTING ADD 2 5/15/2025
099123 INTERIOR PAINTING ADD 2 5/15/2025
099300 STAINING AND TRANSPARENT FINISHING ADD 2 5/15/2025
099600 HIGH-PERFORMANCE COATINGS
DIVISION 10 - SPECIALTIES
101100 VISUAL DISPLAY UNITS ADD 2 5/15/2025
101200 DISPLAY CASES ADD 2 5/15/2025
101416 PLAQUES ADD 2 5/15/2025
101419 DIMENSIONAL LETTER SIGNAGE ADD 2 5/15/2025
101423 PANEL SIGNAGE ADD 2 5/15/2025
102113.19 PLASTIC TOILET COMPARTMENTS ADD 2 5/15/2025
102123 CUBICLE CURTAINS AND TRACK ADD 2 5/15/2025
102800 TOILET, BATH AND LAUNDRY ACCESSORIES ADD 2 5/15/2025
104413 FIRE PROTECTION CABINETS ADD 2 5/15/2025
104416 FIRE EXTINGUISHERS ADD 2 5/15/2025
105113 METAL LOCKERS ADD 2 5/15/2025
105613 METAL STORAGE SHELVING ADD 2 5/15/2025
107516 GROUND-SET FLAGPOLES ADD 2 5/15/2025
DIVISION 11 - EQUIPMENT
112423 WINDOW WASHING SYSTEM ADD 2 5/15/2025
113013 RESIDENTIAL APPLIANCES ADD 2 5/15/2025
114000 FOODSERVICE EQUIPMENT ADD 2 5/15/2025
115213 PROJECTION SCREENS ADD 2 5/15/2025
116123 FOLDING AND PORTABLE STAGES ADD 2 5/15/2025
116143 STAGE CURTAINS ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
116623 GYMNASIUM EQUIPMENT ADD 2 5/15/2025
116653 GYMNASIUM DIVIDERS ADD 2 5/15/2025
116800 PLAY FIELD EQUIPMENT AND STRUCTURES ADD 2 5/15/2025
DIVISION 12 - FURNISHINGS
122413 ROLLER WINDOW SHADES ADD 2 5/15/2025
123216 MANUFACTURED PLASTIC-LAMINATE-CLAD CASEWORK ADD 2 5/15/2025
123661.16 SOLID SURFACING COUNTERTOPS ADD 2 5/15/2025
124816 ENTRANCE FLOOR GRILLES ADD 2 5/15/2025
129200 INTERIOR PLANTERS AND ARTIFICIAL PLANTS ADD 2 5/15/2025
DIVISION 14 - CONVEYING EQUIPMENT
142123.16 MACHINE ROOM-LESS ELECTRIC TRACTION PASSENGER ELEVATORS ADD 2 5/15/2025
VOLUME II
DIVISION 21 - FIRE SUPPRESSION
210500 COMMON WORK RESULTS FOR FIRE SUPPRESSION ADD 2 5/15/2025
210523 GENERAL-DUTY VALVES FOR WATER-BASED FIRE-SUPPRESSION PIPING ADD 2 5/15/2025
210529 HANGERS AND SUPPORTS FOR FIRE-SUPPRESSION PIPING AND EQUIPMENTADD 2 5/15/2025
210548.13 VIBRATION CONTROLS FOR FIRE-SUPPRESSION PIPING AND EQUIPMENTADD 2 5/15/2025
210553 IDENTIFICATION FOR FIRE-SUPPRESSION PIPING AND EQUIPMENT ADD 2 5/15/2025
210800 COMMISSIONING OF FIRE SUPPRESSION ADD 2 5/15/2025
221100 WATER-BASED FIRE-SUPPRESSION SYSTEMS ADD 2 5/15/2025
DIVISION 22 - PLUMBING
220500 COMMON WORK RESULTS FOR PLUMBING ADD 2 5/15/2025
220523 GENERAL-DUTY VALVES FOR WATER-BASED PLUMBING PIPING ADD 2 5/15/2025
220529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
220548.13 VIBRATION CONTROLS FOR PLUMBING PIPING AND EQUIPMENT ADD 2 5/15/2025
220553 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT ADD 2 5/15/2025
220593 TESTING, ADJUSTING AND BALANCING FOR PLUMBING ADD 2 5/15/2025
220716 PLUMBING EQUIPMENT INSULATION ADD 2 5/15/2025
220719 PLUMBING PIPING INSULATION ADD 2 5/15/2025
220800 COMMISSIONING OF PLUMBING ADD 2 5/15/2025
221116 DOMESTIC WATER PIPING ADD 2 5/15/2025
221117 GRAY-WATER PIPING ADD 2 5/15/2025
221119 DOMESTIC WATER PIPING SPECIALTIES ADD 2 5/15/2025
221123.21 INLINE, DOMESTIC-WATER PUMPS ADD 2 5/15/2025
221223.11 FACILITY INDOOR POTABLE-WATER STORAGE TANKS ADD 2 5/15/2025
221316 SANITARY WASTE AND VENT PIPING ADD 2 5/15/2025
221319 SANITARY WASTE PIPING SPECIALTIES ADD 2 5/15/2025
221323 SANITARY WASTER INTERCEPTORS ADD 2 5/15/2025
221329 SANITARY SEWERAGE PUMPS ADD 2 5/15/2025
221343 FACILITY PACKAGED SEWAGE PUMPING STATIONS ADD 2 5/15/2025
221363 FACILITY GRAY-WATER STORAGE TANKS ADD 2 5/15/2025
221413 FACILTY STORM DRAINAGE PIPING ADD 2 5/15/2025
221414 STORM DRAINAGE PIPING ADD 2 5/15/2025
221423 STORM DRAINAGE PIPING SPECIALTIES ADD 2 5/15/2025
221429 SUMP PUMPS ADD 2 5/15/2025
223300 ELECTRIC, DOMESTIC-WATER HEATERS ADD 2 5/15/2025
224213.13 COMMERCIAL WATER CLOSETS ADD 2 5/15/2025
224216.13 COMMERICAL LAVATORIES ADD 2 5/15/2025
224216.16 COMMERCIAL SINKS ADD 2 5/15/2025
224200 COMMERCIAL PLUMBING FIXTURES ADD 2 5/15/2025
224500 EMERGENCY PLUMBING FIXTURES ADD 2 5/15/2025
224713 DRINKING FOUNTAINS ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING
230500 COMMON WORK RESULTS FOR HVAC ADD 2 5/15/2025
230513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT ADD 2 5/15/2025
230517 SLEEVES AND SLEEVE SEALS FOR HVAC PIPING ADD 2 5/15/2025
230518 ESCUTCHEONS FOR HVAC PIPING ADD 2 5/15/2025
230519 METERS AND GAGES FOR HVAC PIPING ADD 2 5/15/2025
230523 GENERAL-DUTY VALVES FOR HVAC PIPING ADD 2 5/15/2025
230523.12 BALL VALVES FOR HVAC PIPING ADD 2 5/15/2025
230523.13 BUTTERFLY VALVES FOR HVAC PIPING ADD 2 5/15/2025
230523.14 CHECK VALVES FOR HVAC PIPING ADD 2 5/15/2025
230529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT ADD 2 5/15/2025
230548.13 VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT ADD 2 5/15/2025
230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT ADD 2 5/15/2025
230593 TESTING, ADJUSTING AND BALANCING FOR HVAC ADD 2 5/15/2025
230713 DUCT INSULATION ADD 2 5/15/2025
230716 HVAC EQUIPMENT INSULATION ADD 2 5/15/2025
230719 HVAC PIPING INSULATION ADD 2 5/15/2025
230800 COMMISSIONING OF HVAC ADD 2 5/15/2025
231123 FACILITY NATURAL-GAS PIPING ADD 2 5/15/2025
232113 HYDRONIC PIPING ADD 2 5/15/2025
232113.33 GROUND-LOOP HEAT-PUMP PIPING ADD 2 5/15/2025
232116 HYDRONIC PIPING SPECIALTIES ADD 2 5/15/2025
232123 HYDRONIC PUMPS ADD 2 5/15/2025
232300 REFRIGERANT PIPING ADD 2 5/15/2025
232500 HVAC FOR WATER TREATMENT ADD 2 5/15/2025
232513 WATER TREATMENT FOR CLOSED-LOOP HYDRONIC SYSTEMS ADD 2 5/15/2025
233113 METAL DUCTS ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
233116 NONMETAL DUCTS ADD 2 5/15/2025
233300 AIR DUCT ACCESSORIES ADD 2 5/15/2025
233346 FLEXIBLE DUCTS ADD 2 5/15/2025
233400 HVAC FANS ADD 2 5/15/2025
233416 CENTRIFUGAL HVAC PLANS ADD 2 5/15/2025
223423 HVAC POWER VENTILATORS ADD 2 5/15/2025
233533 LISTED KITCHEN VENTILATION SYSTEMS EXHAUST DUCTS ADD 2 5/15/2025
233600 AIR TERMINAL UNITS ADD 2 5/15/2025
233713.13 AIR DIFFUSERS ADD 2 5/15/2025
233713.23 REGISTERS AND GRILLES ADD 2 5/15/2025
233716 FABRIC AIR-DISTRIBUTION DEVICES ADD 2 5/15/2025
233813 COMMERCIAL-KITCHEN HOODS ADD 2 5/15/2025
236200 PACKAGED COMPRESSOR AND CONDENSER UNITS ADD 2 5/15/2025
236313 AIR-COOLED REFRIGERANT CONDENSERS ADD 2 5/15/2025
236514.16 CLOSED-CIRCUIT, INDUCED-DRAFT, COUNTERFLOW COOLING TOWERSADD 2 5/15/2025
237223.19 PACKAGED INDOOR FIXED PLATE ENERGY RECOVERY UNITS ADD 2 5/15/2025
237223.23 PACKAGED, OUTDOOR, HEAT WHEEL ENERGY RECOVERY UNITS ADD 2 5/15/2025
238126 SPLIT-SYSTEM AIR-CONDITIONERS ADD 2 5/15/2025
238146 WATER-SOURCE UNITARY HEAT PUMPS ADD 2 5/15/2025
DIVISION 26 - ELECTRICAL
260500 COMMON WORK RESULTS FOR ELECTRICAL ADD 2 5/15/2025
260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES ADD 2 5/15/2025
260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS ADD 2 5/15/2025
260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS ADD 2 5/15/2025
260533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS ADD 2 5/15/2025
260543 UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL SYSTEMS ADD 2 5/15/2025
260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
260570 OVERCURRENT PROTECTIVE DEVICE SHORT-CIRCUIT STUDIES ADD 2 5/15/2025
260800 COMMISSIONING OF ELECTRICAL SYSTEMS ADD 2 5/15/2025
260913 ELECTRICAL POWER MONITORING ADD 2 5/15/2025
260923 LIGHTING CONTROL DEVICES ADD 2 5/15/2025
262213 LOW-VOLTAGE DISTRIBUTION TRANSFORMERS ADD 2 5/15/2025
262413 SWITCHBOARDS ADD 2 5/15/2025
262416 PANELBOARDS ADD 2 5/15/2025
262726 WIRING DEVICES ADD 2 5/15/2025
262813 FUSES ADD 2 5/15/2025
262816 DISCONNECT SWITCHES ADD 2 5/15/2025
262818 CIRCUIT BREAKERS ADD 2 5/15/2025
263213 GAS-ENGINE-DRIVEN GENERATOR SETS ADD 2 5/15/2025
263600 TRANSFER SWITCHES ADD 2 5/15/2025
264113 LIGHTNING PROTECTION FOR STRUCTURES ADD 2 5/15/2025
265100 LIGHTING ADD 2 5/15/2025
DIVISION 27 - COMMUNICATIONS
270005 SPECIAL CONDITIONS FOR COMMUNICATIONS SYSTEMS ADD 2 5/15/2025
270526 GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS ADD 2 5/15/2025
270527 EXTERIOR PATHWAYS FOR COMMUNICATIONS SYSTEMS ADD 2 5/15/2025
270528 INTERIOR PATHWAYS FOR COMMUNICATIONS SYSTEMS ADD 2 5/15/2025
271100 COMMUNICATIONS EQUIPMENT ROOM FITTINGS ADD 2 5/15/2025
271310 COMMUNICATIONS MULTI MODE FIBER OPTIC CABLING ADD 2 5/15/2025
271505 COMMUNICATIONS CABLING CAT6 ADD 2 5/15/2025
274116 INTEGRATED AUDIOVISUAL SYSTEMS AND EQUIPMENT ADD 2 5/15/2025
275116 PUBLIC ADDRESS SYSTEMS ADD 2 5/15/2025
275123.5 EDUCATIONAL INTERCOMMUNICATIONS AND PROGRAM SYSTEMS ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
280005 SPECIAL CONDITIONS FOR SAFETY AND SECURITY SYSTEMS ADD 2 5/15/2025
280513 CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY ADD 2 5/15/2025
281306 ACCESS CONTROL AND ALARM SYSTEM - LENEL ADD 2 5/15/2025
282310 VIDEO SURVEILLANCE DEVICES ADD 2 5/15/2025
284600 FIRE ALARM SYSTEMS ADD 2 5/15/2025
284800 EMERGENCY RESPONSE SYSTEMS ADD 2 5/15/2025
DIVISION 31 - EARTHWORK
310100 EARTHWORK ADD 2 5/15/2025
311000 SITE CLEARING ADD 2 5/15/2025
316613 AGGREGATE PIERS ADD 2 5/15/2025
DIVISION 32 - EXTERIOR IMPROVEMENTS
321216 ASPHALT PAVING ADD 2 5/15/2025
321313 CONCRETE PAVING ADD 2 5/15/2025
321443 POROUS FLEXIBLE PAVING ADD 2 5/15/2025
321813 SYNTHETIC GRASS SURFACING ADD 2 5/15/2025
321916.13 PLAYGROUND PROTECTIVE SAFETY SURFACE ADD 2 5/15/2025
323113 CHAIN LINK FENCES AND GATES ADD 2 5/15/2025
323119 DECORATIVE METAL FENCES AND GATES ADD 2 5/15/2025
323300 SITE FURNISHINGS ADD 2 5/15/2025
329300 EXTERIOR PLANTS ADD 2 5/15/2025
DIVISION 33 - UTILITIES
310000 WATER UTILITIES ADD 2 5/15/2025
333000 SANITARY SEWER UTILITIES ADD 2 5/15/2025
BRENT ELEMENTARY SCHOOL
ADDENDUM 2
DLR GROUP
THURSDAY, MAY 15TH 2025
DRAWINGS & SKETCHES DLR GROUP
DRAWING OR
SKETCH NO. DESCRIPTION REV. NO. DATE ON DOC.
DOCUMENT LIST (DRAWINGS, SKETCHES, SPECIFICATIONS, ADDENDA & OTHER DOCUMENTS
334000 STORM DRAINAGE UTILITIES ADD 2 5/15/2025
g and Specifications
Exhibit B
List of Allowance

OWNER ALLOWANCES
Permit Allowance (Including cost for DOB’s Accelerated Permit Program) $900,000
Public Art Allowance $500,000
Utility Allowance $600,000
Public Space Improvement Allowance $500,000
Owner Directed Changes $3,000,000
Moving allowance for round trip moving services from Brent ES to Meyers ES -
Swing Space and back to Brent $250,000
Six Months Maintenance Allowance (Removed per DGS direction) $0
Excavation of existing partial building below grade for the Archaeology Dig.
Based on a market unit rate of $65/cy for approximately 1,600cy for a 5' cut.
This includes equipment, excavation and haul off. $104,000
Archaeology - Professional Services (Reduced from $750,000 down to
$115,000) $115,000
Site Requirements $187,026
GRAND TOTAL ALLOWANCES $6,156,026
Brent Elementary School Guaranteed Maximum Price (GMP)
List of Allowances
Updated Wednesday, October 8th, 2025

Exhibit C
Contractors Assumptions and
Clarifications

BRENT ELEMENTARY SCHOOL
GUARANTEED MAXIMUM PRICE (GMP) SUBMISSION
ASSUMPTIONS AND CLARIFICATIONS
Friday, September 26th, 2025

GENERAL
1. RFI 086 – School Feedback for Furniture (Reggio Emilia) currently remains open. We have not included
any additional furniture cost in the GMP submission for this pending RFI response. Furniture per the
Ed Spec is included in the GMP.

SUBSTRUCTURE - FOUNDATION & EXCAVATION (Div 02 & Div 03)
1. None

SHELL - SUPERSTRUCTURE/STRUCTURAL SYSTEMS (Div 03, Div 05 & Div 07)
1. None

SHELL - EXTERIOR CLOSURE SYSTEMS (DIV 04, DIV 07 & DIV 08)
1. We do not include parging as described in Spec Section 042000 Unit Masonry, paragraph 3.15.
2. We include one 10’x10’ on-site composite exterior material mockup.

SHELL - ROOFING SYSTEMS (DIV 07)
1. We include electronic leak detection. We do not include active leak monitoring.

INTERIORS – INTERIOR CONSTRUCTION SYSTEMS/STAIRS/FINISHES (Div 05, Div 06 & Div 09)
1. None
EQUIPMENT AND FURNISHINGS (Div 10, 11 & 12)
1. None

SERVICES - FIRE PROTECTION SYSTEMS (Div 21)
1. We have not included a fire pump. Per the fire flow test a fire pump is not needed to achieve water
pressure for the designed building height.

SERVICES – PLUMBING & HVAC SYSTEMS (Div 22 & Div 23)
1. None

SERVICES - ELECTRICAL SYSTEMS & LOW VOLTAGE (Div 26, Div 27 & Div 28)
1. We exclude street light upgrades or replacement. If required by permit review process, these will be
funded from Public Space Allowance.

BUILDING SITE WORK – EARTHWORK/SITE IMPROVEMENTS/SITE UTILITIES SYSTEMS (Div 31, Div 32 &
Div 33)
1. None

GENERAL CONDITIONS & SITE REQUIREMENTS
1. None

Exhibit D
Statement of cost estimate

LETTER CONTRACT ESA # 1 ESA # 2 TOTAL
Div # Description Design & Permitting
Early Trades & Long
Lead Equipment GMP Total Trade Partner Notes Letter + ESA #1 + ESA #2 + GMP% CBE $ CBE % SBE $ SBE
0001
General Requirements (Doesn't include Final Cleaning -
Carried in separate Bid Package)
413,183$ 1,780,917$ Various Trades inc. SMOOT DC
GR reduction due to the
removal of final
cleaning. Final Cleaning
is being carried as a
separate bid package -
see below
2,194,100$ 35% 767,935$ 35% 767,935$
0001 Interim & Final Cleaning -$ 141,000$ DGC Cleaning Services 141,000$ 100% 141,000$ 100% 141,000$
0241116 Demo, Abatement, IH and Support of Excavation (SOE) 845,425$ 1,153,475$ COMBO: Goel DC + HP Environmental + Atlas
Foundations 1,998,900$ 100% 1,998,900$ 100% 1,998,900$
033000 Building Concrete 58,650$ 2,889,950$ LA Howard Construction Co 2,948,600$ 100% 2,948,600$ 100% 2,948,600$
042000 Masonry + Caulking/Joint Sealants (Interior & Exterior)
-$ 2,483,374$ COMBO: Hammer Masonry + Forsythe
Masonry scope
increased from just the
interior CMU Block at
the Stairs, Elevator and
Gym to including the
updated brick façade.
2,483,374$ 30% 745,012$ 30% 745,012$
051200 Structural Steel + Misc. Metals 78,000$ 5,602,125$ Crystal Steel + Creation Steel Fab 5,680,125$ 52% 2,953,665$ 52% 2,953,665$
055000 Metal Fabrications (Included in above in Structural Steel BP) -$ -$ - $ 0% - $ 0% - $
061000 Rough Carpentry -$ 231,108$ P&D Contractors 231,108$ 100% 231,108$ 100% 231,108$
064023 Finish Carpentry -$ 1,206,361$ Architectural Wood LLC 1,206,361$ 20% 241,272$ 20% 241,272$
071326 Waterproofing -$ 301,888$ HRGM 301,888$ 100% 301,888$ 100% 301,888$
072726 Air Vapor Barrier (AVB) -$ 254,388$ Energy One America 254,388$ 0% -$ 0% -$
075419 Roofing -$ 1,749,176$ HRGM 1,749,176$ 100% 1,749,176$ 100% 1,749,176$
079200 Joint Sealants (Included in Masonry) -$ -$ Included w/ the
Masonry BP -$ 0% - $ 0% - $
074213.23 Taktl Panels (Exterior Façade)
74,800$ (74,800)$ - $ 0% - $ 0% - $
088000 Glass, Glazing, Metal Panels, Screen wall & Louvers
45,000$ 4,312,200$ All Pro Glass LLC 4,357,200$ 100% 4,357,200$ 100% 4,357,200$
087100 Doors, Frames, and Hardware -$ 831,625$ Cap 8 831,625$ 100% 831,625$ 100% 831,625$
083323 Overhead Coiling Doors -$ 16,517$ Door Systems 16,517$ 0% -$ 0% -$
092900 Drywall, Framing & Ceilings -$ 3,653,281$ P & D Contractors 3,653,281$ 100% 3,653,281$ 100% 3,653,281$
093013 Hard Tile (Ceramic) -$ 420,105$ Allstate Floors 420,105$ 100% 420,105$ 100% 420,105$
096519 Flooring (Resilient inc. Athletic Flooring & Floor Mats) -$ 777,178$ Source One Flooring + Weyers Flooring 777,178$ 60% 466,307$ 60% 466,307$
096623 Terrazzo Flooring -$ 652,363$ Roman Mosaic 652,363$ 0% -$ 0% -$
096723 Resinous Flooring -$ 75,000$ Majestik Surface Corporation 75,000$ 0% -$ 0% -$
099123 Painting & Wall Covering -$ 380,300$ BB & Co. Construction, LLC 380,300$ 100% 380,300$ 0% -$
101100 Visual Display Systems (Tackboards + Markerboards) -$ 75,260$ Cap 8 75,260$ 100% 75,260$ 100% 75,260$
101423 Signage (Interior + Exterior)
-$ 172,571$ Modulex Mid Atlantic
Increase due to
including additional
signage package for
Meyers ES - Swing Space
172,571$ 100% 172,571$ 100% 172,571$
102800 Div 10 - Specialties -$ 133,019$ Partition Plus, Inc. 133,019$ 0% -$ 0% -$
107516 Flagpoles -$ 7,694$ Flagpoles Etc. 7,694$ 0% -$ 0% -$
110000 Custodial Equipment 44,272$ Custodial Equipment 44,272$ 0% -$ 0% -$
114000 Kitchen Equipment -$ 499,649$ Singer Equipment Co 499,649$ 0% -$ 0% -$
114000 Theater Equipment -$ 92,259$ Pittsburg Stage, Inc. 92,259$ 0% -$ 0% -$
116623 Athletic (Gymnasium) Equipment -$ 198,900$ Degler - Whiting, Inc. 198,900$ 0% -$ 0% -$
116800 Playground Equipment & Play Surfacing -$ 895,559$ All Recreation of VA Kompan is the Basis of
Design (BOD) 895,559$ 0% - $ 0% - $
120000 FF&E (Loose Furnishings) -$ 1,679,547$ COMBO: DES of DC + Peabody Office 1,679,547$ 100% 1,679,547$ 100% 1,679,547$
122413 Window Shades -$ 128,409$ GB Shades 128,409$ 0% -$ 0% -$
124813 Entrance Mats & Frames (Inc. with Resilient Flooring) -$ -$ Source One Flooring + Weyers Flooring -$ 0% -$ 0% -$
142123 Elevator -$ 430,131$ Delaware Elevator 430,131$ 0% -$ 0% -$
210000 Fire Protection (Sprinklers) 197,750$ 753,927$ Continental Fire Sprinkler 951,677$ 20% 190,335$ 20% 190,335$
220000 +
230000 Mechanical (HVAC, Plumbing & Geothermal) 115,000$ 11,312,477$ R & R Mechanical, LLC + Allied Well Driling 11,427,477$ 35% 3,999,617$ 35% 3,999,617$
GMP CBE/SBE PARTICIPATION (TOTAL)
GOAL: 35%
Brent Elementary School - Guaranteed Maximum Price (GMP)
GMP Summary Sheet
Updated Wednesday, October 8th, 2025
10/8/2025
LETTER CONTRACT ESA # 1 ESA # 2 TOTAL
Div # Description Design & Permitting
Early Trades & Long
Lead Equipment GMP Total Trade Partner Notes Letter + ESA #1 + ESA #2 + GMP% CBE $ CBE % SBE $ SBE
GMP CBE/SBE PARTICIPATION (TOTAL)
GOAL: 35%
Brent Elementary School - Guaranteed Maximum Price (GMP)
GMP Summary Sheet
Updated Wednesday, October 8th, 2025
- Mechanical Equipment: RTU, DOAS, WSHP, Fans, Pumps,
VAV's Procurement 1,300,000$ 797,000$ R & R Mechanical, LLC + Allied Well Driling 2,097,000$ 35% 733,950$ 35% 733,950$
260000,
270000 +
2800000 Electrical, Fire Alarm & Low Voltage 1,076,200$ 9,547,554$ Freestate Electric Construction Company + HS
Solutions 10,623,754$ 25% 2,655,939$ 25% 2,655,939$
310000 Earthwork (including Site Demo) 1,284,467$ 313,003$ Goel DC 1,597,470$ 100% 1,597,470$ 100% 1,597,470$
- Excavate partial basement below grade for Archaeology Dig
( See Allowances) -$ -$ - $ 0% - $ 0% - $
Archaeology - Professional Services ( See Allowances) -$ -$ -$ 0% -$ 0% -$
311000 Aggregate Piers -$ 165,000$ Michaels Corporation 165,000$ 0% -$ 0% -$
321216 Asphalt Paving -$ 150,192$ Fort Myer 150,192$ 100% 150,192$ 0% -$
321313 Site Concrete + Brick Paving -$ 700,678$ LA Howard Construction 700,678$ 100% 700,678$ 100% 700,678$
323119 Fences & Gates -$ 133,760$ Hercules Fence of Maryland, LLC 133,760$ 0% -$ 0% -$
329300 Landscaping, Plantings & Site Furnishings -$ 333,401$ W.H. Boyer, Inc. 333,401$ 0% -$ 0% -$
329300 Site Furnishings -$ 300,000$ W.H. Boyer, Inc. 300,000$ 0% -$ 0% -$
330000 Site Utilities -$ 634,020$ JJ Magnolia Inc 634,020$ 100% 634,020$ 0% -$
Bid Package Subtotal: 5,488,475$ 58,335,813$ 63,824,288$ 54% 34,776,953$ 53% 33,612,441$
General Conditions 584,784$ 2,222,179$ 2,806,963$ 100% 2,806,963$ 0% -$
Preconstruction Fees 48,000$ 136,500$ -$ 184,500$ 100% 184,500$ 0% -$
Design Fees (DLR Group + Subconsultants) 747,974$ 2,695,809$ 656,217$ 4,100,000$ 80% 3,280,000$ 0% -$
Additional Design Services: Façade Redesign Scenarios
(+$60k) & the Façade change from UHPC to Brick (+$155.5k) 215,500$ 215,500 $
80% 172,400$ 0% - $
Payment and Performance Bond @ 1.1% 962,446$ 962,446$ 100% 962,446$ 0% -$
Insurances 12,000$ 50,000$ 485,012$ 1,859,104$ 2,406,116$ 100% 2,406,116$ 0% -$
Excess Subcontractor Insurance "Cyber, Pollution &
Professional" 873,772$ 873,772 $ 100% 873,772$ 0% -$
Cost of Work Subtotal: 807,974$ 2,882,309$ 6,558,271$ 65,125,031$ 75,373,585$ 60% 45,463,150$ 45% 33,612,441$
Permit Allowance (Including cost for DOB’s Accelerated
Permit Program) 900,000$ - $ 900,000 $ 0% - $ 0% - $
Public Art Allowance 500,000$ 500,000$ 0% -$ 0% -$
Utility Allowance 600,000$ -$ 600,000$ 0% -$ 0% -$
Public Space Improvement Allowance 500,000$ -$ 500,000$ 0% -$ 0% -$
Owner Directed Changes 500,000$ 2,500,000$ 3,000,000$ 0% -$ 0% -$
Moving allowance for round trip moving services from Brent
ES to Meyers ES - Swing Space and back to Brent 250,000$ 250,000 $
Six Months Maintenance Allowance (Removed per DGS
direction) -$ - $ 0% - $ 0% - $
Excavation of existing partial building below grade for the
Archaeology Dig. Based on a market unit rate of $65/cy for
approximately 1,600cy for a 5' cut. This includes equipment,
excavation and haul off. 104,000$ 104,000 $
100% 104,000$ 100% 104,000$
Archaeology - Professional Services (Reduced from $750,000
down to $115,000) 750,000$ (635,000)$ 115,000 $ 0% - $ 0% - $
Site Requirements 187,026$ -$ 187,026$ 100% 187,026$ 100% 187,026$
Allowance Subtotal -$ 2,000,000$ 1,354,000$ 2,615,000$ 6,156,026$ 5% 291,026$ 5% 291,026$
Construction Contingency 237,368$ 3,862,632$ 4,100,000$ 54% 2,234,032$ 53% 2,159,225$
"Base" DB Fee 63,500$ 117,653$ 864,347$ 1,045,500$ 100% 1,045,500$ 0% -$
"At Risk" DB Fee 820,000$ 820,000$ 100% 820,000$ 0% -$
TOTAL COST W/ OWNER ALLOWANCES 995,000$ 4,945,809$ 8,267,292$ 73,287,010$ 87,495,111$ 57% 49,853,708$ 41% 36,062,692$
10/8/2025
Exhibit E
Baseline Schedule

Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 1 of 24
Brent Elementary School
NTP-1000 Anticipated Award
NTP-1010 NTP/Design Start
Milestones
MIL-1000 Design Start
MIL-1010 Concept Submission
MIL-1020 Early Start Agreement Approved (Remaining FY24 Funding)
MIL-1030 Schematic Design Documents Submitted
MIL-1040 Approve Early Trades for Long Lead Equipment Purchase
MIL-1050 FY25 Funding Approved
MIL-1060 Design Development Documents Submitted
MIL-1070 Mobilize for Archeology Study
MIL-1080 Mobilize On Site for Abatement & Utility Disconnects
MIL-1090 Full Site Access
MIL-1100 Work site Archeology Study Completion
MIL-1110 GMP Approved FY26 Funding
MIL-1115 Temporary Power
MIL-1120 Existing Building Demolished/Razed
MIL-1130 Building Top off
MIL-1135 Temporary Dry in
MIL-1150 Temp heat/Cooling and Install Filter Fabric
MIL-1160 Energize Permanent Power
MIL-1165 Building Watertight
MIL-1170 Substantial Completion
MIL-1180 Teacher Move-in
MIL-1190 Student Start
MIL-1200 Final Completion
MIL-1210 Administrative Completion
FY24 Letter Contract Funding
PRE-1000 Kick-Off Meetings
PRE-1010 Confirmation Site Surveys & Due Diligence
Initial Deliverables
INI-1000 Prep & Submit & Review Baseline Schedule
INI-1010 January Community Meeting
INI-1020 Construction Management Plan
INI-1030 Quality Control Plan
INI-1040 Long Lead/Supply Chain Concerns List
INI-1050 Prep & Submit Assessment Report
FY24 Funding (Early Start Agreement)
ESA-1000 DGS & Design-Build Team Finalize Scope/Budget
ESA-1010 Develop Council Approval Package
1,091d 06-Nov-23 15-Mar-28
5d 06-Nov-23 CC 10-Nov-23
0d 01-Dec-23
1,074d 01-Dec-23 15-Mar-28
0d 01-Dec-23
0d 01-Apr-24
0d 15-May-24
0d 21-Aug-24
0d 13-Jan-25
0d 27-Feb-25
0d 11-Mar-25
0d 24-Jun-25
0d 15-Aug-25
0d 15-Aug-25
0d 25-Aug-25
0d 30-Oct-25
0d 11-Feb-26
0d 04-Mar-26
0d 23-Oct-26
0d 14-Jan-27
0d 14-Jan-27
0d 21-Apr-27
0d 01-Mar-27
0d 15-Jul-27
0d 15-Jul-27 CC
0d 12-Aug-27 CC
0d 17-Jan-28
0d 15-Mar-28
76d 16-Nov-23 29-Feb-24
5d 16-Nov-23 22-Nov-23
68d 16-Nov-23 19-Feb-24
76d 16-Nov-23 29-Feb-24
60d 16-Nov-23 07-Feb-24
0d 16-Jan-24 CC
16d 08-Feb-24 29-Feb-24
16d 08-Feb-24 29-Feb-24
16d 08-Feb-24 29-Feb-24
16d 08-Feb-24 29-Feb-24
87d 11-Jan-24 15-May-24
20d 11-Jan-24 08-Feb-24
20d 09-Feb-24 08-Mar-24
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Brent Elementary SchoBrent Elementary SchoBrent Elementary SchBrent Elementary SchoBrent Elementary Scho
Anticipated AwardAnticipated AwardAnticipated AwardAnticipated AwardAnticipated Award
  NTP/Design StartNTP/Design StartNTP/Design StartNTP/Design StartNTP/Design Start
MilestonesMilestonesMilestonesMilestonesMilestones
  Design StartDesign StartDesign StartDesign StartDesign Start
  Concept SubmissionConcept SubmissionConcept SubmissionConcept SubmissionConcept Submission
  Early Start Agreement Approved (Remaining FY24 Funding)Early Start Agreement Approved (Remaining FY24 Funding)Early Start Agreement Approved (Remaining FY24 Funding)Early Start Agreement Approved (Remaining FY24 Funding)Early Start Agreement Approved (Remaining FY24 Funding)
  Schematic Design Documents SubmittedSchematic Design Documents SubmittedSchematic Design Documents SubmittedSchematic Design Documents SubmittedSchematic Design Documents Submitted
  Approve Early Trades for Long Lead Equipment PurchaseApprove Early Trades for Long Lead Equipment PurchaseApprove Early Trades for Long Lead Equipment PurchaseApprove Early Trades for Long Lead Equipment PurchaseApprove Early Trades for Long Lead Equipment Purchase
  FY25 Funding ApprovedFY25 Funding ApprovedFY25 Funding ApprovedFY25 Funding ApprovedFY25 Funding Approved
  Design Development Documents SubmittedDesign Development Documents SubmittedDesign Development Documents SubmittedDesign Development Documents SubmittedDesign Development Documents Submitted
  Mobilize for Archeology StudyMobilize for Archeology StudyMobilize for Archeology StudyMobilize for Archeology StudyMobilize for Archeology Study
  Mobilize On Site for Abatement & Utility DisconnectsMobilize On Site for Abatement & Utility DisconnectsMobilize On Site for Abatement & Utility DisconnectsMobilize On Site for Abatement & Utility DisconnectsMobilize On Site for Abatement & Utility Disconnects
  Full Site AccessFull Site AccessFull Site AccessFull Site AccessFull Site Access
  Work site Archeology Study CompletionWork site Archeology Study CompletionWork site Archeology Study CompletionWork site Archeology Study CompletionWork site Archeology Study Completion
  GMP Approved FY26 FundingGMP Approved FY26 FundingGMP Approved FY26 FundingGMP Approved FY26 FundingGMP Approved FY26 Funding
  Temporary PowerTemporary PowerTemporary PowerTemporary PowerTemporary Power
  Existing Building Demolished/RazedExisting Building Demolished/RazedExisting Building Demolished/RazedExisting Building Demolished/RazedExisting Building Demolished/Razed
  Building Top offBuilding Top offBuilding Top offBuilding Top offBuilding Top off
  Temporary Dry inTemporary Dry inTemporary Dry inTemporary Dry inTemporary Dry in
  Temp heat/Cooling and Install Filter FabricTemp heat/Cooling and Install Filter FabricTemp heat/Cooling and Install Filter FabricTemp heat/Cooling and Install Filter FabricTemp heat/Cooling and Install Filter Fabric
  Energize Permanent PowerEnergize Permanent PowerEnergize Permanent PowerEnergize Permanent PowerEnergize Permanent Power
  Building WatertightBuilding WatertightBuilding WatertightBuilding WatertightBuilding Watertight
  Substantial CompletionSubstantial CompletionSubstantial CompletionSubstantial CompletionSubstantial Completion
  Teacher Move-inTeacher Move-inTeacher Move-inTeacher Move-inTeacher Move-in
  Student StartStudent StartStudent StartStudent StartStudent Start
  Final CompletionFinal CompletionFinal CompletionFinal CompletionFinal Completion
  Administrative CompAdministrative CompAdministrative CompAdministrative CompAdministrative Comp
FY24 Letter Contract FundingFY24 Letter Contract FundingFY24 Letter Contract FundingFY24 Letter Contract FundingFY24 Letter Contract Funding
Kick-Off MeetingsKick-Off MeetingsKick-Off MeetingsKick-Off MeetingsKick-Off Meetings
Confirmation Site Surveys & Due DiligenceConfirmation Site Surveys & Due DiligenceConfirmation Site Surveys & Due DiligenceConfirmation Site Surveys & Due DiligenceConfirmation Site Surveys & Due Diligence
Initial DeliverablesInitial DeliverablesInitial DeliverablesInitial DeliverablesInitial Deliverables
Prep & Submit & Review Baseline SchedulePrep & Submit & Review Baseline SchedulePrep & Submit & Review Baseline SchedulePrep & Submit & Review Baseline SchedulePrep & Submit & Review Baseline Schedule
  January Community MeetingJanuary Community MeetingJanuary Community MeetingJanuary Community MeetingJanuary Community Meeting
Construction Management PlanConstruction Management PlanConstruction Management PlanConstruction Management PlanConstruction Management Plan
Quality Control PlanQuality Control PlanQuality Control PlanQuality Control PlanQuality Control Plan
Long Lead/Supply Chain Concerns ListLong Lead/Supply Chain Concerns ListLong Lead/Supply Chain Concerns ListLong Lead/Supply Chain Concerns ListLong Lead/Supply Chain Concerns List
Prep & Submit Assessment ReportPrep & Submit Assessment ReportPrep & Submit Assessment ReportPrep & Submit Assessment ReportPrep & Submit Assessment Report
FY24 Funding (Early Start Agreement)FY24 Funding (Early Start Agreement)FY24 Funding (Early Start Agreement)FY24 Funding (Early Start Agreement)FY24 Funding (Early Start Agreement)
DGS & Design-Build Team Finalize Scope/BudgetDGS & Design-Build Team Finalize Scope/BudgetDGS & Design-Build Team Finalize Scope/BudgetDGS & Design-Build Team Finalize Scope/BudgetDGS & Design-Build Team Finalize Scope/Budget
Develop Council Approval PackageDevelop Council Approval PackageDevelop Council Approval PackageDevelop Council Approval PackageDevelop Council Approval Package
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 2 of 24
ESA-1020 Council Approval Process (Remaining FY24 Budget)
ESA-1030 Early Start Agreement Approved
Concept Design
CPT-1000 Develop & Submit Concept Design Package
CPT-1010 Updated Schedule and Logistic Planning
CPT-1020 Prepare & Submit Cost Estimate Budget & VE Suggestion…
CPT-1040 Prep & Submit Construction Concerns
CPT-1050 Dev Preliminary Cash Flow Analysis
CPT-1060 SIT Meeting 1 Kick-off with Design-Build Team
CPT-1070 DGS/Community Meetings Conceptual Approval Process
CPT-1080 SIT Meeting 2 Concept Design Presentation
CPT-1090 SIT Meeting 3 Concept Design Feedback Working
Schematic Design
SCH-1000 Dev & Subt Schematic Design Documents
SCH-1010 Dev & Subt SD Cost Est with Trade Input
SCH-1020 Dev & Subt SD VE Suggestions (If Required)
SCH-1030 Dev & Subt SD Schedule & Site Logistics Updates
SCH-1040 Dev & Sbmt LEED & Sustainable Score Card
SCH-1050 Dev & Subt Updated: SD Cash Flow/Constructability
SCH-1060 SIT Meeting 4 Schematic Design Presentation
SCH-1070 SIT Meeting 5 Schematic Design Feedback Working
SCH-1075 SIT Meeting 6 Playground
SCH-1080 DGS/Team Meetings/Approval of SD Package
SCH-1090 Develop Raze Permit Submission (Advancing SD for Raze …
Archeological Investigation Phase II
AID-1000 SHPO Approval of Phase 1B Investigation
AID-1010 Creation & Submission of Final 1B Report
AID-1020 Recommendation for Phase II Workplan
AID-1030 DGS Approval of Phase II Recommendation
AID-1040 Creation of Phase II Workplan
AID-1050 DGS Approval of Phase II Workplan
AID-1060 SHPO Approval of Phase II Workplan
AID-1070 Acquisition of Trades & labor
AID-1080 Soil Remediation Report
AID-1090 Permit Processing
AID-1100 Execution of Workplan
AID-1105 Additional Archeology on Site
AID-1110 Creation of Draft Report
AID-1120 DGS Approval of Draft Report
AID-1130 SHPO Approval of Draft Report
AID-1140 Creation & Submission of Final Report
47d 11-Mar-24 15-May-24
0d 15-May-24
123d 04-Dec-23 29-May-24
82d 04-Dec-23 01-Apr-24
82d 04-Dec-23 01-Apr-24
82d 04-Dec-23 01-Apr-24
82d 04-Dec-23 01-Apr-24
82d 04-Dec-23 01-Apr-24
10d 12-Feb-24 26-Feb-24
40d 02-Apr-24 29-May-24
17d 02-Apr-24 25-Apr-24
11d 26-Apr-24 10-May-24
164d 30-May-24 24-Jan-25
60d 30-May-24 21-Aug-24
60d 30-May-24 21-Aug-24
60d 30-May-24 21-Aug-24
60d 30-May-24 21-Aug-24
60d 30-May-24 21-Aug-24
60d 30-May-24 21-Aug-24
10d 26-Aug-24 06-Sep-24
10d 09-Sep-24 20-Sep-24
19d 23-Sep-24 18-Oct-24
57d 23-Aug-24 11-Nov-24
50d 12-Nov-24 24-Jan-25
301d 10-Sep-24 20-Nov-25
122d 10-Sep-24 07-Mar-25
126d 10-Mar-25 01-Sep-25
4d 10-Mar-25 13-Mar-25
5d 14-Mar-25 20-Mar-25
4d 10-Mar-25 13-Mar-25
5d 14-Mar-25 20-Mar-25
20d 21-Mar-25 18-Apr-25
45d 21-Apr-25 23-Jun-25
84d 27-Dec-24 23-Apr-25
121d 27-Dec-24 20-Jun-25
44d 24-Jun-25 25-Aug-25
30d 15-Jul-25 25-Aug-25
20d 26-Aug-25 23-Sep-25
5d 24-Sep-25 30-Sep-25
20d 01-Oct-25 29-Oct-25
15d 30-Oct-25 20-Nov-25
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Council Approval Process (Remaining FY24 Budget)Council Approval Process (Remaining FY24 Budget)Council Approval Process (Remaining FY24 Budget)Council Approval Process (Remaining FY24 Budget)Council Approval Process (Remaining FY24 Budget)
  Early Start Agreement ApprovedEarly Start Agreement ApprovedEarly Start Agreement ApprovedEarly Start Agreement ApprovedEarly Start Agreement Approved
Concept DesignConcept DesignConcept DesignConcept DesignConcept Design
Develop & Submit Concept Design PackageDevelop & Submit Concept Design PackageDevelop & Submit Concept Design PackageDevelop & Submit Concept Design PackageDevelop & Submit Concept Design Package
Updated Schedule and Logistic PlanningUpdated Schedule and Logistic PlanningUpdated Schedule and Logistic PlanningUpdated Schedule and Logistic PlanningUpdated Schedule and Logistic Planning
Prepare & Submit Cost Estimate Budget & VE Suggestions (if Required)Prepare & Submit Cost Estimate Budget & VE Suggestions (if Required)Prepare & Submit Cost Estimate Budget & VE Suggestions (if Required)Prepare & Submit Cost Estimate Budget & VE Suggestions (if Required)Prepare & Submit Cost Estimate Budget & VE Suggestions (if Required)
Prep & Submit Construction ConcernsPrep & Submit Construction ConcernsPrep & Submit Construction ConcernsPrep & Submit Construction ConcernsPrep & Submit Construction Concerns
Dev Preliminary Cash Flow AnalysisDev Preliminary Cash Flow AnalysisDev Preliminary Cash Flow AnalysisDev Preliminary Cash Flow AnalysisDev Preliminary Cash Flow Analysis
SIT Meeting 1 Kick-off with Design-Build TeamSIT Meeting 1 Kick-off with Design-Build TeamSIT Meeting 1 Kick-off with Design-Build TeamSIT Meeting 1 Kick-off with Design-Build TeamSIT Meeting 1 Kick-off with Design-Build Team
DGS/Community Meetings Conceptual Approval ProcessDGS/Community Meetings Conceptual Approval ProcessDGS/Community Meetings Conceptual Approval ProcessDGS/Community Meetings Conceptual Approval ProcessDGS/Community Meetings Conceptual Approval Process
SIT Meeting 2 Concept Design PresentationSIT Meeting 2 Concept Design PresentationSIT Meeting 2 Concept Design PresentationSIT Meeting 2 Concept Design PresentationSIT Meeting 2 Concept Design Presentation
SIT Meeting 3 Concept Design Feedback WorkingSIT Meeting 3 Concept Design Feedback WorkingSIT Meeting 3 Concept Design Feedback WorkingSIT Meeting 3 Concept Design Feedback WorkingSIT Meeting 3 Concept Design Feedback Working
Schematic DesignSchematic DesignSchematic DesignSchematic DesignSchematic Design
Dev & Subt Schematic Design DocumentsDev & Subt Schematic Design DocumentsDev & Subt Schematic Design DocumentsDev & Subt Schematic Design DocumentsDev & Subt Schematic Design Documents
Dev & Subt SD Cost Est with Trade InputDev & Subt SD Cost Est with Trade InputDev & Subt SD Cost Est with Trade InputDev & Subt SD Cost Est with Trade InputDev & Subt SD Cost Est with Trade Input
Dev & Subt SD VE Suggestions (If Required)Dev & Subt SD VE Suggestions (If Required)Dev & Subt SD VE Suggestions (If Required)Dev & Subt SD VE Suggestions (If Required)Dev & Subt SD VE Suggestions (If Required)
Dev & Subt SD Schedule & Site Logistics UpdatesDev & Subt SD Schedule & Site Logistics UpdatesDev & Subt SD Schedule & Site Logistics UpdatesDev & Subt SD Schedule & Site Logistics UpdatesDev & Subt SD Schedule & Site Logistics Updates
Dev & Sbmt LEED & Sustainable Score CardDev & Sbmt LEED & Sustainable Score CardDev & Sbmt LEED & Sustainable Score CardDev & Sbmt LEED & Sustainable Score CardDev & Sbmt LEED & Sustainable Score Card
Dev & Subt Updated: SD Cash Flow/ConstructabilityDev & Subt Updated: SD Cash Flow/ConstructabilityDev & Subt Updated: SD Cash Flow/ConstructabilityDev & Subt Updated: SD Cash Flow/ConstructabilityDev & Subt Updated: SD Cash Flow/Constructability
SIT Meeting 4 Schematic Design PresentationSIT Meeting 4 Schematic Design PresentationSIT Meeting 4 Schematic Design PresentationSIT Meeting 4 Schematic Design PresentationSIT Meeting 4 Schematic Design Presentation
SIT Meeting 5 Schematic Design Feedback WorkingSIT Meeting 5 Schematic Design Feedback WorkingSIT Meeting 5 Schematic Design Feedback WorkingSIT Meeting 5 Schematic Design Feedback WorkingSIT Meeting 5 Schematic Design Feedback Working
SIT Meeting 6 PlaygroundSIT Meeting 6 PlaygroundSIT Meeting 6 PlaygroundSIT Meeting 6 PlaygroundSIT Meeting 6 Playground
DGS/Team Meetings/Approval of SD PackageDGS/Team Meetings/Approval of SD PackageDGS/Team Meetings/Approval of SD PackageDGS/Team Meetings/Approval of SD PackageDGS/Team Meetings/Approval of SD Package
Develop Raze Permit Submission (Advancing SD for Raze Permit)Develop Raze Permit Submission (Advancing SD for Raze Permit)Develop Raze Permit Submission (Advancing SD for Raze Permit)Develop Raze Permit Submission (Advancing SD for Raze Permit)Develop Raze Permit Submission (Advancing SD for Raze Permit)
Archeological Investigation Phase IIArcheological Investigation Phase IIArcheological Investigation Phase IIArcheological Investigation Phase IIArcheological Investigation Phase II
SHPO Approval of Phase 1B InvestigationSHPO Approval of Phase 1B InvestigationSHPO Approval of Phase 1B InvestigationSHPO Approval of Phase 1B InvestigationSHPO Approval of Phase 1B Investigation
Creation & Submission of Final 1B ReportCreation & Submission of Final 1B ReportCreation & Submission of Final 1B ReportCreation & Submission of Final 1B ReportCreation & Submission of Final 1B Report
Recommendation for Phase II WorkplanRecommendation for Phase II WorkplanRecommendation for Phase II WorkplanRecommendation for Phase II WorkplanRecommendation for Phase II Workplan
DGS Approval of Phase II RecommendationDGS Approval of Phase II RecommendationDGS Approval of Phase II RecommendationDGS Approval of Phase II RecommendationDGS Approval of Phase II Recommendation
Creation of Phase II WorkplanCreation of Phase II WorkplanCreation of Phase II WorkplanCreation of Phase II WorkplanCreation of Phase II Workplan
DGS Approval of Phase II WorkplanDGS Approval of Phase II WorkplanDGS Approval of Phase II WorkplanDGS Approval of Phase II WorkplanDGS Approval of Phase II Workplan
SHPO Approval of Phase II WorkplanSHPO Approval of Phase II WorkplanSHPO Approval of Phase II WorkplanSHPO Approval of Phase II WorkplanSHPO Approval of Phase II Workplan
Acquisition of Trades & laborAcquisition of Trades & laborAcquisition of Trades & laborAcquisition of Trades & laborAcquisition of Trades & labor
Soil Remediation ReportSoil Remediation ReportSoil Remediation ReportSoil Remediation ReportSoil Remediation Report
Permit ProcessingPermit ProcessingPermit ProcessingPermit ProcessingPermit Processing
Execution of WorkplanExecution of WorkplanExecution of WorkplanExecution of WorkplanExecution of Workplan
Additional Archeology on SiteAdditional Archeology on SiteAdditional Archeology on SiteAdditional Archeology on SiteAdditional Archeology on Site
Creation of Draft ReportCreation of Draft ReportCreation of Draft ReportCreation of Draft ReportCreation of Draft Report
DGS Approval of Draft ReportDGS Approval of Draft ReportDGS Approval of Draft ReportDGS Approval of Draft ReportDGS Approval of Draft Report
SHPO Approval of Draft ReportSHPO Approval of Draft ReportSHPO Approval of Draft ReportSHPO Approval of Draft ReportSHPO Approval of Draft Report
Creation & Submission of Final ReportCreation & Submission of Final ReportCreation & Submission of Final ReportCreation & Submission of Final ReportCreation & Submission of Final Report
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 3 of 24
Package Development for ESA 2 Funding
PDA-1000 Update Scope & Pricing Validation (Based on SD)
PDA-1010 Develop Council Approval Package FY25
PDA-1020 DGS/Council Approval Process FY25 Funding
PDA-1030 FY25 Funding Approved
Outreach & Trades
ORT-1000 Dev First Source & CBE Inclusion Plans for Construction
ORT-1010 Dev Bid Pkg Breakdown to Maximize CBEs
ORT-1020 Facilitate Trade Events
ORT-1030 Dev Bidders List
Fiscal Year 25 Funding
Design Development (FY25 Funding)
DDD-1000 Dev & Subt DD Schedule & Site Logistics Updates
DDD-1010 Resubmit DD
DDD-1020 Exterior Elevations Submitted to DGS
DDD-1040 Facade Direction Received from DCPS
DDD-1060 SIT Meeting 6 Design Development Presentation
DDD-1070 DGS/Team Meetings Review/Approval of DD Package
DDD-1080 Develop Building Permit Submission and 50% CD
Agency Reviews
AR-1000 Department Reviews
AR-1010 IPHP Review
AR-1020 ANC Review
AR-1030 HPRB Review
AR-1040 CFA Review Concept & Final
AR-1050 DDOT Review (PDRM)
AR-1060 EISF/SWPPP/NOI Review
Building Permit & Regulatory Approvals
PMT-1010 Pepco Class of Service (Approved SD)
PMT-1015 WMATA
PMT-1020 Raze Permit Process
PMT-1090 DDOT Curb Cuts Approval Process (Approved DD)
PMT-1100 Building Permit Process
Construction Documents
CCD-1000 25% Construction Doc (GMP Drawings) Submission
CCD-1010 50% Construction Doc (Building Permit Drawings) Review
CCD-1020 90% Construction Documents
BIM Coordination
BIM-1000 Prepare CDs For Clash Detection Process
BIM-1010 Coordinate All Floors
BIM-1020 Develop/Submit MEP/Sprinkler Coordinated Drawings
114d 23-Sep-24 27-Feb-25
20d 23-Sep-24 18-Oct-24
20d 23-Sep-24 18-Oct-24
94d 21-Oct-24 27-Feb-25
0d 27-Feb-25
80d 23-Aug-24 18-Dec-24
20d 23-Aug-24 19-Sep-24
20d 23-Aug-24 19-Sep-24
30d 23-Sep-24 01-Nov-24
60d 23-Sep-24 18-Dec-24
408d 03-Sep-24 21-Apr-26
145d 13-Nov-24 11-Jun-25
75d 13-Nov-24 04-Mar-25
80d 13-Nov-24 11-Mar-25
83d 13-Nov-24 14-Mar-25
103d 13-Nov-24 11-Apr-25
6d 05-Mar-25 12-Mar-25
25d 05-Mar-25 08-Apr-25
44d 09-Apr-25 11-Jun-25
196d 03-Sep-24 13-Jun-25
20d 03-Sep-24 30-Sep-24
21d 01-Oct-24 30-Oct-24
21d 04-Nov-24 04-Dec-24
59d 04-Nov-24 30-Jan-25
144d 10-Sep-24 08-Apr-25
82d 01-Oct-24 30-Jan-25
96d 31-Jan-25 13-Jun-25
265d 13-Nov-24 03-Dec-25
73d 13-Nov-24 28-Feb-25
120d 13-Nov-24 07-May-25
210d 31-Jan-25 02-Dec-25
61d 06-May-25 29-Jul-25
120d 12-Jun-25 03-Dec-25
112d 09-Apr-25 16-Sep-25
15d 09-Apr-25 30-Apr-25
32d 01-May-25 13-Jun-25
67d 16-Jun-25 16-Sep-25
117d 17-Sep-25 09-Mar-26
47d 17-Sep-25 24-Nov-25
59d 26-Nov-25 23-Feb-26
9d 25-Feb-26 09-Mar-26
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Package Development for ESA 2 FundingPackage Development for ESA 2 FundingPackage Development for ESA 2 FundingPackage Development for ESA 2 FundingPackage Development for ESA 2 Funding
Update Scope & Pricing Validation (Based on SD)Update Scope & Pricing Validation (Based on SD)Update Scope & Pricing Validation (Based on SD)Update Scope & Pricing Validation (Based on SD)Update Scope & Pricing Validation (Based on SD)
Develop Council Approval Package FY25Develop Council Approval Package FY25Develop Council Approval Package FY25Develop Council Approval Package FY25Develop Council Approval Package FY25
DGS/Council Approval Process FY25 FundingDGS/Council Approval Process FY25 FundingDGS/Council Approval Process FY25 FundingDGS/Council Approval Process FY25 FundingDGS/Council Approval Process FY25 Funding
  FY25 Funding ApprovedFY25 Funding ApprovedFY25 Funding ApprovedFY25 Funding ApprovedFY25 Funding Approved
Outreach & TradesOutreach & TradesOutreach & TradesOutreach & TradesOutreach & Trades
Dev First Source & CBE Inclusion Plans for ConstructionDev First Source & CBE Inclusion Plans for ConstructionDev First Source & CBE Inclusion Plans for ConstructionDev First Source & CBE Inclusion Plans for ConstructionDev First Source & CBE Inclusion Plans for Construction
Dev Bid Pkg Breakdown to Maximize CBEsDev Bid Pkg Breakdown to Maximize CBEsDev Bid Pkg Breakdown to Maximize CBEsDev Bid Pkg Breakdown to Maximize CBEsDev Bid Pkg Breakdown to Maximize CBEs
Facilitate Trade EventsFacilitate Trade EventsFacilitate Trade EventsFacilitate Trade EventsFacilitate Trade Events
Dev Bidders ListDev Bidders ListDev Bidders ListDev Bidders ListDev Bidders List
Fiscal Year 25 FundingFiscal Year 25 FundingFiscal Year 25 FundingFiscal Year 25 FundingFiscal Year 25 Funding
Design Development (FY25 Funding)Design Development (FY25 Funding)Design Development (FY25 Funding)Design Development (FY25 Funding)Design Development (FY25 Funding)
Dev & Subt DD Schedule & Site Logistics UpdatesDev & Subt DD Schedule & Site Logistics UpdatesDev & Subt DD Schedule & Site Logistics UpdatesDev & Subt DD Schedule & Site Logistics UpdatesDev & Subt DD Schedule & Site Logistics Updates
Resubmit DDResubmit DDResubmit DDResubmit DDResubmit DD
Exterior Elevations Submitted to DGSExterior Elevations Submitted to DGSExterior Elevations Submitted to DGSExterior Elevations Submitted to DGSExterior Elevations Submitted to DGS
Facade Direction Received from DCPSFacade Direction Received from DCPSFacade Direction Received from DCPSFacade Direction Received from DCPSFacade Direction Received from DCPS
SIT Meeting 6 Design Development PresentationSIT Meeting 6 Design Development PresentationSIT Meeting 6 Design Development PresentationSIT Meeting 6 Design Development PresentationSIT Meeting 6 Design Development Presentation
DGS/Team Meetings Review/Approval of DD PackageDGS/Team Meetings Review/Approval of DD PackageDGS/Team Meetings Review/Approval of DD PackageDGS/Team Meetings Review/Approval of DD PackageDGS/Team Meetings Review/Approval of DD Package
Develop Building Permit Submission and 50% CDDevelop Building Permit Submission and 50% CDDevelop Building Permit Submission and 50% CDDevelop Building Permit Submission and 50% CDDevelop Building Permit Submission and 50% CD
Agency ReviewsAgency ReviewsAgency ReviewsAgency ReviewsAgency Reviews
Department ReviewsDepartment ReviewsDepartment ReviewsDepartment ReviewsDepartment Reviews
IPHP ReviewIPHP ReviewIPHP ReviewIPHP ReviewIPHP Review
ANC ReviewANC ReviewANC ReviewANC ReviewANC Review
HPRB ReviewHPRB ReviewHPRB ReviewHPRB ReviewHPRB Review
CFA Review Concept & FinalCFA Review Concept & FinalCFA Review Concept & FinalCFA Review Concept & FinalCFA Review Concept & Final
DDOT Review (PDRM)DDOT Review (PDRM)DDOT Review (PDRM)DDOT Review (PDRM)DDOT Review (PDRM)
EISF/SWPPP/NOI ReviewEISF/SWPPP/NOI ReviewEISF/SWPPP/NOI ReviewEISF/SWPPP/NOI ReviewEISF/SWPPP/NOI Review
Building Permit & Regulatory ApprovalsBuilding Permit & Regulatory ApprovalsBuilding Permit & Regulatory ApprovalsBuilding Permit & Regulatory ApprovalsBuilding Permit & Regulatory Approvals
Pepco Class of Service (Approved SD)Pepco Class of Service (Approved SD)Pepco Class of Service (Approved SD)Pepco Class of Service (Approved SD)Pepco Class of Service (Approved SD)
WMATAWMATAWMATAWMATAWMATA
Raze Permit ProcessRaze Permit ProcessRaze Permit ProcessRaze Permit ProcessRaze Permit Process
DDOT Curb Cuts Approval Process (Approved DD)DDOT Curb Cuts Approval Process (Approved DD)DDOT Curb Cuts Approval Process (Approved DD)DDOT Curb Cuts Approval Process (Approved DD)DDOT Curb Cuts Approval Process (Approved DD)
Building Permit ProcessBuilding Permit ProcessBuilding Permit ProcessBuilding Permit ProcessBuilding Permit Process
Construction DocumentsConstruction DocumentsConstruction DocumentsConstruction DocumentsConstruction Documents
25% Construction Doc (GMP Drawings) Submission25% Construction Doc (GMP Drawings) Submission25% Construction Doc (GMP Drawings) Submission25% Construction Doc (GMP Drawings) Submission25% Construction Doc (GMP Drawings) Submission
50% Construction Doc (Building Permit Drawings) Review50% Construction Doc (Building Permit Drawings) Review50% Construction Doc (Building Permit Drawings) Review50% Construction Doc (Building Permit Drawings) Review50% Construction Doc (Building Permit Drawings) Review
90% Construction Documents90% Construction Documents90% Construction Documents90% Construction Documents90% Construction Documents
BIM CoordinationBIM CoordinationBIM CoordinationBIM CoordinationBIM Coordination
Prepare CDs For Clash Detection ProcessPrepare CDs For Clash Detection ProcessPrepare CDs For Clash Detection ProcessPrepare CDs For Clash Detection ProcessPrepare CDs For Clash Detection Process
Coordinate All FloorsCoordinate All FloorsCoordinate All FloorsCoordinate All FloorsCoordinate All Floors
Develop/Submit MEP/Sprinkler Coordinated DrawingsDevelop/Submit MEP/Sprinkler Coordinated DrawingsDevelop/Submit MEP/Sprinkler Coordinated DrawingsDevelop/Submit MEP/Sprinkler Coordinated DrawingsDevelop/Submit MEP/Sprinkler Coordinated Drawings
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 4 of 24
BIM-1030 Coordinated Drawings
Buy-Out - Early Work Trades (FY25 Funding)
Identify Early Trades
EWT-1000 MEP/FP
EWT-1010 Structural Steel & Concrete
EWT-1020 Geothermal
EWT-1030 Facade and Glazing
EWT-1040 Demolition
EWT-1050 Haz Mat/Abatement
EWT-1060 Eartwork
EWT-1070 Archeology
EWT-1080 SOE and Aggregate Piers
Early Trade Buy-Out Process
EWT-1090 Pre-Bid Meetings & Bidding Early Work & Long Lead
EWT-1100 De-Scope & Develop Bid Leveling Sheets
EWT-1110 Recommend/Approve Early Trade Companies
EWT-1120 Buy Early Trades Equipment
Early Work Construction Start (FY25 Funding)
CON-1000 Start Haz Mat Notifications (30 day Minimum)
CON-1010 DOEE Erosion & Sediment Control Approval
CON-1020 Stakeout LOD & Erosion & Sediment controls
CON-1030 Full Access and Control of the Site & Building
CON-1050 Install Tree protection & stabilzed const ent removal
CON-1060 Set up Site / Mobilize and temporary site power
CON-1070 Install Site Security Fence
CON-1100 Hazmat Remediation
CON-1105 Underpinning Existing Wall
CON-1120 Cut, Cap and Make safe for demo and abatement (trades)
CON-1130 Obtain Remediation Clearances
CON-1140 Raze Permit Received
CON-1151 Phase 1 is Saw Cut/Light Demolition
CON-1152 Phase 2 is Floor by Floor Bull Dozer
CON-1153 Phase 3 is Demolish Foundations & Clear Site
CON-1155 Stake Out new building pad
CON-1156 Support of Excavation
CON-1160 EP Underground Equipment (Geothermal, Etc)
GMP Development for FY26 Funding
GMP-1000 Prepare GMP Bid Packages (Advancing DD)
GMP-1020 Continue Outreach-Maximize Bidders
GMP-1030 Facilitate Pre-bid Meetings & Site Walks
GMP-1040 Trade Bidding
0d 09-Mar-26
73d 13-Nov-24 28-Feb-25
6d 13-Nov-24 20-Nov-24
6d 13-Nov-24 20-Nov-24
6d 13-Nov-24 20-Nov-24
6d 13-Nov-24 20-Nov-24
6d 13-Nov-24 20-Nov-24
6d 13-Nov-24 20-Nov-24
6d 13-Nov-24 20-Nov-24
6d 13-Nov-24 20-Nov-24
6d 13-Nov-24 20-Nov-24
6d 13-Nov-24 20-Nov-24
73d 13-Nov-24 28-Feb-25
6d 13-Nov-24 20-Nov-24
21d 21-Nov-24 20-Dec-24
20d 13-Dec-24 13-Jan-25
30d 16-Jan-25 28-Feb-25
206d 24-Jun-25 21-Apr-26
30d 03-Jul-25 15-Aug-25
10d 24-Jun-25 08-Jul-25
3d 24-Jun-25 26-Jun-25
0d 15-Aug-25 CC
5d 15-Aug-25 21-Aug-25
5d 15-Aug-25 21-Aug-25
2d 15-Aug-25 18-Aug-25
30d 22-Aug-25 03-Oct-25
35d 22-Aug-25 10-Oct-25
5d 22-Aug-25 28-Aug-25
20d 06-Oct-25 03-Nov-25
0d 02-Dec-25
20d 05-Dec-25 05-Jan-26
20d 06-Jan-26 03-Feb-26
20d 04-Feb-26 04-Mar-26
3d 05-Mar-26 09-Mar-26
20d 10-Mar-26 06-Apr-26
30d 10-Mar-26 21-Apr-26
202d 14-Jan-25 30-Oct-25
35d 05-Mar-25 23-Apr-25
40d 14-Jan-25 12-Mar-25
35d 05-Mar-25 23-Apr-25
10d 24-Apr-25 07-May-25
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
  Coordinated DrawingsCoordinated DrawingsCoordinated DrawingsCoordinated DrawingsCoordinated Drawings
Buy-Out - Early Work Trades (FY25 Funding)Buy-Out - Early Work Trades (FY25 Funding)Buy-Out - Early Work Trades (FY25 Funding)Buy-Out - Early Work Trades (FY25 Funding)Buy-Out - Early Work Trades (FY25 Funding)
Identify Early TradesIdentify Early TradesIdentify Early TradesIdentify Early TradesIdentify Early Trades
MEP/FPMEP/FPMEP/FPMEP/FPMEP/FP
Structural Steel & ConcreteStructural Steel & ConcreteStructural Steel & ConcreteStructural Steel & ConcreteStructural Steel & Concrete
GeothermalGeothermalGeothermalGeothermalGeothermal
Facade and GlazingFacade and GlazingFacade and GlazingFacade and GlazingFacade and Glazing
DemolitionDemolitionDemolitionDemolitionDemolition
Haz Mat/AbatementHaz Mat/AbatementHaz Mat/AbatementHaz Mat/AbatementHaz Mat/Abatement
EartworkEartworkEartworkEartworkEartwork
ArcheologyArcheologyArcheologyArcheologyArcheology
SOE and Aggregate PiersSOE and Aggregate PiersSOE and Aggregate PiersSOE and Aggregate PiersSOE and Aggregate Piers
Early Trade Buy-Out ProcessEarly Trade Buy-Out ProcessEarly Trade Buy-Out ProcessEarly Trade Buy-Out ProcessEarly Trade Buy-Out Process
Pre-Bid Meetings & Bidding Early Work & Long LeadPre-Bid Meetings & Bidding Early Work & Long LeadPre-Bid Meetings & Bidding Early Work & Long LeadPre-Bid Meetings & Bidding Early Work & Long LeadPre-Bid Meetings & Bidding Early Work & Long Lead
De-Scope & Develop Bid Leveling SheetsDe-Scope & Develop Bid Leveling SheetsDe-Scope & Develop Bid Leveling SheetsDe-Scope & Develop Bid Leveling SheetsDe-Scope & Develop Bid Leveling Sheets
Recommend/Approve Early Trade CompaniesRecommend/Approve Early Trade CompaniesRecommend/Approve Early Trade CompaniesRecommend/Approve Early Trade CompaniesRecommend/Approve Early Trade Companies
Buy Early Trades EquipmentBuy Early Trades EquipmentBuy Early Trades EquipmentBuy Early Trades EquipmentBuy Early Trades Equipment
Early Work Construction Start (FY25 Funding)Early Work Construction Start (FY25 Funding)Early Work Construction Start (FY25 Funding)Early Work Construction Start (FY25 Funding)Early Work Construction Start (FY25 Funding)
Start Haz Mat Notifications (30 day Minimum)Start Haz Mat Notifications (30 day Minimum)Start Haz Mat Notifications (30 day Minimum)Start Haz Mat Notifications (30 day Minimum)Start Haz Mat Notifications (30 day Minimum)
DOEE Erosion & Sediment Control ApprovalDOEE Erosion & Sediment Control ApprovalDOEE Erosion & Sediment Control ApprovalDOEE Erosion & Sediment Control ApprovalDOEE Erosion & Sediment Control Approval
Stakeout LOD & Erosion & Sediment controlsStakeout LOD & Erosion & Sediment controlsStakeout LOD & Erosion & Sediment controlsStakeout LOD & Erosion & Sediment controlsStakeout LOD & Erosion & Sediment controls
  Full Access and Control of the Site & BuildingFull Access and Control of the Site & BuildingFull Access and Control of the Site & BuildingFull Access and Control of the Site & BuildingFull Access and Control of the Site & Building
Install Tree protection & stabilzed const ent removalInstall Tree protection & stabilzed const ent removalInstall Tree protection & stabilzed const ent removalInstall Tree protection & stabilzed const ent removalInstall Tree protection & stabilzed const ent removal
Set up Site / Mobilize and temporary site powerSet up Site / Mobilize and temporary site powerSet up Site / Mobilize and temporary site powerSet up Site / Mobilize and temporary site powerSet up Site / Mobilize and temporary site power
Install Site Security FenceInstall Site Security FenceInstall Site Security FenceInstall Site Security FenceInstall Site Security Fence
Hazmat RemediationHazmat RemediationHazmat RemediationHazmat RemediationHazmat Remediation
Underpinning Existing WallUnderpinning Existing WallUnderpinning Existing WallUnderpinning Existing WallUnderpinning Existing Wall
Cut, Cap and Make safe for demo and abatement (trades)Cut, Cap and Make safe for demo and abatement (trades)Cut, Cap and Make safe for demo and abatement (trades)Cut, Cap and Make safe for demo and abatement (trades)Cut, Cap and Make safe for demo and abatement (trades)
Obtain Remediation ClearancesObtain Remediation ClearancesObtain Remediation ClearancesObtain Remediation ClearancesObtain Remediation Clearances
  Raze Permit ReceivedRaze Permit ReceivedRaze Permit ReceivedRaze Permit ReceivedRaze Permit Received
Phase 1 is Saw Cut/Light DemolitionPhase 1 is Saw Cut/Light DemolitionPhase 1 is Saw Cut/Light DemolitionPhase 1 is Saw Cut/Light DemolitionPhase 1 is Saw Cut/Light Demolition
Phase 2 is Floor by Floor Bull DozerPhase 2 is Floor by Floor Bull DozerPhase 2 is Floor by Floor Bull DozerPhase 2 is Floor by Floor Bull DozerPhase 2 is Floor by Floor Bull Dozer
Phase 3 is Demolish Foundations & Clear SitePhase 3 is Demolish Foundations & Clear SitePhase 3 is Demolish Foundations & Clear SitePhase 3 is Demolish Foundations & Clear SitePhase 3 is Demolish Foundations & Clear Site
Stake Out new building padStake Out new building padStake Out new building padStake Out new building padStake Out new building pad
Support of ExcavationSupport of ExcavationSupport of ExcavationSupport of ExcavationSupport of Excavation
EP Underground Equipment (Geothermal, Etc)EP Underground Equipment (Geothermal, Etc)EP Underground Equipment (Geothermal, Etc)EP Underground Equipment (Geothermal, Etc)EP Underground Equipment (Geothermal, Etc)
GMP Development for FY26 FundingGMP Development for FY26 FundingGMP Development for FY26 FundingGMP Development for FY26 FundingGMP Development for FY26 Funding
Prepare GMP Bid Packages (Advancing DD)Prepare GMP Bid Packages (Advancing DD)Prepare GMP Bid Packages (Advancing DD)Prepare GMP Bid Packages (Advancing DD)Prepare GMP Bid Packages (Advancing DD)
Continue Outreach-Maximize BiddersContinue Outreach-Maximize BiddersContinue Outreach-Maximize BiddersContinue Outreach-Maximize BiddersContinue Outreach-Maximize Bidders
Facilitate Pre-bid Meetings & Site WalksFacilitate Pre-bid Meetings & Site WalksFacilitate Pre-bid Meetings & Site WalksFacilitate Pre-bid Meetings & Site WalksFacilitate Pre-bid Meetings & Site Walks
Trade BiddingTrade BiddingTrade BiddingTrade BiddingTrade Bidding
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 5 of 24
GMP-1050 Develop Bid Tabulation
GMP-1060 Prepare GMP
GMP-1070 Submit GMP
GMP-1080 Reconciliation/Approval for Full GMP Construction Start
GMP-1090 GMP Approved
Buy-Out Trades FY26 Funding
Tier 1 Trades - After GMP Approved
TR1-1000 Buy Elevator/Walls/Ceilings/Rough Carpentry
TR1-1010 Buy Exterior/Roofing/Waterproofing
TR1-1020 Buy Thermal Moisture Protection
Tier 2 Trades - After GMP
TR2-1000 Buy Paint/Wall Covering
TR2-1010 Buy Flooring/Tiles
Tier 3 Trades - After GMP
TR3-1000 Buy Drs/Frms/HW/Toilet Accessories/Specialties
TR3-1010 Buy Millwork/Casework/Equipment/FF&E
Tier 4 Trades - After GMP
TR4-1000 Buy Landscaping/Sidewalks/Paving/Bio Retention
TR4-1010 Buy Play Equipment/Site Furnishings
Procurement/Submittals/Long Lead Material Acquisition
PRO-1000 Prepare submittal Documents for Early Trades
Division 03 - Concrete
PD3-1004 Prepare submittal Documents for Concrete
PD3-1006 Prepare/Submit - Formwork and Accessories
PD3-1007 Review/Approve - Formwork and Accessories
PD3-1008 Order/Fab - Formwork and Accessories
PD3-1030 Prepare/Submit - Rebar (Reinforcing Steel)
PD3-1040 Review/Approve - Rebar (Reinforcing Steel)
PD3-1050 Order/Fab - Rebar (Reinforcing Steel)
PD3-1060 Prepare/Submit - Mill Certificates for Rebar
PD3-1070 Review/Approve - Mill Certificates for Rebar
PD3-1080 Prepare/Submit - Cast-in-Place Concrete Mix Design
PD3-1090 Review/Approve - Cast-in-Place Concrete Mix Design
PD3-1100 Order/Fab - Concrete Materials
PD3-1110 Prepare/Submit - Gypsum Cement Underlayment
PD3-1120 Review/Approve - Gypsum Cement Underlayment
PD3-1130 Order/Fab - Gypsum Cement Underlayment
Division 04 – Masonry
PD4-1000 Prepare submittal Documents for Massonary
PD4-1005 Prepare/Submit - Unit Masonry (CMU Block)
PD4-1010 Review/Approve - Unit Masonry (CMU Block)
5d 08-May-25 14-May-25
5d 08-May-25 14-May-25
0d 14-May-25
117d 15-May-25 30-Oct-25
0d 30-Oct-25
60d 31-Oct-25 29-Jan-26
15d 31-Oct-25 21-Nov-25
15d 31-Oct-25 21-Nov-25
15d 31-Oct-25 21-Nov-25
15d 31-Oct-25 21-Nov-25
15d 24-Nov-25 15-Dec-25
15d 24-Nov-25 15-Dec-25
15d 24-Nov-25 15-Dec-25
15d 16-Dec-25 07-Jan-26
15d 16-Dec-25 07-Jan-26
15d 16-Dec-25 07-Jan-26
15d 08-Jan-26 29-Jan-26
15d 08-Jan-26 29-Jan-26
15d 08-Jan-26 29-Jan-26
479d 12-Jun-25 11-May-27
34d 12-Jun-25 30-Jul-25
145d 01-Aug-25 03-Mar-26
85d 01-Aug-25 03-Dec-25
10d 04-Dec-25 17-Dec-25
10d 18-Dec-25 02-Jan-26
30d 05-Jan-26 17-Feb-26
10d 04-Dec-25 17-Dec-25
10d 18-Dec-25 02-Jan-26
40d 05-Jan-26 03-Mar-26
10d 18-Dec-25 02-Jan-26
10d 05-Jan-26 16-Jan-26
10d 18-Dec-25 02-Jan-26
10d 05-Jan-26 16-Jan-26
30d 20-Jan-26 03-Mar-26
10d 18-Dec-25 02-Jan-26
10d 05-Jan-26 16-Jan-26
30d 20-Jan-26 03-Mar-26
70d 04-Dec-25 17-Mar-26
20d 04-Dec-25 02-Jan-26
10d 05-Jan-26 16-Jan-26
10d 20-Jan-26 02-Feb-26
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Develop Bid TabulationDevelop Bid TabulationDevelop Bid TabulationDevelop Bid TabulationDevelop Bid Tabulation
Prepare GMPPrepare GMPPrepare GMPPrepare GMPPrepare GMP
  Submit GMPSubmit GMPSubmit GMPSubmit GMPSubmit GMP
Reconciliation/Approval for Full GMP Construction StartReconciliation/Approval for Full GMP Construction StartReconciliation/Approval for Full GMP Construction StartReconciliation/Approval for Full GMP Construction StartReconciliation/Approval for Full GMP Construction Start
  GMP ApprovedGMP ApprovedGMP ApprovedGMP ApprovedGMP Approved
Buy-Out Trades FY26 FundingBuy-Out Trades FY26 FundingBuy-Out Trades FY26 FundingBuy-Out Trades FY26 FundingBuy-Out Trades FY26 Funding
Tier 1 Trades - After GMP ApprovedTier 1 Trades - After GMP ApprovedTier 1 Trades - After GMP ApprovedTier 1 Trades - After GMP ApprovedTier 1 Trades - After GMP Approved
Buy Elevator/Walls/Ceilings/Rough CarpentryBuy Elevator/Walls/Ceilings/Rough CarpentryBuy Elevator/Walls/Ceilings/Rough CarpentryBuy Elevator/Walls/Ceilings/Rough CarpentryBuy Elevator/Walls/Ceilings/Rough Carpentry
Buy Exterior/Roofing/WaterproofingBuy Exterior/Roofing/WaterproofingBuy Exterior/Roofing/WaterproofingBuy Exterior/Roofing/WaterproofingBuy Exterior/Roofing/Waterproofing
Buy Thermal Moisture ProtectionBuy Thermal Moisture ProtectionBuy Thermal Moisture ProtectionBuy Thermal Moisture ProtectionBuy Thermal Moisture Protection
Tier 2 Trades - After GMPTier 2 Trades - After GMPTier 2 Trades - After GMPTier 2 Trades - After GMPTier 2 Trades - After GMP
Buy Paint/Wall CoveringBuy Paint/Wall CoveringBuy Paint/Wall CoveringBuy Paint/Wall CoveringBuy Paint/Wall Covering
Buy Flooring/TilesBuy Flooring/TilesBuy Flooring/TilesBuy Flooring/TilesBuy Flooring/Tiles
Tier 3 Trades - After GMPTier 3 Trades - After GMPTier 3 Trades - After GMPTier 3 Trades - After GMPTier 3 Trades - After GMP
Buy Drs/Frms/HW/Toilet Accessories/SpecialtiesBuy Drs/Frms/HW/Toilet Accessories/SpecialtiesBuy Drs/Frms/HW/Toilet Accessories/SpecialtiesBuy Drs/Frms/HW/Toilet Accessories/SpecialtiesBuy Drs/Frms/HW/Toilet Accessories/Specialties
Buy Millwork/Casework/Equipment/FF&EBuy Millwork/Casework/Equipment/FF&EBuy Millwork/Casework/Equipment/FF&EBuy Millwork/Casework/Equipment/FF&EBuy Millwork/Casework/Equipment/FF&E
Tier 4 Trades - After GMPTier 4 Trades - After GMPTier 4 Trades - After GMPTier 4 Trades - After GMPTier 4 Trades - After GMP
Buy Landscaping/Sidewalks/Paving/Bio RetentionBuy Landscaping/Sidewalks/Paving/Bio RetentionBuy Landscaping/Sidewalks/Paving/Bio RetentionBuy Landscaping/Sidewalks/Paving/Bio RetentionBuy Landscaping/Sidewalks/Paving/Bio Retention
Buy Play Equipment/Site FurnishingsBuy Play Equipment/Site FurnishingsBuy Play Equipment/Site FurnishingsBuy Play Equipment/Site FurnishingsBuy Play Equipment/Site Furnishings
Procurement/Submittals/Long Lead MateriaProcurement/Submittals/Long Lead MateriaProcurement/Submittals/Long Lead MateriProcurement/Submittals/Long Lead MateriaProcurement/Submittals/Long Lead Materia
Prepare submittal Documents for Early TradesPrepare submittal Documents for Early TradesPrepare submittal Documents for Early TradesPrepare submittal Documents for Early TradesPrepare submittal Documents for Early Trades
Division 03 - ConcreteDivision 03 - ConcreteDivision 03 - ConcreteDivision 03 - ConcreteDivision 03 - Concrete
Prepare submittal Documents for ConcretePrepare submittal Documents for ConcretePrepare submittal Documents for ConcretePrepare submittal Documents for ConcretePrepare submittal Documents for Concrete
Prepare/Submit - Formwork and AccessoriesPrepare/Submit - Formwork and AccessoriesPrepare/Submit - Formwork and AccessoriesPrepare/Submit - Formwork and AccessoriesPrepare/Submit - Formwork and Accessories
Review/Approve - Formwork and AccessoriesReview/Approve - Formwork and AccessoriesReview/Approve - Formwork and AccessoriesReview/Approve - Formwork and AccessoriesReview/Approve - Formwork and Accessories
Order/Fab - Formwork and AccessoriesOrder/Fab - Formwork and AccessoriesOrder/Fab - Formwork and AccessoriesOrder/Fab - Formwork and AccessoriesOrder/Fab - Formwork and Accessories
Prepare/Submit - Rebar (Reinforcing Steel)Prepare/Submit - Rebar (Reinforcing Steel)Prepare/Submit - Rebar (Reinforcing Steel)Prepare/Submit - Rebar (Reinforcing Steel)Prepare/Submit - Rebar (Reinforcing Steel)
Review/Approve - Rebar (Reinforcing Steel)Review/Approve - Rebar (Reinforcing Steel)Review/Approve - Rebar (Reinforcing Steel)Review/Approve - Rebar (Reinforcing Steel)Review/Approve - Rebar (Reinforcing Steel)
Order/Fab - Rebar (Reinforcing Steel)Order/Fab - Rebar (Reinforcing Steel)Order/Fab - Rebar (Reinforcing Steel)Order/Fab - Rebar (Reinforcing Steel)Order/Fab - Rebar (Reinforcing Steel)
Prepare/Submit - Mill Certificates for RebarPrepare/Submit - Mill Certificates for RebarPrepare/Submit - Mill Certificates for RebarPrepare/Submit - Mill Certificates for RebarPrepare/Submit - Mill Certificates for Rebar
Review/Approve - Mill Certificates for RebarReview/Approve - Mill Certificates for RebarReview/Approve - Mill Certificates for RebarReview/Approve - Mill Certificates for RebarReview/Approve - Mill Certificates for Rebar
Prepare/Submit - Cast-in-Place Concrete Mix DesignPrepare/Submit - Cast-in-Place Concrete Mix DesignPrepare/Submit - Cast-in-Place Concrete Mix DesignPrepare/Submit - Cast-in-Place Concrete Mix DesignPrepare/Submit - Cast-in-Place Concrete Mix Design
Review/Approve - Cast-in-Place Concrete Mix DesignReview/Approve - Cast-in-Place Concrete Mix DesignReview/Approve - Cast-in-Place Concrete Mix DesignReview/Approve - Cast-in-Place Concrete Mix DesignReview/Approve - Cast-in-Place Concrete Mix Design
Order/Fab - Concrete MaterialsOrder/Fab - Concrete MaterialsOrder/Fab - Concrete MaterialsOrder/Fab - Concrete MaterialsOrder/Fab - Concrete Materials
Prepare/Submit - Gypsum Cement UnderlaymentPrepare/Submit - Gypsum Cement UnderlaymentPrepare/Submit - Gypsum Cement UnderlaymentPrepare/Submit - Gypsum Cement UnderlaymentPrepare/Submit - Gypsum Cement Underlayment
Review/Approve - Gypsum Cement UnderlaymentReview/Approve - Gypsum Cement UnderlaymentReview/Approve - Gypsum Cement UnderlaymentReview/Approve - Gypsum Cement UnderlaymentReview/Approve - Gypsum Cement Underlayment
Order/Fab - Gypsum Cement UnderlaymentOrder/Fab - Gypsum Cement UnderlaymentOrder/Fab - Gypsum Cement UnderlaymentOrder/Fab - Gypsum Cement UnderlaymentOrder/Fab - Gypsum Cement Underlayment
Division 04 – MasonryDivision 04 – MasonryDivision 04 – MasonryDivision 04 – MasonryDivision 04 – Masonry
Prepare submittal Documents for MassonaryPrepare submittal Documents for MassonaryPrepare submittal Documents for MassonaryPrepare submittal Documents for MassonaryPrepare submittal Documents for Massonary
Prepare/Submit - Unit Masonry (CMU Block)Prepare/Submit - Unit Masonry (CMU Block)Prepare/Submit - Unit Masonry (CMU Block)Prepare/Submit - Unit Masonry (CMU Block)Prepare/Submit - Unit Masonry (CMU Block)
Review/Approve - Unit Masonry (CMU Block)Review/Approve - Unit Masonry (CMU Block)Review/Approve - Unit Masonry (CMU Block)Review/Approve - Unit Masonry (CMU Block)Review/Approve - Unit Masonry (CMU Block)
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 6 of 24
PD4-1020 Order/Fab - Unit Masonry (CMU Block)
PD4-1030 Prepare/Submit - Masonry Reinforcement
PD4-1040 Review/Approve - Masonry Reinforcement
PD4-1050 Order/Fab - Masonry Reinforcement (Rebar, Mesh)
PD4-1060 Prepare/Submit - Masonry Flashings & Anchors
PD4-1070 Review/Approve - Masonry Flashings & Anchors
PD4-1080 Order/Fab - Masonry Flashings & Anchors
PD4-1090 Prepare/Submit - Brick Veneer (Modular Brick)
PD4-1100 Review/Approve - Brick Veneer (Modular Brick)
PD4-1110 Order/Fab - Brick Veneer (Modular Brick)
PD4-1120 Prepare/Submit - Brick Mortar & Accessories
PD4-1130 Review/Approve - Brick Mortar & Accessories
PD4-1140 Order/Fab - Brick Mortar & Accessories
Division 05 – Metals
PD5-1000 Prepare submittal Documents for Metals
PD5-1002 Prepare/Submit - Structural Steel Framing
PD5-1010 Review/Approve - Structural Steel Framing
PD5-1020 Order/Fab - Structural Steel Framing
PD5-1030 Prepare/Submit - Steel Decking
PD5-1040 Review/Approve - Steel Decking
PD5-1050 Order/Fab - Steel Decking
PD5-1060 Prepare/Submit - Cold-Formed Metal Framing
PD5-1070 Review/Approve - Cold-Formed Metal Framing
PD5-1080 Order/Fab - Cold-Formed Metal Framing
PD5-1090 Prepare/Submit - Miscellaneous Metal Fabrications
PD5-1100 Review/Approve - Miscellaneous Metal Fabrications
PD5-1110 Order/Fab - Miscellaneous Metal Fabrications
PD5-1120 Prepare/Submit - Metal Pan Stairs (Typical)
PD5-1130 Review/Approve - Metal Pan Stairs (Typical)
PD5-1140 Order/Fab - Metal Pan Stairs (Typical)
PD5-1150 Prepare/Submit - Monumental Stair Delegated Design
PD5-1160 Review/Approve - Monumental Stair Delegated Design
PD5-1170 Order/Fab - Monumental Stair
PD5-1180 Prepare/Submit - Pipe and Tube Railings
PD5-1190 Review/Approve - Pipe and Tube Railings
PD5-1200 Order/Fab - Pipe and Tube Railings
PD5-1210 Prepare/Submit - Bar Gratings
PD5-1220 Review/Approve - Bar Gratings
PD5-1230 Order/Fab - Bar Gratings
PD5-1240 Prepare/Submit - Column Covers
PD5-1250 Review/Approve - Column Covers
20d 03-Feb-26 03-Mar-26
10d 05-Jan-26 16-Jan-26
10d 20-Jan-26 02-Feb-26
20d 03-Feb-26 03-Mar-26
10d 20-Jan-26 02-Feb-26
10d 03-Feb-26 17-Feb-26
20d 18-Feb-26 17-Mar-26
10d 20-Jan-26 02-Feb-26
10d 03-Feb-26 17-Feb-26
20d 18-Feb-26 17-Mar-26
10d 20-Jan-26 02-Feb-26
10d 03-Feb-26 17-Feb-26
20d 18-Feb-26 17-Mar-26
155d 31-Jul-25 16-Mar-26
65d 31-Jul-25 31-Oct-25
10d 03-Nov-25 17-Nov-25
10d 18-Nov-25 02-Dec-25
40d 03-Dec-25 30-Jan-26
10d 03-Nov-25 17-Nov-25
10d 18-Nov-25 02-Dec-25
40d 03-Dec-25 30-Jan-26
10d 24-Nov-25 08-Dec-25
10d 09-Dec-25 22-Dec-25
40d 23-Dec-25 20-Feb-26
10d 18-Nov-25 02-Dec-25
10d 03-Dec-25 16-Dec-25
40d 17-Dec-25 13-Feb-26
10d 18-Nov-25 02-Dec-25
10d 03-Dec-25 16-Dec-25
40d 17-Dec-25 13-Feb-26
10d 03-Dec-25 16-Dec-25
10d 17-Dec-25 31-Dec-25
40d 02-Jan-26 02-Mar-26
10d 17-Dec-25 31-Dec-25
10d 02-Jan-26 15-Jan-26
40d 16-Jan-26 16-Mar-26
10d 17-Dec-25 31-Dec-25
10d 02-Jan-26 15-Jan-26
40d 16-Jan-26 16-Mar-26
10d 17-Dec-25 31-Dec-25
10d 02-Jan-26 15-Jan-26
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Order/Fab - Unit Masonry (CMU Block)Order/Fab - Unit Masonry (CMU Block)Order/Fab - Unit Masonry (CMU Block)Order/Fab - Unit Masonry (CMU Block)Order/Fab - Unit Masonry (CMU Block)
Prepare/Submit - Masonry ReinforcementPrepare/Submit - Masonry ReinforcementPrepare/Submit - Masonry ReinforcementPrepare/Submit - Masonry ReinforcementPrepare/Submit - Masonry Reinforcement
Review/Approve - Masonry ReinforcementReview/Approve - Masonry ReinforcementReview/Approve - Masonry ReinforcementReview/Approve - Masonry ReinforcementReview/Approve - Masonry Reinforcement
Order/Fab - Masonry Reinforcement (Rebar, Mesh)Order/Fab - Masonry Reinforcement (Rebar, Mesh)Order/Fab - Masonry Reinforcement (Rebar, Mesh)Order/Fab - Masonry Reinforcement (Rebar, Mesh)Order/Fab - Masonry Reinforcement (Rebar, Mesh)
Prepare/Submit - Masonry Flashings & AnchorsPrepare/Submit - Masonry Flashings & AnchorsPrepare/Submit - Masonry Flashings & AnchorsPrepare/Submit - Masonry Flashings & AnchorsPrepare/Submit - Masonry Flashings & Anchors
Review/Approve - Masonry Flashings & AnchorsReview/Approve - Masonry Flashings & AnchorsReview/Approve - Masonry Flashings & AnchorsReview/Approve - Masonry Flashings & AnchorsReview/Approve - Masonry Flashings & Anchors
Order/Fab - Masonry Flashings & AnchorsOrder/Fab - Masonry Flashings & AnchorsOrder/Fab - Masonry Flashings & AnchorsOrder/Fab - Masonry Flashings & AnchorsOrder/Fab - Masonry Flashings & Anchors
Prepare/Submit - Brick Veneer (Modular Brick)Prepare/Submit - Brick Veneer (Modular Brick)Prepare/Submit - Brick Veneer (Modular Brick)Prepare/Submit - Brick Veneer (Modular Brick)Prepare/Submit - Brick Veneer (Modular Brick)
Review/Approve - Brick Veneer (Modular Brick)Review/Approve - Brick Veneer (Modular Brick)Review/Approve - Brick Veneer (Modular Brick)Review/Approve - Brick Veneer (Modular Brick)Review/Approve - Brick Veneer (Modular Brick)
Order/Fab - Brick Veneer (Modular Brick)Order/Fab - Brick Veneer (Modular Brick)Order/Fab - Brick Veneer (Modular Brick)Order/Fab - Brick Veneer (Modular Brick)Order/Fab - Brick Veneer (Modular Brick)
Prepare/Submit - Brick Mortar & AccessoriesPrepare/Submit - Brick Mortar & AccessoriesPrepare/Submit - Brick Mortar & AccessoriesPrepare/Submit - Brick Mortar & AccessoriesPrepare/Submit - Brick Mortar & Accessories
Review/Approve - Brick Mortar & AccessoriesReview/Approve - Brick Mortar & AccessoriesReview/Approve - Brick Mortar & AccessoriesReview/Approve - Brick Mortar & AccessoriesReview/Approve - Brick Mortar & Accessories
Order/Fab - Brick Mortar & AccessoriesOrder/Fab - Brick Mortar & AccessoriesOrder/Fab - Brick Mortar & AccessoriesOrder/Fab - Brick Mortar & AccessoriesOrder/Fab - Brick Mortar & Accessories
Division 05 – MetalsDivision 05 – MetalsDivision 05 – MetalsDivision 05 – MetalsDivision 05 – Metals
Prepare submittal Documents for MetalsPrepare submittal Documents for MetalsPrepare submittal Documents for MetalsPrepare submittal Documents for MetalsPrepare submittal Documents for Metals
Prepare/Submit - Structural Steel FramingPrepare/Submit - Structural Steel FramingPrepare/Submit - Structural Steel FramingPrepare/Submit - Structural Steel FramingPrepare/Submit - Structural Steel Framing
Review/Approve - Structural Steel FramingReview/Approve - Structural Steel FramingReview/Approve - Structural Steel FramingReview/Approve - Structural Steel FramingReview/Approve - Structural Steel Framing
Order/Fab - Structural Steel FramingOrder/Fab - Structural Steel FramingOrder/Fab - Structural Steel FramingOrder/Fab - Structural Steel FramingOrder/Fab - Structural Steel Framing
Prepare/Submit - Steel DeckingPrepare/Submit - Steel DeckingPrepare/Submit - Steel DeckingPrepare/Submit - Steel DeckingPrepare/Submit - Steel Decking
Review/Approve - Steel DeckingReview/Approve - Steel DeckingReview/Approve - Steel DeckingReview/Approve - Steel DeckingReview/Approve - Steel Decking
Order/Fab - Steel DeckingOrder/Fab - Steel DeckingOrder/Fab - Steel DeckingOrder/Fab - Steel DeckingOrder/Fab - Steel Decking
Prepare/Submit - Cold-Formed Metal FramingPrepare/Submit - Cold-Formed Metal FramingPrepare/Submit - Cold-Formed Metal FramingPrepare/Submit - Cold-Formed Metal FramingPrepare/Submit - Cold-Formed Metal Framing
Review/Approve - Cold-Formed Metal FramingReview/Approve - Cold-Formed Metal FramingReview/Approve - Cold-Formed Metal FramingReview/Approve - Cold-Formed Metal FramingReview/Approve - Cold-Formed Metal Framing
Order/Fab - Cold-Formed Metal FramingOrder/Fab - Cold-Formed Metal FramingOrder/Fab - Cold-Formed Metal FramingOrder/Fab - Cold-Formed Metal FramingOrder/Fab - Cold-Formed Metal Framing
Prepare/Submit - Miscellaneous Metal FabricationsPrepare/Submit - Miscellaneous Metal FabricationsPrepare/Submit - Miscellaneous Metal FabricationsPrepare/Submit - Miscellaneous Metal FabricationsPrepare/Submit - Miscellaneous Metal Fabrications
Review/Approve - Miscellaneous Metal FabricationsReview/Approve - Miscellaneous Metal FabricationsReview/Approve - Miscellaneous Metal FabricationsReview/Approve - Miscellaneous Metal FabricationsReview/Approve - Miscellaneous Metal Fabrications
Order/Fab - Miscellaneous Metal FabricationsOrder/Fab - Miscellaneous Metal FabricationsOrder/Fab - Miscellaneous Metal FabricationsOrder/Fab - Miscellaneous Metal FabricationsOrder/Fab - Miscellaneous Metal Fabrications
Prepare/Submit - Metal Pan Stairs (Typical)Prepare/Submit - Metal Pan Stairs (Typical)Prepare/Submit - Metal Pan Stairs (Typical)Prepare/Submit - Metal Pan Stairs (Typical)Prepare/Submit - Metal Pan Stairs (Typical)
Review/Approve - Metal Pan Stairs (Typical)Review/Approve - Metal Pan Stairs (Typical)Review/Approve - Metal Pan Stairs (Typical)Review/Approve - Metal Pan Stairs (Typical)Review/Approve - Metal Pan Stairs (Typical)
Order/Fab - Metal Pan Stairs (Typical)Order/Fab - Metal Pan Stairs (Typical)Order/Fab - Metal Pan Stairs (Typical)Order/Fab - Metal Pan Stairs (Typical)Order/Fab - Metal Pan Stairs (Typical)
Prepare/Submit - Monumental Stair Delegated DesignPrepare/Submit - Monumental Stair Delegated DesignPrepare/Submit - Monumental Stair Delegated DesignPrepare/Submit - Monumental Stair Delegated DesignPrepare/Submit - Monumental Stair Delegated Design
Review/Approve - Monumental Stair Delegated DesignReview/Approve - Monumental Stair Delegated DesignReview/Approve - Monumental Stair Delegated DesignReview/Approve - Monumental Stair Delegated DesignReview/Approve - Monumental Stair Delegated Design
Order/Fab - Monumental StairOrder/Fab - Monumental StairOrder/Fab - Monumental StairOrder/Fab - Monumental StairOrder/Fab - Monumental Stair
Prepare/Submit - Pipe and Tube RailingsPrepare/Submit - Pipe and Tube RailingsPrepare/Submit - Pipe and Tube RailingsPrepare/Submit - Pipe and Tube RailingsPrepare/Submit - Pipe and Tube Railings
Review/Approve - Pipe and Tube RailingsReview/Approve - Pipe and Tube RailingsReview/Approve - Pipe and Tube RailingsReview/Approve - Pipe and Tube RailingsReview/Approve - Pipe and Tube Railings
Order/Fab - Pipe and Tube RailingsOrder/Fab - Pipe and Tube RailingsOrder/Fab - Pipe and Tube RailingsOrder/Fab - Pipe and Tube RailingsOrder/Fab - Pipe and Tube Railings
Prepare/Submit - Bar GratingsPrepare/Submit - Bar GratingsPrepare/Submit - Bar GratingsPrepare/Submit - Bar GratingsPrepare/Submit - Bar Gratings
Review/Approve - Bar GratingsReview/Approve - Bar GratingsReview/Approve - Bar GratingsReview/Approve - Bar GratingsReview/Approve - Bar Gratings
Order/Fab - Bar GratingsOrder/Fab - Bar GratingsOrder/Fab - Bar GratingsOrder/Fab - Bar GratingsOrder/Fab - Bar Gratings
Prepare/Submit - Column CoversPrepare/Submit - Column CoversPrepare/Submit - Column CoversPrepare/Submit - Column CoversPrepare/Submit - Column Covers
Review/Approve - Column CoversReview/Approve - Column CoversReview/Approve - Column CoversReview/Approve - Column CoversReview/Approve - Column Covers
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 7 of 24
PD5-1260 Order/Fab - Column Covers
Division 06 – Woods, Plastics, And Composites
PD6-1000 Prepare/Submit - Interior Architectural Woodwork
PD6-1010 Review/Approve - Interior Architectural Woodwork
PD6-1020 Order/Fab - Interior Architectural Woodwork
PD6-1030 Prepare/Submit - Plastic-Laminate-Clad Architectural Cab…
PD6-1040 Review/Approve - Plastic-Laminate-Clad Architectural Ca…
PD6-1050 Order/Fab - Plastic-Laminate-Clad Architectural Cabinets
PD6-1060 Prepare/Submit - Plastic-Laminate-Faced Wood Paneling
PD6-1070 Review/Approve - Plastic-Laminate-Faced Wood Paneling
PD6-1080 Order/Fab - Plastic-Laminate-Faced Wood Paneling
PD6-1090 Prepare/Submit - Rough Carpentry
PD6-1100 Review/Approve - Rough Carpentry
PD6-1110 Order/Fab - Rough Carpentry
Division 07 – Thermal And Moisture Protection
PD7-1000 Prepare submittal Documents for Thermal and Moisture P…
PD7-1001 Prepare/Submit - Self-Adhering Sheet Waterproofing
PD7-1010 Review/Approve - Self-Adhering Sheet Waterproofing
PD7-1020 Order/Fab - Self-Adhering Sheet Waterproofing
PD7-1030 Prepare/Submit - Thermal Insulation
PD7-1040 Review/Approve - Thermal Insulation
PD7-1050 Order/Fab - Thermal Insulation
PD7-1060 Prepare/Submit - Fluid-Applied Membrane Air Barriers
PD7-1070 Review/Approve - Fluid-Applied Membrane Air Barriers
PD7-1080 Order/Fab - Fluid-Applied Membrane Air Barriers
PD7-1090 Prepare/Submit - Metal Composite Material Wall Panels
PD7-1100 Review/Approve - Metal Composite Material Wall Panels
PD7-1110 Order/Fab - Metal Composite Material Wall Panels
PD7-1120 Prepare/Submit - Soffit Panels
PD7-1130 Review/Approve - Soffit Panels
PD7-1140 Order/Fab - Soffit Panels
PD7-1150 Prepare/Submit - PVC Roofing
PD7-1160 Review/Approve - PVC Roofing
PD7-1170 Order/Fab - PVC Roofing
PD7-1180 Prepare/Submit - Sheet Metal Flashing and Trim
PD7-1190 Review/Approve - Sheet Metal Flashing and Trim
PD7-1200 Order/Fab - Sheet Metal Flashing and Trim
PD7-1210 Prepare/Submit - Roof Accessories
PD7-1220 Review/Approve - Roof Accessories
PD7-1230 Order/Fab - Roof Accessories
PD7-1240 Prepare/Submit - Vegetated Roof Systems
40d 16-Jan-26 16-Mar-26
90d 24-Nov-25 03-Apr-26
10d 08-Jan-26 22-Jan-26
10d 23-Jan-26 05-Feb-26
40d 06-Feb-26 03-Apr-26
10d 08-Jan-26 22-Jan-26
10d 23-Jan-26 05-Feb-26
40d 06-Feb-26 03-Apr-26
10d 08-Jan-26 22-Jan-26
10d 23-Jan-26 05-Feb-26
40d 06-Feb-26 03-Apr-26
10d 24-Nov-25 08-Dec-25
10d 09-Dec-25 22-Dec-25
5d 23-Dec-25 30-Dec-25
90d 05-Jan-26 13-May-26
20d 05-Jan-26 02-Feb-26
10d 03-Feb-26 17-Feb-26
10d 18-Feb-26 03-Mar-26
20d 04-Mar-26 31-Mar-26
10d 03-Feb-26 17-Feb-26
10d 18-Feb-26 03-Mar-26
20d 04-Mar-26 31-Mar-26
10d 03-Feb-26 17-Feb-26
10d 18-Feb-26 03-Mar-26
20d 04-Mar-26 31-Mar-26
10d 18-Feb-26 03-Mar-26
10d 04-Mar-26 17-Mar-26
20d 18-Mar-26 14-Apr-26
10d 18-Feb-26 03-Mar-26
10d 04-Mar-26 17-Mar-26
20d 18-Mar-26 14-Apr-26
10d 18-Feb-26 03-Mar-26
10d 04-Mar-26 17-Mar-26
20d 18-Mar-26 14-Apr-26
10d 04-Mar-26 17-Mar-26
10d 18-Mar-26 31-Mar-26
20d 01-Apr-26 29-Apr-26
10d 04-Mar-26 17-Mar-26
10d 18-Mar-26 31-Mar-26
20d 01-Apr-26 29-Apr-26
10d 04-Mar-26 17-Mar-26
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Order/Fab - Column CoversOrder/Fab - Column CoversOrder/Fab - Column CoversOrder/Fab - Column CoversOrder/Fab - Column Covers
Division 06 – Woods, Plastics, And CompositesDivision 06 – Woods, Plastics, And CompositesDivision 06 – Woods, Plastics, And CompositesDivision 06 – Woods, Plastics, And CompositesDivision 06 – Woods, Plastics, And Composites
Prepare/Submit - Interior Architectural WoodworkPrepare/Submit - Interior Architectural WoodworkPrepare/Submit - Interior Architectural WoodworkPrepare/Submit - Interior Architectural WoodworkPrepare/Submit - Interior Architectural Woodwork
Review/Approve - Interior Architectural WoodworkReview/Approve - Interior Architectural WoodworkReview/Approve - Interior Architectural WoodworkReview/Approve - Interior Architectural WoodworkReview/Approve - Interior Architectural Woodwork
Order/Fab - Interior Architectural WoodworkOrder/Fab - Interior Architectural WoodworkOrder/Fab - Interior Architectural WoodworkOrder/Fab - Interior Architectural WoodworkOrder/Fab - Interior Architectural Woodwork
Prepare/Submit - Plastic-Laminate-Clad Architectural CabinetsPrepare/Submit - Plastic-Laminate-Clad Architectural CabinetsPrepare/Submit - Plastic-Laminate-Clad Architectural CabinetsPrepare/Submit - Plastic-Laminate-Clad Architectural CabinetsPrepare/Submit - Plastic-Laminate-Clad Architectural Cabinets
Review/Approve - Plastic-Laminate-Clad Architectural CabinetsReview/Approve - Plastic-Laminate-Clad Architectural CabinetsReview/Approve - Plastic-Laminate-Clad Architectural CabinetsReview/Approve - Plastic-Laminate-Clad Architectural CabinetsReview/Approve - Plastic-Laminate-Clad Architectural Cabinets
Order/Fab - Plastic-Laminate-Clad Architectural CabinetsOrder/Fab - Plastic-Laminate-Clad Architectural CabinetsOrder/Fab - Plastic-Laminate-Clad Architectural CabinetsOrder/Fab - Plastic-Laminate-Clad Architectural CabinetsOrder/Fab - Plastic-Laminate-Clad Architectural Cabinets
Prepare/Submit - Plastic-Laminate-Faced Wood PanelingPrepare/Submit - Plastic-Laminate-Faced Wood PanelingPrepare/Submit - Plastic-Laminate-Faced Wood PanelingPrepare/Submit - Plastic-Laminate-Faced Wood PanelingPrepare/Submit - Plastic-Laminate-Faced Wood Paneling
Review/Approve - Plastic-Laminate-Faced Wood PanelingReview/Approve - Plastic-Laminate-Faced Wood PanelingReview/Approve - Plastic-Laminate-Faced Wood PanelingReview/Approve - Plastic-Laminate-Faced Wood PanelingReview/Approve - Plastic-Laminate-Faced Wood Paneling
Order/Fab - Plastic-Laminate-Faced Wood PanelingOrder/Fab - Plastic-Laminate-Faced Wood PanelingOrder/Fab - Plastic-Laminate-Faced Wood PanelingOrder/Fab - Plastic-Laminate-Faced Wood PanelingOrder/Fab - Plastic-Laminate-Faced Wood Paneling
Prepare/Submit - Rough CarpentryPrepare/Submit - Rough CarpentryPrepare/Submit - Rough CarpentryPrepare/Submit - Rough CarpentryPrepare/Submit - Rough Carpentry
Review/Approve - Rough CarpentryReview/Approve - Rough CarpentryReview/Approve - Rough CarpentryReview/Approve - Rough CarpentryReview/Approve - Rough Carpentry
Order/Fab - Rough CarpentryOrder/Fab - Rough CarpentryOrder/Fab - Rough CarpentryOrder/Fab - Rough CarpentryOrder/Fab - Rough Carpentry
Division 07 – Thermal And Moisture ProtectionDivision 07 – Thermal And Moisture ProtectionDivision 07 – Thermal And Moisture ProtectionDivision 07 – Thermal And Moisture ProtectionDivision 07 – Thermal And Moisture Protection
Prepare submittal Documents for Thermal and Moisture ProtectionPrepare submittal Documents for Thermal and Moisture ProtectionPrepare submittal Documents for Thermal and Moisture ProtectionPrepare submittal Documents for Thermal and Moisture ProtectionPrepare submittal Documents for Thermal and Moisture Protection
Prepare/Submit - Self-Adhering Sheet WaterproofingPrepare/Submit - Self-Adhering Sheet WaterproofingPrepare/Submit - Self-Adhering Sheet WaterproofingPrepare/Submit - Self-Adhering Sheet WaterproofingPrepare/Submit - Self-Adhering Sheet Waterproofing
Review/Approve - Self-Adhering Sheet WaterproofingReview/Approve - Self-Adhering Sheet WaterproofingReview/Approve - Self-Adhering Sheet WaterproofingReview/Approve - Self-Adhering Sheet WaterproofingReview/Approve - Self-Adhering Sheet Waterproofing
Order/Fab - Self-Adhering Sheet WaterproofingOrder/Fab - Self-Adhering Sheet WaterproofingOrder/Fab - Self-Adhering Sheet WaterproofingOrder/Fab - Self-Adhering Sheet WaterproofingOrder/Fab - Self-Adhering Sheet Waterproofing
Prepare/Submit - Thermal InsulationPrepare/Submit - Thermal InsulationPrepare/Submit - Thermal InsulationPrepare/Submit - Thermal InsulationPrepare/Submit - Thermal Insulation
Review/Approve - Thermal InsulationReview/Approve - Thermal InsulationReview/Approve - Thermal InsulationReview/Approve - Thermal InsulationReview/Approve - Thermal Insulation
Order/Fab - Thermal InsulationOrder/Fab - Thermal InsulationOrder/Fab - Thermal InsulationOrder/Fab - Thermal InsulationOrder/Fab - Thermal Insulation
Prepare/Submit - Fluid-Applied Membrane Air BarriersPrepare/Submit - Fluid-Applied Membrane Air BarriersPrepare/Submit - Fluid-Applied Membrane Air BarriersPrepare/Submit - Fluid-Applied Membrane Air BarriersPrepare/Submit - Fluid-Applied Membrane Air Barriers
Review/Approve - Fluid-Applied Membrane Air BarriersReview/Approve - Fluid-Applied Membrane Air BarriersReview/Approve - Fluid-Applied Membrane Air BarriersReview/Approve - Fluid-Applied Membrane Air BarriersReview/Approve - Fluid-Applied Membrane Air Barriers
Order/Fab - Fluid-Applied Membrane Air BarriersOrder/Fab - Fluid-Applied Membrane Air BarriersOrder/Fab - Fluid-Applied Membrane Air BarriersOrder/Fab - Fluid-Applied Membrane Air BarriersOrder/Fab - Fluid-Applied Membrane Air Barriers
Prepare/Submit - Metal Composite Material Wall PanelsPrepare/Submit - Metal Composite Material Wall PanelsPrepare/Submit - Metal Composite Material Wall PanelsPrepare/Submit - Metal Composite Material Wall PanelsPrepare/Submit - Metal Composite Material Wall Panels
Review/Approve - Metal Composite Material Wall PanelsReview/Approve - Metal Composite Material Wall PanelsReview/Approve - Metal Composite Material Wall PanelsReview/Approve - Metal Composite Material Wall PanelsReview/Approve - Metal Composite Material Wall Panels
Order/Fab - Metal Composite Material Wall PanelsOrder/Fab - Metal Composite Material Wall PanelsOrder/Fab - Metal Composite Material Wall PanelsOrder/Fab - Metal Composite Material Wall PanelsOrder/Fab - Metal Composite Material Wall Panels
Prepare/Submit - Soffit PanelsPrepare/Submit - Soffit PanelsPrepare/Submit - Soffit PanelsPrepare/Submit - Soffit PanelsPrepare/Submit - Soffit Panels
Review/Approve - Soffit PanelsReview/Approve - Soffit PanelsReview/Approve - Soffit PanelsReview/Approve - Soffit PanelsReview/Approve - Soffit Panels
Order/Fab - Soffit PanelsOrder/Fab - Soffit PanelsOrder/Fab - Soffit PanelsOrder/Fab - Soffit PanelsOrder/Fab - Soffit Panels
Prepare/Submit - PVC RoofingPrepare/Submit - PVC RoofingPrepare/Submit - PVC RoofingPrepare/Submit - PVC RoofingPrepare/Submit - PVC Roofing
Review/Approve - PVC RoofingReview/Approve - PVC RoofingReview/Approve - PVC RoofingReview/Approve - PVC RoofingReview/Approve - PVC Roofing
Order/Fab - PVC RoofingOrder/Fab - PVC RoofingOrder/Fab - PVC RoofingOrder/Fab - PVC RoofingOrder/Fab - PVC Roofing
Prepare/Submit - Sheet Metal Flashing and TrimPrepare/Submit - Sheet Metal Flashing and TrimPrepare/Submit - Sheet Metal Flashing and TrimPrepare/Submit - Sheet Metal Flashing and TrimPrepare/Submit - Sheet Metal Flashing and Trim
Review/Approve - Sheet Metal Flashing and TrimReview/Approve - Sheet Metal Flashing and TrimReview/Approve - Sheet Metal Flashing and TrimReview/Approve - Sheet Metal Flashing and TrimReview/Approve - Sheet Metal Flashing and Trim
Order/Fab - Sheet Metal Flashing and TrimOrder/Fab - Sheet Metal Flashing and TrimOrder/Fab - Sheet Metal Flashing and TrimOrder/Fab - Sheet Metal Flashing and TrimOrder/Fab - Sheet Metal Flashing and Trim
Prepare/Submit - Roof AccessoriesPrepare/Submit - Roof AccessoriesPrepare/Submit - Roof AccessoriesPrepare/Submit - Roof AccessoriesPrepare/Submit - Roof Accessories
Review/Approve - Roof AccessoriesReview/Approve - Roof AccessoriesReview/Approve - Roof AccessoriesReview/Approve - Roof AccessoriesReview/Approve - Roof Accessories
Order/Fab - Roof AccessoriesOrder/Fab - Roof AccessoriesOrder/Fab - Roof AccessoriesOrder/Fab - Roof AccessoriesOrder/Fab - Roof Accessories
Prepare/Submit - Vegetated Roof SystemsPrepare/Submit - Vegetated Roof SystemsPrepare/Submit - Vegetated Roof SystemsPrepare/Submit - Vegetated Roof SystemsPrepare/Submit - Vegetated Roof Systems
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 8 of 24
PD7-1250 Review/Approve - Vegetated Roof Systems
PD7-1260 Order/Fab - Vegetated Roof Systems
PD7-1270 Prepare/Submit - Penetration Firestopping
PD7-1280 Review/Approve - Penetration Firestopping
PD7-1290 Order/Fab - Penetration Firestopping
PD7-1300 Prepare/Submit - Joint Sealants
PD7-1310 Review/Approve - Joint Sealants
PD7-1320 Order/Fab - Joint Sealants
PD7-1330 Prepare/Submit - Acoustical Joint Sealants
PD7-1340 Review/Approve - Acoustical Joint Sealants
PD7-1350 Order/Fab - Acoustical Joint Sealants
Division 08 - Openings
PD8-1003 Prepare submittal Documents for Openings
PD8-1004 Prepare/Submit - Hollow Metal Doors and Frames
PD8-1010 Review/Approve - Hollow Metal Doors and Frames
PD8-1020 Order/Fab - Hollow Metal Doors and Frames
PD8-1030 Prepare/Submit - Interior Aluminum Doors and Frames
PD8-1040 Review/Approve - Interior Aluminum Doors and Frames
PD8-1050 Order/Fab - Interior Aluminum Doors and Frames
PD8-1060 Prepare/Submit - Aluminum Terrace Doors
PD8-1070 Review/Approve - Aluminum Terrace Doors
PD8-1080 Order/Fab - Aluminum Terrace Doors
PD8-1090 Prepare/Submit - Flush Wood Doors
PD8-1100 Review/Approve - Flush Wood Doors
PD8-1110 Order/Fab - Flush Wood Doors
PD8-1120 Prepare/Submit - Access Doors and Frames
PD8-1130 Review/Approve - Access Doors and Frames
PD8-1140 Order/Fab - Access Doors and Frames
PD8-1150 Prepare/Submit - Overhead Coiling Doors
PD8-1160 Review/Approve - Overhead Coiling Doors
PD8-1170 Order/Fab - Overhead Coiling Doors
PD8-1180 Prepare/Submit - Aluminum-Framed Storefronts
PD8-1190 Review/Approve - Aluminum-Framed Storefronts
PD8-1200 Order/Fab - Aluminum-Framed Storefronts
PD8-1210 Prepare/Submit - Door Hardware
PD8-1220 Review/Approve - Door Hardware
PD8-1230 Order/Fab - Door Hardware
PD8-1240 Prepare/Submit - Power Door Operators
PD8-1250 Review/Approve - Power Door Operators
PD8-1260 Order/Fab - Power Door Operators
PD8-1270 Prepare/Submit - Glazing
10d 18-Mar-26 31-Mar-26
20d 01-Apr-26 29-Apr-26
10d 18-Mar-26 31-Mar-26
10d 01-Apr-26 14-Apr-26
20d 15-Apr-26 13-May-26
10d 18-Mar-26 31-Mar-26
10d 01-Apr-26 14-Apr-26
20d 15-Apr-26 13-May-26
10d 18-Mar-26 31-Mar-26
10d 01-Apr-26 14-Apr-26
20d 15-Apr-26 13-May-26
181d 03-Feb-26 20-Oct-26
80d 03-Feb-26 28-May-26
10d 29-May-26 11-Jun-26
10d 12-Jun-26 25-Jun-26
20d 26-Jun-26 24-Jul-26
10d 29-May-26 11-Jun-26
10d 12-Jun-26 25-Jun-26
20d 26-Jun-26 24-Jul-26
10d 12-Jun-26 25-Jun-26
10d 26-Jun-26 10-Jul-26
20d 13-Jul-26 07-Aug-26
10d 12-Jun-26 25-Jun-26
10d 26-Jun-26 10-Jul-26
20d 13-Jul-26 07-Aug-26
10d 26-Jun-26 10-Jul-26
10d 13-Jul-26 24-Jul-26
20d 27-Jul-26 21-Aug-26
10d 26-Jun-26 10-Jul-26
10d 13-Jul-26 24-Jul-26
20d 27-Jul-26 21-Aug-26
10d 13-Jul-26 24-Jul-26
10d 27-Jul-26 07-Aug-26
20d 10-Aug-26 04-Sep-26
10d 13-Jul-26 24-Jul-26
10d 27-Jul-26 07-Aug-26
20d 10-Aug-26 04-Sep-26
10d 27-Jul-26 07-Aug-26
10d 10-Aug-26 21-Aug-26
20d 24-Aug-26 21-Sep-26
10d 27-Jul-26 07-Aug-26
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Review/Approve - Vegetated Roof SystemsReview/Approve - Vegetated Roof SystemsReview/Approve - Vegetated Roof SystemsReview/Approve - Vegetated Roof SystemsReview/Approve - Vegetated Roof Systems
Order/Fab - Vegetated Roof SystemsOrder/Fab - Vegetated Roof SystemsOrder/Fab - Vegetated Roof SystemsOrder/Fab - Vegetated Roof SystemsOrder/Fab - Vegetated Roof Systems
Prepare/Submit - Penetration FirestoppingPrepare/Submit - Penetration FirestoppingPrepare/Submit - Penetration FirestoppingPrepare/Submit - Penetration FirestoppingPrepare/Submit - Penetration Firestopping
Review/Approve - Penetration FirestoppingReview/Approve - Penetration FirestoppingReview/Approve - Penetration FirestoppingReview/Approve - Penetration FirestoppingReview/Approve - Penetration Firestopping
Order/Fab - Penetration FirestoppingOrder/Fab - Penetration FirestoppingOrder/Fab - Penetration FirestoppingOrder/Fab - Penetration FirestoppingOrder/Fab - Penetration Firestopping
Prepare/Submit - Joint SealantsPrepare/Submit - Joint SealantsPrepare/Submit - Joint SealantsPrepare/Submit - Joint SealantsPrepare/Submit - Joint Sealants
Review/Approve - Joint SealantsReview/Approve - Joint SealantsReview/Approve - Joint SealantsReview/Approve - Joint SealantsReview/Approve - Joint Sealants
Order/Fab - Joint SealantsOrder/Fab - Joint SealantsOrder/Fab - Joint SealantsOrder/Fab - Joint SealantsOrder/Fab - Joint Sealants
Prepare/Submit - Acoustical Joint SealantsPrepare/Submit - Acoustical Joint SealantsPrepare/Submit - Acoustical Joint SealantsPrepare/Submit - Acoustical Joint SealantsPrepare/Submit - Acoustical Joint Sealants
Review/Approve - Acoustical Joint SealantsReview/Approve - Acoustical Joint SealantsReview/Approve - Acoustical Joint SealantsReview/Approve - Acoustical Joint SealantsReview/Approve - Acoustical Joint Sealants
Order/Fab - Acoustical Joint SealantsOrder/Fab - Acoustical Joint SealantsOrder/Fab - Acoustical Joint SealantsOrder/Fab - Acoustical Joint SealantsOrder/Fab - Acoustical Joint Sealants
Division 08 - OpeningsDivision 08 - OpeningsDivision 08 - OpeningsDivision 08 - OpeningsDivision 08 - Openings
Prepare submittal Documents for OpeningsPrepare submittal Documents for OpeningsPrepare submittal Documents for OpeningsPrepare submittal Documents for OpeningsPrepare submittal Documents for Openings
Prepare/Submit - Hollow Metal Doors and FramesPrepare/Submit - Hollow Metal Doors and FramesPrepare/Submit - Hollow Metal Doors and FramesPrepare/Submit - Hollow Metal Doors and FramesPrepare/Submit - Hollow Metal Doors and Frames
Review/Approve - Hollow Metal Doors and FramesReview/Approve - Hollow Metal Doors and FramesReview/Approve - Hollow Metal Doors and FramesReview/Approve - Hollow Metal Doors and FramesReview/Approve - Hollow Metal Doors and Frames
Order/Fab - Hollow Metal Doors and FramesOrder/Fab - Hollow Metal Doors and FramesOrder/Fab - Hollow Metal Doors and FramesOrder/Fab - Hollow Metal Doors and FramesOrder/Fab - Hollow Metal Doors and Frames
Prepare/Submit - Interior Aluminum Doors and FramesPrepare/Submit - Interior Aluminum Doors and FramesPrepare/Submit - Interior Aluminum Doors and FramesPrepare/Submit - Interior Aluminum Doors and FramesPrepare/Submit - Interior Aluminum Doors and Frames
Review/Approve - Interior Aluminum Doors and FramesReview/Approve - Interior Aluminum Doors and FramesReview/Approve - Interior Aluminum Doors and FramesReview/Approve - Interior Aluminum Doors and FramesReview/Approve - Interior Aluminum Doors and Frames
Order/Fab - Interior Aluminum Doors and FramesOrder/Fab - Interior Aluminum Doors and FramesOrder/Fab - Interior Aluminum Doors and FramesOrder/Fab - Interior Aluminum Doors and FramesOrder/Fab - Interior Aluminum Doors and Frames
Prepare/Submit - Aluminum Terrace DoorsPrepare/Submit - Aluminum Terrace DoorsPrepare/Submit - Aluminum Terrace DoorsPrepare/Submit - Aluminum Terrace DoorsPrepare/Submit - Aluminum Terrace Doors
Review/Approve - Aluminum Terrace DoorsReview/Approve - Aluminum Terrace DoorsReview/Approve - Aluminum Terrace DoorsReview/Approve - Aluminum Terrace DoorsReview/Approve - Aluminum Terrace Doors
Order/Fab - Aluminum Terrace DoorsOrder/Fab - Aluminum Terrace DoorsOrder/Fab - Aluminum Terrace DoorsOrder/Fab - Aluminum Terrace DoorsOrder/Fab - Aluminum Terrace Doors
Prepare/Submit - Flush Wood DoorsPrepare/Submit - Flush Wood DoorsPrepare/Submit - Flush Wood DoorsPrepare/Submit - Flush Wood DoorsPrepare/Submit - Flush Wood Doors
Review/Approve - Flush Wood DoorsReview/Approve - Flush Wood DoorsReview/Approve - Flush Wood DoorsReview/Approve - Flush Wood DoorsReview/Approve - Flush Wood Doors
Order/Fab - Flush Wood DoorsOrder/Fab - Flush Wood DoorsOrder/Fab - Flush Wood DoorsOrder/Fab - Flush Wood DoorsOrder/Fab - Flush Wood Doors
Prepare/Submit - Access Doors and FramesPrepare/Submit - Access Doors and FramesPrepare/Submit - Access Doors and FramesPrepare/Submit - Access Doors and FramesPrepare/Submit - Access Doors and Frames
Review/Approve - Access Doors and FramesReview/Approve - Access Doors and FramesReview/Approve - Access Doors and FramesReview/Approve - Access Doors and FramesReview/Approve - Access Doors and Frames
Order/Fab - Access Doors and FramesOrder/Fab - Access Doors and FramesOrder/Fab - Access Doors and FramesOrder/Fab - Access Doors and FramesOrder/Fab - Access Doors and Frames
Prepare/Submit - Overhead Coiling DoorsPrepare/Submit - Overhead Coiling DoorsPrepare/Submit - Overhead Coiling DoorsPrepare/Submit - Overhead Coiling DoorsPrepare/Submit - Overhead Coiling Doors
Review/Approve - Overhead Coiling DoorsReview/Approve - Overhead Coiling DoorsReview/Approve - Overhead Coiling DoorsReview/Approve - Overhead Coiling DoorsReview/Approve - Overhead Coiling Doors
Order/Fab - Overhead Coiling DoorsOrder/Fab - Overhead Coiling DoorsOrder/Fab - Overhead Coiling DoorsOrder/Fab - Overhead Coiling DoorsOrder/Fab - Overhead Coiling Doors
Prepare/Submit - Aluminum-Framed StorefrontsPrepare/Submit - Aluminum-Framed StorefrontsPrepare/Submit - Aluminum-Framed StorefrontsPrepare/Submit - Aluminum-Framed StorefrontsPrepare/Submit - Aluminum-Framed Storefronts
Review/Approve - Aluminum-Framed StorefrontsReview/Approve - Aluminum-Framed StorefrontsReview/Approve - Aluminum-Framed StorefrontsReview/Approve - Aluminum-Framed StorefrontsReview/Approve - Aluminum-Framed Storefronts
Order/Fab - Aluminum-Framed StorefrontsOrder/Fab - Aluminum-Framed StorefrontsOrder/Fab - Aluminum-Framed StorefrontsOrder/Fab - Aluminum-Framed StorefrontsOrder/Fab - Aluminum-Framed Storefronts
Prepare/Submit - Door HardwarePrepare/Submit - Door HardwarePrepare/Submit - Door HardwarePrepare/Submit - Door HardwarePrepare/Submit - Door Hardware
Review/Approve - Door HardwareReview/Approve - Door HardwareReview/Approve - Door HardwareReview/Approve - Door HardwareReview/Approve - Door Hardware
Order/Fab - Door HardwareOrder/Fab - Door HardwareOrder/Fab - Door HardwareOrder/Fab - Door HardwareOrder/Fab - Door Hardware
Prepare/Submit - Power Door OperatorsPrepare/Submit - Power Door OperatorsPrepare/Submit - Power Door OperatorsPrepare/Submit - Power Door OperatorsPrepare/Submit - Power Door Operators
Review/Approve - Power Door OperatorsReview/Approve - Power Door OperatorsReview/Approve - Power Door OperatorsReview/Approve - Power Door OperatorsReview/Approve - Power Door Operators
Order/Fab - Power Door OperatorsOrder/Fab - Power Door OperatorsOrder/Fab - Power Door OperatorsOrder/Fab - Power Door OperatorsOrder/Fab - Power Door Operators
Prepare/Submit - GlazingPrepare/Submit - GlazingPrepare/Submit - GlazingPrepare/Submit - GlazingPrepare/Submit - Glazing
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 9 of 24
PD8-1280 Review/Approve - Glazing
PD8-1290 Order/Fab - Glazing
PD8-1300 Prepare/Submit - Decorative Glass Glazing
PD8-1310 Review/Approve - Decorative Glass Glazing
PD8-1320 Order/Fab - Decorative Glass Glazing
PD8-1330 Prepare/Submit - Mirrors
PD8-1340 Review/Approve - Mirrors
PD8-1350 Order/Fab - Mirrors
PD8-1360 Prepare/Submit - Fixed Louvers
PD8-1370 Review/Approve - Fixed Louvers
PD8-1380 Order/Fab - Fixed Louvers
Division 09 - Finishes
PD9-1002 Prepare submittal documents for High-Performance Coati…
PD9-1004 Prepare submittal documents for other Finishes
PD9-1005 Prepare/Submit - Ceramic Tiling
PD9-1010 Review/Approve - Ceramic Tiling
PD9-1020 Order/Fab - Ceramic Tiling
PD9-1030 Prepare/Submit - Acoustical Panel Ceilings
PD9-1040 Review/Approve - Acoustical Panel Ceilings
PD9-1050 Order/Fab - Acoustical Panel Ceilings
PD9-1060 Prepare/Submit - Suspended Wood Ceilings
PD9-1070 Review/Approve - Suspended Wood Ceilings
PD9-1080 Order/Fab - Suspended Wood Ceilings
PD9-1090 Prepare/Submit - Resilient Base and Accessories
PD9-1100 Review/Approve - Resilient Base and Accessories
PD9-1110 Order/Fab - Resilient Base and Accessories
PD9-1120 Prepare/Submit - Resilient Tile Flooring
PD9-1130 Review/Approve - Resilient Tile Flooring
PD9-1140 Order/Fab - Resilient Tile Flooring
PD9-1150 Prepare/Submit - Resilient Athletic Flooring
PD9-1160 Review/Approve - Resilient Athletic Flooring
PD9-1170 Order/Fab - Resilient Athletic Flooring
PD9-1180 Prepare/Submit - Resinous Matrix Terrazzo Flooring
PD9-1190 Review/Approve - Resinous Matrix Terrazzo Flooring
PD9-1200 Order/Fab - Terrazzo Flooring
PD9-1210 Prepare/Submit - Acoustic Room Components
PD9-1220 Review/Approve - Acoustic Room Components
PD9-1230 Order/Fab - Acoustic Room Components
PD9-1240 Prepare/Submit - Exterior Painting
PD9-1250 Review/Approve - Exterior Painting
PD9-1260 Prepare/Submit - Interior Painting
10d 10-Aug-26 21-Aug-26
20d 24-Aug-26 21-Sep-26
10d 10-Aug-26 21-Aug-26
10d 24-Aug-26 04-Sep-26
20d 08-Sep-26 05-Oct-26
10d 10-Aug-26 21-Aug-26
10d 24-Aug-26 04-Sep-26
20d 08-Sep-26 05-Oct-26
10d 24-Aug-26 04-Sep-26
10d 08-Sep-26 21-Sep-26
20d 22-Sep-26 20-Oct-26
160d 29-May-26 19-Jan-27
60d 29-May-26 21-Aug-26
40d 24-Aug-26 20-Oct-26
10d 21-Oct-26 03-Nov-26
10d 04-Nov-26 18-Nov-26
20d 19-Nov-26 17-Dec-26
10d 21-Oct-26 03-Nov-26
10d 04-Nov-26 18-Nov-26
20d 19-Nov-26 17-Dec-26
10d 21-Oct-26 03-Nov-26
10d 04-Nov-26 18-Nov-26
20d 19-Nov-26 17-Dec-26
10d 04-Nov-26 18-Nov-26
10d 19-Nov-26 03-Dec-26
20d 04-Dec-26 04-Jan-27
10d 04-Nov-26 18-Nov-26
10d 19-Nov-26 03-Dec-26
20d 04-Dec-26 04-Jan-27
10d 04-Nov-26 18-Nov-26
10d 19-Nov-26 03-Dec-26
20d 04-Dec-26 04-Jan-27
10d 19-Nov-26 03-Dec-26
10d 04-Dec-26 17-Dec-26
20d 18-Dec-26 19-Jan-27
10d 19-Nov-26 03-Dec-26
10d 04-Dec-26 17-Dec-26
20d 18-Dec-26 19-Jan-27
10d 19-Nov-26 03-Dec-26
10d 04-Dec-26 17-Dec-26
10d 04-Dec-26 17-Dec-26
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Review/Approve - GlazingReview/Approve - GlazingReview/Approve - GlazingReview/Approve - GlazingReview/Approve - Glazing
Order/Fab - GlazingOrder/Fab - GlazingOrder/Fab - GlazingOrder/Fab - GlazingOrder/Fab - Glazing
Prepare/Submit - Decorative Glass GlazingPrepare/Submit - Decorative Glass GlazingPrepare/Submit - Decorative Glass GlazingPrepare/Submit - Decorative Glass GlazingPrepare/Submit - Decorative Glass Glazing
Review/Approve - Decorative Glass GlazingReview/Approve - Decorative Glass GlazingReview/Approve - Decorative Glass GlazingReview/Approve - Decorative Glass GlazingReview/Approve - Decorative Glass Glazing
Order/Fab - Decorative Glass GlazingOrder/Fab - Decorative Glass GlazingOrder/Fab - Decorative Glass GlazingOrder/Fab - Decorative Glass GlazingOrder/Fab - Decorative Glass Glazing
Prepare/Submit - MirrorsPrepare/Submit - MirrorsPrepare/Submit - MirrorsPrepare/Submit - MirrorsPrepare/Submit - Mirrors
Review/Approve - MirrorsReview/Approve - MirrorsReview/Approve - MirrorsReview/Approve - MirrorsReview/Approve - Mirrors
Order/Fab - MirrorsOrder/Fab - MirrorsOrder/Fab - MirrorsOrder/Fab - MirrorsOrder/Fab - Mirrors
Prepare/Submit - Fixed LouversPrepare/Submit - Fixed LouversPrepare/Submit - Fixed LouversPrepare/Submit - Fixed LouversPrepare/Submit - Fixed Louvers
Review/Approve - Fixed LouversReview/Approve - Fixed LouversReview/Approve - Fixed LouversReview/Approve - Fixed LouversReview/Approve - Fixed Louvers
Order/Fab - Fixed LouversOrder/Fab - Fixed LouversOrder/Fab - Fixed LouversOrder/Fab - Fixed LouversOrder/Fab - Fixed Louvers
Division 09 - FinishesDivision 09 - FinishesDivision 09 - FinishesDivision 09 - FinishesDivision 09 - Finishes
Prepare submittal documents for High-Performance CoatingsPrepare submittal documents for High-Performance CoatingsPrepare submittal documents for High-Performance CoatingsPrepare submittal documents for High-Performance CoatingsPrepare submittal documents for High-Performance Coatings
Prepare submittal documents for other FinishesPrepare submittal documents for other FinishesPrepare submittal documents for other FinishesPrepare submittal documents for other FinishesPrepare submittal documents for other Finishes
Prepare/Submit - Ceramic TilingPrepare/Submit - Ceramic TilingPrepare/Submit - Ceramic TilingPrepare/Submit - Ceramic TilingPrepare/Submit - Ceramic Tiling
Review/Approve - Ceramic TilingReview/Approve - Ceramic TilingReview/Approve - Ceramic TilingReview/Approve - Ceramic TilingReview/Approve - Ceramic Tiling
Order/Fab - Ceramic TilingOrder/Fab - Ceramic TilingOrder/Fab - Ceramic TilingOrder/Fab - Ceramic TilingOrder/Fab - Ceramic Tiling
Prepare/Submit - Acoustical Panel CeilingsPrepare/Submit - Acoustical Panel CeilingsPrepare/Submit - Acoustical Panel CeilingsPrepare/Submit - Acoustical Panel CeilingsPrepare/Submit - Acoustical Panel Ceilings
Review/Approve - Acoustical Panel CeilingsReview/Approve - Acoustical Panel CeilingsReview/Approve - Acoustical Panel CeilingsReview/Approve - Acoustical Panel CeilingsReview/Approve - Acoustical Panel Ceilings
Order/Fab - Acoustical Panel CeilingsOrder/Fab - Acoustical Panel CeilingsOrder/Fab - Acoustical Panel CeilingsOrder/Fab - Acoustical Panel CeilingsOrder/Fab - Acoustical Panel Ceilings
Prepare/Submit - Suspended Wood CeilingsPrepare/Submit - Suspended Wood CeilingsPrepare/Submit - Suspended Wood CeilingsPrepare/Submit - Suspended Wood CeilingsPrepare/Submit - Suspended Wood Ceilings
Review/Approve - Suspended Wood CeilingsReview/Approve - Suspended Wood CeilingsReview/Approve - Suspended Wood CeilingsReview/Approve - Suspended Wood CeilingsReview/Approve - Suspended Wood Ceilings
Order/Fab - Suspended Wood CeilingsOrder/Fab - Suspended Wood CeilingsOrder/Fab - Suspended Wood CeilingsOrder/Fab - Suspended Wood CeilingsOrder/Fab - Suspended Wood Ceilings
Prepare/Submit - Resilient Base and AccessoriesPrepare/Submit - Resilient Base and AccessoriesPrepare/Submit - Resilient Base and AccessoriesPrepare/Submit - Resilient Base and AccessoriesPrepare/Submit - Resilient Base and Accessories
Review/Approve - Resilient Base and AccessoriesReview/Approve - Resilient Base and AccessoriesReview/Approve - Resilient Base and AccessoriesReview/Approve - Resilient Base and AccessoriesReview/Approve - Resilient Base and Accessories
Order/Fab - Resilient Base and AccessoriesOrder/Fab - Resilient Base and AccessoriesOrder/Fab - Resilient Base and AccessoriesOrder/Fab - Resilient Base and AccessoriesOrder/Fab - Resilient Base and Accessories
Prepare/Submit - Resilient Tile FlooringPrepare/Submit - Resilient Tile FlooringPrepare/Submit - Resilient Tile FlooringPrepare/Submit - Resilient Tile FlooringPrepare/Submit - Resilient Tile Flooring
Review/Approve - Resilient Tile FlooringReview/Approve - Resilient Tile FlooringReview/Approve - Resilient Tile FlooringReview/Approve - Resilient Tile FlooringReview/Approve - Resilient Tile Flooring
Order/Fab - Resilient Tile FlooringOrder/Fab - Resilient Tile FlooringOrder/Fab - Resilient Tile FlooringOrder/Fab - Resilient Tile FlooringOrder/Fab - Resilient Tile Flooring
Prepare/Submit - Resilient Athletic FlooringPrepare/Submit - Resilient Athletic FlooringPrepare/Submit - Resilient Athletic FlooringPrepare/Submit - Resilient Athletic FlooringPrepare/Submit - Resilient Athletic Flooring
Review/Approve - Resilient Athletic FlooringReview/Approve - Resilient Athletic FlooringReview/Approve - Resilient Athletic FlooringReview/Approve - Resilient Athletic FlooringReview/Approve - Resilient Athletic Flooring
Order/Fab - Resilient Athletic FlooringOrder/Fab - Resilient Athletic FlooringOrder/Fab - Resilient Athletic FlooringOrder/Fab - Resilient Athletic FlooringOrder/Fab - Resilient Athletic Flooring
Prepare/Submit - Resinous Matrix Terrazzo FlooringPrepare/Submit - Resinous Matrix Terrazzo FlooringPrepare/Submit - Resinous Matrix Terrazzo FlooringPrepare/Submit - Resinous Matrix Terrazzo FlooringPrepare/Submit - Resinous Matrix Terrazzo Flooring
Review/Approve - Resinous Matrix Terrazzo FlooringReview/Approve - Resinous Matrix Terrazzo FlooringReview/Approve - Resinous Matrix Terrazzo FlooringReview/Approve - Resinous Matrix Terrazzo FlooringReview/Approve - Resinous Matrix Terrazzo Flooring
Order/Fab - Terrazzo FlooringOrder/Fab - Terrazzo FlooringOrder/Fab - Terrazzo FlooringOrder/Fab - Terrazzo FlooringOrder/Fab - Terrazzo Flooring
Prepare/Submit - Acoustic Room ComponentsPrepare/Submit - Acoustic Room ComponentsPrepare/Submit - Acoustic Room ComponentsPrepare/Submit - Acoustic Room ComponentsPrepare/Submit - Acoustic Room Components
Review/Approve - Acoustic Room ComponentsReview/Approve - Acoustic Room ComponentsReview/Approve - Acoustic Room ComponentsReview/Approve - Acoustic Room ComponentsReview/Approve - Acoustic Room Components
Order/Fab - Acoustic Room ComponentsOrder/Fab - Acoustic Room ComponentsOrder/Fab - Acoustic Room ComponentsOrder/Fab - Acoustic Room ComponentsOrder/Fab - Acoustic Room Components
Prepare/Submit - Exterior PaintingPrepare/Submit - Exterior PaintingPrepare/Submit - Exterior PaintingPrepare/Submit - Exterior PaintingPrepare/Submit - Exterior Painting
Review/Approve - Exterior PaintingReview/Approve - Exterior PaintingReview/Approve - Exterior PaintingReview/Approve - Exterior PaintingReview/Approve - Exterior Painting
Prepare/Submit - Interior PaintingPrepare/Submit - Interior PaintingPrepare/Submit - Interior PaintingPrepare/Submit - Interior PaintingPrepare/Submit - Interior Painting
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 10 of 24
PD9-1270 Review/Approve - Interior Painting
PD9-1280 Prepare/Submit - Staining and Transparent Finishing
PD9-1290 Review/Approve - Staining and Transparent Finishing
PD9-1300 Prepare/Submit - High-Performance Coatings
PD9-1310 Review/Approve - High-Performance Coatings
PD9-1320 Order/Fab - High-Performance Coatings
Division 10 – Specialties
PD10-1000 Prepare/Submit - Signage & Wayfinding
PD10-1010 Review/Approve - Signage & Wayfinding
PD10-1020 Order/Fabricate - Signage & Wayfinding
PD10-1030 Prepare/Submit - Toilet Partitions
PD10-1040 Review/Approve - Toilet Partitions
PD10-1050 Order/Fabricate - Toilet Partitions
PD10-1060 Prepare/Submit - Toilet Accessories
PD10-1070 Review/Approve - Toilet Accessories
PD10-1080 Order/Fabricate - Toilet Accessories
PD10-1090 Prepare/Submit - Metal Shelving
PD10-1100 Review/Approve - Metal Shelving
PD10-1110 Order/Fabricate - Metal Shelving
PD10-1120 Prepare/Submit - Metal Display Cases
PD10-1130 Review/Approve - Metal Display Cases
PD10-1140 Order/Fabricate - Metal Display Cases
PD10-1150 Prepare/Submit - Monumental LED Signage
PD10-1160 Review/Approve - Monumental LED Signage
PD10-1170 Order/Fabricate - Monumental LED Signage
PD10-1180 Prepare/Submit - Flagpoles
PD10-1190 Review/Approve - Flagpoles
PD10-1200 Order/Fabricate - Flagpoles
Division 11 – Equipment
PD11-1000 Prepare/Submit - Kitchen Equipment
PD11-1010 Review/Approve - Kitchen Equipment
PD11-1020 Order/Fabricate - Kitchen Equipment
PD11-1030 Prepare/Submit - Folding and Portable Stages Submittals
PD11-1040 Review/Approve - Folding and Portable Stages Submittals
PD11-1050 Order/Fab - Folding and Portable Stages
PD11-1060 Deliver/Install - Folding and Portable Stages
PD11-1070 Prepare/Submit - Stage Curtains Submittals
PD11-1080 Review/Approve - Stage Curtains Submittals
PD11-1090 Order/Fab - Stage Curtains
PD11-1100 Deliver/Install - Stage Curtains
PD11-1110 Prepare/Submit - Gymnasium Equipment
10d 18-Dec-26 04-Jan-27
10d 04-Dec-26 17-Dec-26
10d 18-Dec-26 04-Jan-27
10d 24-Aug-26 04-Sep-26
10d 08-Sep-26 21-Sep-26
30d 22-Sep-26 03-Nov-26
120d 21-Oct-26 14-Apr-27
10d 21-Oct-26 03-Nov-26
10d 04-Nov-26 18-Nov-26
40d 19-Nov-26 19-Jan-27
10d 04-Nov-26 18-Nov-26
10d 19-Nov-26 03-Dec-26
40d 04-Dec-26 02-Feb-27
10d 19-Nov-26 03-Dec-26
10d 04-Dec-26 17-Dec-26
40d 18-Dec-26 17-Feb-27
10d 04-Dec-26 17-Dec-26
10d 18-Dec-26 04-Jan-27
40d 05-Jan-27 03-Mar-27
10d 18-Dec-26 04-Jan-27
10d 05-Jan-27 19-Jan-27
40d 20-Jan-27 17-Mar-27
10d 05-Jan-27 19-Jan-27
10d 20-Jan-27 02-Feb-27
40d 03-Feb-27 31-Mar-27
10d 20-Jan-27 02-Feb-27
10d 03-Feb-27 17-Feb-27
40d 18-Feb-27 14-Apr-27
233d 29-May-26 04-May-27
10d 29-May-26 11-Jun-26
10d 12-Jun-26 25-Jun-26
40d 26-Jun-26 21-Aug-26
10d 29-May-26 11-Jun-26
10d 12-Jun-26 25-Jun-26
30d 26-Jun-26 07-Aug-26
20d 06-Apr-27 04-May-27
10d 12-Jun-26 25-Jun-26
10d 26-Jun-26 10-Jul-26
30d 13-Jul-26 21-Aug-26
20d 06-Apr-27 04-May-27
10d 12-Jun-26 25-Jun-26
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Review/Approve - Interior PaintingReview/Approve - Interior PaintingReview/Approve - Interior PaintingReview/Approve - Interior PaintingReview/Approve - Interior Painting
Prepare/Submit - Staining and Transparent FinishingPrepare/Submit - Staining and Transparent FinishingPrepare/Submit - Staining and Transparent FinishingPrepare/Submit - Staining and Transparent FinishingPrepare/Submit - Staining and Transparent Finishing
Review/Approve - Staining and Transparent FinishingReview/Approve - Staining and Transparent FinishingReview/Approve - Staining and Transparent FinishingReview/Approve - Staining and Transparent FinishingReview/Approve - Staining and Transparent Finishing
Prepare/Submit - High-Performance CoatingsPrepare/Submit - High-Performance CoatingsPrepare/Submit - High-Performance CoatingsPrepare/Submit - High-Performance CoatingsPrepare/Submit - High-Performance Coatings
Review/Approve - High-Performance CoatingsReview/Approve - High-Performance CoatingsReview/Approve - High-Performance CoatingsReview/Approve - High-Performance CoatingsReview/Approve - High-Performance Coatings
Order/Fab - High-Performance CoatingsOrder/Fab - High-Performance CoatingsOrder/Fab - High-Performance CoatingsOrder/Fab - High-Performance CoatingsOrder/Fab - High-Performance Coatings
Division 10 – SpecialtiesDivision 10 – SpecialtiesDivision 10 – SpecialtiesDivision 10 – SpecialtiesDivision 10 – Specialties
Prepare/Submit - Signage & WayfindingPrepare/Submit - Signage & WayfindingPrepare/Submit - Signage & WayfindingPrepare/Submit - Signage & WayfindingPrepare/Submit - Signage & Wayfinding
Review/Approve - Signage & WayfindingReview/Approve - Signage & WayfindingReview/Approve - Signage & WayfindingReview/Approve - Signage & WayfindingReview/Approve - Signage & Wayfinding
Order/Fabricate - Signage & WayfindingOrder/Fabricate - Signage & WayfindingOrder/Fabricate - Signage & WayfindingOrder/Fabricate - Signage & WayfindingOrder/Fabricate - Signage & Wayfinding
Prepare/Submit - Toilet PartitionsPrepare/Submit - Toilet PartitionsPrepare/Submit - Toilet PartitionsPrepare/Submit - Toilet PartitionsPrepare/Submit - Toilet Partitions
Review/Approve - Toilet PartitionsReview/Approve - Toilet PartitionsReview/Approve - Toilet PartitionsReview/Approve - Toilet PartitionsReview/Approve - Toilet Partitions
Order/Fabricate - Toilet PartitionsOrder/Fabricate - Toilet PartitionsOrder/Fabricate - Toilet PartitionsOrder/Fabricate - Toilet PartitionsOrder/Fabricate - Toilet Partitions
Prepare/Submit - Toilet AccessoriesPrepare/Submit - Toilet AccessoriesPrepare/Submit - Toilet AccessoriesPrepare/Submit - Toilet AccessoriesPrepare/Submit - Toilet Accessories
Review/Approve - Toilet AccessoriesReview/Approve - Toilet AccessoriesReview/Approve - Toilet AccessoriesReview/Approve - Toilet AccessoriesReview/Approve - Toilet Accessories
Order/Fabricate - Toilet AccessoriesOrder/Fabricate - Toilet AccessoriesOrder/Fabricate - Toilet AccessoriesOrder/Fabricate - Toilet AccessoriesOrder/Fabricate - Toilet Accessories
Prepare/Submit - Metal ShelvingPrepare/Submit - Metal ShelvingPrepare/Submit - Metal ShelvingPrepare/Submit - Metal ShelvingPrepare/Submit - Metal Shelving
Review/Approve - Metal ShelvingReview/Approve - Metal ShelvingReview/Approve - Metal ShelvingReview/Approve - Metal ShelvingReview/Approve - Metal Shelving
Order/Fabricate - Metal ShelvingOrder/Fabricate - Metal ShelvingOrder/Fabricate - Metal ShelvingOrder/Fabricate - Metal ShelvingOrder/Fabricate - Metal Shelving
Prepare/Submit - Metal Display CasesPrepare/Submit - Metal Display CasesPrepare/Submit - Metal Display CasesPrepare/Submit - Metal Display CasesPrepare/Submit - Metal Display Cases
Review/Approve - Metal Display CasesReview/Approve - Metal Display CasesReview/Approve - Metal Display CasesReview/Approve - Metal Display CasesReview/Approve - Metal Display Cases
Order/Fabricate - Metal Display CasesOrder/Fabricate - Metal Display CasesOrder/Fabricate - Metal Display CasesOrder/Fabricate - Metal Display CasesOrder/Fabricate - Metal Display Cases
Prepare/Submit - Monumental LED SignagePrepare/Submit - Monumental LED SignagePrepare/Submit - Monumental LED SignagePrepare/Submit - Monumental LED SignagePrepare/Submit - Monumental LED Signage
Review/Approve - Monumental LED SignageReview/Approve - Monumental LED SignageReview/Approve - Monumental LED SignageReview/Approve - Monumental LED SignageReview/Approve - Monumental LED Signage
Order/Fabricate - Monumental LED SignageOrder/Fabricate - Monumental LED SignageOrder/Fabricate - Monumental LED SignageOrder/Fabricate - Monumental LED SignageOrder/Fabricate - Monumental LED Signage
Prepare/Submit - FlagpolesPrepare/Submit - FlagpolesPrepare/Submit - FlagpolesPrepare/Submit - FlagpolesPrepare/Submit - Flagpoles
Review/Approve - FlagpolesReview/Approve - FlagpolesReview/Approve - FlagpolesReview/Approve - FlagpolesReview/Approve - Flagpoles
Order/Fabricate - FlagpolesOrder/Fabricate - FlagpolesOrder/Fabricate - FlagpolesOrder/Fabricate - FlagpolesOrder/Fabricate - Flagpoles
Division 11 – EquipmentDivision 11 – EquipmentDivision 11 – EquipmentDivision 11 – EquipmentDivision 11 – Equipment
Prepare/Submit - Kitchen EquipmentPrepare/Submit - Kitchen EquipmentPrepare/Submit - Kitchen EquipmentPrepare/Submit - Kitchen EquipmentPrepare/Submit - Kitchen Equipment
Review/Approve - Kitchen EquipmentReview/Approve - Kitchen EquipmentReview/Approve - Kitchen EquipmentReview/Approve - Kitchen EquipmentReview/Approve - Kitchen Equipment
Order/Fabricate - Kitchen EquipmentOrder/Fabricate - Kitchen EquipmentOrder/Fabricate - Kitchen EquipmentOrder/Fabricate - Kitchen EquipmentOrder/Fabricate - Kitchen Equipment
Prepare/Submit - Folding and Portable Stages SubmittalsPrepare/Submit - Folding and Portable Stages SubmittalsPrepare/Submit - Folding and Portable Stages SubmittalsPrepare/Submit - Folding and Portable Stages SubmittalsPrepare/Submit - Folding and Portable Stages Submittals
Review/Approve - Folding and Portable Stages SubmittalsReview/Approve - Folding and Portable Stages SubmittalsReview/Approve - Folding and Portable Stages SubmittalsReview/Approve - Folding and Portable Stages SubmittalsReview/Approve - Folding and Portable Stages Submittals
Order/Fab - Folding and Portable StagesOrder/Fab - Folding and Portable StagesOrder/Fab - Folding and Portable StagesOrder/Fab - Folding and Portable StagesOrder/Fab - Folding and Portable Stages
Deliver/Install - Folding and Portable StagesDeliver/Install - Folding and Portable StagesDeliver/Install - Folding and Portable StagesDeliver/Install - Folding and Portable StagesDeliver/Install - Folding and Portable Stages
Prepare/Submit - Stage Curtains SubmittalsPrepare/Submit - Stage Curtains SubmittalsPrepare/Submit - Stage Curtains SubmittalsPrepare/Submit - Stage Curtains SubmittalsPrepare/Submit - Stage Curtains Submittals
Review/Approve - Stage Curtains SubmittalsReview/Approve - Stage Curtains SubmittalsReview/Approve - Stage Curtains SubmittalsReview/Approve - Stage Curtains SubmittalsReview/Approve - Stage Curtains Submittals
Order/Fab - Stage CurtainsOrder/Fab - Stage CurtainsOrder/Fab - Stage CurtainsOrder/Fab - Stage CurtainsOrder/Fab - Stage Curtains
Deliver/Install - Stage CurtainsDeliver/Install - Stage CurtainsDeliver/Install - Stage CurtainsDeliver/Install - Stage CurtainsDeliver/Install - Stage Curtains
Prepare/Submit - Gymnasium EquipmentPrepare/Submit - Gymnasium EquipmentPrepare/Submit - Gymnasium EquipmentPrepare/Submit - Gymnasium EquipmentPrepare/Submit - Gymnasium Equipment
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 11 of 24
PD11-1120 Review/Approve - Gymnasium Equipment
PD11-1130 Order/Fabricate - Gymnasium Equipment
PD11-1140 Prepare/Submit - Gymnasium Dividers Submittals
PD11-1150 Review/Approve - Gymnasium Dividers Submittals
PD11-1160 Order/Fab - Gymnasium Dividers
PD11-1170 Deliver/Install - Gymnasium Dividers
PD11-1180 Prepare/Submit - Theater Equipment
PD11-1190 Review/Approve - Theater Equipment
PD11-1200 Order/Fabricate - Theater Equipment
PD11-1210 Prepare/Submit - Play Equipment and Surfacing
PD11-1220 Review/Approve - Play Equipment and Surfacing
PD11-1230 Order/Fabricate - Play Equipment and Surfacing
Division 12 – Furnishings
PD12-1000 Prepare/Submit - Window Treatment
PD12-1010 Review/Approve - Window Treatment
PD12-1020 Order/Fabricate - Window Treatment
PD12-1030 Prepare/Submit - Roller Window Shades Submittals
PD12-1040 Review/Approve - Roller Window Shades Submittals
PD12-1050 Order/Fab - Roller Window Shades
PD12-1060 Deliver/Install - Roller Window Shades
PD12-1070 Prepare/Submit - Plastic-Laminate-Clad Casework Submi…
PD12-1080 Review/Approve - Plastic-Laminate-Clad Casework Submi…
PD12-1090 Order/Fab - Plastic-Laminate-Clad Casework
PD12-1100 Deliver/Install - Plastic-Laminate-Clad Casework
PD12-1110 Prepare/Submit - Solid Surfacing Countertops Submittals
PD12-1120 Review/Approve - Solid Surfacing Countertops Submittals
PD12-1130 Order/Fab - Solid Surfacing Countertops
PD12-1140 Deliver/Install - Solid Surfacing Countertops
PD12-1150 Prepare/Submit - Entrance Floor Mats
PD12-1160 Review/Approve - Entrance Floor Mats
PD12-1170 Order/Fabricate - Entrance Floor Mats
PD12-1180 Prepare/Submit - Loose Furniture (FF&E)
PD12-1190 Review/Approve - Loose Furniture (FF&E)
PD12-1200 Order/Fabricate - Loose Furniture (FF&E)
Division 14 – Conveying Equipment
PD14-1000 Prepare/Submit - MRL Traction Passenger Elevator
PD14-1010 Review/Approve - MRL Traction Passenger Elevator
PD14-1020 Order/Fabricate - MRL Traction Passenger Elevator
Division 21 – Fire Suppression
PD21-1000 Prepare submittal Documents for Fire Suppression
PD21-1005 Prepare/Submit - Fire Suppression Systems
10d 26-Jun-26 10-Jul-26
40d 13-Jul-26 04-Sep-26
10d 26-Jun-26 10-Jul-26
10d 13-Jul-26 24-Jul-26
30d 27-Jul-26 04-Sep-26
20d 06-Apr-27 04-May-27
10d 26-Jun-26 10-Jul-26
10d 13-Jul-26 24-Jul-26
40d 27-Jul-26 21-Sep-26
10d 13-Jul-26 24-Jul-26
10d 27-Jul-26 07-Aug-26
30d 10-Aug-26 21-Sep-26
336d 08-Jan-26 11-May-27
10d 08-Jan-26 22-Jan-26
10d 23-Jan-26 05-Feb-26
40d 06-Feb-26 03-Apr-26
10d 08-Jan-26 22-Jan-26
10d 23-Jan-26 05-Feb-26
30d 06-Feb-26 20-Mar-26
20d 13-Apr-27 11-May-27
10d 23-Jan-26 05-Feb-26
10d 06-Feb-26 20-Feb-26
30d 23-Feb-26 03-Apr-26
20d 06-Apr-27 04-May-27
10d 23-Jan-26 05-Feb-26
10d 06-Feb-26 20-Feb-26
30d 23-Feb-26 03-Apr-26
20d 06-Apr-27 04-May-27
10d 06-Feb-26 20-Feb-26
10d 23-Feb-26 06-Mar-26
40d 09-Mar-26 04-May-26
10d 06-Feb-26 20-Feb-26
10d 23-Feb-26 06-Mar-26
40d 09-Mar-26 04-May-26
60d 24-Nov-25 20-Feb-26
10d 24-Nov-25 08-Dec-25
10d 09-Dec-25 22-Dec-25
40d 23-Dec-25 20-Feb-26
120d 31-Jul-25 23-Jan-26
60d 31-Jul-25 24-Oct-25
10d 27-Oct-25 07-Nov-25
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Review/Approve - Gymnasium EquipmentReview/Approve - Gymnasium EquipmentReview/Approve - Gymnasium EquipmentReview/Approve - Gymnasium EquipmentReview/Approve - Gymnasium Equipment
Order/Fabricate - Gymnasium EquipmentOrder/Fabricate - Gymnasium EquipmentOrder/Fabricate - Gymnasium EquipmentOrder/Fabricate - Gymnasium EquipmentOrder/Fabricate - Gymnasium Equipment
Prepare/Submit - Gymnasium Dividers SubmittalsPrepare/Submit - Gymnasium Dividers SubmittalsPrepare/Submit - Gymnasium Dividers SubmittalsPrepare/Submit - Gymnasium Dividers SubmittalsPrepare/Submit - Gymnasium Dividers Submittals
Review/Approve - Gymnasium Dividers SubmittalsReview/Approve - Gymnasium Dividers SubmittalsReview/Approve - Gymnasium Dividers SubmittalsReview/Approve - Gymnasium Dividers SubmittalsReview/Approve - Gymnasium Dividers Submittals
Order/Fab - Gymnasium DividersOrder/Fab - Gymnasium DividersOrder/Fab - Gymnasium DividersOrder/Fab - Gymnasium DividersOrder/Fab - Gymnasium Dividers
Deliver/Install - Gymnasium DividersDeliver/Install - Gymnasium DividersDeliver/Install - Gymnasium DividersDeliver/Install - Gymnasium DividersDeliver/Install - Gymnasium Dividers
Prepare/Submit - Theater EquipmentPrepare/Submit - Theater EquipmentPrepare/Submit - Theater EquipmentPrepare/Submit - Theater EquipmentPrepare/Submit - Theater Equipment
Review/Approve - Theater EquipmentReview/Approve - Theater EquipmentReview/Approve - Theater EquipmentReview/Approve - Theater EquipmentReview/Approve - Theater Equipment
Order/Fabricate - Theater EquipmentOrder/Fabricate - Theater EquipmentOrder/Fabricate - Theater EquipmentOrder/Fabricate - Theater EquipmentOrder/Fabricate - Theater Equipment
Prepare/Submit - Play Equipment and SurfacingPrepare/Submit - Play Equipment and SurfacingPrepare/Submit - Play Equipment and SurfacingPrepare/Submit - Play Equipment and SurfacingPrepare/Submit - Play Equipment and Surfacing
Review/Approve - Play Equipment and SurfacingReview/Approve - Play Equipment and SurfacingReview/Approve - Play Equipment and SurfacingReview/Approve - Play Equipment and SurfacingReview/Approve - Play Equipment and Surfacing
Order/Fabricate - Play Equipment and SurfacingOrder/Fabricate - Play Equipment and SurfacingOrder/Fabricate - Play Equipment and SurfacingOrder/Fabricate - Play Equipment and SurfacingOrder/Fabricate - Play Equipment and Surfacing
Division 12 – FurnishingsDivision 12 – FurnishingsDivision 12 – FurnishingsDivision 12 – FurnishingsDivision 12 – Furnishings
Prepare/Submit - Window TreatmentPrepare/Submit - Window TreatmentPrepare/Submit - Window TreatmentPrepare/Submit - Window TreatmentPrepare/Submit - Window Treatment
Review/Approve - Window TreatmentReview/Approve - Window TreatmentReview/Approve - Window TreatmentReview/Approve - Window TreatmentReview/Approve - Window Treatment
Order/Fabricate - Window TreatmentOrder/Fabricate - Window TreatmentOrder/Fabricate - Window TreatmentOrder/Fabricate - Window TreatmentOrder/Fabricate - Window Treatment
Prepare/Submit - Roller Window Shades SubmittalsPrepare/Submit - Roller Window Shades SubmittalsPrepare/Submit - Roller Window Shades SubmittalsPrepare/Submit - Roller Window Shades SubmittalsPrepare/Submit - Roller Window Shades Submittals
Review/Approve - Roller Window Shades SubmittalsReview/Approve - Roller Window Shades SubmittalsReview/Approve - Roller Window Shades SubmittalsReview/Approve - Roller Window Shades SubmittalsReview/Approve - Roller Window Shades Submittals
Order/Fab - Roller Window ShadesOrder/Fab - Roller Window ShadesOrder/Fab - Roller Window ShadesOrder/Fab - Roller Window ShadesOrder/Fab - Roller Window Shades
Deliver/Install - Roller Window ShadesDeliver/Install - Roller Window ShadesDeliver/Install - Roller Window ShadesDeliver/Install - Roller Window ShadesDeliver/Install - Roller Window Shades
Prepare/Submit - Plastic-Laminate-Clad Casework SubmittalsPrepare/Submit - Plastic-Laminate-Clad Casework SubmittalsPrepare/Submit - Plastic-Laminate-Clad Casework SubmittalsPrepare/Submit - Plastic-Laminate-Clad Casework SubmittalsPrepare/Submit - Plastic-Laminate-Clad Casework Submittals
Review/Approve - Plastic-Laminate-Clad Casework SubmittalsReview/Approve - Plastic-Laminate-Clad Casework SubmittalsReview/Approve - Plastic-Laminate-Clad Casework SubmittalsReview/Approve - Plastic-Laminate-Clad Casework SubmittalsReview/Approve - Plastic-Laminate-Clad Casework Submittals
Order/Fab - Plastic-Laminate-Clad CaseworkOrder/Fab - Plastic-Laminate-Clad CaseworkOrder/Fab - Plastic-Laminate-Clad CaseworkOrder/Fab - Plastic-Laminate-Clad CaseworkOrder/Fab - Plastic-Laminate-Clad Casework
Deliver/Install - Plastic-Laminate-Clad CasewDeliver/Install - Plastic-Laminate-Clad CasewDeliver/Install - Plastic-Laminate-Clad CasewDeliver/Install - Plastic-Laminate-Clad CasewDeliver/Install - Plastic-Laminate-Clad Casew
Prepare/Submit - Solid Surfacing Countertops SubmittalsPrepare/Submit - Solid Surfacing Countertops SubmittalsPrepare/Submit - Solid Surfacing Countertops SubmittalsPrepare/Submit - Solid Surfacing Countertops SubmittalsPrepare/Submit - Solid Surfacing Countertops Submittals
Review/Approve - Solid Surfacing Countertops SubmittalsReview/Approve - Solid Surfacing Countertops SubmittalsReview/Approve - Solid Surfacing Countertops SubmittalsReview/Approve - Solid Surfacing Countertops SubmittalsReview/Approve - Solid Surfacing Countertops Submittals
Order/Fab - Solid Surfacing CountertopsOrder/Fab - Solid Surfacing CountertopsOrder/Fab - Solid Surfacing CountertopsOrder/Fab - Solid Surfacing CountertopsOrder/Fab - Solid Surfacing Countertops
Deliver/Install - Solid Surfacing CountertopsDeliver/Install - Solid Surfacing CountertopsDeliver/Install - Solid Surfacing CountertopsDeliver/Install - Solid Surfacing CountertopsDeliver/Install - Solid Surfacing Countertops
Prepare/Submit - Entrance Floor MatsPrepare/Submit - Entrance Floor MatsPrepare/Submit - Entrance Floor MatsPrepare/Submit - Entrance Floor MatsPrepare/Submit - Entrance Floor Mats
Review/Approve - Entrance Floor MatsReview/Approve - Entrance Floor MatsReview/Approve - Entrance Floor MatsReview/Approve - Entrance Floor MatsReview/Approve - Entrance Floor Mats
Order/Fabricate - Entrance Floor MatsOrder/Fabricate - Entrance Floor MatsOrder/Fabricate - Entrance Floor MatsOrder/Fabricate - Entrance Floor MatsOrder/Fabricate - Entrance Floor Mats
Prepare/Submit - Loose Furniture (FF&E)Prepare/Submit - Loose Furniture (FF&E)Prepare/Submit - Loose Furniture (FF&E)Prepare/Submit - Loose Furniture (FF&E)Prepare/Submit - Loose Furniture (FF&E)
Review/Approve - Loose Furniture (FF&E)Review/Approve - Loose Furniture (FF&E)Review/Approve - Loose Furniture (FF&E)Review/Approve - Loose Furniture (FF&E)Review/Approve - Loose Furniture (FF&E)
Order/Fabricate - Loose Furniture (FF&E)Order/Fabricate - Loose Furniture (FF&E)Order/Fabricate - Loose Furniture (FF&E)Order/Fabricate - Loose Furniture (FF&E)Order/Fabricate - Loose Furniture (FF&E)
Division 14 – Conveying EquipmentDivision 14 – Conveying EquipmentDivision 14 – Conveying EquipmentDivision 14 – Conveying EquipmentDivision 14 – Conveying Equipment
Prepare/Submit - MRL Traction Passenger ElevatorPrepare/Submit - MRL Traction Passenger ElevatorPrepare/Submit - MRL Traction Passenger ElevatorPrepare/Submit - MRL Traction Passenger ElevatorPrepare/Submit - MRL Traction Passenger Elevator
Review/Approve - MRL Traction Passenger ElevatorReview/Approve - MRL Traction Passenger ElevatorReview/Approve - MRL Traction Passenger ElevatorReview/Approve - MRL Traction Passenger ElevatorReview/Approve - MRL Traction Passenger Elevator
Order/Fabricate - MRL Traction Passenger ElevatorOrder/Fabricate - MRL Traction Passenger ElevatorOrder/Fabricate - MRL Traction Passenger ElevatorOrder/Fabricate - MRL Traction Passenger ElevatorOrder/Fabricate - MRL Traction Passenger Elevator
Division 21 – Fire SuppressionDivision 21 – Fire SuppressionDivision 21 – Fire SuppressionDivision 21 – Fire SuppressionDivision 21 – Fire Suppression
Prepare submittal Documents for Fire SuppressionPrepare submittal Documents for Fire SuppressionPrepare submittal Documents for Fire SuppressionPrepare submittal Documents for Fire SuppressionPrepare submittal Documents for Fire Suppression
Prepare/Submit - Fire Suppression SystemsPrepare/Submit - Fire Suppression SystemsPrepare/Submit - Fire Suppression SystemsPrepare/Submit - Fire Suppression SystemsPrepare/Submit - Fire Suppression Systems
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 12 of 24
PD21-1010 Review/Approve - Fire Suppression Systems
PD21-1020 Order/Fabricate - Fire Suppression Systems
Division 22 - Plumbing
PD22-1000 Prepare/Submit - Inline Domestic Water Pumps
PD22-1010 Review/Approve - Inline Domestic Water Pumps
PD22-1020 Order/Fabricate - Inline Domestic Water Pumps
PD22-1030 Prepare/Submit - Indoor Potable-Water Storage Tanks
PD22-1040 Review/Approve - Indoor Potable-Water Storage Tanks
PD22-1050 Order/Fabricate - Indoor Potable-Water Storage Tanks
PD22-1060 Prepare/Submit - Sump Pumps
PD22-1070 Review/Approve - Sump Pumps
PD22-1080 Order/Fabricate - Sump Pumps
PD22-1090 Prepare/Submit - Water Heaters
PD22-1100 Review/Approve - Water Heaters
PD22-1110 Order/Fabricate - Water Heaters
PD22-1120 Prepare/Submit - Plumbing Fixtures
PD22-1130 Review/Approve - Plumbing Fixtures
PD22-1140 Order/Fabricate - Plumbing Fixtures
Division 23 - HVAC
PD23-1000 Prepare/Submit - Valves and Strainers
PD23-1010 Review/Approve - Valves and Strainers
PD23-1020 Order/Fabricate - Valves and Strainers
PD23-1030 Prepare/Submit - Hydraulic Separator
PD23-1040 Review/Approve - Hydraulic Separator
PD23-1050 Order/Fabricate - Hydraulic Separator
PD23-1060 Prepare/Submit - BAS Server / Software
PD23-1070 Review/Approve - BAS Server / Software
PD23-1080 Order/Fabricate - BAS Server / Software
PD23-1090 Prepare/Submit - Control Panel (DDC/BAS)
PD23-1100 Review/Approve - Control Panel (DDC/BAS)
PD23-1110 Order/Fabricate - Control Panel (DDC/BAS)
PD23-1120 Prepare/Submit - Thermostats / Zone Sensors
PD23-1130 Review/Approve - Thermostats / Zone Sensors
PD23-1140 Order/Fabricate - Thermostats / Zone Sensors
PD23-1150 Prepare/Submit - HVAC Pumps (CWP, GWP)
PD23-1160 Review/Approve - HVAC Pumps (CWP, GWP)
PD23-1170 Order/Fabricate - HVAC Pumps (CWP, GWP)
PD23-1180 Prepare/Submit - Air Separator
PD23-1190 Review/Approve - Air Separator
PD23-1200 Order/Fabricate - Air Separator
PD23-1210 Prepare/Submit - Expansion Tanks
10d 10-Nov-25 24-Nov-25
40d 25-Nov-25 23-Jan-26
80d 04-Dec-25 31-Mar-26
10d 04-Dec-25 17-Dec-25
10d 18-Dec-25 02-Jan-26
40d 05-Jan-26 03-Mar-26
10d 04-Dec-25 17-Dec-25
10d 18-Dec-25 02-Jan-26
40d 05-Jan-26 03-Mar-26
10d 18-Dec-25 02-Jan-26
10d 05-Jan-26 16-Jan-26
40d 20-Jan-26 17-Mar-26
10d 18-Dec-25 02-Jan-26
10d 05-Jan-26 16-Jan-26
40d 20-Jan-26 17-Mar-26
10d 05-Jan-26 16-Jan-26
10d 20-Jan-26 02-Feb-26
40d 03-Feb-26 31-Mar-26
411d 31-Jul-25 23-Mar-27
10d 31-Jul-25 13-Aug-25
10d 14-Aug-25 27-Aug-25
40d 28-Aug-25 24-Oct-25
10d 31-Jul-25 13-Aug-25
10d 14-Aug-25 27-Aug-25
40d 28-Aug-25 24-Oct-25
10d 31-Jul-25 13-Aug-25
10d 14-Aug-25 27-Aug-25
40d 28-Aug-25 24-Oct-25
10d 31-Jul-25 13-Aug-25
10d 14-Aug-25 27-Aug-25
40d 28-Aug-25 24-Oct-25
10d 31-Jul-25 13-Aug-25
10d 14-Aug-25 27-Aug-25
40d 28-Aug-25 24-Oct-25
10d 31-Jul-25 13-Aug-25
10d 14-Aug-25 27-Aug-25
40d 28-Aug-25 24-Oct-25
10d 14-Aug-25 27-Aug-25
10d 28-Aug-25 11-Sep-25
40d 12-Sep-25 07-Nov-25
10d 14-Aug-25 27-Aug-25
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Review/Approve - Fire Suppression SystemsReview/Approve - Fire Suppression SystemsReview/Approve - Fire Suppression SystemsReview/Approve - Fire Suppression SystemsReview/Approve - Fire Suppression Systems
Order/Fabricate - Fire Suppression SystemsOrder/Fabricate - Fire Suppression SystemsOrder/Fabricate - Fire Suppression SystemsOrder/Fabricate - Fire Suppression SystemsOrder/Fabricate - Fire Suppression Systems
Division 22 - PlumbingDivision 22 - PlumbingDivision 22 - PlumbingDivision 22 - PlumbingDivision 22 - Plumbing
Prepare/Submit - Inline Domestic Water PumpsPrepare/Submit - Inline Domestic Water PumpsPrepare/Submit - Inline Domestic Water PumpsPrepare/Submit - Inline Domestic Water PumpsPrepare/Submit - Inline Domestic Water Pumps
Review/Approve - Inline Domestic Water PumpsReview/Approve - Inline Domestic Water PumpsReview/Approve - Inline Domestic Water PumpsReview/Approve - Inline Domestic Water PumpsReview/Approve - Inline Domestic Water Pumps
Order/Fabricate - Inline Domestic Water PumpsOrder/Fabricate - Inline Domestic Water PumpsOrder/Fabricate - Inline Domestic Water PumpsOrder/Fabricate - Inline Domestic Water PumpsOrder/Fabricate - Inline Domestic Water Pumps
Prepare/Submit - Indoor Potable-Water Storage TanksPrepare/Submit - Indoor Potable-Water Storage TanksPrepare/Submit - Indoor Potable-Water Storage TanksPrepare/Submit - Indoor Potable-Water Storage TanksPrepare/Submit - Indoor Potable-Water Storage Tanks
Review/Approve - Indoor Potable-Water Storage TanksReview/Approve - Indoor Potable-Water Storage TanksReview/Approve - Indoor Potable-Water Storage TanksReview/Approve - Indoor Potable-Water Storage TanksReview/Approve - Indoor Potable-Water Storage Tanks
Order/Fabricate - Indoor Potable-Water Storage TanksOrder/Fabricate - Indoor Potable-Water Storage TanksOrder/Fabricate - Indoor Potable-Water Storage TanksOrder/Fabricate - Indoor Potable-Water Storage TanksOrder/Fabricate - Indoor Potable-Water Storage Tanks
Prepare/Submit - Sump PumpsPrepare/Submit - Sump PumpsPrepare/Submit - Sump PumpsPrepare/Submit - Sump PumpsPrepare/Submit - Sump Pumps
Review/Approve - Sump PumpsReview/Approve - Sump PumpsReview/Approve - Sump PumpsReview/Approve - Sump PumpsReview/Approve - Sump Pumps
Order/Fabricate - Sump PumpsOrder/Fabricate - Sump PumpsOrder/Fabricate - Sump PumpsOrder/Fabricate - Sump PumpsOrder/Fabricate - Sump Pumps
Prepare/Submit - Water HeatersPrepare/Submit - Water HeatersPrepare/Submit - Water HeatersPrepare/Submit - Water HeatersPrepare/Submit - Water Heaters
Review/Approve - Water HeatersReview/Approve - Water HeatersReview/Approve - Water HeatersReview/Approve - Water HeatersReview/Approve - Water Heaters
Order/Fabricate - Water HeatersOrder/Fabricate - Water HeatersOrder/Fabricate - Water HeatersOrder/Fabricate - Water HeatersOrder/Fabricate - Water Heaters
Prepare/Submit - Plumbing FixturesPrepare/Submit - Plumbing FixturesPrepare/Submit - Plumbing FixturesPrepare/Submit - Plumbing FixturesPrepare/Submit - Plumbing Fixtures
Review/Approve - Plumbing FixturesReview/Approve - Plumbing FixturesReview/Approve - Plumbing FixturesReview/Approve - Plumbing FixturesReview/Approve - Plumbing Fixtures
Order/Fabricate - Plumbing FixturesOrder/Fabricate - Plumbing FixturesOrder/Fabricate - Plumbing FixturesOrder/Fabricate - Plumbing FixturesOrder/Fabricate - Plumbing Fixtures
Division 23 - HVACDivision 23 - HVACDivision 23 - HVACDivision 23 - HVACDivision 23 - HVAC
Prepare/Submit - Valves and StrainersPrepare/Submit - Valves and StrainersPrepare/Submit - Valves and StrainersPrepare/Submit - Valves and StrainersPrepare/Submit - Valves and Strainers
Review/Approve - Valves and StrainersReview/Approve - Valves and StrainersReview/Approve - Valves and StrainersReview/Approve - Valves and StrainersReview/Approve - Valves and Strainers
Order/Fabricate - Valves and StrainersOrder/Fabricate - Valves and StrainersOrder/Fabricate - Valves and StrainersOrder/Fabricate - Valves and StrainersOrder/Fabricate - Valves and Strainers
Prepare/Submit - Hydraulic SeparatorPrepare/Submit - Hydraulic SeparatorPrepare/Submit - Hydraulic SeparatorPrepare/Submit - Hydraulic SeparatorPrepare/Submit - Hydraulic Separator
Review/Approve - Hydraulic SeparatorReview/Approve - Hydraulic SeparatorReview/Approve - Hydraulic SeparatorReview/Approve - Hydraulic SeparatorReview/Approve - Hydraulic Separator
Order/Fabricate - Hydraulic SeparatorOrder/Fabricate - Hydraulic SeparatorOrder/Fabricate - Hydraulic SeparatorOrder/Fabricate - Hydraulic SeparatorOrder/Fabricate - Hydraulic Separator
Prepare/Submit - BAS Server / SoftwarePrepare/Submit - BAS Server / SoftwarePrepare/Submit - BAS Server / SoftwarePrepare/Submit - BAS Server / SoftwarePrepare/Submit - BAS Server / Software
Review/Approve - BAS Server / SoftwareReview/Approve - BAS Server / SoftwareReview/Approve - BAS Server / SoftwareReview/Approve - BAS Server / SoftwareReview/Approve - BAS Server / Software
Order/Fabricate - BAS Server / SoftwareOrder/Fabricate - BAS Server / SoftwareOrder/Fabricate - BAS Server / SoftwareOrder/Fabricate - BAS Server / SoftwareOrder/Fabricate - BAS Server / Software
Prepare/Submit - Control Panel (DDC/BAS)Prepare/Submit - Control Panel (DDC/BAS)Prepare/Submit - Control Panel (DDC/BAS)Prepare/Submit - Control Panel (DDC/BAS)Prepare/Submit - Control Panel (DDC/BAS)
Review/Approve - Control Panel (DDC/BAS)Review/Approve - Control Panel (DDC/BAS)Review/Approve - Control Panel (DDC/BAS)Review/Approve - Control Panel (DDC/BAS)Review/Approve - Control Panel (DDC/BAS)
Order/Fabricate - Control Panel (DDC/BAS)Order/Fabricate - Control Panel (DDC/BAS)Order/Fabricate - Control Panel (DDC/BAS)Order/Fabricate - Control Panel (DDC/BAS)Order/Fabricate - Control Panel (DDC/BAS)
Prepare/Submit - Thermostats / Zone SensorsPrepare/Submit - Thermostats / Zone SensorsPrepare/Submit - Thermostats / Zone SensorsPrepare/Submit - Thermostats / Zone SensorsPrepare/Submit - Thermostats / Zone Sensors
Review/Approve - Thermostats / Zone SensorsReview/Approve - Thermostats / Zone SensorsReview/Approve - Thermostats / Zone SensorsReview/Approve - Thermostats / Zone SensorsReview/Approve - Thermostats / Zone Sensors
Order/Fabricate - Thermostats / Zone SensorsOrder/Fabricate - Thermostats / Zone SensorsOrder/Fabricate - Thermostats / Zone SensorsOrder/Fabricate - Thermostats / Zone SensorsOrder/Fabricate - Thermostats / Zone Sensors
Prepare/Submit - HVAC Pumps (CWP, GWP)Prepare/Submit - HVAC Pumps (CWP, GWP)Prepare/Submit - HVAC Pumps (CWP, GWP)Prepare/Submit - HVAC Pumps (CWP, GWP)Prepare/Submit - HVAC Pumps (CWP, GWP)
Review/Approve - HVAC Pumps (CWP, GWP)Review/Approve - HVAC Pumps (CWP, GWP)Review/Approve - HVAC Pumps (CWP, GWP)Review/Approve - HVAC Pumps (CWP, GWP)Review/Approve - HVAC Pumps (CWP, GWP)
Order/Fabricate - HVAC Pumps (CWP, GWP)Order/Fabricate - HVAC Pumps (CWP, GWP)Order/Fabricate - HVAC Pumps (CWP, GWP)Order/Fabricate - HVAC Pumps (CWP, GWP)Order/Fabricate - HVAC Pumps (CWP, GWP)
Prepare/Submit - Air SeparatorPrepare/Submit - Air SeparatorPrepare/Submit - Air SeparatorPrepare/Submit - Air SeparatorPrepare/Submit - Air Separator
Review/Approve - Air SeparatorReview/Approve - Air SeparatorReview/Approve - Air SeparatorReview/Approve - Air SeparatorReview/Approve - Air Separator
Order/Fabricate - Air SeparatorOrder/Fabricate - Air SeparatorOrder/Fabricate - Air SeparatorOrder/Fabricate - Air SeparatorOrder/Fabricate - Air Separator
Prepare/Submit - Expansion TanksPrepare/Submit - Expansion TanksPrepare/Submit - Expansion TanksPrepare/Submit - Expansion TanksPrepare/Submit - Expansion Tanks
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 13 of 24
PD23-1220 Review/Approve - Expansion Tanks
PD23-1230 Order/Fabricate - Expansion Tanks
PD23-1240 Prepare/Submit - Exhaust / Supply / Return Fans
PD23-1250 Review/Approve - Exhaust / Supply / Return Fans
PD23-1260 Order/Fabricate - Exhaust / Supply / Return Fans
PD23-1270 Prepare/Submit - Vibration Isolators
PD23-1280 Review/Approve - Vibration Isolators
PD23-1290 Order/Fabricate - Vibration Isolators
PD23-1300 Prepare/Submit - Louvers
PD23-1310 Review/Approve - Louvers
PD23-1320 Order/Fabricate - Louvers
PD23-1330 Prepare/Submit - VAV Terminals
PD23-1340 Review/Approve - VAV Terminals
PD23-1350 Order/Fabricate - VAV Terminals
PD23-1360 Prepare/Submit - Air-Cooled Refrigerant Condensers Sub…
PD23-1370 Review/Approve - Air-Cooled Refrigerant Condensers Sub…
PD23-1380 Order/Fab - Air-Cooled Refrigerant Condensers
PD23-1390 Deliver/Install - Air-Cooled Refrigerant Condensers
PD23-1400 Prepare/Submit - Cooling Towers Submittals
PD23-1410 Review/Approve - Cooling Towers Submittals
PD23-1420 Order/Fab - Cooling Towers
PD23-1430 Deliver/Install - Cooling Towers
PD23-1440 Prepare/Submit - Energy Recovery Units Submittals
PD23-1450 Review/Approve - Energy Recovery Units Submittals
PD23-1460 Order/Fab - Energy Recovery Units
PD23-1470 Deliver/Install - Energy Recovery Units
PD23-1480 Prepare/Submit - DOAS
PD23-1490 Review/Approve - DOAS
PD23-1500 Order/Fabricate - DOAS
PD23-1510 Prepare/Submit - Energy Recovery Ventilator
PD23-1520 Review/Approve - Energy Recovery Ventilator
PD23-1530 Order/Fabricate - Energy Recovery Ventilator
PD23-1540 Prepare/Submit - AHU (Gym)
PD23-1550 Review/Approve - AHU (Gym)
PD23-1560 Order/Fabricate - AHU (Gym)
PD23-1570 Prepare/Submit - Split System Units
PD23-1580 Review/Approve - Split System Units
PD23-1590 Order/Fabricate - Split System Units
PD23-1600 Prepare/Submit - Water-Source Heat Pumps Submittals
PD23-1610 Review/Approve - Water-Source Heat Pumps Submittals
PD23-1620 Order/Fab - Water-Source Heat Pumps
10d 28-Aug-25 11-Sep-25
40d 12-Sep-25 07-Nov-25
10d 14-Aug-25 27-Aug-25
10d 28-Aug-25 11-Sep-25
40d 12-Sep-25 07-Nov-25
10d 14-Aug-25 27-Aug-25
10d 28-Aug-25 11-Sep-25
40d 12-Sep-25 07-Nov-25
10d 14-Aug-25 27-Aug-25
10d 28-Aug-25 11-Sep-25
40d 12-Sep-25 07-Nov-25
10d 14-Aug-25 27-Aug-25
10d 28-Aug-25 11-Sep-25
40d 12-Sep-25 07-Nov-25
10d 28-Aug-25 11-Sep-25
10d 12-Sep-25 25-Sep-25
30d 26-Sep-25 07-Nov-25
20d 16-Feb-27 15-Mar-27
10d 28-Aug-25 11-Sep-25
10d 12-Sep-25 25-Sep-25
30d 26-Sep-25 07-Nov-25
20d 16-Feb-27 15-Mar-27
10d 28-Aug-25 11-Sep-25
10d 12-Sep-25 25-Sep-25
30d 26-Sep-25 07-Nov-25
20d 15-Jan-27 12-Feb-27
10d 28-Aug-25 11-Sep-25
10d 12-Sep-25 25-Sep-25
40d 26-Sep-25 24-Nov-25
10d 28-Aug-25 11-Sep-25
10d 12-Sep-25 25-Sep-25
40d 26-Sep-25 24-Nov-25
10d 28-Aug-25 11-Sep-25
10d 12-Sep-25 25-Sep-25
40d 26-Sep-25 24-Nov-25
10d 12-Sep-25 25-Sep-25
10d 26-Sep-25 09-Oct-25
40d 10-Oct-25 09-Dec-25
10d 12-Sep-25 25-Sep-25
10d 26-Sep-25 09-Oct-25
30d 10-Oct-25 24-Nov-25
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Review/Approve - Expansion TanksReview/Approve - Expansion TanksReview/Approve - Expansion TanksReview/Approve - Expansion TanksReview/Approve - Expansion Tanks
Order/Fabricate - Expansion TanksOrder/Fabricate - Expansion TanksOrder/Fabricate - Expansion TanksOrder/Fabricate - Expansion TanksOrder/Fabricate - Expansion Tanks
Prepare/Submit - Exhaust / Supply / Return FansPrepare/Submit - Exhaust / Supply / Return FansPrepare/Submit - Exhaust / Supply / Return FansPrepare/Submit - Exhaust / Supply / Return FansPrepare/Submit - Exhaust / Supply / Return Fans
Review/Approve - Exhaust / Supply / Return FansReview/Approve - Exhaust / Supply / Return FansReview/Approve - Exhaust / Supply / Return FansReview/Approve - Exhaust / Supply / Return FansReview/Approve - Exhaust / Supply / Return Fans
Order/Fabricate - Exhaust / Supply / Return FansOrder/Fabricate - Exhaust / Supply / Return FansOrder/Fabricate - Exhaust / Supply / Return FansOrder/Fabricate - Exhaust / Supply / Return FansOrder/Fabricate - Exhaust / Supply / Return Fans
Prepare/Submit - Vibration IsolatorsPrepare/Submit - Vibration IsolatorsPrepare/Submit - Vibration IsolatorsPrepare/Submit - Vibration IsolatorsPrepare/Submit - Vibration Isolators
Review/Approve - Vibration IsolatorsReview/Approve - Vibration IsolatorsReview/Approve - Vibration IsolatorsReview/Approve - Vibration IsolatorsReview/Approve - Vibration Isolators
Order/Fabricate - Vibration IsolatorsOrder/Fabricate - Vibration IsolatorsOrder/Fabricate - Vibration IsolatorsOrder/Fabricate - Vibration IsolatorsOrder/Fabricate - Vibration Isolators
Prepare/Submit - LouversPrepare/Submit - LouversPrepare/Submit - LouversPrepare/Submit - LouversPrepare/Submit - Louvers
Review/Approve - LouversReview/Approve - LouversReview/Approve - LouversReview/Approve - LouversReview/Approve - Louvers
Order/Fabricate - LouversOrder/Fabricate - LouversOrder/Fabricate - LouversOrder/Fabricate - LouversOrder/Fabricate - Louvers
Prepare/Submit - VAV TerminalsPrepare/Submit - VAV TerminalsPrepare/Submit - VAV TerminalsPrepare/Submit - VAV TerminalsPrepare/Submit - VAV Terminals
Review/Approve - VAV TerminalsReview/Approve - VAV TerminalsReview/Approve - VAV TerminalsReview/Approve - VAV TerminalsReview/Approve - VAV Terminals
Order/Fabricate - VAV TerminalsOrder/Fabricate - VAV TerminalsOrder/Fabricate - VAV TerminalsOrder/Fabricate - VAV TerminalsOrder/Fabricate - VAV Terminals
Prepare/Submit - Air-Cooled Refrigerant Condensers SubmittalsPrepare/Submit - Air-Cooled Refrigerant Condensers SubmittalsPrepare/Submit - Air-Cooled Refrigerant Condensers SubmittalsPrepare/Submit - Air-Cooled Refrigerant Condensers SubmittalsPrepare/Submit - Air-Cooled Refrigerant Condensers Submittals
Review/Approve - Air-Cooled Refrigerant Condensers SubmittalsReview/Approve - Air-Cooled Refrigerant Condensers SubmittalsReview/Approve - Air-Cooled Refrigerant Condensers SubmittalsReview/Approve - Air-Cooled Refrigerant Condensers SubmittalsReview/Approve - Air-Cooled Refrigerant Condensers Submittals
Order/Fab - Air-Cooled Refrigerant CondensersOrder/Fab - Air-Cooled Refrigerant CondensersOrder/Fab - Air-Cooled Refrigerant CondensersOrder/Fab - Air-Cooled Refrigerant CondensersOrder/Fab - Air-Cooled Refrigerant Condensers
Deliver/Install - Air-Cooled Refrigerant CondensDeliver/Install - Air-Cooled Refrigerant CondensDeliver/Install - Air-Cooled Refrigerant CondensDeliver/Install - Air-Cooled Refrigerant CondenseDeliver/Install - Air-Cooled Refrigerant Condens
Prepare/Submit - Cooling Towers SubmittalsPrepare/Submit - Cooling Towers SubmittalsPrepare/Submit - Cooling Towers SubmittalsPrepare/Submit - Cooling Towers SubmittalsPrepare/Submit - Cooling Towers Submittals
Review/Approve - Cooling Towers SubmittalsReview/Approve - Cooling Towers SubmittalsReview/Approve - Cooling Towers SubmittalsReview/Approve - Cooling Towers SubmittalsReview/Approve - Cooling Towers Submittals
Order/Fab - Cooling TowersOrder/Fab - Cooling TowersOrder/Fab - Cooling TowersOrder/Fab - Cooling TowersOrder/Fab - Cooling Towers
Deliver/Install - Cooling TowersDeliver/Install - Cooling TowersDeliver/Install - Cooling TowersDeliver/Install - Cooling TowersDeliver/Install - Cooling Towers
Prepare/Submit - Energy Recovery Units SubmittalsPrepare/Submit - Energy Recovery Units SubmittalsPrepare/Submit - Energy Recovery Units SubmittalsPrepare/Submit - Energy Recovery Units SubmittalsPrepare/Submit - Energy Recovery Units Submittals
Review/Approve - Energy Recovery Units SubmittalsReview/Approve - Energy Recovery Units SubmittalsReview/Approve - Energy Recovery Units SubmittalsReview/Approve - Energy Recovery Units SubmittalsReview/Approve - Energy Recovery Units Submittals
Order/Fab - Energy Recovery UnitsOrder/Fab - Energy Recovery UnitsOrder/Fab - Energy Recovery UnitsOrder/Fab - Energy Recovery UnitsOrder/Fab - Energy Recovery Units
Deliver/Install - Energy Recovery UnitsDeliver/Install - Energy Recovery UnitsDeliver/Install - Energy Recovery UnitsDeliver/Install - Energy Recovery UnitsDeliver/Install - Energy Recovery Units
Prepare/Submit - DOASPrepare/Submit - DOASPrepare/Submit - DOASPrepare/Submit - DOASPrepare/Submit - DOAS
Review/Approve - DOASReview/Approve - DOASReview/Approve - DOASReview/Approve - DOASReview/Approve - DOAS
Order/Fabricate - DOASOrder/Fabricate - DOASOrder/Fabricate - DOASOrder/Fabricate - DOASOrder/Fabricate - DOAS
Prepare/Submit - Energy Recovery VentilatorPrepare/Submit - Energy Recovery VentilatorPrepare/Submit - Energy Recovery VentilatorPrepare/Submit - Energy Recovery VentilatorPrepare/Submit - Energy Recovery Ventilator
Review/Approve - Energy Recovery VentilatorReview/Approve - Energy Recovery VentilatorReview/Approve - Energy Recovery VentilatorReview/Approve - Energy Recovery VentilatorReview/Approve - Energy Recovery Ventilator
Order/Fabricate - Energy Recovery VentilatorOrder/Fabricate - Energy Recovery VentilatorOrder/Fabricate - Energy Recovery VentilatorOrder/Fabricate - Energy Recovery VentilatorOrder/Fabricate - Energy Recovery Ventilator
Prepare/Submit - AHU (Gym)Prepare/Submit - AHU (Gym)Prepare/Submit - AHU (Gym)Prepare/Submit - AHU (Gym)Prepare/Submit - AHU (Gym)
Review/Approve - AHU (Gym)Review/Approve - AHU (Gym)Review/Approve - AHU (Gym)Review/Approve - AHU (Gym)Review/Approve - AHU (Gym)
Order/Fabricate - AHU (Gym)Order/Fabricate - AHU (Gym)Order/Fabricate - AHU (Gym)Order/Fabricate - AHU (Gym)Order/Fabricate - AHU (Gym)
Prepare/Submit - Split System UnitsPrepare/Submit - Split System UnitsPrepare/Submit - Split System UnitsPrepare/Submit - Split System UnitsPrepare/Submit - Split System Units
Review/Approve - Split System UnitsReview/Approve - Split System UnitsReview/Approve - Split System UnitsReview/Approve - Split System UnitsReview/Approve - Split System Units
Order/Fabricate - Split System UnitsOrder/Fabricate - Split System UnitsOrder/Fabricate - Split System UnitsOrder/Fabricate - Split System UnitsOrder/Fabricate - Split System Units
Prepare/Submit - Water-Source Heat Pumps SubmittalsPrepare/Submit - Water-Source Heat Pumps SubmittalsPrepare/Submit - Water-Source Heat Pumps SubmittalsPrepare/Submit - Water-Source Heat Pumps SubmittalsPrepare/Submit - Water-Source Heat Pumps Submittals
Review/Approve - Water-Source Heat Pumps SubmittalsReview/Approve - Water-Source Heat Pumps SubmittalsReview/Approve - Water-Source Heat Pumps SubmittalsReview/Approve - Water-Source Heat Pumps SubmittalsReview/Approve - Water-Source Heat Pumps Submittals
Order/Fab - Water-Source Heat PumpsOrder/Fab - Water-Source Heat PumpsOrder/Fab - Water-Source Heat PumpsOrder/Fab - Water-Source Heat PumpsOrder/Fab - Water-Source Heat Pumps
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 14 of 24
PD23-1630 Deliver/Install - Water-Source Heat Pumps
PD23-1640 Prepare/Submit - Water Source Heat Pumps
PD23-1650 Review/Approve - Water Source Heat Pumps
PD23-1660 Order/Fabricate - Water Source Heat Pumps
PD23-1670 Prepare/Submit - Geothermal Well
PD23-1680 Order/Fabricate - Geothermal Well
PD23-1690 Review/Approve - Geothermal Well
Division 26 - Electrical
PD26-1000 Prepare/Submit - Coordination Study
PD26-1010 Review/Approve - Coordination Study
PD26-1020 Order/Fab - Coordination Study
PD26-1030 Prepare/Submit - Transformers
PD26-1040 Review/Approve - Transformers
PD26-1050 Order/Fab - Transformers
PD26-1060 Prepare/Submit - Switchboards
PD26-1070 Review/Approve - Switchboards
PD26-1080 Order/Fab - Switchboards
PD26-1090 Prepare/Submit - Panelboards
PD26-1100 Review/Approve - Panelboards
PD26-1110 Order/Fab - Panelboards
PD26-1120 Prepare/Submit - Generator Sets Submittals
PD26-1130 Review/Approve - Generator Sets Submittals
PD26-1140 Order/Fab - Generator Sets
PD26-1150 Deliver/Install - Generator Sets
PD26-1160 Prepare/Submit - Transfer Switches Submittals
PD26-1170 Review/Approve - Transfer Switches Submittals
PD26-1180 Order/Fab - Transfer Switches
PD26-1190 Deliver/Install - Transfer Switches
Division 27 - Communications
PD27-1000 Prepare/Submit - AV/IT Equipment
PD27-1010 Review/Approve - AV/IT Equipment
PD27-1020 Order/Fab - AV/IT Equipment
PD27-1030 Prepare/Submit - PA/Clock and Bell System
PD27-1040 Review/Approve - PA/Clock and Bell System
PD27-1050 Order/Fab - PA/Clock and Bell System
Division 28 – Electronic Safety And Security
PD28-1000 Prepare/Submit - Access Control System Submittals
PD28-1010 Review/Approve - Access Control System Submittals
PD28-1020 Order/Fab - Access Control System
PD28-1030 Deliver/Install - Access Control System
PD28-1040 Prepare/Submit - Video Surveillance Submittals
20d 24-Feb-27 23-Mar-27
10d 12-Sep-25 25-Sep-25
10d 26-Sep-25 09-Oct-25
40d 10-Oct-25 09-Dec-25
10d 12-Sep-25 25-Sep-25
30d 10-Oct-25 24-Nov-25
10d 26-Sep-25 09-Oct-25
401d 31-Jul-25 09-Mar-27
10d 31-Jul-25 13-Aug-25
10d 14-Aug-25 27-Aug-25
80d 28-Aug-25 23-Dec-25
10d 31-Jul-25 13-Aug-25
10d 14-Aug-25 27-Aug-25
100d 28-Aug-25 23-Jan-26
10d 31-Jul-25 13-Aug-25
10d 14-Aug-25 27-Aug-25
380d 28-Aug-25 09-Mar-27
10d 14-Aug-25 27-Aug-25
10d 28-Aug-25 11-Sep-25
140d 12-Sep-25 06-Apr-26
10d 14-Aug-25 27-Aug-25
10d 28-Aug-25 11-Sep-25
30d 12-Sep-25 24-Oct-25
20d 15-Jan-27 12-Feb-27
10d 14-Aug-25 27-Aug-25
10d 28-Aug-25 11-Sep-25
30d 12-Sep-25 24-Oct-25
20d 15-Jan-27 12-Feb-27
70d 21-Oct-26 02-Feb-27
10d 21-Oct-26 03-Nov-26
10d 04-Nov-26 18-Nov-26
50d 19-Nov-26 02-Feb-27
10d 04-Nov-26 18-Nov-26
10d 19-Nov-26 03-Dec-26
35d 04-Dec-26 26-Jan-27
190d 29-May-26 03-Mar-27
10d 21-Oct-26 03-Nov-26
10d 04-Nov-26 18-Nov-26
30d 19-Nov-26 04-Jan-27
20d 03-Feb-27 03-Mar-27
10d 21-Oct-26 03-Nov-26
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Deliver/Install - Water-Source Heat PumpsDeliver/Install - Water-Source Heat PumpsDeliver/Install - Water-Source Heat PumpsDeliver/Install - Water-Source Heat PumpsDeliver/Install - Water-Source Heat Pumps
Prepare/Submit - Water Source Heat PumpsPrepare/Submit - Water Source Heat PumpsPrepare/Submit - Water Source Heat PumpsPrepare/Submit - Water Source Heat PumpsPrepare/Submit - Water Source Heat Pumps
Review/Approve - Water Source Heat PumpsReview/Approve - Water Source Heat PumpsReview/Approve - Water Source Heat PumpsReview/Approve - Water Source Heat PumpsReview/Approve - Water Source Heat Pumps
Order/Fabricate - Water Source Heat PumpsOrder/Fabricate - Water Source Heat PumpsOrder/Fabricate - Water Source Heat PumpsOrder/Fabricate - Water Source Heat PumpsOrder/Fabricate - Water Source Heat Pumps
Prepare/Submit - Geothermal WellPrepare/Submit - Geothermal WellPrepare/Submit - Geothermal WellPrepare/Submit - Geothermal WellPrepare/Submit - Geothermal Well
Order/Fabricate - Geothermal WellOrder/Fabricate - Geothermal WellOrder/Fabricate - Geothermal WellOrder/Fabricate - Geothermal WellOrder/Fabricate - Geothermal Well
Review/Approve - Geothermal WellReview/Approve - Geothermal WellReview/Approve - Geothermal WellReview/Approve - Geothermal WellReview/Approve - Geothermal Well
Division 26 - ElectricalDivision 26 - ElectricalDivision 26 - ElectricalDivision 26 - ElectricalDivision 26 - Electrical
Prepare/Submit - Coordination StudyPrepare/Submit - Coordination StudyPrepare/Submit - Coordination StudyPrepare/Submit - Coordination StudyPrepare/Submit - Coordination Study
Review/Approve - Coordination StudyReview/Approve - Coordination StudyReview/Approve - Coordination StudyReview/Approve - Coordination StudyReview/Approve - Coordination Study
Order/Fab - Coordination StudyOrder/Fab - Coordination StudyOrder/Fab - Coordination StudyOrder/Fab - Coordination StudyOrder/Fab - Coordination Study
Prepare/Submit - TransformersPrepare/Submit - TransformersPrepare/Submit - TransformersPrepare/Submit - TransformersPrepare/Submit - Transformers
Review/Approve - TransformersReview/Approve - TransformersReview/Approve - TransformersReview/Approve - TransformersReview/Approve - Transformers
Order/Fab - TransformersOrder/Fab - TransformersOrder/Fab - TransformersOrder/Fab - TransformersOrder/Fab - Transformers
Prepare/Submit - SwitchboardsPrepare/Submit - SwitchboardsPrepare/Submit - SwitchboardsPrepare/Submit - SwitchboardsPrepare/Submit - Switchboards
Review/Approve - SwitchboardsReview/Approve - SwitchboardsReview/Approve - SwitchboardsReview/Approve - SwitchboardsReview/Approve - Switchboards
Order/Fab - SwitchboardsOrder/Fab - SwitchboardsOrder/Fab - SwitchboardsOrder/Fab - SwitchboardsOrder/Fab - Switchboards
Prepare/Submit - PanelboardsPrepare/Submit - PanelboardsPrepare/Submit - PanelboardsPrepare/Submit - PanelboardsPrepare/Submit - Panelboards
Review/Approve - PanelboardsReview/Approve - PanelboardsReview/Approve - PanelboardsReview/Approve - PanelboardsReview/Approve - Panelboards
Order/Fab - PanelboardsOrder/Fab - PanelboardsOrder/Fab - PanelboardsOrder/Fab - PanelboardsOrder/Fab - Panelboards
Prepare/Submit - Generator Sets SubmittalsPrepare/Submit - Generator Sets SubmittalsPrepare/Submit - Generator Sets SubmittalsPrepare/Submit - Generator Sets SubmittalsPrepare/Submit - Generator Sets Submittals
Review/Approve - Generator Sets SubmittalsReview/Approve - Generator Sets SubmittalsReview/Approve - Generator Sets SubmittalsReview/Approve - Generator Sets SubmittalsReview/Approve - Generator Sets Submittals
Order/Fab - Generator SetsOrder/Fab - Generator SetsOrder/Fab - Generator SetsOrder/Fab - Generator SetsOrder/Fab - Generator Sets
Deliver/Install - Generator SetsDeliver/Install - Generator SetsDeliver/Install - Generator SetsDeliver/Install - Generator SetsDeliver/Install - Generator Sets
Prepare/Submit - Transfer Switches SubmittalsPrepare/Submit - Transfer Switches SubmittalsPrepare/Submit - Transfer Switches SubmittalsPrepare/Submit - Transfer Switches SubmittalsPrepare/Submit - Transfer Switches Submittals
Review/Approve - Transfer Switches SubmittalsReview/Approve - Transfer Switches SubmittalsReview/Approve - Transfer Switches SubmittalsReview/Approve - Transfer Switches SubmittalsReview/Approve - Transfer Switches Submittals
Order/Fab - Transfer SwitchesOrder/Fab - Transfer SwitchesOrder/Fab - Transfer SwitchesOrder/Fab - Transfer SwitchesOrder/Fab - Transfer Switches
Deliver/Install - Transfer SwitchesDeliver/Install - Transfer SwitchesDeliver/Install - Transfer SwitchesDeliver/Install - Transfer SwitchesDeliver/Install - Transfer Switches
Division 27 - CommunicationsDivision 27 - CommunicationsDivision 27 - CommunicationsDivision 27 - CommunicationsDivision 27 - Communications
Prepare/Submit - AV/IT EquipmentPrepare/Submit - AV/IT EquipmentPrepare/Submit - AV/IT EquipmentPrepare/Submit - AV/IT EquipmentPrepare/Submit - AV/IT Equipment
Review/Approve - AV/IT EquipmentReview/Approve - AV/IT EquipmentReview/Approve - AV/IT EquipmentReview/Approve - AV/IT EquipmentReview/Approve - AV/IT Equipment
Order/Fab - AV/IT EquipmentOrder/Fab - AV/IT EquipmentOrder/Fab - AV/IT EquipmentOrder/Fab - AV/IT EquipmentOrder/Fab - AV/IT Equipment
Prepare/Submit - PA/Clock and Bell SystemPrepare/Submit - PA/Clock and Bell SystemPrepare/Submit - PA/Clock and Bell SystemPrepare/Submit - PA/Clock and Bell SystemPrepare/Submit - PA/Clock and Bell System
Review/Approve - PA/Clock and Bell SystemReview/Approve - PA/Clock and Bell SystemReview/Approve - PA/Clock and Bell SystemReview/Approve - PA/Clock and Bell SystemReview/Approve - PA/Clock and Bell System
Order/Fab - PA/Clock and Bell SystemOrder/Fab - PA/Clock and Bell SystemOrder/Fab - PA/Clock and Bell SystemOrder/Fab - PA/Clock and Bell SystemOrder/Fab - PA/Clock and Bell System
Division 28 – Electronic Safety And SecurityDivision 28 – Electronic Safety And SecurityDivision 28 – Electronic Safety And SecurityDivision 28 – Electronic Safety And SecurityDivision 28 – Electronic Safety And Security
Prepare/Submit - Access Control System SubmittalsPrepare/Submit - Access Control System SubmittalsPrepare/Submit - Access Control System SubmittalsPrepare/Submit - Access Control System SubmittalsPrepare/Submit - Access Control System Submittals
Review/Approve - Access Control System SubmittalsReview/Approve - Access Control System SubmittalsReview/Approve - Access Control System SubmittalsReview/Approve - Access Control System SubmittalsReview/Approve - Access Control System Submittals
Order/Fab - Access Control SystemOrder/Fab - Access Control SystemOrder/Fab - Access Control SystemOrder/Fab - Access Control SystemOrder/Fab - Access Control System
Deliver/Install - Access Control SystemDeliver/Install - Access Control SystemDeliver/Install - Access Control SystemDeliver/Install - Access Control SystemDeliver/Install - Access Control System
Prepare/Submit - Video Surveillance SubmittalsPrepare/Submit - Video Surveillance SubmittalsPrepare/Submit - Video Surveillance SubmittalsPrepare/Submit - Video Surveillance SubmittalsPrepare/Submit - Video Surveillance Submittals
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 15 of 24
PD28-1050 Review/Approve - Video Surveillance Submittals
PD28-1060 Order/Fab - Video Surveillance
PD28-1070 Deliver/Install - Video Surveillance
PD28-1080 Prepare/Submit - Fire Alarm Devices
PD28-1090 Review/Approve - Fire Alarm Devices
PD28-1100 Order/Fab - Fire Alarm Devices
PD28-1110 Prepare/Submit - Emergency Response Systems Submittals
PD28-1120 Review/Approve - Emergency Response Systems Submittals
PD28-1130 Order/Fab - Emergency Response Systems
PD28-1140 Deliver/Install - Emergency Response Systems
Division 31 - Earthwork
PD31-1000 Prepare/Submit - Earthwork Submittals
PD31-1010 Review/Approve - Earthwork Submittals
PD31-1020 Order/Fab - Earthwork Materials
PD31-1030 Prepare/Submit - Site Clearing
PD31-1040 Review/Approve - Site Clearing
PD31-1050 Order/Fab - Site Clearing Materials
PD31-1060 Prepare/Submit - Aggregate Piers
PD31-1070 Review/Approve - Aggregate Piers
PD31-1080 Order/Fab - Aggregate Piers
Division 32 – Exterior Improvements
PD32-1000 Prepare/Submit - Asphalt Paving
PD32-1010 Review/Approve - Asphalt Paving
PD32-1020 Order/Fab - Asphalt Materials
PD32-1030 Prepare/Submit - Concrete Paving
PD32-1040 Review/Approve - Concrete Paving
PD32-1050 Order/Fab - Concrete Paving Materials
PD32-1060 Prepare/Submit - Chain Link Fences and Gates
PD32-1070 Review/Approve - Chain Link Fences and Gates
PD32-1080 Order/Fab - Chain Link Fences and Gates
PD32-1090 Prepare/Submit - Landscape Planting Plan and Materials
PD32-1100 Review/Approve - Landscape Planting Plan and Materials
PD32-1110 Order/Fab - Landscape Planting and Soil Amendments
PD32-1120 Prepare/Submit - Irrigation System Design and Equipment
PD32-1130 Review/Approve - Irrigation System Design and Equipment
PD32-1140 Order/Fab - Irrigation System Materials
PD32-1150 Prepare/Submit - Site Furnishings (Benches, Trash Recept…
PD32-1160 Review/Approve - Site Furnishings (Benches, Trash Recep…
PD32-1170 Order/Fab - Site Furnishings
Division 33 - Utilities
PD33-1000 Prepare/Submit - Water Utilities
10d 04-Nov-26 18-Nov-26
30d 19-Nov-26 04-Jan-27
20d 03-Feb-27 03-Mar-27
10d 29-May-26 11-Jun-26
10d 12-Jun-26 25-Jun-26
160d 26-Jun-26 17-Feb-27
10d 04-Nov-26 18-Nov-26
10d 19-Nov-26 03-Dec-26
30d 04-Dec-26 19-Jan-27
20d 27-Jan-27 24-Feb-27
70d 31-Jul-25 07-Nov-25
10d 31-Jul-25 13-Aug-25
10d 14-Aug-25 27-Aug-25
20d 28-Aug-25 25-Sep-25
10d 14-Aug-25 27-Aug-25
10d 28-Aug-25 11-Sep-25
15d 12-Sep-25 02-Oct-25
10d 28-Aug-25 11-Sep-25
10d 12-Sep-25 25-Sep-25
30d 26-Sep-25 07-Nov-25
60d 21-Oct-26 19-Jan-27
10d 21-Oct-26 03-Nov-26
10d 04-Nov-26 18-Nov-26
20d 19-Nov-26 17-Dec-26
10d 21-Oct-26 03-Nov-26
10d 04-Nov-26 18-Nov-26
20d 19-Nov-26 17-Dec-26
10d 04-Nov-26 18-Nov-26
10d 19-Nov-26 03-Dec-26
25d 04-Dec-26 11-Jan-27
10d 04-Nov-26 18-Nov-26
10d 19-Nov-26 03-Dec-26
20d 04-Dec-26 04-Jan-27
10d 19-Nov-26 03-Dec-26
10d 04-Dec-26 17-Dec-26
20d 18-Dec-26 19-Jan-27
10d 19-Nov-26 03-Dec-26
10d 04-Dec-26 17-Dec-26
20d 18-Dec-26 19-Jan-27
50d 30-Jan-26 10-Apr-26
10d 30-Jan-26 12-Feb-26
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Review/Approve - Video Surveillance SubmittalsReview/Approve - Video Surveillance SubmittalsReview/Approve - Video Surveillance SubmittalsReview/Approve - Video Surveillance SubmittalsReview/Approve - Video Surveillance Submittals
Order/Fab - Video SurveillanceOrder/Fab - Video SurveillanceOrder/Fab - Video SurveillanceOrder/Fab - Video SurveillanceOrder/Fab - Video Surveillance
Deliver/Install - Video SurveillanceDeliver/Install - Video SurveillanceDeliver/Install - Video SurveillanceDeliver/Install - Video SurveillanceDeliver/Install - Video Surveillance
Prepare/Submit - Fire Alarm DevicesPrepare/Submit - Fire Alarm DevicesPrepare/Submit - Fire Alarm DevicesPrepare/Submit - Fire Alarm DevicesPrepare/Submit - Fire Alarm Devices
Review/Approve - Fire Alarm DevicesReview/Approve - Fire Alarm DevicesReview/Approve - Fire Alarm DevicesReview/Approve - Fire Alarm DevicesReview/Approve - Fire Alarm Devices
Order/Fab - Fire Alarm DevicesOrder/Fab - Fire Alarm DevicesOrder/Fab - Fire Alarm DevicesOrder/Fab - Fire Alarm DevicesOrder/Fab - Fire Alarm Devices
Prepare/Submit - Emergency Response Systems SubmittPrepare/Submit - Emergency Response Systems SubmittPrepare/Submit - Emergency Response Systems SubmittPrepare/Submit - Emergency Response Systems SubmittPrepare/Submit - Emergency Response Systems Submitt
Review/Approve - Emergency Response Systems SubmReview/Approve - Emergency Response Systems SubmReview/Approve - Emergency Response Systems SubmReview/Approve - Emergency Response Systems SubmReview/Approve - Emergency Response Systems Subm
Order/Fab - Emergency Response SystemsOrder/Fab - Emergency Response SystemsOrder/Fab - Emergency Response SystemsOrder/Fab - Emergency Response SystemsOrder/Fab - Emergency Response Systems
Deliver/Install - Emergency Response SystemsDeliver/Install - Emergency Response SystemsDeliver/Install - Emergency Response SystemsDeliver/Install - Emergency Response SystemsDeliver/Install - Emergency Response Systems
Division 31 - EarthworkDivision 31 - EarthworkDivision 31 - EarthworkDivision 31 - EarthworkDivision 31 - Earthwork
Prepare/Submit - Earthwork SubmittalsPrepare/Submit - Earthwork SubmittalsPrepare/Submit - Earthwork SubmittalsPrepare/Submit - Earthwork SubmittalsPrepare/Submit - Earthwork Submittals
Review/Approve - Earthwork SubmittalsReview/Approve - Earthwork SubmittalsReview/Approve - Earthwork SubmittalsReview/Approve - Earthwork SubmittalsReview/Approve - Earthwork Submittals
Order/Fab - Earthwork MaterialsOrder/Fab - Earthwork MaterialsOrder/Fab - Earthwork MaterialsOrder/Fab - Earthwork MaterialsOrder/Fab - Earthwork Materials
Prepare/Submit - Site ClearingPrepare/Submit - Site ClearingPrepare/Submit - Site ClearingPrepare/Submit - Site ClearingPrepare/Submit - Site Clearing
Review/Approve - Site ClearingReview/Approve - Site ClearingReview/Approve - Site ClearingReview/Approve - Site ClearingReview/Approve - Site Clearing
Order/Fab - Site Clearing MaterialsOrder/Fab - Site Clearing MaterialsOrder/Fab - Site Clearing MaterialsOrder/Fab - Site Clearing MaterialsOrder/Fab - Site Clearing Materials
Prepare/Submit - Aggregate PiersPrepare/Submit - Aggregate PiersPrepare/Submit - Aggregate PiersPrepare/Submit - Aggregate PiersPrepare/Submit - Aggregate Piers
Review/Approve - Aggregate PiersReview/Approve - Aggregate PiersReview/Approve - Aggregate PiersReview/Approve - Aggregate PiersReview/Approve - Aggregate Piers
Order/Fab - Aggregate PiersOrder/Fab - Aggregate PiersOrder/Fab - Aggregate PiersOrder/Fab - Aggregate PiersOrder/Fab - Aggregate Piers
Division 32 – Exterior ImprovementsDivision 32 – Exterior ImprovementsDivision 32 – Exterior ImprovementsDivision 32 – Exterior ImprovementsDivision 32 – Exterior Improvements
Prepare/Submit - Asphalt PavingPrepare/Submit - Asphalt PavingPrepare/Submit - Asphalt PavingPrepare/Submit - Asphalt PavingPrepare/Submit - Asphalt Paving
Review/Approve - Asphalt PavingReview/Approve - Asphalt PavingReview/Approve - Asphalt PavingReview/Approve - Asphalt PavingReview/Approve - Asphalt Paving
Order/Fab - Asphalt MaterialsOrder/Fab - Asphalt MaterialsOrder/Fab - Asphalt MaterialsOrder/Fab - Asphalt MaterialsOrder/Fab - Asphalt Materials
Prepare/Submit - Concrete PavingPrepare/Submit - Concrete PavingPrepare/Submit - Concrete PavingPrepare/Submit - Concrete PavingPrepare/Submit - Concrete Paving
Review/Approve - Concrete PavingReview/Approve - Concrete PavingReview/Approve - Concrete PavingReview/Approve - Concrete PavingReview/Approve - Concrete Paving
Order/Fab - Concrete Paving MaterialsOrder/Fab - Concrete Paving MaterialsOrder/Fab - Concrete Paving MaterialsOrder/Fab - Concrete Paving MaterialsOrder/Fab - Concrete Paving Materials
Prepare/Submit - Chain Link Fences and GatesPrepare/Submit - Chain Link Fences and GatesPrepare/Submit - Chain Link Fences and GatesPrepare/Submit - Chain Link Fences and GatesPrepare/Submit - Chain Link Fences and Gates
Review/Approve - Chain Link Fences and GatesReview/Approve - Chain Link Fences and GatesReview/Approve - Chain Link Fences and GatesReview/Approve - Chain Link Fences and GatesReview/Approve - Chain Link Fences and Gates
Order/Fab - Chain Link Fences and GatesOrder/Fab - Chain Link Fences and GatesOrder/Fab - Chain Link Fences and GatesOrder/Fab - Chain Link Fences and GatesOrder/Fab - Chain Link Fences and Gates
Prepare/Submit - Landscape Planting Plan and MaterialsPrepare/Submit - Landscape Planting Plan and MaterialsPrepare/Submit - Landscape Planting Plan and MaterialsPrepare/Submit - Landscape Planting Plan and MaterialsPrepare/Submit - Landscape Planting Plan and Materials
Review/Approve - Landscape Planting Plan and MateriaReview/Approve - Landscape Planting Plan and MateriaReview/Approve - Landscape Planting Plan and MateriaReview/Approve - Landscape Planting Plan and MateriaReview/Approve - Landscape Planting Plan and Materia
Order/Fab - Landscape Planting and Soil AmendmenOrder/Fab - Landscape Planting and Soil AmendmenOrder/Fab - Landscape Planting and Soil AmendmenOrder/Fab - Landscape Planting and Soil AmendmentOrder/Fab - Landscape Planting and Soil Amendmen
Prepare/Submit - Irrigation System Design and EquipmPrepare/Submit - Irrigation System Design and EquipmPrepare/Submit - Irrigation System Design and EquipmPrepare/Submit - Irrigation System Design and EquipmPrepare/Submit - Irrigation System Design and Equipm
Review/Approve - Irrigation System Design and EquipmReview/Approve - Irrigation System Design and EquipmReview/Approve - Irrigation System Design and EquipmReview/Approve - Irrigation System Design and EquipmReview/Approve - Irrigation System Design and Equipm
Order/Fab - Irrigation System MaterialsOrder/Fab - Irrigation System MaterialsOrder/Fab - Irrigation System MaterialsOrder/Fab - Irrigation System MaterialsOrder/Fab - Irrigation System Materials
Prepare/Submit - Site Furnishings (Benches, Trash RecePrepare/Submit - Site Furnishings (Benches, Trash RecePrepare/Submit - Site Furnishings (Benches, Trash RecePrepare/Submit - Site Furnishings (Benches, Trash RecePrepare/Submit - Site Furnishings (Benches, Trash Rece
Review/Approve - Site Furnishings (Benches, Trash RecReview/Approve - Site Furnishings (Benches, Trash RecReview/Approve - Site Furnishings (Benches, Trash ReReview/Approve - Site Furnishings (Benches, Trash RecReview/Approve - Site Furnishings (Benches, Trash Rec
Order/Fab - Site FurnishingsOrder/Fab - Site FurnishingsOrder/Fab - Site FurnishingsOrder/Fab - Site FurnishingsOrder/Fab - Site Furnishings
Division 33 - UtilitiesDivision 33 - UtilitiesDivision 33 - UtilitiesDivision 33 - UtilitiesDivision 33 - Utilities
Prepare/Submit - Water UtilitiesPrepare/Submit - Water UtilitiesPrepare/Submit - Water UtilitiesPrepare/Submit - Water UtilitiesPrepare/Submit - Water Utilities
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 16 of 24
PD33-1010 Review/Approve - Water Utilities
PD33-1020 Order/Fab - Water Utility Materials
PD33-1030 Prepare/Submit - Sanitary Sewer Utilities
PD33-1040 Review/Approve - Sanitary Sewer Utilities
PD33-1050 Order/Fab - Sanitary Sewer Utility Materials
PD33-1060 Prepare/Submit - Storm Drainage Utilities
PD33-1070 Review/Approve - Storm Drainage Utilities
PD33-1080 Order/Fab - Storm Drainage Utility Materials
New Construction
Foundations & CIP
FFM-1020 Excavate For the Basement
FFM-1030 Excavate Footers And Columns
FFM-1040 Install underbasement utilities & main branch lines
FFM-1050 Soil & Compaction Testing/Inspections
FFM-1070 Excavate To Bring The Site To Rough Grade
FFM-1080 Install Utilities under SOG/ EP
FFM-1083 Waterproofing Foundation
FFM-1085 Backfilling
Basement Concrete
CIP-1000 Form Footers
CIP-1010 Install Footer Rebar
CIP-1020 Footer Rebar Inspection
CIP-1030 Pour Concrete Footer
CIP-1040 Form One Side of Walls
CIP-1050 Install Wall Rebar
CIP-1060 Wall Rebar Inspection
CIP-1070 Form up Outside Wall
CIP-1080 Pour Concrete Walls
CIP-1090 Foundation Wall Reinforcement
CIP-1100 Install Column Rebar
CIP-1110 Column Rebar Inspection
CIP-1120 Form Coulumns
CIP-1130 Pour Concrete Columns
CIP-1140 Install Underlayment Basement
CIP-1150 Install Slab Rebar
CIP-1160 Slab Rebar Inspection
CIP-1170 Pour Concrete Basement Slab
Slab on Grade and Up Concrete
CIP-1175 Aggregate Piers
CIP-1180 Form Footers for SOG
CIP-1190 Install Footer Rebar for SOG
10d 13-Feb-26 27-Feb-26
20d 02-Mar-26 27-Mar-26
10d 13-Feb-26 27-Feb-26
10d 02-Mar-26 13-Mar-26
20d 16-Mar-26 10-Apr-26
10d 30-Jan-26 12-Feb-26
10d 13-Feb-26 27-Feb-26
20d 02-Mar-26 27-Mar-26
375d 06-Jan-26 02-Jul-27
143d 10-Mar-26 29-Sep-26
20d 17-Mar-26 13-Apr-26
10d 14-Apr-26 28-Apr-26
10d 14-Apr-26 28-Apr-26
0d 28-Apr-26
5d 29-Apr-26 05-May-26
5d 06-May-26 12-May-26
10d 22-Jun-26 06-Jul-26
10d 07-Jul-26 20-Jul-26
38d 29-Apr-26 19-Jun-26
4d 29-Apr-26 04-May-26
3d 05-May-26 07-May-26
1d 08-May-26 08-May-26
1d 11-May-26 11-May-26
3d 12-May-26 14-May-26
3d 15-May-26 19-May-26
1d 20-May-26 20-May-26
3d 21-May-26 26-May-26
3d 27-May-26 29-May-26
1d 01-Jun-26 01-Jun-26
3d 02-Jun-26 04-Jun-26
1d 05-Jun-26 05-Jun-26
3d 08-Jun-26 10-Jun-26
1d 11-Jun-26 11-Jun-26
1d 12-Jun-26 12-Jun-26
3d 15-Jun-26 17-Jun-26
1d 18-Jun-26 18-Jun-26
1d 19-Jun-26 19-Jun-26
143d 10-Mar-26 29-Sep-26
15d 10-Mar-26 30-Mar-26
3d 13-May-26 15-May-26
3d 18-May-26 20-May-26
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Review/Approve - Water UtilitiesReview/Approve - Water UtilitiesReview/Approve - Water UtilitiesReview/Approve - Water UtilitiesReview/Approve - Water Utilities
Order/Fab - Water Utility MaterialsOrder/Fab - Water Utility MaterialsOrder/Fab - Water Utility MaterialsOrder/Fab - Water Utility MaterialsOrder/Fab - Water Utility Materials
Prepare/Submit - Sanitary Sewer UtilitiesPrepare/Submit - Sanitary Sewer UtilitiesPrepare/Submit - Sanitary Sewer UtilitiesPrepare/Submit - Sanitary Sewer UtilitiesPrepare/Submit - Sanitary Sewer Utilities
Review/Approve - Sanitary Sewer UtilitiesReview/Approve - Sanitary Sewer UtilitiesReview/Approve - Sanitary Sewer UtilitiesReview/Approve - Sanitary Sewer UtilitiesReview/Approve - Sanitary Sewer Utilities
Order/Fab - Sanitary Sewer Utility MaterialsOrder/Fab - Sanitary Sewer Utility MaterialsOrder/Fab - Sanitary Sewer Utility MaterialsOrder/Fab - Sanitary Sewer Utility MaterialsOrder/Fab - Sanitary Sewer Utility Materials
Prepare/Submit - Storm Drainage UtilitiesPrepare/Submit - Storm Drainage UtilitiesPrepare/Submit - Storm Drainage UtilitiesPrepare/Submit - Storm Drainage UtilitiesPrepare/Submit - Storm Drainage Utilities
Review/Approve - Storm Drainage UtilitiesReview/Approve - Storm Drainage UtilitiesReview/Approve - Storm Drainage UtilitiesReview/Approve - Storm Drainage UtilitiesReview/Approve - Storm Drainage Utilities
Order/Fab - Storm Drainage Utility MaterialsOrder/Fab - Storm Drainage Utility MaterialsOrder/Fab - Storm Drainage Utility MaterialsOrder/Fab - Storm Drainage Utility MaterialsOrder/Fab - Storm Drainage Utility Materials
New ConstructionNew ConstructionNew ConstructionNew ConstructionNew Construction
Foundations & CIPFoundations & CIPFoundations & CIPFoundations & CIPFoundations & CIP
Excavate For the BasementExcavate For the BasementExcavate For the BasementExcavate For the BasementExcavate For the Basement
Excavate Footers And ColumnsExcavate Footers And ColumnsExcavate Footers And ColumnsExcavate Footers And ColumnsExcavate Footers And Columns
Install underbasement utilities & main branch linesInstall underbasement utilities & main branch linesInstall underbasement utilities & main branch linesInstall underbasement utilities & main branch linesInstall underbasement utilities & main branch lines
  Soil & Compaction Testing/InspectionsSoil & Compaction Testing/InspectionsSoil & Compaction Testing/InspectionsSoil & Compaction Testing/InspectionsSoil & Compaction Testing/Inspections
Excavate To Bring The Site To Rough GradeExcavate To Bring The Site To Rough GradeExcavate To Bring The Site To Rough GradeExcavate To Bring The Site To Rough GradeExcavate To Bring The Site To Rough Grade
Install Utilities under SOG/ EPInstall Utilities under SOG/ EPInstall Utilities under SOG/ EPInstall Utilities under SOG/ EPInstall Utilities under SOG/ EP
Waterproofing FoundationWaterproofing FoundationWaterproofing FoundationWaterproofing FoundationWaterproofing Foundation
BackfillingBackfillingBackfillingBackfillingBackfilling
Basement ConcreteBasement ConcreteBasement ConcreteBasement ConcreteBasement Concrete
Form FootersForm FootersForm FootersForm FootersForm Footers
Install Footer RebarInstall Footer RebarInstall Footer RebarInstall Footer RebarInstall Footer Rebar
Footer Rebar InspectionFooter Rebar InspectionFooter Rebar InspectionFooter Rebar InspectionFooter Rebar Inspection
Pour Concrete FooterPour Concrete FooterPour Concrete FooterPour Concrete FooterPour Concrete Footer
Form One Side of WallsForm One Side of WallsForm One Side of WallsForm One Side of WallsForm One Side of Walls
Install Wall RebarInstall Wall RebarInstall Wall RebarInstall Wall RebarInstall Wall Rebar
Wall Rebar InspectionWall Rebar InspectionWall Rebar InspectionWall Rebar InspectionWall Rebar Inspection
Form up Outside WallForm up Outside WallForm up Outside WallForm up Outside WallForm up Outside Wall
Pour Concrete WallsPour Concrete WallsPour Concrete WallsPour Concrete WallsPour Concrete Walls
Foundation Wall ReinforcementFoundation Wall ReinforcementFoundation Wall ReinforcementFoundation Wall ReinforcementFoundation Wall Reinforcement
Install Column RebarInstall Column RebarInstall Column RebarInstall Column RebarInstall Column Rebar
Column Rebar InspectionColumn Rebar InspectionColumn Rebar InspectionColumn Rebar InspectionColumn Rebar Inspection
Form CoulumnsForm CoulumnsForm CoulumnsForm CoulumnsForm Coulumns
Pour Concrete ColumnsPour Concrete ColumnsPour Concrete ColumnsPour Concrete ColumnsPour Concrete Columns
Install Underlayment BasementInstall Underlayment BasementInstall Underlayment BasementInstall Underlayment BasementInstall Underlayment Basement
Install Slab RebarInstall Slab RebarInstall Slab RebarInstall Slab RebarInstall Slab Rebar
Slab Rebar InspectionSlab Rebar InspectionSlab Rebar InspectionSlab Rebar InspectionSlab Rebar Inspection
Pour Concrete Basement SlabPour Concrete Basement SlabPour Concrete Basement SlabPour Concrete Basement SlabPour Concrete Basement Slab
Slab on Grade and Up ConcreteSlab on Grade and Up ConcreteSlab on Grade and Up ConcreteSlab on Grade and Up ConcreteSlab on Grade and Up Concrete
Aggregate PiersAggregate PiersAggregate PiersAggregate PiersAggregate Piers
Form Footers for SOGForm Footers for SOGForm Footers for SOGForm Footers for SOGForm Footers for SOG
Install Footer Rebar for SOGInstall Footer Rebar for SOGInstall Footer Rebar for SOGInstall Footer Rebar for SOGInstall Footer Rebar for SOG
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 17 of 24
CIP-1200 SOG Footer Rebar Inspection
CIP-1210 Pour Concrete Footers for SOG
CIP-1220 Form SOG
CIP-1230 Install underlayment SOG
CIP-1240 Install SOG Rebar
CIP-1250 SOG Rebar Inspection
CIP-1260 Pour concrete SOG
CIP-1270 Form/Reinforce/Inspect/Place Slab on Deck-1st Floor
CIP-1280 Cure Slab On Deck-1st Floor
CIP-1290 Form/Reinforce/Inspect/Place Slab on Deck-2nd Floor
CIP-1300 Cure Slab On Deck-2nd Floor
CIP-1310 Form/Reinforce/Inspect/Place Slab on Deck-3rd Floor
CIP-1320 Cure Slab On Deck-3rd Floor
Site Utilities
UTI-1000 Install the Temp power Duct bank
UTI-1010 Install the temp power shed
UTI-1020 Setup (panels, disconnects, connections, etc.)
UTI-1030 Inspection
UTI-1040 Set CT Cabinet and meter
UTI-1050 Pull cable & terminate
UTI-1060 Temporary power
UTI-1070 Install Duct banks & Pepco Vaults & IT Pathways
UTI-1080 Install Gas & Water Lines
UTI-1090 Install Service Pathways (Sleeves, Conduits, Trenching)
UTI-1100 Site Grading
UTI-1110 Ductbank Inspection
UTI-1120 Site Utiliy Pads
Structure
STR-1050 Layout/Prep & Install CMU Towers
STR-1051 Install Stairs #1 (East side)
STR-1052 Install Stairs #2 (Middle)
STR-1053 Install Stairs #3 (Monumental Stairs)
STR-1054 Install Stairs #4 (South side)
STR-1055 Install Stairs Finishes
Level 1
STR-1000 Install metal beams Level 1
STR-1030 Install leveling plates Level 1
STR-1040 Steel Columns/Post-Tenstion Inspection Level 1
Level 2
STR-2000 Install beams Level 2
STR-2030 Steel Columns/Post-Tenstion Inspection Level 2
1d 21-May-26 21-May-26
1d 22-May-26 22-May-26
5d 26-May-26 01-Jun-26
1d 02-Jun-26 02-Jun-26
3d 03-Jun-26 05-Jun-26
1d 08-Jun-26 08-Jun-26
1d 09-Jun-26 09-Jun-26
8d 02-Jul-26 14-Jul-26
1d 15-Jul-26 15-Jul-26
8d 12-Aug-26 21-Aug-26
1d 24-Aug-26 24-Aug-26
8d 17-Sep-26 28-Sep-26
1d 29-Sep-26 29-Sep-26
121d 06-Jan-26 26-Jun-26
5d 06-Jan-26 12-Jan-26
3d 13-Jan-26 15-Jan-26
5d 16-Jan-26 23-Jan-26
2d 26-Jan-26 27-Jan-26
5d 28-Jan-26 03-Feb-26
5d 04-Feb-26 10-Feb-26
0d 10-Feb-26
40d 10-Mar-26 05-May-26
15d 30-Mar-26 20-Apr-26
15d 21-Apr-26 11-May-26
10d 12-May-26 26-May-26
20d 06-May-26 03-Jun-26
5d 22-Jun-26 26-Jun-26
132d 22-Jun-26 30-Dec-26
15d 26-Oct-26 16-Nov-26
15d 17-Nov-26 08-Dec-26
15d 17-Nov-26 08-Dec-26
15d 17-Nov-26 08-Dec-26
15d 17-Nov-26 08-Dec-26
15d 09-Dec-26 30-Dec-26
28d 22-Jun-26 30-Jul-26
8d 22-Jun-26 01-Jul-26
3d 15-Jul-26 17-Jul-26
9d 20-Jul-26 30-Jul-26
25d 31-Jul-26 03-Sep-26
8d 31-Jul-26 11-Aug-26
9d 24-Aug-26 03-Sep-26
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
SOG Footer Rebar InspectionSOG Footer Rebar InspectionSOG Footer Rebar InspectionSOG Footer Rebar InspectionSOG Footer Rebar Inspection
Pour Concrete Footers for SOGPour Concrete Footers for SOGPour Concrete Footers for SOGPour Concrete Footers for SOGPour Concrete Footers for SOG
Form SOGForm SOGForm SOGForm SOGForm SOG
Install underlayment SOGInstall underlayment SOGInstall underlayment SOGInstall underlayment SOGInstall underlayment SOG
Install SOG RebarInstall SOG RebarInstall SOG RebarInstall SOG RebarInstall SOG Rebar
SOG Rebar InspectionSOG Rebar InspectionSOG Rebar InspectionSOG Rebar InspectionSOG Rebar Inspection
Pour concrete SOGPour concrete SOGPour concrete SOGPour concrete SOGPour concrete SOG
Form/Reinforce/Inspect/Place Slab on Deck-1st FloorForm/Reinforce/Inspect/Place Slab on Deck-1st FloorForm/Reinforce/Inspect/Place Slab on Deck-1st FloorForm/Reinforce/Inspect/Place Slab on Deck-1st FloorForm/Reinforce/Inspect/Place Slab on Deck-1st Floor
Cure Slab On Deck-1st FloorCure Slab On Deck-1st FloorCure Slab On Deck-1st FloorCure Slab On Deck-1st FloorCure Slab On Deck-1st Floor
Form/Reinforce/Inspect/Place Slab on Deck-2nd FloorForm/Reinforce/Inspect/Place Slab on Deck-2nd FloorForm/Reinforce/Inspect/Place Slab on Deck-2nd FloorForm/Reinforce/Inspect/Place Slab on Deck-2nd FloorForm/Reinforce/Inspect/Place Slab on Deck-2nd Floor
Cure Slab On Deck-2nd FloorCure Slab On Deck-2nd FloorCure Slab On Deck-2nd FloorCure Slab On Deck-2nd FloorCure Slab On Deck-2nd Floor
Form/Reinforce/Inspect/Place Slab on Deck-3rd FloorForm/Reinforce/Inspect/Place Slab on Deck-3rd FloorForm/Reinforce/Inspect/Place Slab on Deck-3rd FloorForm/Reinforce/Inspect/Place Slab on Deck-3rd FloorForm/Reinforce/Inspect/Place Slab on Deck-3rd Floor
Cure Slab On Deck-3rd FloorCure Slab On Deck-3rd FloorCure Slab On Deck-3rd FloorCure Slab On Deck-3rd FloorCure Slab On Deck-3rd Floor
Site UtilitiesSite UtilitiesSite UtilitiesSite UtilitiesSite Utilities
Install the Temp power Duct bankInstall the Temp power Duct bankInstall the Temp power Duct bankInstall the Temp power Duct bankInstall the Temp power Duct bank
Install the temp power shedInstall the temp power shedInstall the temp power shedInstall the temp power shedInstall the temp power shed
Setup (panels, disconnects, connections, etc.)Setup (panels, disconnects, connections, etc.)Setup (panels, disconnects, connections, etc.)Setup (panels, disconnects, connections, etc.)Setup (panels, disconnects, connections, etc.)
InspectionInspectionInspectionInspectionInspection
Set CT Cabinet and meterSet CT Cabinet and meterSet CT Cabinet and meterSet CT Cabinet and meterSet CT Cabinet and meter
Pull cable & terminatePull cable & terminatePull cable & terminatePull cable & terminatePull cable & terminate
  Temporary powerTemporary powerTemporary powerTemporary powerTemporary power
Install Duct banks & Pepco Vaults & IT PathwaysInstall Duct banks & Pepco Vaults & IT PathwaysInstall Duct banks & Pepco Vaults & IT PathwaysInstall Duct banks & Pepco Vaults & IT PathwaysInstall Duct banks & Pepco Vaults & IT Pathways
Install Gas & Water LinesInstall Gas & Water LinesInstall Gas & Water LinesInstall Gas & Water LinesInstall Gas & Water Lines
Install Service Pathways (Sleeves, Conduits, Trenching)Install Service Pathways (Sleeves, Conduits, Trenching)Install Service Pathways (Sleeves, Conduits, Trenching)Install Service Pathways (Sleeves, Conduits, Trenching)Install Service Pathways (Sleeves, Conduits, Trenching)
Site GradingSite GradingSite GradingSite GradingSite Grading
Ductbank InspectionDuctbank InspectionDuctbank InspectionDuctbank InspectionDuctbank Inspection
Site Utiliy PadsSite Utiliy PadsSite Utiliy PadsSite Utiliy PadsSite Utiliy Pads
StructureStructureStructureStructureStructure
Layout/Prep & Install CMU TowersLayout/Prep & Install CMU TowersLayout/Prep & Install CMU TowersLayout/Prep & Install CMU TowersLayout/Prep & Install CMU Towers
Install Stairs #1 (East side)Install Stairs #1 (East side)Install Stairs #1 (East side)Install Stairs #1 (East side)Install Stairs #1 (East side)
Install Stairs #2 (Middle)Install Stairs #2 (Middle)Install Stairs #2 (Middle)Install Stairs #2 (Middle)Install Stairs #2 (Middle)
Install Stairs #3 (Monumental Stairs)Install Stairs #3 (Monumental Stairs)Install Stairs #3 (Monumental Stairs)Install Stairs #3 (Monumental Stairs)Install Stairs #3 (Monumental Stairs)
Install Stairs #4 (South side)Install Stairs #4 (South side)Install Stairs #4 (South side)Install Stairs #4 (South side)Install Stairs #4 (South side)
Install Stairs FinishesInstall Stairs FinishesInstall Stairs FinishesInstall Stairs FinishesInstall Stairs Finishes
Level 1Level 1Level 1Level 1Level 1
Install metal beams Level 1Install metal beams Level 1Install metal beams Level 1Install metal beams Level 1Install metal beams Level 1
Install leveling plates Level 1Install leveling plates Level 1Install leveling plates Level 1Install leveling plates Level 1Install leveling plates Level 1
Steel Columns/Post-Tenstion Inspection Level 1Steel Columns/Post-Tenstion Inspection Level 1Steel Columns/Post-Tenstion Inspection Level 1Steel Columns/Post-Tenstion Inspection Level 1Steel Columns/Post-Tenstion Inspection Level 1
Level 2Level 2Level 2Level 2Level 2
Install beams Level 2Install beams Level 2Install beams Level 2Install beams Level 2Install beams Level 2
Steel Columns/Post-Tenstion Inspection Level 2Steel Columns/Post-Tenstion Inspection Level 2Steel Columns/Post-Tenstion Inspection Level 2Steel Columns/Post-Tenstion Inspection Level 2Steel Columns/Post-Tenstion Inspection Level 2
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 18 of 24
Level 3 to Roof
STR-3000 Install beams Level 3
STR-3020 Steel Columns/Post-Tenstion Inspection Level 3
STR-3030 Install beams Roof Level
STR-3040 Install Deck- Roof Floor
Envelope
ENV-1010 Install Roof Insulation And Cladding
ENV-1020 Frame Up CMF Wall - Floor 1
ENV-1030 Sheathing and Air Barrier - Floor 1
ENV-1031 Frame Up CMF Wall - Floor 2
ENV-1032 Sheathing and Air Barrier - Floor 2
ENV-1033 Frame Up CMF Wall - Floor 3
ENV-1034 Sheathing and Air Barrier - Floor 3
ENV-1040 Install Brick Facade on East and North Elevations
ENV-1045 Install Brick Facade on West and South Elevations
ENV-1060 Install Glazing & Window Systems
ENV-1065 Temporary Dry in
ENV-1070 Install Store Front Systems
ENV-1075 Install Front door Metal Paneling
ENV-1080 Install Exterior Door Frames
ENV-1085 Install Exterior Doors
ENV-1090 Building Water tight
MEP Equipment & Elevator
MEP-1010 Rough in Racks and Panels at IT Closets
MEP-1020 Buildout IT Closets
MEP-1030 Rough-in MEP Electrical Room
MEP-1040 Buildout Electrical Room and Closets - Install Electrical Eq…
MEP-1045 Buildout Electrical Room and Closets - Finalize Terminatio…
MEP-1050 Set new electrical switchgear
MEP-1060 Tie-in ductbank / conduits to switchgear
MEP-1070 Switchgear Inspection
MEP-1080 Electrical service provider to pull building cabling (feeds)
MEP-1090 Energize permanent power
MEP-1100 Rough-in MEP Roof Top Units
MEP-1110 Install Roof Top Equipment
MEP-1120 Rough-in MEP Mechanical Room
MEP-1130 Temp heat/Cooling and Install Filter Fabric
MEP-1140 Buildout Mechanical Rooms - Install Mechanical Equipme…
MEP-1145 Buildout Mechanical Rooms - Finalize Insulation, Commis…
MEP-1150 Prepare Pre-Functional Checklist for Mechanical Room
MEP-1160 Prepare Pre-Functional Checklist for Mechanical Basement
34d 04-Sep-26 23-Oct-26
8d 04-Sep-26 16-Sep-26
9d 29-Sep-26 09-Oct-26
6d 13-Oct-26 20-Oct-26
3d 21-Oct-26 23-Oct-26
85d 26-Oct-26 01-Mar-27
15d 26-Oct-26 16-Nov-26
15d 26-Oct-26 16-Nov-26
15d 02-Nov-26 23-Nov-26
15d 17-Nov-26 08-Dec-26
15d 24-Nov-26 15-Dec-26
15d 09-Dec-26 30-Dec-26
15d 16-Dec-26 07-Jan-27
20d 08-Jan-27 05-Feb-27
15d 08-Feb-27 01-Mar-27
20d 15-Jan-27 12-Feb-27
5d 08-Jan-27 14-Jan-27
5d 08-Feb-27 12-Feb-27
5d 16-Feb-27 22-Feb-27
5d 16-Feb-27 22-Feb-27
5d 23-Feb-27 01-Mar-27
0d 01-Mar-27
120d 17-Nov-26 11-May-27
20d 17-Nov-26 15-Dec-26
20d 03-Feb-27 03-Mar-27
20d 17-Nov-26 15-Dec-26
15d 15-Jan-27 05-Feb-27
15d 08-Feb-27 01-Mar-27
15d 10-Mar-27 30-Mar-27
1d 31-Mar-27 31-Mar-27
10d 01-Apr-27 14-Apr-27
4d 15-Apr-27 21-Apr-27
0d 21-Apr-27
20d 17-Nov-26 15-Dec-26
20d 16-Feb-27 15-Mar-27
20d 17-Nov-26 15-Dec-26
20d 16-Dec-26 14-Jan-27
20d 15-Jan-27 12-Feb-27
10d 16-Feb-27 01-Mar-27
5d 16-Dec-26 22-Dec-26
5d 17-Feb-27 23-Feb-27
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Level 3 to RoofLevel 3 to RoofLevel 3 to RoofLevel 3 to RoofLevel 3 to Roof
Install beams Level 3Install beams Level 3Install beams Level 3Install beams Level 3Install beams Level 3
Steel Columns/Post-Tenstion Inspection Level 3Steel Columns/Post-Tenstion Inspection Level 3Steel Columns/Post-Tenstion Inspection Level 3Steel Columns/Post-Tenstion Inspection Level 3Steel Columns/Post-Tenstion Inspection Level 3
Install beams Roof LevelInstall beams Roof LevelInstall beams Roof LevelInstall beams Roof LevelInstall beams Roof Level
Install Deck- Roof FloorInstall Deck- Roof FloorInstall Deck- Roof FloorInstall Deck- Roof FloorInstall Deck- Roof Floor
EnvelopeEnvelopeEnvelopeEnvelopeEnvelope
Install Roof Insulation And CladdingInstall Roof Insulation And CladdingInstall Roof Insulation And CladdingInstall Roof Insulation And CladdingInstall Roof Insulation And Cladding
Frame Up CMF Wall - Floor 1Frame Up CMF Wall - Floor 1Frame Up CMF Wall - Floor 1Frame Up CMF Wall - Floor 1Frame Up CMF Wall - Floor 1
Sheathing and Air Barrier - Floor 1Sheathing and Air Barrier - Floor 1Sheathing and Air Barrier - Floor 1Sheathing and Air Barrier - Floor 1Sheathing and Air Barrier - Floor 1
Frame Up CMF Wall - Floor 2Frame Up CMF Wall - Floor 2Frame Up CMF Wall - Floor 2Frame Up CMF Wall - Floor 2Frame Up CMF Wall - Floor 2
Sheathing and Air Barrier - Floor 2Sheathing and Air Barrier - Floor 2Sheathing and Air Barrier - Floor 2Sheathing and Air Barrier - Floor 2Sheathing and Air Barrier - Floor 2
Frame Up CMF Wall - Floor 3Frame Up CMF Wall - Floor 3Frame Up CMF Wall - Floor 3Frame Up CMF Wall - Floor 3Frame Up CMF Wall - Floor 3
Sheathing and Air Barrier - Floor 3Sheathing and Air Barrier - Floor 3Sheathing and Air Barrier - Floor 3Sheathing and Air Barrier - Floor 3Sheathing and Air Barrier - Floor 3
Install Brick Facade on East and North ElevationsInstall Brick Facade on East and North ElevationsInstall Brick Facade on East and North ElevationsInstall Brick Facade on East and North ElevationsInstall Brick Facade on East and North Elevations
Install Brick Facade on West and South ElevationsInstall Brick Facade on West and South ElevationsInstall Brick Facade on West and South ElevationsInstall Brick Facade on West and South ElevationsInstall Brick Facade on West and South Elevations
Install Glazing & Window SystemsInstall Glazing & Window SystemsInstall Glazing & Window SystemsInstall Glazing & Window SystemsInstall Glazing & Window Systems
Temporary Dry inTemporary Dry inTemporary Dry inTemporary Dry inTemporary Dry in
Install Store Front SystemsInstall Store Front SystemsInstall Store Front SystemsInstall Store Front SystemsInstall Store Front Systems
Install Front door Metal PanelingInstall Front door Metal PanelingInstall Front door Metal PanelingInstall Front door Metal PanelingInstall Front door Metal Paneling
Install Exterior Door FramesInstall Exterior Door FramesInstall Exterior Door FramesInstall Exterior Door FramesInstall Exterior Door Frames
Install Exterior DoorsInstall Exterior DoorsInstall Exterior DoorsInstall Exterior DoorsInstall Exterior Doors
  Building Water tightBuilding Water tightBuilding Water tightBuilding Water tightBuilding Water tight
MEP Equipment & ElevatorMEP Equipment & ElevatorMEP Equipment & ElevatorMEP Equipment & ElevatorMEP Equipment & Elevator
Rough in Racks and Panels at IT ClosetsRough in Racks and Panels at IT ClosetsRough in Racks and Panels at IT ClosetsRough in Racks and Panels at IT ClosetsRough in Racks and Panels at IT Closets
Buildout IT ClosetsBuildout IT ClosetsBuildout IT ClosetsBuildout IT ClosetsBuildout IT Closets
Rough-in MEP Electrical RoomRough-in MEP Electrical RoomRough-in MEP Electrical RoomRough-in MEP Electrical RoomRough-in MEP Electrical Room
Buildout Electrical Room and Closets - Install ElectrBuildout Electrical Room and Closets - Install ElectrBuildout Electrical Room and Closets - Install ElectrBuildout Electrical Room and Closets - Install ElectrBuildout Electrical Room and Closets - Install Electr
Buildout Electrical Room and Closets - Finalize TeBuildout Electrical Room and Closets - Finalize TeBuildout Electrical Room and Closets - Finalize TeBuildout Electrical Room and Closets - Finalize TeBuildout Electrical Room and Closets - Finalize Te
Set new electrical switchgearSet new electrical switchgearSet new electrical switchgearSet new electrical switchgearSet new electrical switchgear
Tie-in ductbank / conduits to switchgearTie-in ductbank / conduits to switchgearTie-in ductbank / conduits to switchgearTie-in ductbank / conduits to switchgearTie-in ductbank / conduits to switchgear
Switchgear InspectionSwitchgear InspectionSwitchgear InspectionSwitchgear InspectionSwitchgear Inspection
Electrical service provider to pull building cablElectrical service provider to pull building cablElectrical service provider to pull building cabElectrical service provider to pull building cablElectrical service provider to pull building cabl
  Energize permanent powerEnergize permanent powerEnergize permanent powerEnergize permanent powerEnergize permanent power
Rough-in MEP Roof Top UnitsRough-in MEP Roof Top UnitsRough-in MEP Roof Top UnitsRough-in MEP Roof Top UnitsRough-in MEP Roof Top Units
Install Roof Top EquipmentInstall Roof Top EquipmentInstall Roof Top EquipmentInstall Roof Top EquipmentInstall Roof Top Equipment
Rough-in MEP Mechanical RoomRough-in MEP Mechanical RoomRough-in MEP Mechanical RoomRough-in MEP Mechanical RoomRough-in MEP Mechanical Room
Temp heat/Cooling and Install Filter FabricTemp heat/Cooling and Install Filter FabricTemp heat/Cooling and Install Filter FabricTemp heat/Cooling and Install Filter FabricTemp heat/Cooling and Install Filter Fabric
Buildout Mechanical Rooms - Install Mechanical EqBuildout Mechanical Rooms - Install Mechanical EqBuildout Mechanical Rooms - Install Mechanical EqBuildout Mechanical Rooms - Install Mechanical EqBuildout Mechanical Rooms - Install Mechanical Eq
Buildout Mechanical Rooms - Finalize Insulation, Buildout Mechanical Rooms - Finalize Insulation, Buildout Mechanical Rooms - Finalize Insulation, Buildout Mechanical Rooms - Finalize Insulation, Buildout Mechanical Rooms - Finalize Insulation,
Prepare Pre-Functional Checklist for Mechanical RoomPrepare Pre-Functional Checklist for Mechanical RoomPrepare Pre-Functional Checklist for Mechanical RoomPrepare Pre-Functional Checklist for Mechanical RoomPrepare Pre-Functional Checklist for Mechanical Room
Prepare Pre-Functional Checklist for Mechanical BPrepare Pre-Functional Checklist for Mechanical BPrepare Pre-Functional Checklist for Mechanical BPrepare Pre-Functional Checklist for Mechanical BPrepare Pre-Functional Checklist for Mechanical B
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 19 of 24
MEP-1170 Prepare Pre-Functional Checklist for Mechanical Level 1
MEP-1180 Prepare Pre-Functional Checklist for Mechanical Level 2
MEP-1190 Prepare Pre-Functional Checklist for Mechanical Level 3
MEP-1200 Mechanical Starters & Controls
MEP-1210 Start Up Equipment for Commissioning
Elevator installation
ELV-1000 Install elevator rails
ELV-1010 Install elevator machine room equipment and raceways to…
ELV-1020 Install elevator platform, hoistway motors, sills and cab shell
ELV-1030 Install hoistway wiring and rough-in call boxes and lanterns
ELV-1040 Set hoistway frames and doors
ELV-1050 Install elevator cab finishes
ELV-1060 Test and adjust elevators
ELV-1070 Elevator Installation Complete
Interior
Basement Level/Gym/Music/Stage
Rough-in
INL0-1040 Wall Rough-in EP Basement
INL0-1050 Wall Close-in Inspections Basement
INL0-1100 OH MEP Layout Basement
INL0-1120 OH Electrical & Fire Alarm Rough-in Basement
INL0-1130 OH Mechanical Rough-in Basement
INL0-1140 Rough-in Sprinkler Basement
INL0-1150 OH Plumbing Rough-in Basement
INL0-1160 Test Mechanical Piping Basement
INL0-1170 Perform HVAC air leakage test Basement
INL0-1180 Flush Mechanical Pipe Basement
INL0-1200 Review & Approve Duct Air Leakage and all HVAC Control…
INL0-1210 Install Heat Pumps Basement
INL0-1230 QC Punch-Out Inspection Basement
INL0-1240 Complete Punch - Out Items Above Ceiling Basement
INL0-1250 Install OH Lighting Basement
INL0-1260 Pre-Final Inspection Basement
INL0-1270 Complete Pre-Final Items Above Ceiling Basement
INL0-1280 Ceiling Close-in Inspections Basement
Finishes
INL0-1000 Verify/Confirm Slab Elevations
INL0-1010 Set Floor Control Lines Basement
INL0-1020 Frame Walls and Soffits Basement
INL0-1030 Framing inspection Basement
INL0-1055 Install Door frame Basement
5d 26-Feb-27 04-Mar-27
5d 09-Mar-27 15-Mar-27
5d 18-Mar-27 24-Mar-27
5d 28-Apr-27 04-May-27
5d 05-May-27 11-May-27
70d 15-Jan-27 27-Apr-27
20d 15-Jan-27 12-Feb-27
20d 01-Feb-27 01-Mar-27
20d 16-Feb-27 15-Mar-27
20d 02-Mar-27 29-Mar-27
10d 16-Mar-27 29-Mar-27
10d 30-Mar-27 12-Apr-27
15d 06-Apr-27 27-Apr-27
0d 27-Apr-27
132d 17-Nov-26 27-May-27
105d 17-Nov-26 20-Apr-27
48d 05-Jan-27 15-Mar-27
7d 05-Jan-27 13-Jan-27
1d 14-Jan-27 14-Jan-27
3d 27-Jan-27 29-Jan-27
7d 18-Feb-27 26-Feb-27
7d 01-Feb-27 09-Feb-27
7d 01-Feb-27 09-Feb-27
7d 01-Feb-27 09-Feb-27
1d 10-Feb-27 10-Feb-27
3d 10-Feb-27 12-Feb-27
1d 11-Feb-27 11-Feb-27
3d 16-Feb-27 18-Feb-27
3d 24-Feb-27 26-Feb-27
1d 01-Mar-27 01-Mar-27
5d 02-Mar-27 08-Mar-27
5d 08-Mar-27 12-Mar-27
1d 09-Mar-27 09-Mar-27
3d 10-Mar-27 12-Mar-27
1d 15-Mar-27 15-Mar-27
105d 17-Nov-26 20-Apr-27
5d 17-Nov-26 23-Nov-26
2d 24-Nov-26 25-Nov-26
10d 27-Nov-26 10-Dec-26
1d 11-Dec-26 11-Dec-26
7d 14-Dec-26 22-Dec-26
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Prepare Pre-Functional Checklist for Mechanical Prepare Pre-Functional Checklist for Mechanical Prepare Pre-Functional Checklist for Mechanical Prepare Pre-Functional Checklist for Mechanical LPrepare Pre-Functional Checklist for Mechanical
Prepare Pre-Functional Checklist for MechanicalPrepare Pre-Functional Checklist for MechanicalPrepare Pre-Functional Checklist for MechanicalPrepare Pre-Functional Checklist for Mechanical Prepare Pre-Functional Checklist for Mechanical
Prepare Pre-Functional Checklist for MechanicaPrepare Pre-Functional Checklist for MechanicaPrepare Pre-Functional Checklist for MechanicaPrepare Pre-Functional Checklist for MechanicaPrepare Pre-Functional Checklist for Mechanica
Mechanical Starters & ControlsMechanical Starters & ControlsMechanical Starters & ControlsMechanical Starters & ControlsMechanical Starters & Controls
Start Up Equipment for CommissioningStart Up Equipment for CommissioningStart Up Equipment for CommissioningStart Up Equipment for CommissioningStart Up Equipment for Commissioning
Elevator installationElevator installationElevator installationElevator installationElevator installation
Install elevator railsInstall elevator railsInstall elevator railsInstall elevator railsInstall elevator rails
Install elevator machine room equipment and racInstall elevator machine room equipment and racInstall elevator machine room equipment and racInstall elevator machine room equipment and racInstall elevator machine room equipment and rac
Install elevator platform, hoistway motors, sills aInstall elevator platform, hoistway motors, sills aInstall elevator platform, hoistway motors, sills aInstall elevator platform, hoistway motors, sills aInstall elevator platform, hoistway motors, sills a
Install hoistway wiring and rough-in call boxes aInstall hoistway wiring and rough-in call boxes aInstall hoistway wiring and rough-in call boxes Install hoistway wiring and rough-in call boxes aInstall hoistway wiring and rough-in call boxes a
Set hoistway frames and doorsSet hoistway frames and doorsSet hoistway frames and doorsSet hoistway frames and doorsSet hoistway frames and doors
Install elevator cab finishesInstall elevator cab finishesInstall elevator cab finishesInstall elevator cab finishesInstall elevator cab finishes
Test and adjust elevatorsTest and adjust elevatorsTest and adjust elevatorsTest and adjust elevatorsTest and adjust elevators
  Elevator Installation CompleteElevator Installation CompleteElevator Installation CompleteElevator Installation CompleteElevator Installation Complete
InteriorInteriorInteriorInteriorInterior
Basement Level/Gym/Music/StageBasement Level/Gym/Music/StageBasement Level/Gym/Music/StageBasement Level/Gym/Music/StageBasement Level/Gym/Music/Stage
Rough-inRough-inRough-inRough-inRough-in
Wall Rough-in EP BasementWall Rough-in EP BasementWall Rough-in EP BasementWall Rough-in EP BasementWall Rough-in EP Basement
Wall Close-in Inspections BasementWall Close-in Inspections BasementWall Close-in Inspections BasementWall Close-in Inspections BasementWall Close-in Inspections Basement
OH MEP Layout BasementOH MEP Layout BasementOH MEP Layout BasementOH MEP Layout BasementOH MEP Layout Basement
OH Electrical & Fire Alarm Rough-in BasementOH Electrical & Fire Alarm Rough-in BasementOH Electrical & Fire Alarm Rough-in BasementOH Electrical & Fire Alarm Rough-in BasementOH Electrical & Fire Alarm Rough-in Basement
OH Mechanical Rough-in BasementOH Mechanical Rough-in BasementOH Mechanical Rough-in BasementOH Mechanical Rough-in BasementOH Mechanical Rough-in Basement
Rough-in Sprinkler BasementRough-in Sprinkler BasementRough-in Sprinkler BasementRough-in Sprinkler BasementRough-in Sprinkler Basement
OH Plumbing Rough-in BasementOH Plumbing Rough-in BasementOH Plumbing Rough-in BasementOH Plumbing Rough-in BasementOH Plumbing Rough-in Basement
Test Mechanical Piping BasementTest Mechanical Piping BasementTest Mechanical Piping BasementTest Mechanical Piping BasementTest Mechanical Piping Basement
Perform HVAC air leakage test BasementPerform HVAC air leakage test BasementPerform HVAC air leakage test BasementPerform HVAC air leakage test BasementPerform HVAC air leakage test Basement
Flush Mechanical Pipe BasementFlush Mechanical Pipe BasementFlush Mechanical Pipe BasementFlush Mechanical Pipe BasementFlush Mechanical Pipe Basement
Review & Approve Duct Air Leakage and all HVAC Review & Approve Duct Air Leakage and all HVAC Review & Approve Duct Air Leakage and all HVACReview & Approve Duct Air Leakage and all HVAC Review & Approve Duct Air Leakage and all HVAC
Install Heat Pumps BasementInstall Heat Pumps BasementInstall Heat Pumps BasementInstall Heat Pumps BasementInstall Heat Pumps Basement
QC Punch-Out Inspection BasementQC Punch-Out Inspection BasementQC Punch-Out Inspection BasementQC Punch-Out Inspection BasementQC Punch-Out Inspection Basement
Complete Punch - Out Items Above Ceiling BasemComplete Punch - Out Items Above Ceiling BasemComplete Punch - Out Items Above Ceiling BasemComplete Punch - Out Items Above Ceiling BasemComplete Punch - Out Items Above Ceiling Basem
Install OH Lighting BasementInstall OH Lighting BasementInstall OH Lighting BasementInstall OH Lighting BasementInstall OH Lighting Basement
Pre-Final Inspection BasementPre-Final Inspection BasementPre-Final Inspection BasementPre-Final Inspection BasementPre-Final Inspection Basement
Complete Pre-Final Items Above Ceiling BasemeComplete Pre-Final Items Above Ceiling BasemeComplete Pre-Final Items Above Ceiling BasemeComplete Pre-Final Items Above Ceiling BasemeComplete Pre-Final Items Above Ceiling Baseme
Ceiling Close-in Inspections BasementCeiling Close-in Inspections BasementCeiling Close-in Inspections BasementCeiling Close-in Inspections BasementCeiling Close-in Inspections Basement
FinishesFinishesFinishesFinishesFinishes
Verify/Confirm Slab ElevationsVerify/Confirm Slab ElevationsVerify/Confirm Slab ElevationsVerify/Confirm Slab ElevationsVerify/Confirm Slab Elevations
Set Floor Control Lines BasementSet Floor Control Lines BasementSet Floor Control Lines BasementSet Floor Control Lines BasementSet Floor Control Lines Basement
Frame Walls and Soffits BasementFrame Walls and Soffits BasementFrame Walls and Soffits BasementFrame Walls and Soffits BasementFrame Walls and Soffits Basement
Framing inspection BasementFraming inspection BasementFraming inspection BasementFraming inspection BasementFraming inspection Basement
Install Door frame BasementInstall Door frame BasementInstall Door frame BasementInstall Door frame BasementInstall Door frame Basement
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 20 of 24
INL0-1060 Start One side drywall Basement
INL0-1070 Install insulation Basement
INL0-1090 Hang/tape/finish GWB Basement
INL0-1110 Mud Block &Tape/Prime & First Coat of Paint Basement
INL0-1190 Insulate Mechanical Pipe Basement
INL0-1220 Install Acoustical Ceiling Frame Basement
INL0-1290 Install acoustical ceiling Tile and drywall ceiling Basement
INL0-1310 Install Wall and Flooring finishes Basement
INL0-1320 Install Mechanical Finishes Basement
INL0-1330 Install Plumbing Finishes Basement
INL0-1340 Final Painting Basement
INL0-1345 Install Doors & Hardware Basement
INL0-1350 Install Appliances Basement
INL0-1360 Install Casework, Millwork Basement
INL0-1370 Install Toilet Partitions Basement
INL0-1380 Install FF & E / Connect MEP Basement
INL0-1390 Final Clean Basement
First Level Common Space/Classrooms/Offices/ Kitchen and Dining Area
Rough-in
INL1-1030 Wall Rough-in EP Level 1
INL1-1040 Wall Close-in Inspections Level 1
INL1-1090 OH MEP Layout Level 1
INL1-1110 OH Mechanical Rough-in Level 1
INL1-1120 OH Plumbing Rough-in Level 1
INL1-1130 Rough-in Sprinkler Level 1
INL1-1140 OH Electrical & Fire Alarm Rough-in Level 1
INL1-1150 Install Fire Alarm Control Panel Level 1
INL1-1160 Test Mechanical Piping Level 1
INL1-1170 Perform HVAC air leakage test Level 1
INL1-1180 Flush Mechanical Pipe Level 1
INL1-1200 Review & Approve Duct Air Leakage and all HVAC Control…
INL1-1220 Install Heat Pumps Level 1
INL1-1230 QC Punch-Out Inspection Level 1
INL1-1240 Complete Punch - Out Items Above Ceiling Level 1
INL1-1250 Install OH Lighting Level 1
INL1-1260 Pre-Final Inspection Level 1
INL1-1270 Ceiling Close-in Inspections Level 1
INL1-1280 Complete Pre-Final Items Above Ceiling Level 1
Finishes
INL1-1000 Set Floor Control Lines Level 1
INL1-1010 Frame Walls and Soffits Level 1
7d 14-Dec-26 22-Dec-26
7d 23-Dec-26 04-Jan-27
7d 15-Jan-27 26-Jan-27
7d 27-Jan-27 04-Feb-27
7d 12-Feb-27 23-Feb-27
5d 01-Mar-27 05-Mar-27
5d 16-Mar-27 22-Mar-27
5d 23-Mar-27 29-Mar-27
5d 23-Mar-27 29-Mar-27
5d 30-Mar-27 05-Apr-27
5d 30-Mar-27 05-Apr-27
5d 30-Mar-27 05-Apr-27
5d 06-Apr-27 12-Apr-27
5d 06-Apr-27 12-Apr-27
5d 06-Apr-27 12-Apr-27
5d 06-Apr-27 12-Apr-27
5d 13-Apr-27 20-Apr-27
110d 09-Dec-26 18-May-27
47d 14-Jan-27 23-Mar-27
7d 14-Jan-27 25-Jan-27
1d 26-Jan-27 26-Jan-27
3d 05-Feb-27 09-Feb-27
5d 10-Feb-27 17-Feb-27
5d 10-Feb-27 17-Feb-27
5d 10-Feb-27 17-Feb-27
5d 01-Mar-27 05-Mar-27
5d 18-Feb-27 24-Feb-27
1d 18-Feb-27 18-Feb-27
3d 18-Feb-27 22-Feb-27
1d 19-Feb-27 19-Feb-27
3d 23-Feb-27 25-Feb-27
3d 05-Mar-27 09-Mar-27
1d 10-Mar-27 10-Mar-27
5d 11-Mar-27 17-Mar-27
5d 15-Mar-27 19-Mar-27
1d 18-Mar-27 18-Mar-27
1d 22-Mar-27 22-Mar-27
3d 19-Mar-27 23-Mar-27
110d 09-Dec-26 18-May-27
2d 09-Dec-26 10-Dec-26
10d 11-Dec-26 24-Dec-26
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Start One side drywall BasementStart One side drywall BasementStart One side drywall BasementStart One side drywall BasementStart One side drywall Basement
Install insulation BasementInstall insulation BasementInstall insulation BasementInstall insulation BasementInstall insulation Basement
Hang/tape/finish GWB BasementHang/tape/finish GWB BasementHang/tape/finish GWB BasementHang/tape/finish GWB BasementHang/tape/finish GWB Basement
Mud Block &Tape/Prime & First Coat of Paint BasemMud Block &Tape/Prime & First Coat of Paint BasemMud Block &Tape/Prime & First Coat of Paint BaseMud Block &Tape/Prime & First Coat of Paint BasemMud Block &Tape/Prime & First Coat of Paint Basem
Insulate Mechanical Pipe BasementInsulate Mechanical Pipe BasementInsulate Mechanical Pipe BasementInsulate Mechanical Pipe BasementInsulate Mechanical Pipe Basement
Install Acoustical Ceiling Frame BasementInstall Acoustical Ceiling Frame BasementInstall Acoustical Ceiling Frame BasementInstall Acoustical Ceiling Frame BasementInstall Acoustical Ceiling Frame Basement
Install acoustical ceiling Tile and drywall ceiling Install acoustical ceiling Tile and drywall ceiling Install acoustical ceiling Tile and drywall ceiling Install acoustical ceiling Tile and drywall ceiling Install acoustical ceiling Tile and drywall ceiling
Install Wall and Flooring finishes BasementInstall Wall and Flooring finishes BasementInstall Wall and Flooring finishes BasementInstall Wall and Flooring finishes BasementInstall Wall and Flooring finishes Basement
Install Mechanical Finishes BasementInstall Mechanical Finishes BasementInstall Mechanical Finishes BasementInstall Mechanical Finishes BasementInstall Mechanical Finishes Basement
Install Plumbing Finishes BasementInstall Plumbing Finishes BasementInstall Plumbing Finishes BasementInstall Plumbing Finishes BasementInstall Plumbing Finishes Basement
Final Painting BasementFinal Painting BasementFinal Painting BasementFinal Painting BasementFinal Painting Basement
Install Doors & Hardware BasementInstall Doors & Hardware BasementInstall Doors & Hardware BasementInstall Doors & Hardware BasementInstall Doors & Hardware Basement
Install Appliances BasementInstall Appliances BasementInstall Appliances BasementInstall Appliances BasementInstall Appliances Basement
Install Casework, Millwork BasementInstall Casework, Millwork BasementInstall Casework, Millwork BasementInstall Casework, Millwork BasementInstall Casework, Millwork Basement
Install Toilet Partitions BasementInstall Toilet Partitions BasementInstall Toilet Partitions BasementInstall Toilet Partitions BasementInstall Toilet Partitions Basement
Install FF & E / Connect MEP BasementInstall FF & E / Connect MEP BasementInstall FF & E / Connect MEP BasementInstall FF & E / Connect MEP BasementInstall FF & E / Connect MEP Basement
Final Clean BasementFinal Clean BasementFinal Clean BasementFinal Clean BasementFinal Clean Basement
First Level Common Space/Classrooms/OffiFirst Level Common Space/Classrooms/OffiFirst Level Common Space/Classrooms/OffiFirst Level Common Space/Classrooms/OffiFirst Level Common Space/Classrooms/Offi
Rough-inRough-inRough-inRough-inRough-in
Wall Rough-in EP Level 1Wall Rough-in EP Level 1Wall Rough-in EP Level 1Wall Rough-in EP Level 1Wall Rough-in EP Level 1
Wall Close-in Inspections Level 1Wall Close-in Inspections Level 1Wall Close-in Inspections Level 1Wall Close-in Inspections Level 1Wall Close-in Inspections Level 1
OH MEP Layout Level 1OH MEP Layout Level 1OH MEP Layout Level 1OH MEP Layout Level 1OH MEP Layout Level 1
OH Mechanical Rough-in Level 1OH Mechanical Rough-in Level 1OH Mechanical Rough-in Level 1OH Mechanical Rough-in Level 1OH Mechanical Rough-in Level 1
OH Plumbing Rough-in Level 1OH Plumbing Rough-in Level 1OH Plumbing Rough-in Level 1OH Plumbing Rough-in Level 1OH Plumbing Rough-in Level 1
Rough-in Sprinkler Level 1Rough-in Sprinkler Level 1Rough-in Sprinkler Level 1Rough-in Sprinkler Level 1Rough-in Sprinkler Level 1
OH Electrical & Fire Alarm Rough-in Level 1OH Electrical & Fire Alarm Rough-in Level 1OH Electrical & Fire Alarm Rough-in Level 1OH Electrical & Fire Alarm Rough-in Level 1OH Electrical & Fire Alarm Rough-in Level 1
Install Fire Alarm Control Panel Level 1Install Fire Alarm Control Panel Level 1Install Fire Alarm Control Panel Level 1Install Fire Alarm Control Panel Level 1Install Fire Alarm Control Panel Level 1
Test Mechanical Piping Level 1Test Mechanical Piping Level 1Test Mechanical Piping Level 1Test Mechanical Piping Level 1Test Mechanical Piping Level 1
Perform HVAC air leakage test Level 1Perform HVAC air leakage test Level 1Perform HVAC air leakage test Level 1Perform HVAC air leakage test Level 1Perform HVAC air leakage test Level 1
Flush Mechanical Pipe Level 1Flush Mechanical Pipe Level 1Flush Mechanical Pipe Level 1Flush Mechanical Pipe Level 1Flush Mechanical Pipe Level 1
Review & Approve Duct Air Leakage and all HVACReview & Approve Duct Air Leakage and all HVACReview & Approve Duct Air Leakage and all HVACReview & Approve Duct Air Leakage and all HVACReview & Approve Duct Air Leakage and all HVAC
Install Heat Pumps Level 1Install Heat Pumps Level 1Install Heat Pumps Level 1Install Heat Pumps Level 1Install Heat Pumps Level 1
QC Punch-Out Inspection Level 1QC Punch-Out Inspection Level 1QC Punch-Out Inspection Level 1QC Punch-Out Inspection Level 1QC Punch-Out Inspection Level 1
Complete Punch - Out Items Above Ceiling LeveComplete Punch - Out Items Above Ceiling LeveComplete Punch - Out Items Above Ceiling LeveComplete Punch - Out Items Above Ceiling LevelComplete Punch - Out Items Above Ceiling Leve
Install OH Lighting Level 1Install OH Lighting Level 1Install OH Lighting Level 1Install OH Lighting Level 1Install OH Lighting Level 1
Pre-Final Inspection Level 1Pre-Final Inspection Level 1Pre-Final Inspection Level 1Pre-Final Inspection Level 1Pre-Final Inspection Level 1
Ceiling Close-in Inspections Level 1Ceiling Close-in Inspections Level 1Ceiling Close-in Inspections Level 1Ceiling Close-in Inspections Level 1Ceiling Close-in Inspections Level 1
Complete Pre-Final Items Above Ceiling Level 1Complete Pre-Final Items Above Ceiling Level 1Complete Pre-Final Items Above Ceiling Level 1Complete Pre-Final Items Above Ceiling Level 1Complete Pre-Final Items Above Ceiling Level 1
FinishesFinishesFinishesFinishesFinishes
Set Floor Control Lines Level 1Set Floor Control Lines Level 1Set Floor Control Lines Level 1Set Floor Control Lines Level 1Set Floor Control Lines Level 1
Frame Walls and Soffits Level 1Frame Walls and Soffits Level 1Frame Walls and Soffits Level 1Frame Walls and Soffits Level 1Frame Walls and Soffits Level 1
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 21 of 24
INL1-1020 Framing inspection Level 1
INL1-1050 Install Door frame Level 1
INL1-1060 Install insulation Level 1
INL1-1070 Start One side drywall Level 1
INL1-1080 Hang/tape/finish GWB Level 1
INL1-1100 Mud Block &Tape/Prime & First Coat of Paint Level 1
INL1-1190 Insulate Mechanical Pipe Level 1
INL1-1210 Install Acoustical Ceiling Frame Level 1
INL1-1290 Install acoustical ceiling Tile and drywall ceiling Level 1
INL1-1300 Install Kitchen Casework & Cabinets
INL1-1305 Install Kitchen Equipment & Fixtures
INL1-1310 Install Wall and Flooring finishes Level 1
INL1-1320 Install Doors & Hardware Level 1
INL1-1330 Install Mechanical Finishes Level 1
INL1-1340 Install Plumbing Finishes Level 1
INL1-1350 Final Painting Level 1
INL1-1360 Install Appliances Level 1
INL1-1370 Install Toilet Partitions Level 1
INL1-1380 Install FF & E / Connect MEP Level 1
INL1-1390 Install Casework, Millwork Level 1
INL1-1400 Final Clean level 1
Second Level Classrooms/Support/Labs/Library
Rough-in
INL2-1030 Wall Rough-in EP Level 2
INL2-1040 Wall Close-in Inspections Level 2
INL2-1090 OH MEP Layout Level 2
INL2-1110 Rough-in Sprinkler Level 2
INL2-1120 OH Plumbing Rough-in Level 2
INL2-1130 OH Mechanical Rough-in Level 2
INL2-1140 OH Electrical & Fire Alarm Rough-in Level 2
INL2-1150 Test Mechanical Piping Level 2
INL2-1160 Perform HVAC air leakage test Level 2
INL2-1170 Flush Mechanical Pipe Level 2
INL2-1190 Review & Approve Duct Air Leakage and all HVAC Control…
INL2-1200 Install Heat Pumps Level 2
INL2-1220 QC Punch-Out Inspection Level 2
INL2-1230 Complete Punch - Out Items Above Ceiling Level 2
INL2-1240 Install OH Lighting Level 2
INL2-1250 Pre-Final Inspection Level 2
INL2-1260 Ceiling Close-in Inspections Level 2
INL2-1270 Complete Pre-Final Items Above Ceiling Level 2
1d 28-Dec-26 28-Dec-26
5d 29-Dec-26 05-Jan-27
7d 08-Jan-27 19-Jan-27
7d 29-Dec-26 07-Jan-27
7d 27-Jan-27 04-Feb-27
7d 05-Feb-27 16-Feb-27
7d 24-Feb-27 04-Mar-27
5d 08-Mar-27 12-Mar-27
5d 23-Mar-27 29-Mar-27
15d 06-Apr-27 27-Apr-27
15d 28-Apr-27 18-May-27
5d 30-Mar-27 05-Apr-27
5d 06-Apr-27 12-Apr-27
5d 30-Mar-27 05-Apr-27
5d 06-Apr-27 12-Apr-27
5d 06-Apr-27 12-Apr-27
5d 13-Apr-27 20-Apr-27
5d 13-Apr-27 20-Apr-27
5d 13-Apr-27 20-Apr-27
5d 13-Apr-27 20-Apr-27
5d 21-Apr-27 27-Apr-27
91d 23-Dec-26 05-May-27
47d 26-Jan-27 01-Apr-27
7d 26-Jan-27 03-Feb-27
1d 04-Feb-27 04-Feb-27
3d 17-Feb-27 19-Feb-27
5d 22-Feb-27 26-Feb-27
5d 22-Feb-27 26-Feb-27
5d 22-Feb-27 26-Feb-27
5d 08-Mar-27 12-Mar-27
1d 01-Mar-27 01-Mar-27
3d 01-Mar-27 03-Mar-27
1d 02-Mar-27 02-Mar-27
3d 04-Mar-27 08-Mar-27
3d 16-Mar-27 18-Mar-27
1d 19-Mar-27 19-Mar-27
5d 22-Mar-27 26-Mar-27
5d 23-Mar-27 29-Mar-27
1d 29-Mar-27 29-Mar-27
1d 30-Mar-27 30-Mar-27
3d 30-Mar-27 01-Apr-27
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Framing inspection Level 1Framing inspection Level 1Framing inspection Level 1Framing inspection Level 1Framing inspection Level 1
Install Door frame Level 1Install Door frame Level 1Install Door frame Level 1Install Door frame Level 1Install Door frame Level 1
Install insulation Level 1Install insulation Level 1Install insulation Level 1Install insulation Level 1Install insulation Level 1
Start One side drywall Level 1Start One side drywall Level 1Start One side drywall Level 1Start One side drywall Level 1Start One side drywall Level 1
Hang/tape/finish GWB Level 1Hang/tape/finish GWB Level 1Hang/tape/finish GWB Level 1Hang/tape/finish GWB Level 1Hang/tape/finish GWB Level 1
Mud Block &Tape/Prime & First Coat of Paint LeveMud Block &Tape/Prime & First Coat of Paint LeveMud Block &Tape/Prime & First Coat of Paint LeveMud Block &Tape/Prime & First Coat of Paint LeveMud Block &Tape/Prime & First Coat of Paint Leve
Insulate Mechanical Pipe Level 1Insulate Mechanical Pipe Level 1Insulate Mechanical Pipe Level 1Insulate Mechanical Pipe Level 1Insulate Mechanical Pipe Level 1
Install Acoustical Ceiling Frame Level 1Install Acoustical Ceiling Frame Level 1Install Acoustical Ceiling Frame Level 1Install Acoustical Ceiling Frame Level 1Install Acoustical Ceiling Frame Level 1
Install acoustical ceiling Tile and drywall ceilingInstall acoustical ceiling Tile and drywall ceilingInstall acoustical ceiling Tile and drywall ceilingInstall acoustical ceiling Tile and drywall ceiling Install acoustical ceiling Tile and drywall ceiling
Install Kitchen Casework & CabinetsInstall Kitchen Casework & CabinetsInstall Kitchen Casework & CabinetsInstall Kitchen Casework & CabinetsInstall Kitchen Casework & Cabinets
Install Kitchen Equipment & FixturesInstall Kitchen Equipment & FixturesInstall Kitchen Equipment & FixturesInstall Kitchen Equipment & FixturesInstall Kitchen Equipment & Fixtures
Install Wall and Flooring finishes Level 1Install Wall and Flooring finishes Level 1Install Wall and Flooring finishes Level 1Install Wall and Flooring finishes Level 1Install Wall and Flooring finishes Level 1
Install Doors & Hardware Level 1Install Doors & Hardware Level 1Install Doors & Hardware Level 1Install Doors & Hardware Level 1Install Doors & Hardware Level 1
Install Mechanical Finishes Level 1Install Mechanical Finishes Level 1Install Mechanical Finishes Level 1Install Mechanical Finishes Level 1Install Mechanical Finishes Level 1
Install Plumbing Finishes Level 1Install Plumbing Finishes Level 1Install Plumbing Finishes Level 1Install Plumbing Finishes Level 1Install Plumbing Finishes Level 1
Final Painting Level 1Final Painting Level 1Final Painting Level 1Final Painting Level 1Final Painting Level 1
Install Appliances Level 1Install Appliances Level 1Install Appliances Level 1Install Appliances Level 1Install Appliances Level 1
Install Toilet Partitions Level 1Install Toilet Partitions Level 1Install Toilet Partitions Level 1Install Toilet Partitions Level 1Install Toilet Partitions Level 1
Install FF & E / Connect MEP Level 1Install FF & E / Connect MEP Level 1Install FF & E / Connect MEP Level 1Install FF & E / Connect MEP Level 1Install FF & E / Connect MEP Level 1
Install Casework, Millwork Level 1Install Casework, Millwork Level 1Install Casework, Millwork Level 1Install Casework, Millwork Level 1Install Casework, Millwork Level 1
Final Clean level 1Final Clean level 1Final Clean level 1Final Clean level 1Final Clean level 1
Second Level Classrooms/Support/Labs/LibSecond Level Classrooms/Support/Labs/LibSecond Level Classrooms/Support/Labs/LibSecond Level Classrooms/Support/Labs/LibSecond Level Classrooms/Support/Labs/Lib
Rough-inRough-inRough-inRough-inRough-in
Wall Rough-in EP Level 2Wall Rough-in EP Level 2Wall Rough-in EP Level 2Wall Rough-in EP Level 2Wall Rough-in EP Level 2
Wall Close-in Inspections Level 2Wall Close-in Inspections Level 2Wall Close-in Inspections Level 2Wall Close-in Inspections Level 2Wall Close-in Inspections Level 2
OH MEP Layout Level 2OH MEP Layout Level 2OH MEP Layout Level 2OH MEP Layout Level 2OH MEP Layout Level 2
Rough-in Sprinkler Level 2Rough-in Sprinkler Level 2Rough-in Sprinkler Level 2Rough-in Sprinkler Level 2Rough-in Sprinkler Level 2
OH Plumbing Rough-in Level 2OH Plumbing Rough-in Level 2OH Plumbing Rough-in Level 2OH Plumbing Rough-in Level 2OH Plumbing Rough-in Level 2
OH Mechanical Rough-in Level 2OH Mechanical Rough-in Level 2OH Mechanical Rough-in Level 2OH Mechanical Rough-in Level 2OH Mechanical Rough-in Level 2
OH Electrical & Fire Alarm Rough-in Level 2OH Electrical & Fire Alarm Rough-in Level 2OH Electrical & Fire Alarm Rough-in Level 2OH Electrical & Fire Alarm Rough-in Level 2OH Electrical & Fire Alarm Rough-in Level 2
Test Mechanical Piping Level 2Test Mechanical Piping Level 2Test Mechanical Piping Level 2Test Mechanical Piping Level 2Test Mechanical Piping Level 2
Perform HVAC air leakage test Level 2Perform HVAC air leakage test Level 2Perform HVAC air leakage test Level 2Perform HVAC air leakage test Level 2Perform HVAC air leakage test Level 2
Flush Mechanical Pipe Level 2Flush Mechanical Pipe Level 2Flush Mechanical Pipe Level 2Flush Mechanical Pipe Level 2Flush Mechanical Pipe Level 2
Review & Approve Duct Air Leakage and all HVACReview & Approve Duct Air Leakage and all HVACReview & Approve Duct Air Leakage and all HVACReview & Approve Duct Air Leakage and all HVACReview & Approve Duct Air Leakage and all HVAC
Install Heat Pumps Level 2Install Heat Pumps Level 2Install Heat Pumps Level 2Install Heat Pumps Level 2Install Heat Pumps Level 2
QC Punch-Out Inspection Level 2QC Punch-Out Inspection Level 2QC Punch-Out Inspection Level 2QC Punch-Out Inspection Level 2QC Punch-Out Inspection Level 2
Complete Punch - Out Items Above Ceiling LeveComplete Punch - Out Items Above Ceiling LeveComplete Punch - Out Items Above Ceiling LeveComplete Punch - Out Items Above Ceiling LeveComplete Punch - Out Items Above Ceiling Leve
Install OH Lighting Level 2Install OH Lighting Level 2Install OH Lighting Level 2Install OH Lighting Level 2Install OH Lighting Level 2
Pre-Final Inspection Level 2Pre-Final Inspection Level 2Pre-Final Inspection Level 2Pre-Final Inspection Level 2Pre-Final Inspection Level 2
Ceiling Close-in Inspections Level 2Ceiling Close-in Inspections Level 2Ceiling Close-in Inspections Level 2Ceiling Close-in Inspections Level 2Ceiling Close-in Inspections Level 2
Complete Pre-Final Items Above Ceiling Level 2Complete Pre-Final Items Above Ceiling Level 2Complete Pre-Final Items Above Ceiling Level 2Complete Pre-Final Items Above Ceiling Level 2Complete Pre-Final Items Above Ceiling Level 2
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 22 of 24
Finishes
INL2-1000 Set Floor Control Lines Level 2
INL2-1010 Frame Walls and Soffits Level 2
INL2-1020 Framing inspection Level 2
INL2-1050 Install insulation Level 2
INL2-1060 Start One side drywall Level 2
INL2-1070 Install Door frame Level 2
INL2-1080 Hang/tape/finish GWB Level 2
INL2-1100 Mud Block &Tape/Prime & First Coat of Paint Level 2
INL2-1180 Insulate Mechanical Pipe Level 2
INL2-1210 Install Acoustical Ceiling Frame Level 2
INL2-1280 Install acoustical ceiling Tile and drywall ceiling Level 2
INL2-1290 Install Doors & Hardware Level 2
INL2-1300 Install Wall and Flooring finishes Level 2
INL2-1310 Install Mechanical Finishes Level 2
INL2-1320 Final Painting Level 2
INL2-1330 Install Plumbing Finishes Level 2
INL2-1340 Install Toilet Partitions Level 2
INL2-1350 Install FF & E / Connect MEP Level 2
INL2-1360 Install Appliances Level 2
INL2-1370 Install Casework, Millwork Level 2
INL2-1380 Final Clean level 2
Third Level Classrooms/Support/Labs/Mental Health Suite
Rough-in
INL3-1030 Wall Rough-in EP Level 3
INL3-1040 Wall Close-in Inspections Level 3
INL3-1090 OH MEP Layout Level 3
INL3-1110 Rough-in Sprinkler Level 3
INL3-1120 OH Mechanical Rough-in Level 3
INL3-1130 OH Electrical & Fire Alarm Rough-in Level 3
INL3-1140 OH Plumbing Rough-in Level 3
INL3-1150 Hydro testing All Levels
INL3-1160 Test Mechanical Piping Level 3
INL3-1170 Perform HVAC air leakage test Level 3
INL3-1180 Flush Mechanical Pipe Level 3
INL3-1190 Review & Approve Duct Air Leakage and all HVAC Control…
INL3-1220 Install Heat Pumps Level 3
INL3-1230 QC Punch-Out Inspection Level 3
INL3-1240 Complete Punch - Out Items Above Ceiling Level 3
INL3-1250 Install OH Lighting Level 3
INL3-1260 Pre-Final Inspection Level 3
91d 23-Dec-26 05-May-27
2d 23-Dec-26 24-Dec-26
10d 28-Dec-26 11-Jan-27
1d 12-Jan-27 12-Jan-27
7d 25-Jan-27 02-Feb-27
7d 13-Jan-27 22-Jan-27
5d 13-Jan-27 20-Jan-27
7d 05-Feb-27 16-Feb-27
7d 24-Feb-27 04-Mar-27
7d 05-Mar-27 15-Mar-27
5d 16-Mar-27 22-Mar-27
5d 31-Mar-27 06-Apr-27
5d 14-Apr-27 21-Apr-27
5d 07-Apr-27 13-Apr-27
5d 07-Apr-27 13-Apr-27
5d 14-Apr-27 21-Apr-27
5d 14-Apr-27 21-Apr-27
5d 22-Apr-27 28-Apr-27
5d 22-Apr-27 28-Apr-27
5d 22-Apr-27 28-Apr-27
5d 22-Apr-27 28-Apr-27
5d 29-Apr-27 05-May-27
97d 08-Jan-27 27-May-27
47d 04-Feb-27 12-Apr-27
5d 04-Feb-27 10-Feb-27
1d 11-Feb-27 11-Feb-27
3d 24-Feb-27 26-Feb-27
6d 01-Mar-27 08-Mar-27
6d 01-Mar-27 08-Mar-27
6d 15-Mar-27 22-Mar-27
6d 01-Mar-27 08-Mar-27
0d 08-Mar-27
1d 09-Mar-27 09-Mar-27
3d 09-Mar-27 11-Mar-27
1d 10-Mar-27 10-Mar-27
3d 12-Mar-27 16-Mar-27
3d 25-Mar-27 29-Mar-27
1d 30-Mar-27 30-Mar-27
5d 31-Mar-27 06-Apr-27
5d 01-Apr-27 07-Apr-27
1d 07-Apr-27 07-Apr-27
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
FinishesFinishesFinishesFinishesFinishes
Set Floor Control Lines Level 2Set Floor Control Lines Level 2Set Floor Control Lines Level 2Set Floor Control Lines Level 2Set Floor Control Lines Level 2
Frame Walls and Soffits Level 2Frame Walls and Soffits Level 2Frame Walls and Soffits Level 2Frame Walls and Soffits Level 2Frame Walls and Soffits Level 2
Framing inspection Level 2Framing inspection Level 2Framing inspection Level 2Framing inspection Level 2Framing inspection Level 2
Install insulation Level 2Install insulation Level 2Install insulation Level 2Install insulation Level 2Install insulation Level 2
Start One side drywall Level 2Start One side drywall Level 2Start One side drywall Level 2Start One side drywall Level 2Start One side drywall Level 2
Install Door frame Level 2Install Door frame Level 2Install Door frame Level 2Install Door frame Level 2Install Door frame Level 2
Hang/tape/finish GWB Level 2Hang/tape/finish GWB Level 2Hang/tape/finish GWB Level 2Hang/tape/finish GWB Level 2Hang/tape/finish GWB Level 2
Mud Block &Tape/Prime & First Coat of Paint LevMud Block &Tape/Prime & First Coat of Paint LevMud Block &Tape/Prime & First Coat of Paint LevMud Block &Tape/Prime & First Coat of Paint LevMud Block &Tape/Prime & First Coat of Paint Lev
Insulate Mechanical Pipe Level 2Insulate Mechanical Pipe Level 2Insulate Mechanical Pipe Level 2Insulate Mechanical Pipe Level 2Insulate Mechanical Pipe Level 2
Install Acoustical Ceiling Frame Level 2Install Acoustical Ceiling Frame Level 2Install Acoustical Ceiling Frame Level 2Install Acoustical Ceiling Frame Level 2Install Acoustical Ceiling Frame Level 2
Install acoustical ceiling Tile and drywall ceilingInstall acoustical ceiling Tile and drywall ceilingInstall acoustical ceiling Tile and drywall ceilingInstall acoustical ceiling Tile and drywall ceilingInstall acoustical ceiling Tile and drywall ceiling
Install Doors & Hardware Level 2Install Doors & Hardware Level 2Install Doors & Hardware Level 2Install Doors & Hardware Level 2Install Doors & Hardware Level 2
Install Wall and Flooring finishes Level 2Install Wall and Flooring finishes Level 2Install Wall and Flooring finishes Level 2Install Wall and Flooring finishes Level 2Install Wall and Flooring finishes Level 2
Install Mechanical Finishes Level 2Install Mechanical Finishes Level 2Install Mechanical Finishes Level 2Install Mechanical Finishes Level 2Install Mechanical Finishes Level 2
Final Painting Level 2Final Painting Level 2Final Painting Level 2Final Painting Level 2Final Painting Level 2
Install Plumbing Finishes Level 2Install Plumbing Finishes Level 2Install Plumbing Finishes Level 2Install Plumbing Finishes Level 2Install Plumbing Finishes Level 2
Install Toilet Partitions Level 2Install Toilet Partitions Level 2Install Toilet Partitions Level 2Install Toilet Partitions Level 2Install Toilet Partitions Level 2
Install FF & E / Connect MEP Level 2Install FF & E / Connect MEP Level 2Install FF & E / Connect MEP Level 2Install FF & E / Connect MEP Level 2Install FF & E / Connect MEP Level 2
Install Appliances Level 2Install Appliances Level 2Install Appliances Level 2Install Appliances Level 2Install Appliances Level 2
Install Casework, Millwork Level 2Install Casework, Millwork Level 2Install Casework, Millwork Level 2Install Casework, Millwork Level 2Install Casework, Millwork Level 2
Final Clean level 2Final Clean level 2Final Clean level 2Final Clean level 2Final Clean level 2
Third Level Classrooms/Support/Labs/MeThird Level Classrooms/Support/Labs/MeThird Level Classrooms/Support/Labs/MeThird Level Classrooms/Support/Labs/MeThird Level Classrooms/Support/Labs/Me
Rough-inRough-inRough-inRough-inRough-in
Wall Rough-in EP Level 3Wall Rough-in EP Level 3Wall Rough-in EP Level 3Wall Rough-in EP Level 3Wall Rough-in EP Level 3
Wall Close-in Inspections Level 3Wall Close-in Inspections Level 3Wall Close-in Inspections Level 3Wall Close-in Inspections Level 3Wall Close-in Inspections Level 3
OH MEP Layout Level 3OH MEP Layout Level 3OH MEP Layout Level 3OH MEP Layout Level 3OH MEP Layout Level 3
Rough-in Sprinkler Level 3Rough-in Sprinkler Level 3Rough-in Sprinkler Level 3Rough-in Sprinkler Level 3Rough-in Sprinkler Level 3
OH Mechanical Rough-in Level 3OH Mechanical Rough-in Level 3OH Mechanical Rough-in Level 3OH Mechanical Rough-in Level 3OH Mechanical Rough-in Level 3
OH Electrical & Fire Alarm Rough-in Level 3OH Electrical & Fire Alarm Rough-in Level 3OH Electrical & Fire Alarm Rough-in Level 3OH Electrical & Fire Alarm Rough-in Level 3OH Electrical & Fire Alarm Rough-in Level 3
OH Plumbing Rough-in Level 3OH Plumbing Rough-in Level 3OH Plumbing Rough-in Level 3OH Plumbing Rough-in Level 3OH Plumbing Rough-in Level 3
  Hydro testing All LevelsHydro testing All LevelsHydro testing All LevelsHydro testing All LevelsHydro testing All Levels
Test Mechanical Piping Level 3Test Mechanical Piping Level 3Test Mechanical Piping Level 3Test Mechanical Piping Level 3Test Mechanical Piping Level 3
Perform HVAC air leakage test Level 3Perform HVAC air leakage test Level 3Perform HVAC air leakage test Level 3Perform HVAC air leakage test Level 3Perform HVAC air leakage test Level 3
Flush Mechanical Pipe Level 3Flush Mechanical Pipe Level 3Flush Mechanical Pipe Level 3Flush Mechanical Pipe Level 3Flush Mechanical Pipe Level 3
Review & Approve Duct Air Leakage and all HVAReview & Approve Duct Air Leakage and all HVAReview & Approve Duct Air Leakage and all HVAReview & Approve Duct Air Leakage and all HVAReview & Approve Duct Air Leakage and all HVA
Install Heat Pumps Level 3Install Heat Pumps Level 3Install Heat Pumps Level 3Install Heat Pumps Level 3Install Heat Pumps Level 3
QC Punch-Out Inspection Level 3QC Punch-Out Inspection Level 3QC Punch-Out Inspection Level 3QC Punch-Out Inspection Level 3QC Punch-Out Inspection Level 3
Complete Punch - Out Items Above Ceiling LevComplete Punch - Out Items Above Ceiling LevComplete Punch - Out Items Above Ceiling LevComplete Punch - Out Items Above Ceiling LevComplete Punch - Out Items Above Ceiling Lev
Install OH Lighting Level 3Install OH Lighting Level 3Install OH Lighting Level 3Install OH Lighting Level 3Install OH Lighting Level 3
Pre-Final Inspection Level 3Pre-Final Inspection Level 3Pre-Final Inspection Level 3Pre-Final Inspection Level 3Pre-Final Inspection Level 3
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 23 of 24
INL3-1270 Complete Pre-Final Items Above Ceiling Level 3
INL3-1280 Ceiling Close-in Inspections Level 3
Finishes
INL3-1000 Set Floor Control Lines Level 3
INL3-1010 Frame Walls and Soffits Level 3
INL3-1020 Framing inspection Level 3
INL3-1050 Install Door frame Level 3
INL3-1060 Install insulation Level 3
INL3-1070 Start One side drywall Level 3
INL3-1080 Hang/tape/finish GWB Level 3
INL3-1100 Mud Block &Tape/Prime & First Coat of Paint Level 3
INL3-1200 Insulate Mechanical Pipe Level 3
INL3-1210 Install Acoustical Ceiling Frame Level 3
INL3-1290 Install acoustical ceiling Tile and drywall ceiling Level 3
INL3-1300 Install Wall and Flooring finishes Level 3
INL3-1310 Install Doors & Hardware Level 3
INL3-1320 Install Mechanical Finishes Level 3
INL3-1330 Install Plumbing Finishes Level 3
INL3-1340 Final Painting Level 3
INL3-1350 Install Appliances Level 3
INL3-1360 Install Casework, Millwork Level 3
INL3-1370 Install FF & E / Connect MEP Level 3
INL3-1380 Install Toilet Partitions Level 3
INL3-1390 Final Clean level 3
Site Work
STE-1000 Install Bio-Retention Areas
STE-1010 Landscaping
STE-1020 Install Playground
STE-1030 Sidewalks, Curbs & Paving
STE-1040 Remove Traffic Control And Site/ Silt Fence
STE-1050 Install Final Coat of Asphalt
STE-1060 Install Site Lighting & Site Amenities
Closeout
CLO-1000 Commissioning
CLO-1010 Submission and approval of testing and air balance (TAB)
CLO-1020 Mechanical Report
CLO-1030 Electrical Report
CLO-1040 O&M Manuals
CLO-1050 Water Test
CLO-1060 As-built drawing
CLO-1070 Move in Furniture & Furnishings
3d 08-Apr-27 12-Apr-27
1d 08-Apr-27 08-Apr-27
97d 08-Jan-27 27-May-27
2d 08-Jan-27 11-Jan-27
10d 12-Jan-27 26-Jan-27
1d 27-Jan-27 27-Jan-27
6d 28-Jan-27 04-Feb-27
6d 05-Feb-27 12-Feb-27
6d 28-Jan-27 04-Feb-27
5d 17-Feb-27 23-Feb-27
6d 22-Apr-27 29-Apr-27
7d 16-Mar-27 24-Mar-27
5d 25-Mar-27 31-Mar-27
5d 09-Apr-27 15-Apr-27
5d 30-Apr-27 06-May-27
5d 07-May-27 13-May-27
5d 19-Apr-27 23-Apr-27
5d 07-May-27 13-May-27
5d 07-May-27 13-May-27
5d 14-May-27 20-May-27
5d 14-May-27 20-May-27
5d 14-May-27 20-May-27
5d 14-May-27 20-May-27
5d 21-May-27 27-May-27
87d 02-Mar-27 02-Jul-27
20d 02-Mar-27 29-Mar-27
20d 15-Apr-27 13-May-27
5d 14-May-27 20-May-27
20d 14-May-27 11-Jun-27
3d 14-Jun-27 16-Jun-27
5d 14-Jun-27 18-Jun-27
15d 14-Jun-27 02-Jul-27
305d 16-Dec-26 07-Mar-28
120d 15-Jan-27 08-Jul-27
10d 24-Jun-27 08-Jul-27
5d 01-Jul-27 08-Jul-27
5d 01-Jul-27 08-Jul-27
20d 16-Dec-26 14-Jan-27
1d 14-May-27 14-May-27
5d 14-May-27 20-May-27
15d 21-May-27 10-Jun-27
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Complete Pre-Final Items Above Ceiling Level Complete Pre-Final Items Above Ceiling Level Complete Pre-Final Items Above Ceiling Level Complete Pre-Final Items Above Ceiling Level 3Complete Pre-Final Items Above Ceiling Level
Ceiling Close-in Inspections Level 3Ceiling Close-in Inspections Level 3Ceiling Close-in Inspections Level 3Ceiling Close-in Inspections Level 3Ceiling Close-in Inspections Level 3
FinishesFinishesFinishesFinishesFinishes
Set Floor Control Lines Level 3Set Floor Control Lines Level 3Set Floor Control Lines Level 3Set Floor Control Lines Level 3Set Floor Control Lines Level 3
Frame Walls and Soffits Level 3Frame Walls and Soffits Level 3Frame Walls and Soffits Level 3Frame Walls and Soffits Level 3Frame Walls and Soffits Level 3
Framing inspection Level 3Framing inspection Level 3Framing inspection Level 3Framing inspection Level 3Framing inspection Level 3
Install Door frame Level 3Install Door frame Level 3Install Door frame Level 3Install Door frame Level 3Install Door frame Level 3
Install insulation Level 3Install insulation Level 3Install insulation Level 3Install insulation Level 3Install insulation Level 3
Start One side drywall Level 3Start One side drywall Level 3Start One side drywall Level 3Start One side drywall Level 3Start One side drywall Level 3
Hang/tape/finish GWB Level 3Hang/tape/finish GWB Level 3Hang/tape/finish GWB Level 3Hang/tape/finish GWB Level 3Hang/tape/finish GWB Level 3
Mud Block &Tape/Prime & First Coat of PaintMud Block &Tape/Prime & First Coat of PaintMud Block &Tape/Prime & First Coat of PaintMud Block &Tape/Prime & First Coat of PaintMud Block &Tape/Prime & First Coat of Paint
Insulate Mechanical Pipe Level 3Insulate Mechanical Pipe Level 3Insulate Mechanical Pipe Level 3Insulate Mechanical Pipe Level 3Insulate Mechanical Pipe Level 3
Install Acoustical Ceiling Frame Level 3Install Acoustical Ceiling Frame Level 3Install Acoustical Ceiling Frame Level 3Install Acoustical Ceiling Frame Level 3Install Acoustical Ceiling Frame Level 3
Install acoustical ceiling Tile and drywall ceilinInstall acoustical ceiling Tile and drywall ceilinInstall acoustical ceiling Tile and drywall ceilinInstall acoustical ceiling Tile and drywall ceilingInstall acoustical ceiling Tile and drywall ceilin
Install Wall and Flooring finishes Level 3Install Wall and Flooring finishes Level 3Install Wall and Flooring finishes Level 3Install Wall and Flooring finishes Level 3Install Wall and Flooring finishes Level 3
Install Doors & Hardware Level 3Install Doors & Hardware Level 3Install Doors & Hardware Level 3Install Doors & Hardware Level 3Install Doors & Hardware Level 3
Install Mechanical Finishes Level 3Install Mechanical Finishes Level 3Install Mechanical Finishes Level 3Install Mechanical Finishes Level 3Install Mechanical Finishes Level 3
Install Plumbing Finishes Level 3Install Plumbing Finishes Level 3Install Plumbing Finishes Level 3Install Plumbing Finishes Level 3Install Plumbing Finishes Level 3
Final Painting Level 3Final Painting Level 3Final Painting Level 3Final Painting Level 3Final Painting Level 3
Install Appliances Level 3Install Appliances Level 3Install Appliances Level 3Install Appliances Level 3Install Appliances Level 3
Install Casework, Millwork Level 3Install Casework, Millwork Level 3Install Casework, Millwork Level 3Install Casework, Millwork Level 3Install Casework, Millwork Level 3
Install FF & E / Connect MEP Level 3Install FF & E / Connect MEP Level 3Install FF & E / Connect MEP Level 3Install FF & E / Connect MEP Level 3Install FF & E / Connect MEP Level 3
Install Toilet Partitions Level 3Install Toilet Partitions Level 3Install Toilet Partitions Level 3Install Toilet Partitions Level 3Install Toilet Partitions Level 3
Final Clean level 3Final Clean level 3Final Clean level 3Final Clean level 3Final Clean level 3
Site WorkSite WorkSite WorkSite WorkSite Work
Install Bio-Retention AreasInstall Bio-Retention AreasInstall Bio-Retention AreasInstall Bio-Retention AreasInstall Bio-Retention Areas
LandscapingLandscapingLandscapingLandscapingLandscaping
Install PlaygroundInstall PlaygroundInstall PlaygroundInstall PlaygroundInstall Playground
Sidewalks, Curbs & PavingSidewalks, Curbs & PavingSidewalks, Curbs & PavingSidewalks, Curbs & PavingSidewalks, Curbs & Paving
Remove Traffic Control And Site/ Silt FencRemove Traffic Control And Site/ Silt FencRemove Traffic Control And Site/ Silt FencRemove Traffic Control And Site/ Silt FencRemove Traffic Control And Site/ Silt Fenc
Install Final Coat of AsphaltInstall Final Coat of AsphaltInstall Final Coat of AsphaltInstall Final Coat of AsphaltInstall Final Coat of Asphalt
Install Site Lighting & Site AmenitiesInstall Site Lighting & Site AmenitiesInstall Site Lighting & Site AmenitiesInstall Site Lighting & Site AmenitiesInstall Site Lighting & Site Amenities
CloseoutCloseoutCloseoutCloseoutCloseout
CommissioningCommissioningCommissioningCommissioningCommissioning
Submission and approval of testing and Submission and approval of testing and Submission and approval of testing andSubmission and approval of testing and Submission and approval of testing and
Mechanical ReportMechanical ReportMechanical ReportMechanical ReportMechanical Report
Electrical ReportElectrical ReportElectrical ReportElectrical ReportElectrical Report
O&M ManualsO&M ManualsO&M ManualsO&M ManualsO&M Manuals
Water TestWater TestWater TestWater TestWater Test
As-built drawingAs-built drawingAs-built drawingAs-built drawingAs-built drawing
Move in Furniture & FurnishingsMove in Furniture & FurnishingsMove in Furniture & FurnishingsMove in Furniture & FurnishingsMove in Furniture & Furnishings
ID Name
Planned
Duration Start Finish
Project Name: Brent Elementary School Data Date: 06-Nov-23
Current  Milestones
Progress Summary
Critical
Brent Elementary School Schedule
Page 24 of 24
CLO-1080 Training
CLO-1090 Building Final Occupancy Inspections
CLO-1100 DOB Certificate Occupancy - Zoning
CLO-1110 Health Department Approvals
CLO-1120 Substantial Completion
CLO-1130 Complete Punchlist
CLO-1140 Teacher Move-in
CLO-1150 Student Start
CLO-1160 Mechanical Support Heating/Cooling After Substantial Co…
CLO-1170 Warranties/Record Drawings/Attic Stock & All Closeout D…
CLO-1180 Final Completion
Administrative Completion
ADM-1020 Administrative Closeout Documentation
5d 11-Jun-27 17-Jun-27
2d 09-Jul-27 12-Jul-27
2d 13-Jul-27 14-Jul-27
1d 15-Jul-27 15-Jul-27
0d 15-Jul-27
45d 16-Jul-27 17-Sep-27
0d 15-Jul-27
0d 12-Aug-27
160d 16-Jul-27 07-Mar-28
132d 16-Jul-27 17-Jan-28
0d 17-Jan-28
6d 08-Mar-28 15-Mar-28
6d 08-Mar-28 15-Mar-28
2023 2024 2025 2026 2027 2028
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
TrainingTrainingTrainingTrainingTraining
Building Final Occupancy InspectionsBuilding Final Occupancy InspectionsBuilding Final Occupancy InspectionsBuilding Final Occupancy InspectionsBuilding Final Occupancy Inspections
DOB Certificate Occupancy - ZoningDOB Certificate Occupancy - ZoningDOB Certificate Occupancy - ZoningDOB Certificate Occupancy - ZoningDOB Certificate Occupancy - Zoning
Health Department ApprovalsHealth Department ApprovalsHealth Department ApprovalsHealth Department ApprovalsHealth Department Approvals
  Substantial CompletionSubstantial CompletionSubstantial CompletionSubstantial CompletionSubstantial Completion
Complete PunchlistComplete PunchlistComplete PunchlistComplete PunchlistComplete Punchlist
  Teacher Move-inTeacher Move-inTeacher Move-inTeacher Move-inTeacher Move-in
  Student StartStudent StartStudent StartStudent StartStudent Start
Mechanical Support HeMechanical Support HeMechanical Support HeMechanical Support HeMechanical Support He
Warranties/Record DrawinWarranties/Record DrawinWarranties/Record DrawinWarranties/Record DrawinWarranties/Record Drawin
  Final CompletionFinal CompletionFinal CompletionFinal CompletionFinal Completion
Administrative CompleAdministrative CompleAdministrative ComplAdministrative CompleAdministrative Comple
Administrative CloseoAdministrative CloseoAdministrative CloseoAdministrative CloseouAdministrative Closeo
ID Name
Planned
Duration Start Finish
Exhibit F
SBE Subcontracting Plan

BRENT ES MODERNIZATION

GUARANTEED MAXIMUM PRICE (GMP) PROPOSAL

SECTION 11 – CBE/SBE
SUBCONTRACTING PLAN

DRAFT - WILL BE UPDATED TO REFLECT FINAL GMP NEGOTIATIONS
SECTION 8 - CBE/SBE
SUBCONTRACTNG PLAN
Revised October 9, 2025
29
BRENT ELEMENTARY SCHOOL MODERNIZATION | DCAM-23-CS-RFP-0016 | SMOOTDC-DLR GROUP
NOTE: This is a Design-Build contract with no bid packages at this time. Subcontract values are estimates and are not based on actual
bids. SBE contract amounts and lower tier participation will be verified and submitted at time of GMP .

ȁ‡˜‹•‡†ƒ”
ŠʹͲʹ͵
SECTION 1.BENEFICIARY AND SOLICITATION/CONTRACT/SPORTS WAGERING
APPLICANTINFORMATION
Section 1A. BENEFICIARY INFORMATION
Contact #: 202-243-6688__ Email address: pmjohnson@smootbuilds.com Company: Smoot Construction Co. of Washington DC
Street Address: 5335 Wisconsin Avenue NW, Suite 940 City/ State/ Zip Code: _Washington, DC 20015________
Company’s point of contact for agency contract, private project, or Sports Wagering Licensee:
Title: _Vice President__________
Email address: pmjohnson@smootbuilds.com
Point of Contact: Pamela Murray Johnson_
Contact #: _202-243-6688____________
Street Address: 5335 Wisconsin Avenue NW, Suite 940____
Section 1B. SOLICITATION/CONTRACT/SPORTS WAGERING APPLICANT INFORMATION
Solicitation /Contract/ApplicantNo.: _DCAM-23-CS-RFP-0017___
Agency: _DGS____________
Please select all the applicable subcontracting requirements for
this solicitation:
35% Subcontracting Requirement
50% Subcontracting Requirement
DSLBD approved an adjusted subcontracting requirement:
¾ Adjusted Subcontracting Requirement: ____%
Solicitation Due Date: _July 14, 2023___________
Total Dollar Amount of Contract: _$72,500,000__________
Total Value of ALL CBE Subcontracts: _$25,375,000________
(Include all lower tiers)
I affirm that the value of all my CBE Subcontracts meets or
exceeds the subcontracting requirement required under this
solicitation or contract. Further, I understand that DSLBD will
only provide credit towards my SBE Subcontracting Requirement
for work whereby a CBE provided a commercially useful function
with its own organization and resources.
I AGREE
I DISAGREE
Section 1C. CBE BENEFICIARY (ONLY COMPLETE IF THE BENEFICIARY IS A CERTIFIED BUSINESS ENTERPRISE)

If the Beneficiary is a Certified Business Enterprise, select all that apply and provide the following information:
I am a CBE that WILL perform 100% of the contracting effort with my own organization and resources and will not subcontract any
portion of the contract. Therefore, I am NOT required to submit an SBE Subcontracting Plan that demonstrates subcontracting.
I am a CBE that WILL NOT perform 100% of the contracting effort with my own organization and resources and will subcontract a
portion of the contract. Therefore, I understand I am required to submit an SBE Subcontracting Plan (located in Section on 2) that
demonstrates that the required subcontracting amount, as indicated above, will go to qualified CBEs.
Please include the percentage of the contract the CBE Prime will perform under the contract or project.
¾ The CBE Prime will self-perform of the contra ct’s total dollar volume of the contract or project.
Please provide the current CBE Certification Number of the CBE Prime.
¾ CBE Certification No. ______________
X
X
X
LXR63883052024
DCAM-23-CS-RFP-0016 September 1, 2023
Department of General Servicees $82,000,000
$28,700,000
$716,114
$995,000
25%
3939 Wisconsin Avenue NW 2nd Floor
Washington, DC 20016
3939 Wisconsin Avenue NW 2nd Floor
$5,940,809.00
$3,294,922.00
:4%
$13,522,616
$6,128,039
LXR20781062027
$14,208,101
$5,399,689
$5,498,700
$84,154,494
$33,273,037
6%
$33,414,037
$87,495,111
$33,564,229

SBE SUBCONTRACTNG PLAN | Revised March 2023
BENEFICIARY ATTESTATION

I declare, certify, verif y, attest , and state under penalty of perjury that the i nformation provided above is
true and correct to the best of my knowl edge a nd belief. Pursuant to D.C. Offici al Code § 22 -2402, I
understand that a person convicted of perjury shall be fined not mor e than $5, 000 or imprisoned for not
more than 10 years, or both. I understand that any false or fraudulent statement that I pro vide or assert
may be grounds for re vocation of my CBE registration pursuant to D.C. Official Co de § 2-218.63. Further,
a Prime Contractor, Dev eloper, CBE, Certified Joint Venture , or Sports Wagering Licensee that fails to
comply with the requirements of the Small and Certified Business Enterprise Development and Assistance
Amendment Act of 20 05, as amended, (D.C. Law 20 -108) (the “Act”), sha ll be subje ct to pena lties as
outlined in the Act.

PRINT NAME: ____________________________ SIGNATURE: ____________________________
JOB TITLE: ____________________________ DATE: ____________________________

Section 2. SBE/CBE SUBCONTRACTORS (FOR EACH TIER):

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
function by the CBE
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____

DLR Group of DC PC
701 8TH STREET
NW,Washington,DC 20001
202-393-6445
Architecture & MEP
Engineering
Rachel Chung
Principal Owner
Wiles Mensch
Corporation - D.C.
rchung@dlrgroup.com
Bradley Site Design, Inc
510 8TH STREET
SE,WASHINGTON,DC 20003
LS17119052025
1010 Wisconsin Ave
NW,WASHINGTON,DC
20007
LSDZ22309092025
Civil Engineering
Landscape Architecture
1st to DLR
1st to DLR
$747,024
89
X
$36,965
$14,728
LZR43043092024
Pamela Murray Johnson
Vice President
11/10/2023
$3,443,783.00
50%
$192,270
$77,103
2/6/2024
___________________ _________________ ____ $ ________________ ________________ ____

20007
Schnabel Engineering DC,
Inc.
4200 WISCONSIN AVENUE
NW,Washington,DC 20016
L22378032026
$49,850
Geotechnical Engineering
1st to DLR
01/17/2025

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
function by the CBE
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

DLR Group of DC PC
701 8TH STREET
NW,Washington,DC 20001
202-393-6445
Architecture & MEP
Engineering
Rachel Chung
Principal Owner
rchung@dlrgroup.com
$747,024
89
X
LZR43043092024
$3,443,783.00
50%
1/28/2025
X
$4,31,5500
9/29/2025
BRENT ELEMENTARY SCHOOL MODERNIZATION | DCAM-23-CS-RFP-0016 | SMOOTDC-DLR GROUP

ȁ‡˜‹•

$4,315,500
10/09/2025
LZR3190903
2028
31
BRENT ELEMENTARY SCHOOL MODERNIZATION | DCAM-23-CS-RFP-0016 | SMOOTDC-DLR GROUP
NOTE: This is a Design-Build contract with no bid packages at this time. Subcontract values are estimates and are not based on actual
bids. SBE contract amounts and lower tier participation will be verified and submitted at time of GMP .


ȁ‡˜‹•‡†ƒ”
ŠʹͲʹ͵

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
function by the CBE
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
JJ Prime 1421 Kenilworth Ave
NE, Washington, DC
20019
LSD64283022025 $1,151,403 Site Utilities
Juan Aguirre X
Operations
202-399-0060
______contact@jjprimeservices.com
*TBD
First Choice Masonry 1818 New York Ave
NE, Washington, DC
20002
LSDZ23893122024 $2,296,000 Masonry
Cory Jones X
President
202-529-0195
______cory@firstchoicemasonry.net
*TBD
Earthwork
$1,446,432
Site Demo &
Pavement Patching
2585 RHODE ISLAND
AVE NE,Washington,DC
20018
District
Logistics, LLC
LSDZRE85401042026
$70,000
Robert Terrell
Owner
202-302-9506
mydclogistics@gmail.com
$1,284,467
DGC Cleaning Services
640 KENYON
STREET
NW,Washington,D
C 20010
LSDZRE205
41042027
$141,000
Cleaning
Jorge Flores
Principal
202-903-9713
info@dgccleaning.com

SBE SUBCONTRACTNG PLAN | Revised March 2023

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
function by the CBE
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
Regional Contracting
Services, LLC
Beverly L Thomas
Owner
202-234-8981
719 KENNEDY STREET
NW,WASHINGTON,DC
20011
LSDZ71109092025
$254,000
Carpentry &
Cleaning Labor
info@regionalcontractingsvcs.com
X
Goel DC, LLC
Prabodh Goel
Owner
202-567-3900
info@goeldc.com
3109 MARTIN
LUTHER KING JR
AVENUE
SE,Washington,DC
20032
LSZ18780062026
$876,770
Haz Mat
Abatement &
Demolition

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
All Pro Glass, LLC
Allen Proctor;Leopole Tandjong
Owner
301-536-3328
rproctor@allproglassllc.com
X
5650 3RD STREET
NE,Washington,DC
20011
LS90900012025
$45,000
Glass & Glazing
$119,800
and Facade
Panels
$4,357,200
BRENT ELEMENTARY SCHOOL MODERNIZATION | DCAM-23-CS-RFP-0016 | SMOOTDC-DLR GROUP

ȁ‡˜‹•

LSDZ9569
3092028
LS752170120
28

SBE SUBCONTRACTNG PLAN | Revised March 2023

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
function by the CBE
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
L. A. Howard Construction
Company
1016 5TH STREET
NE,WASHINGTON
,DC 20002
LSDZRE30
376072026
LaZerrick Howard
Principal Owner
202-543-5399
lhoward@lahcco.com
$58,650
Concrete
Creation Steel Fabricators
6400 GEORGIA
AVENUE
NW,Washington,DC
20012
LS430730
82025
$78,000
Steel
Richard Parker
Principal Owner
540-656-3300
richardparker@creationsteel.com
X
X
$3,649,278
$2,953,665
BRENT ELEMENTARY SCHOOL MODERNIZATION | DCAM-23-CS-RFP-0016 | SMOOTDC-DLR GROUP

ȁ‡˜‹•

2318 18TH STREET NW
Washington,DC 20009
LS48483092
028

SBE SUBCONTRACTNG PLAN | Revised March 2023

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
function by the CBE
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
HS Solutions, LLC
4201
CONNECTICUT
AVENUE
NW,WASHINGTON
,DC 20008
LSD58782
112027
$187,000
Telecommunications, IT,
AV
Jack Hsin
Principal Owner
202-652-1040
info@hssolutions-llc.com
X
Forsythe DC Inc
$176,918.00
2412 MINNESOTA
AVENUE SE
Washington,DC
20020
LSZ39978
082027
Caulking
Sarah Lovell;Justin Lovell
Principal
202-579-2573
info@forsythedc.com
X
Masonry & Caulking
$2,655,939
$745,012
BRENT ELEMENTARY SCHOOL MODERNIZATION | DCAM-23-CS-RFP-0016 | SMOOTDC-DLR GROUP

ȁ‡˜‹•

SBE SUBCONTRACTNG PLAN | Revised March 2023

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
function by the CBE
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

DLR Group of DC PC
701 8TH STREET
NW,Washington,DC 20001
202-393-6445
Architecture & MEP
Engineering
Rachel Chung
Principal Owner
rchung@dlrgroup.com
$747,024
89
X
LZR43043092024
$3,443,783.00
50%

ow

ow
DES-DC Inc
$1,730,348.00
1228 31ST STREET
NW,WASHINGTON,
DC 20007
LS7339707
2025
Furniture/FF&E
Robert Moller
Principal
2027335007
bob.moller@des-dc.com
X
Fort Myer
2237 33RD STREET
NE,WASHINGTON,
DC 20018
LZXM0197
6102026
$97,076.00
Paving
Jose Rodriguez;Lewis Shrensky
Principal
2026369535
fortmyer@fortmyer.com
X
LS872830
92028
$1,672,420
TPM Group, LLC
1301 K STREET
NW,WASHINGTON
,DC 20005
LSDZ7816
5092027
$148,110
Move/Relocation
Services
Lincoln Tyson
Principal
202-775-0096
lincolntyson@icloud.com
BRENT ELEMENTARY SCHOOL MODERNIZATION | DCAM-23-CS-RFP-0016 | SMOOTDC-DLR GROUP

ȁ‡˜‹•

SBE SUBCONTRACTNG PLAN | Revised March 2023

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
function by the CBE
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

DLR Group of DC PC
701 8TH STREET
NW,Washington,DC 20001
202-393-6445
Architecture & MEP
Engineering
Rachel Chung
Principal Owner
rchung@dlrgroup.com
$747,024
89
X
LZR43043092024
$3,443,783.00
50%

ow

ow
Dynamic Contracting
806 DOUGLAS
STREET NE
WASHINGTON,DC
20018
LSDZ3385
5062025
$306,469.00
Carpentry
Herminia P Orellana;Maria Cartagena
Principal
mariac@dynamic-contracting.com
X
Cap8Construction
5786 2ND STREET
NE,WASHINGTON,
DC 20011
LSDRE678
41102027
Doors/Frames
/Hardware
Lisa Williams
Principal
2025381777
lisa@cap8doors.com
X
LDZ506240
62028
$231,108
$906,885
BRENT ELEMENTARY SCHOOL MODERNIZATION | DCAM-23-CS-RFP-0016 | SMOOTDC-DLR GROUP

ȁ‡˜‹•

31
BRENT ELEMENTARY SCHOOL MODERNIZATION | DCAM-23-CS-RFP-0016 | SMOOTDC-DLR GROUP
NOTE: This is a Design-Build contract with no bid packages at this time. Subcontract values are estimates and are not based on actual
bids. SBE contract amounts and lower tier participation will be verified and submitted at time of GMP .


ȁ‡˜‹•‡†ƒ”
ŠʹͲʹ͵

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
function by the CBE
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
JJ Prime 1421 Kenilworth Ave
NE, Washington, DC
20019
LSD64283022025 $1,151,403 Site Utilities
Juan Aguirre X
Operations
202-399-0060
______contact@jjprimeservices.com
*TBD
First Choice Masonry 1818 New York Ave
NE, Washington, DC
20002
LSDZ23893122024 $2,296,000 Masonry
Cory Jones X
President
202-529-0195
______cory@firstchoicemasonry.net
*TBD
Earthwork
$1,446,432
Site Demo &
Pavement Patching
2585 RHODE ISLAND
AVE NE,Washington,DC
20018
District
Logistics, LLC
LSDZRE85401042026
$70,000
Robert Terrell
Owner
202-302-9506
mydclogistics@gmail.com
$1,284,467
GOEL DC LLC
3109 MARTIN
LUTHER KING JR
AVENUE SE
Washington,DC
20032
LSZ18780
062026
Prabodh Goel
Principal
2025673900
info@goeldc.com
Demolition
$3,700,370
Fort Myer Construction
Corporation
2237 33RD
STREET
NE,WASHINGTON,
DC 20018
LZXM01976
102026
$150,192
Paving
Jose Rodriguez;Lewis Shrensky
Principal
202-636-9535
fortmyer@fortmyer.com

SBE SUBCONTRACTNG PLAN | Revised March 2023

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
function by the CBE
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

DLR Group of DC PC
701 8TH STREET
NW,Washington,DC 20001
202-393-6445
Architecture & MEP
Engineering
Rachel Chung
Principal Owner
rchung@dlrgroup.com
$747,024
89
X
LZR43043092024
$3,443,783.00
50%

ow

ow
Joseph J. Magnolia, Inc.
600 GALLATIN
STREET NE
WASHINGTON,DC
20017
LX9732210
2027
$746,500.00
Site Utilities
John D Magnolia
Principal
2028298510
ddisque@magnolia-companies.com
X
Schnabel Engineering
DC, Inc.
$5,473.00
4200 WISCONSIN
AVENUE NW
Washington,DC
20016
L2237803
2026
Geothecnical
Bill Khouri
Principal
2026774120
bkhouri@schnabeldc.com
X
$634,020
BRENT ELEMENTARY SCHOOL MODERNIZATION | DCAM-23-CS-RFP-0016 | SMOOTDC-DLR GROUP

ȁ‡˜‹•

SBE SUBCONTRACTNG PLAN | Revised March 2023

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
function by the CBE
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

DLR Group of DC PC
701 8TH STREET
NW,Washington,DC 20001
202-393-6445
Architecture & MEP
Engineering
Rachel Chung
Principal Owner
rchung@dlrgroup.com
$747,024
89
X
LZR43043092024
$3,443,783.00
50%

ow

ow
P & D Contractors, LLC
6115 CHILLUM
PLACE NE
WASHINGTON,DC
20011
LSD15091
092025
$3,682,333.00
Drywall/Ceilings
Sean Juman
Principal
2027226800
panddcontractors@comcast.net
X
Allstate Floors
6031 KANSAS
AVENUE NW
WASHINGTON,
DC 20011
LSDRE452
41052027
Flooring
Kristin Ortiz
Principal
202-291-5960
jgreenwell@allstatefloors.com
X
LSD5158
2082028
$3,653,281
$886,412
BRENT ELEMENTARY SCHOOL MODERNIZATION | DCAM-23-CS-RFP-0016 | SMOOTDC-DLR GROUP

ȁ‡˜‹•

SBE SUBCONTRACTNG PLAN | Revised March 2023

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
function by the CBE
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____
___________________ _________________ ____ $ ________________ ________________ ____

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

LOWER TIER
CBE Subcontractor
Name
Address Certification No. Price to be paid to the
CBE Subcontractor
Description of
subcontract scope of
work to be performed
that shall be for a
commercially useful
Tier
(e.g., 1st,
2nd, 3rd,
4th, etc.)

CBE Subcontractor
Company Name Address Certification
No.
Price to be paid to the
CBE Subcontractor
Description of subcontract scope
of work to be performed that shall
be for a commercially useful
function by the CBE
___________________ _________________ ____ ________________ ________________

SBE/CBE Point of Contact:

CBE Subcontractor Self-Performance Indicator:

Name: _________

Title: _______

Telephone Number: ________

Email Address: ________

This CBE will perform the ENTIRE subcontract with its
own organization and resources.
This CBE will subcontract a portion of the subcontract and
will perform ____% of the subcontract’s total dollar volume.
NOTE: If the CBE will not self-perform 100% of the
subcontract, it must list each lower-tier CBE
subcontractor below.

DLR Group of DC PC
701 8TH STREET
NW,Washington,DC 20001
202-393-6445
Architecture & MEP
Engineering
Rachel Chung
Principal Owner
rchung@dlrgroup.com
$747,024
89
X
LZR43043092024
$3,443,783.00
50%

ow

ow
Precision Wall Tech
605 RALEIGH
PLACE SE
WASHINGTON,DC
20032
LSDZ4039
3112027
$407,912.00
Paint & Wall
Coverings
Cindy Athey
Principal
2023300955
cathey@precisionwall.com
X
William P. Gelberg
Inc./Gelberg Signs
$377,979.00
6511 CHILLUM
PLACE NW
WASHINGTON,DC
20012
LSXM366
84062027
Signage
James Lerner;Hanh Lerner
Principal
2028827733
execacct@gelbergsigns.com
X
$380,300
HRGM
Corporation
2021 Shannon
Pl SE
Washington
DC 20020
LSZXR599
45072027
$2,054,064
Roofing/Waterproofing
Rachna Butani Bhatt
Director
202-889-8400
butani@hrgm.com
BRENT ELEMENTARY SCHOOL MODERNIZATION | DCAM-23-CS-RFP-0016 | SMOOTDC-DLR GROUP

ȁ‡˜‹•

35
BRENT ELEMENTARY SCHOOL MODERNIZATION | DCAM-23-CS-RFP-0016 | SMOOTDC-DLR GROUP
NOTE: This is a Design-Build contract with no bid packages at this time. Subcontract values are estimates and are not based on actual
bids. SBE contract amounts and lower tier participation will be verified and submitted at time of GMP .


ȁ‡˜‹•‡†ƒ”
ŠʹͲʹ͵
AGENCY CONTRACT AWARD

Agency: ________
Prime Contractor: ________
Contract Number: ________
Date SBE Subcontracting Plan Accepted: ________
Date agency contract signed: ________

Anticipated Start Date of Contract: ________
Anticipated End Date of Contract: ________

Total Dollar Amount of Contract: $________

*Design-Build must include total contract amount for both
design and build phase of the project.

35% of the Total Contract Amount: $________

50% of Total Dollar Amount of Contract: $______________
(pursuant to D.C. Law 24-39)

Total Amount of All SBE/CBE Subcontracts: $________
(include every tier)

(ضif applies)
Base Period Contract – Option/Extension Period: ________
Multi-year Contract
First Year (Period) of Contract: ________
Current Year (Period) of Contract: ________
Design-Build – Date of Guaranteed Contract: ________

Check if prime contractor is a CBE and will perform the
ENTIRE government-assisted project (agency contract) with its
own organization and resources and NOT subcontract any portion
of the services or goods.

PRIVATE PROJECT SUBSIDY AWARD

Agency Providing Subsidy: ________
District Subsidy: ________
Developer: ________
Amount of District Subsidy: ________
Date District Subsidy Provided/ contract signed: ________

Anticipated Start Date of Project: ________
Anticipated End Date of Project: ________

Project Name: ________
Project Address: ________

Total Development Project Budget: $________
(include pre-construction and construction costs)

35% of the Total Development Project Budget: $________

50% of Total Dollar Amount of Contract: $______________
(pursuant to D.C. Law 24-39)

Total Amount of All SBE/CBE Subcontracts: $________
(include every lower tier)

Check if developer is a CBE and will perform the ENTIRE
government-assisted project (private project) with its own
organization and resources and NOT subcontract any portion of
services or goods.

AGENCY CONTRACTING OFFICER’S AFFIRMATION OR AGENCY PROJECT MANAGER’S AFFIRMATION
(ضضwhich applies)

The below Agency Contracting Officer or Agency Project Manager affirms the following (ضto affirm):
If the Beneficiary is a CBE, DSLBD was contacted to confirm Beneficiary’s CBE certification.

The fully executed Contract (Base or Option or Extension or Multi-Year) or subsidy document, between the Beneficiary and Agency, was
emailed to DSLBD at Compliance.Enforcement@dc.gov within five (5) days of signing:

FOR AGENCY CONTRACT the SBE Subcontracting Plan, submitted by Beneficiary, was emailed to DSLBD at
Compliance.Enforcement@dc.gov within five (5) days of signing the contract between the Beneficiary and Agency.

________
Name of Agency Contracting Officer or Agency Project Manager

________
Title of Agency Contracting Officer or Agency Project Manager

________
Signature
________
Date

DGS
Smoot Construction Company of Washington DC
DCAM-23-CS-RFP-0016
84,154,494
$87,495,111
30,623,289
33,564,229
Exhibit G
First Source Agreement and Employment Plan

BRENT ES MODERNIZATION

GUARANTEED MAXIMUM PRICE (GMP) PROPOSAL

SECTION 11 – CBE/SBE
SUBCONTRACTING PLAN

DRAFT - WILL BE UPDATED TO REFLECT FINAL GMP NEGOTIATIONS
SECTION 11 - FIRST SOURCE
EMPLOYMENT AGREEMENT &
FIRST SOURCE EMPLOYMENT PLAN
Revised October 9, 2025
$84,794,307.00
$84,794,307.00
$84,154,494
$84,154,494
9/29/2025
$87,495,111
$87,495,111
10-09-2025
DOESisthefirstsourceforrecruitment,referral,andplacementofnewhiresoremployeesforalljobscreatedbytheGovernmentAssistedProjectorContract(Project).
ThePartiesagreetothetermsandconditionsoftheAgreementasfollows:
L DEFINITIONS
ThefollowingdefinitionsshallgovernthetermsusedinthisAgreement.A.Apprenticemeansaworkerwhoisemployedtolearnanapprenticeableoccupationunderthetermsandconditionsofapprovedapprenticeshipstandards.
B.Beneficiarymeans:
1.ThesignatorytoacontractexecutedbytheMayorwhichinvolvesanyDistrictof
Columbiagovernmentfunds,orfundswhich,inaccordancewithafederalgrantor
otherwise,theDistrictgovernmentadministersandwhichdetailsthenumberanddescriptionofalljobscreatedbya government-assistedProjectforwhichthe
beneficiaryisrequiredtousetheFirstSourceRegister;
2.A recipientofa Districtgovernmenteconomicdevelopmentactionincludingcontracts,grants,loans,taxabatements,landtransfersforredevelopment,ortaxincrementfinancingthatresultsinafinancialbenefitof$300,000ormorefromanagency,commission,instrumentality,or otherentityoftheDistrictgovernment,
includingafinancialorbankinginstitutionwhichservesastherepositoryfor$1million or more of Districtof Columbia funds.
C. ContractingAgencymeansanyDistrictofColumbiaagencythatawardedagovernment
assistedProjecttotaling$300,000ormore.
D. Directlaborcostsmeansallcosts,includingwagesandbenefits,associatedwiththehiring
andemploymentofpersonnelassignedtoaprocessinwhichpayrollexpensesaretracedto
theunitsofoutputandareincludedinthecostofgoodssold.
E. EMPLOYER meansanyentityawardedagovernmentassistedProjecttotaling$300,000or
more,includingallindividualcontractorandsubcontractorentitiesatanytierwhoworkontheProject.

F. FirstSourceEmployerPortalisawebsiteconsistingofaconnectedgroupofstaticanddynamicwebpageswiththeabilityforEmployerstoenterdatausingtheinternet.The
websiteisaccessiblebyaUniformResourceLocator(URL)andismaintainedbyDOES.
‘ThewebsiteprovidesreportinginformationtoFirstSourceEMPLOYERS.

G. FirstSourceRegistermeanstheDOESAutomatedApplicantFiles,whichconsistsofthe
namesofDC residentsregisteredwithDOES.

H. GoodfaitheffortmeansanEMPLOYERhasexhaustedallreasonablemeanstocomplywithanyaffirmativeaction,hiring,orcontractualgoal(s)pursuanttotheFirstSourcelawandAgreement.
1. Government-assistedprojector contract(Project)meansanyconstructionornon-
constructionProjectthatreceivesfundsorresources,valuedat$300,000ormore,fromtheDistrictofColumbia,orfundsorresourceswhich,inaccordancewitha federalgrantor
otherwise,theDistrictofColumbiagovernmentadministers,includingcontracts,grants,
loans,taxabatementsorexemptions,landtransfers,landdispositionanddevelopmentagreements,taxincrementfinancing,oranycombinationoftheaforementioned.
Page2of11 FirsSourceEmploymentAgreement,RevisedFebuary13,2018

i
N.
HardtoemploymeansaDistrictofColumbiaresidentwhoisconfirmedbyDOESas:
‘Anex-offenderwhohasbeenreleasedfromprisonwithinthelast10years;A participantoftheTemporaryAssistanceforNeedyFamiliesprogram;‘AparticipantoftheSupplementalNutritionAssistanceProgram;Livingwitha permanentdisabilityverifiedbytheSocialSecurityAdministrationor
Districtvocationalrehabilitationprogram;5. Unemployedfor6monthsormoreinthelast12-monthperiod;
6.Homeless;7.A participantorgraduateoftheTransitionalEmploymentProgramestablishedby§32-1331
8. An individualwhoqualifiedforinclusionintheWorkOpportunityTaxCredit
ProgramascertifiedbytheDepartmentofEmploymentServices.

Indirectlaborcostsmeansallcosts,includingwagesandbenefits,thatarepartofoperating
expensesandareassociatedwiththehiringandemploymentofpersonnelassignedtotasks
otherthanproducingproducts.
Jobsmeansany unionandnon-unionmanagerial,non-managerial,professional,nonprofessional,technicalornontechnicalpositionincluding:clericalandsalesoccupations,serviceoccupations,processingoccupations,machinetradeoccupations,benchworkoccupations,structuralwork occupations,agricultural,fishery,forestry,and related
occupations,andanyotheroccupationsastheDepartmentofEmploymentServicesmayidentifyintheDictionaryofOccupationalTitles,UnitedStatesDepartmentof Labor.
NewHire:Individual(s)newlyhiredbytheEMPLOYERtoperformworkonagovernment
assistedProject.

Transfer:Project.istingEMPLOYER employeewhohasbeenmovedfromoneProjecttoanother
Journeymanmeansa workerwho hasattaineda levelofskill,abilitiesandcompetencies
recognizedwithinanindustryashavingmasteredtheskillsandcompetenciesrequiredfortheoccupation.

RevisedEmploymentPlanmeansadocumentpreparedandsubmittedbytheEMPLOYERthat includesthe following:
1.A projectionofthetotalnumberofhourstobeworkedontheProjectbytrade;
2. A projectionofthetotalnumberofjourneyworkerhours,bytrade,tobeworkedon
theProjectandthetotalnumberofjourneyworkerhours,bytrade,tobeworkedby
DC residents;
3.A projectionofthetotalnumberofapprenticehours,bytrade,tobeworkedontheProjectandthetotalnumberofapprenticehours,bytrade,tobeworkedbyDCresidents;
4. A projectionofthetotalnumberofskilledlaborerhours,bytrade,tobeworkedontheProjectandthetotalnumberofskilledlaborerhours,bytrade,tobeworkedby
DC residents;
5. A projectionofthetotalnumberofcommonlaborerhourstobeworkedonthe
Page3 of11 FirtSouceEmploymentAreementRevisedFebmary18,2018

12.
13
ProjectandthetotalnumberofcommonlaborerhourstobeworkedbyDC residents;
A timetableoutliningthetotalhoursworkedbytradeoverthelifeoftheProjectand
anassociatedhiringschedule;
Descriptionsoftheskillrequirementsbyjobtitleorposition,includingindustry-recognizedcertificationsrequiredforthedifferentpositions;
A strategytofillthehoursrequiredtobeworkedbyDC residentspursuanttothis
paragraph,includinga componenton communicatingtheserequirementstocontractorsandsubcontractorsandacomponentonpotentialcommunityoutreach
partnershipswiththeUniversityoftheDistrictofColumbia,theUniversityofthe
DistrictofColumbiaCommunityCollege,theDepartmentofEmploymentServices,JointlyFundedApprenticeshipPrograms,theDistrictofColumbiaWorkforce
Intermediary,or othergovernment-approved,community-basedjobtraining
providers;

‘Aremediationstrategytoameliorateanyproblemsassociatedwithmeetingthesehiringrequirements,includinganyproblemsencounteredwithcontractorsandsubcontractors;
‘Thedesignationofa seniorofficialfromtheEMPLOYER(S)orgeneralcontractor
whowillberesponsibleforimplementingthehiringandreportingrequirements;
DescriptionsofthehealthandretirementbenefitsthatwillbeprovidedtoDC
residentsworkingontheProject;
AstrategytoensurethatDistrictresidentswho workontheProjectreceiveongoing
employmentandtrainingopportunitiesaftertheycompleteworkonthejobforwhichtheywereinitiallyhiredandareviewofpastpracticesincontinuingtoemployDCresidentsfromoneProjecttothenext;

A strategy to hire graduates of Districtof Columbia Public Schools, Districtof
Columbiapubliccharterschools,andcommunity-basedjobtrainingproviders,andhard-to-employresidents;and

A disclosureofpastcompliancewiththeWorkforceActandtheDavis-BaconAct,whereapplicable,andthebidderorofferor'sgeneralDC residenthiringpracticeson
projectsorcontractscompletedwithinthelast2years.
Q. TierSubcontractormeansanysubcontractorselectedbytheprimarycontractortoperformportion(s)oralllworkrelatedtothetradeoroccupationarea(s)onaProjectsubjecttothis
FirstSourceAgreement.
R. WashingtonMetropolitanStatisticalAreameanstheDistrictofColumbia;VirginiaCities
ofAlexandria,Fairfax,FallsChurch,Fredericksburg,Manassas,andManassasPark;theVirginiaCountiesof Arlington,Clarke,Fairfax,Fauquier,Loudon,PrinceWilliam,
Spotsylvania,Stafford,andWarren;theMarylandCountiesofCalvert,Charles,Frederick,
MontgomeryandPrinceGeorges;andtheWestVirginiaCountyofJefferson.
S. WorkforceIntermediaryPilotProgrammeanstheintermediarybetweenemployersandtrainingproviderstoprovideemployerswithqualifiedDC residentjobapplicants.SeeDC
OfficialCode§2-219.04b.
Page4 of 11 PintSourceEmploymentAgreementRevisedFebruary18,2018

H.
GENERAL TERMS
Subjecttothetermsandconditionssetforthherein,DOESwillreceivetheAgreementfrom
theContractingAgencynolessthan7calendardaysinadvanceoftheProjectstartdate.NoworkassociatedwiththerelevantProjectcanbeginuntiltheAgreementhasbeenacceptedby
DOES.
‘TheBeneficiaryand/orEMPLOYER shallrequireallProjectcontractorsandsubcontractors,underaProjectreceivinggovernmentassistanceorbenefitsvaluedat$300,000ormore,to
enterintoanAgreementwithDOES.
Agreementwilltakeaffectoncebeneficiary/Employerawardedcontractandstartworkon
thegovernmentassistedProjectandnoworkcanbeginpriortoexecutionoftheAgreementandwillbefullyeffectivethroughtheduration,anyextensionormodificationsoftheProject,anduntilsuchtimeasconstructioniscompleteanda certificateofoccupancyisissued,

Ifan EMPLOYER beganworkpriortotheexecutionofa FirstSourceEmployment
‘Agreement,theEMPLOYER shallceaseworkontheProjectandsigna FirstSource
EmploymentAgreementtobeboundbytheapplicableFirstSourceEmploymentAgreementrequirements,retroactively,fromthestartofworkthroughoutthedurationofthecontract.

DOESwillproviderecruitment,referral,andplacementservicestotheEMPLOYER,subject
tothelimitationsinthisAgreement.

DOES andtheEMPLOYER agreethat,forpurposesofthisAgreement,newhiresandjobscreatedfortheProject(bothunionandnonunion)includeallofEMPLOYER'SjobopeningsandvacanciesintheWashingtonMetropolitanStatisticalAreacreatedfortheProjectasa
resultofinternalpromotions,terminations,andexpansionsoftheEMPLOYER'Sworkforce,
asaresultofthisProject.
ThisAgreementincludesapprenticesasdefinedinD.C.OfficialCode§§32-1401-1431
DOES willmakeeveryefforttoworkwithinthetermsofallcollectivebargaining
agreementstowhichtheEMPLOYERisaparty.TheEMPLOYERwillprovideDOESwithwrittendocumentationthattheEMPLOYERhasprovidedtherepresentativeofanycollective
bargainingunitinvolvedwiththisProjecta copyofthisAgreementandhasrequested
commentsor objections.Iftherepresentativehasanycommentsorobjections,theEMPLOYERwillpromptlyprovidethemtoDOES

TheEMPLOYER whocontractswiththeDistrictofColumbiagovernmenttoperformconstruction,renovationwork,orinformationtechnologyworkwitha singlecontract,or
cumulativecontracts,ofatleast$500,000,withina 12-monthperiodwillberequiredto
registeranapprenticeshipprogramwiththeDistrictofColumbiaApprenticeshipCouncilas
requiredbyDC Code32-1431
If,duringthetermofthisAgreement,theEMPLOYER shouldtransferpossessionofalloraportionofitsbusinessconcernsaffectedbythisAgreementtoanyotherpartybylease,sale,
assignment,merger,orotherwisethisFirstSourceAgreementshallremaininfullforceandeffectandtransfereeshallremainsubjecttoallprovisionsherein.Inaddition,the
EMPLOYERasaconditionoftransfershall:
1. NotifythepartytakingpossessionoftheexistenceofthisEMPLOYER'SFirst
SourceEmploymentAgreement.
2. NotifyDOES within7businessdaysofthe transfer.Thisnoticewill

\cludethe
PageSof11 FitSourceEmploymentAgreementRevisedFebruary15,2018

nameofthepartytakingpossessionandthenameandtelephoneofthatparty's
representative.
1. The EMPLOYER andDOES may mutuallyagreetomodifythisAgreement.Any
modificationshallbeinwriting,signedbytheEMPLOYERandDOESandattachedtothe
originalAgreement.
J.TotheextentthatthisAgreementisinconflictwithanyfederallaborlawsorgovernmentalregulations,thefederallawsorregulationsshallprevail.
I TRAINING
A. DOES andtheEMPLOYER mayagreetodevelopskillstrainingandon-the-jobtraining
programsasapprovedbyDOES;thetrainingspecificationsandcostforsuchtrainingwillbemutuallyagreeduponbytheEMPLOYER andDOES andwillbesetforthina separate
TrainingAgreement.
IV.| RECRUITMENT
A. TheEMPLOYER shallcompletetheattachedRevisedEmploymentPlanthatwillincludethe
informationoutlinedinSectionLP.

‘TheEMPLOYER shallregisterandpostalljobvacancieswiththeJobBankServicesofDOESatwww.denetworks.orga minimumof10days.Shouldyouneedassistanceposting
jobvacancies,pleasecontactJobBankServicesat(202)698-6001
C.TheEMPLOYERshallnotifyDOESofallnewjobscreatedfortheProjectwithinatleast7businessdays(Monday-Friday)oftheEMPLOYERS”identification/creationofthenewjobs.TheNoticeofNewJobCreationshallincludethenumberofemployeesneededbyjobtitle,qualificationsandspecificskillsrequiredtoperformthejob,hiringdate,rateofpay,hoursofwork,durationofemployment,andadescriptionoftheworktobeperformed.Thismustbedonebeforeusinganyotherreferralsource.
D. JobopeningstobefilledbyinternalpromotionfromtheEMPLOYER'Scurrentworkforce
shallbe reportedtoDOES forplacementandreferral,ifthejobisnewlycreated.
EMPLOYERshallprovideDOESaNoticeofNewJobCreationthatdetailssuchpromotions
inaccordancewithSectionIV.C.
E.TheEMPLOYERwillsubmittoDOES,priortocommencingworkontheProject,alistofCurrentEmployeesthatincludesthename,socialsecuritynumber,andresidencystatusofall
currentemployees,includingapprentices,trainees,andlaid-offworkerswhowillbeemployedontheProject.AllEMPLOYERinformationreviewedorgathered,includingsocialsecuritynumbers,asaresultofDOES’ monitoringandenforcementactivitieswillbeheldconfidential
inaccordancewithallDistrictandfederalconfidentialityandprivacylawsandusedonlyforthepurposesthatitwasreviewedorgathered.

V. REFERRAL
A. DOES willscreenapplicantsthroughcarefullyplannedrecruitmentandtrainingeventsandprovidetheEMPLOYER witha listofqualifiedapplicantsaccordingtothenumberof
‘employeesneededbyjobtitle,qualificationsandspecificskillsrequiredtoperformthejob,
hiringdate,rateofpay,hoursofwork,durationofemployment,andadescriptionoftheworktobeperformedassuppliedbytheEMPLOYERinitsNoticeofNewJobCreationsetforth
aboveinSectionIV.C.
Page6of11 FirstSourceEmplymen!Agreement,RevvedFebmary5,218
Vi.

B. DOES will notifythe EMPLOYER of the number of applicantsDOES willrefer,priorto the
anticipatedhiringdates.
PLACEMENT
A. EMPLOYER shall in good faith,use reasonable effortsto selectitsnew hires or employees
fromamongthequalifiedapplicantsreferredbyDOES.Allhiringdecisionsaremadebythe
EMPLOYER.
B. IntheeventthatDOES isunabletoreferqualifiedapplicantsmeetingtheEMPLOYER'S
establishedqualifications,within7 businessdays(Monday- Friday)fromthedateof
notificationfromtheEMPLOYER,theEMPLOYER willbefreetodirectlyfillremainingpositionsforwhichnoqualifiedapplicantshavebeenreferred.However,theEMPLOYERshall
stillberequiredtomeettheFirstSourcehiringrequirementsorhoursworkedpercentagesfor
alljobscreatedbytheProject.
C.AftertheEMPLOYERhasselecteditsemployees,DOESisnotresponsiblefortheemployees’actions and the EMPLOYER hereby releases DOES, and the Government of the Districtof
Columbia,theDistrictofColumbiaMunicipalCorporation,andtheofficersandemployeesoftheDistrictofColumbiafromanyliabilityforemployees’actions.
VII. REPORTING REQUIREMENTS
A. EMPLOYER with a single contract valued at $300,000 or more on a Project that received
governmentassistancetotalingbetween$300,000and$5,000,000,aprovisionthatatleast51%ofthenewemployeeshiredtoworkontheProjectshallbeDistrictresidents.
B. EMPLOYER shallregisterintheFirstSourceOnlineRegistrationandReportingSystemforelectronicsubmissionofallmonthlyContractCompliancedata,weeklycertifiedpayrollsand
anyotherdocumentsrequiredbyDOESforreportingandmonitoring.
C. EMPLOYERshallsubmittotheDepartmentofEmploymentServiceseachmonthfollowingthe
startoftheProjectahiringcompliancereportfortheProjectthatincludesthe:1,Numberofnewjobopeningscreated/available;
‘NumberofnewjobopeningslistedwithDOES,oranyotherDistrictAgency;
‘NumberofDC residentshiredfornewjobs;

2.3
4.NumberofemployeestransferredtotheProject;5. Number of DC residentstransferredto the Project;
6.Directorindirectlaborcostassociatedwiththeproject;7.Bachemployee’sname,jobtitle,socialsecuritynumber,hiredate,residence,andreferralsource;and8. Workforcestatisticsthroughouttheentireprojecttenure.
D. EMPLOYERwitha singlecontractvaluedat$300,000ormoreona Projectthatreceivedgovernmentassistancetotaling$5millionormoreshallmeetthefollowinghoursworked
percentagesforalljobscreatedbytheProject:1. Atleast20%ofjourneyworkerhoursbytradeshallbeperformedbyDC residents;
2. Atleast60%ofapprenticehoursbytradeshallbeperformedbyDC residents;
3. Atleast51%oftheskilledlaborerhoursbytradeshallbeperformedbyDC
residents;and4, Atleast70%ofcommonlaborerhoursshallbeperformedbyDCresidents.
Page7of 11 rsSourceEmploymentAgreement,RevisedFebrary15.2018

E.EMPLOYERSshallprovidethefollowingcumulativestatistics,thatwillbeusedtocreate
themonthlyreport,byuploadingcertifiedpayrollsorpayrolldataintotheLCPtracker
reportingsystem:
1,NumberofjourneyworkerhoursworkedbyDC residentsbytrade;
‘Numberofhoursworkedbyalljourneyworkersbytrade;
NumberofapprenticehoursworkedbyDCresidentsbytrade;
Numberofhoursworkedbyallapprenticesbytrade;
‘NumberofskilledlaborerworkerhoursworkedbyDCresidentsbytrade;
Numberofhoursworkedbyallskilledlaborersbytrade;‘Numberof common laborerhoursworkedbyDC residentsbytrade;and
‘Numberofhoursworkedbyallcommonlaborersbytrade.SI
AHAYN
F.EMPLOYERmay“doublecount”hoursforthe“hardtoemploy”upto15%oftotalhoursworkedbyDC Residents;however,acollectivebargainingagreementshallnotbeabasisforwaiverofthisrequirement.
G. ForconstructionProjectsthatarenotsubjecttoDavis-Baconlawinwhichcertifiedpayrollrecordsdonotexist,EMPLOYER shallsubmitmonthlydocumentsofworkersemployedon
theProjecttoDOES,includingDC residentsandallemploymentclassificationsofhours
worked
H. EMPLOYER may alsobe requiredto provideverificationof hoursworkedor hiring
percentagesofDCresidents,suchasinternalpayrollrecordsforconstructionProjectsthatarenotsubjecttoDavis-Bacon.
1. Monthly,EMPLOYERshallsubmitweeklycertifiedpayrollsfromallsubcontractorsatanytier
workingontheProjecttotheContractingAgency.EMPLOYER isalsorequiredtomakepayrollrecordsavailabletoDOESasapartofcompliancemonitoring,uponrequestatjobsites.
VU. FINALREPORT AND GOOD FAITH EFFORTS

A. WiththesubmissionofthefinalrequestforpaymentfromtheContractingAgency,theBeneficiaryand/orEMPLOYERshall:
1. ReporttoDOES itscompliancewiththehiringorhoursworkedpercentagerequirementsforalljobscreatedbytheProject,andreportthehoursthatDC
residentsworkedforeachtradeclassificationsineachareaoftheProject;or
2. SubmittoDOESarequestforawaiverofthehiringorhoursworkedpercentagerequirements for alljobs created by the Project that will include the following
documentation:
a.DocumentationsupportingEMPLOYER’Sgoodfaithefforttocomply;b.ReferralsprovidedbyDOESandotherreferralsources;andc. Advertisementofjob openings listedwith DOES and other referralsources.
B. DOESmaywaiveorpartiallywaivethehiringorhoursworkedpercentagerequirementsforJobscreatedbytheProject,and/ortherequiredhoursofDC residentsforeachtrade
classifications,ifDOESfindsthattheBeneficiaryorEMPLOYER,includingitscontractorsorsubcontractors:
1.DOEScertifiedthatBeneficiaryorEmployerdemonstrateda goodfaithefforttocomply,assetforthinSectionVIII.C.;or
Page8of11 FirstSourceEmploymentAgreement,RevisedFebruary15,2018

2. IslocatedoutsidetheWashingtonMetropolitanStatisticalArea,andnoneofthe
contractworkisperformedinsidetheWashingtonMetropolitanStatisticalArea;

3. Thebeneficiarypublishedeachjobopeningorpart-timeworkneededfor7 calendar
daysinaDistrictnewspaperofcity-widecirculation;and
4. TheDOEScertifiedthatthereareinsufficienteligibleapplicantsfromtheFirstSource
Registerthatpossesstheskillsrequiredbythepositions,ortheeligibleapplicantsarenot
availableforpart-timeworkordonothaveameanstotraveltotheonsitejobs;or
5. Beneficiary/Employerenteredintoa specialworkforcedevelopmenttrainingor
placementarrangementwithDOES orwiththeDistrictofColumbiaWorkforce
Intermediary.
C. DOES shallconsiderdocumentationofthefollowingwhenmakinga determinationofa
good-faithefforttocomply:

1.DOEShascertifiedthatthereareinsufficientnumberof Districtresidentsinthelabor
marketpossessingtheskillsrequiredbytheEMPLOYERforthepositionscreatedas
aresultoftheProject.
2.WhethertheEMPLOYERpostedthejobsontheDOESjobwebsiteforaminimumof10calendardays;
3. WhethertheEMPLOYERadvertisedeachjobopeninginaDistrictnewspaperwith
city-widecirculationforaminimumof7 calendardays;
4,WhethertheEMPLOYERadvertisedeachjobopeninginspecialinterestpublicationsand on specialinterestmedia fora minimum of 7 calendar days;
5. WhethertheEMPLOYER hostedinformational/recruitingorhiringfairs;
6. WhethertheEMPLOYERcontactedchurches,unions,and/oradditiDevelopmentOrganizations; alWorkforce

7.WhethertheEMPLOYERinterviewedemployablecandidates;
8.WhethertheEMPLOYERcreatedorparticipatedina workforcedevelopmentprogramapprovedbyDOES;
9. WhethertheEMPLOYER createdorparticipatedina workforcedevelopmentprogramapprovedbytheDistrictofColumbiaWorkforceIntermediary;
10.WhethertheEMPLOYERsubstantiallycompliedwiththerelevantmonthlyreporting
requirementssetforthinthissection;
11,WhethertheEMPLOYER hassubmittedandsubstantiallycompliedwithitsmost
recentemploymentplanthathasbeenapprovedbyDOES;and
12,Anyadditionaldocumentédefforts.
Page9of11 iatSourceEmplymenAgreementRevisedFebuary15,2018

Ix.
x.
MONITORING
A.DOESistheDistrictagencyauthorizedtomonitorandenforcetherequirementsoftheWorkforceIntermediaryEstablishmentandReformoftheFirstSourceAmendmentActof2011(D.C.OfficialCode§§2 219.01- 2.219.05),andrelevantprovisionsofthe
ApprenticeshipRequirementsAmendmentActof2004(D.C.OfficialCode§2-219.03
and§ 32-1431).As a partofmonitoringandenforcement,DOES mayrequireandEMPLOYERshallgrantaccesstoProjectsites,employees,anddocuments
. EMPLOYER’SnoncompliancewiththeprovisionsofthisAgreementmayresultinthe
impositionofpenalties.
AllEMPLOYER informationreviewedorgathered,includingsocialsecuritynumbers,asaresultof DOES’monitoringandenforcementactivitieswillbe heldconfidentialin
accordancewithallDistrictandfederalconfidentialityandprivacylawsandusedonlyforthe
purposesthatitwasreviewedorgathered.
D. DOES shallmonitorallProjectsasauthorizedbylaw.DOES will:
1, Review all contract controls to determine if the Beneficiary or EMPLOYER,
includinganyContractorsorSubcontractors,aresubjecttotheWorkforceIntermediary Establishment and Reform of the FirstSource Amendment Act of 2011.
2.Notifystakeholdersandcompanyofficialsandestablishmeetingstoprovidetechnicalassistanceinvolving the FirstSource Process.
3. MakeregularconstructionsitevisitstodetermineifthePrimeorSubcontractors’workforceisinconcurrencewiththesubmittedAgreementandMonthlyCompliance
Reports.
4, Inspectandcopycertifiedpayroll,personnelrecordsandanyotherrecordsor
informationnecessarytoensuretherequiredworkforceutilizationisincompliancewiththeFirstSourceLaw.
5.ConductdeskreviewsofMonthlyComplianceReports.
6. EducateEMPLOYERS aboutadditionalservicesofferedbyDOES,suchasOn-the-
JobtrainingprogramsandtaxincentivesforEMPLOYERS who hirefromcertain
categories.
7.Monitorandcompletestatisticalreportsthatidentifytheoverallproject,contractor,andsubcontractors”hiringorhoursworkedpercentages.
8. Provideformalnotificationofnon-compliancewiththerequiredhiringorhours
workedpercentages,oranyallegedbreachoftheFirstSourceLawtoallcontracting
agencies,andstakeholders.(Pleasenote:EMPLOYERS aregranted30daysto
correctanyallegeddeficienciesstatedinthenotification.)
PENALTIES
A. WillfulBreachoftheAgreementby theEMPLOYER,failuretosubmitthecontract
compliancereports,deliberatesubmissionoffalsifieddatamayresultinDOESimposingafineof5%ofthetotalamountofthedirectandindirectlaborcostsoftheProject,inadditiontootherpenaltiesprovidedbylaw.Failuretomeettherequiredhiringrequirementsorfailure
toreceivegoodfaithwaivermayresultintheDepartmentofEmploymentServices
Page10of11 FirstSourceEmploymentAgreement,RevisedFebmary15,2018,

9/29/2025
10-09-2025
$84,794,307.00
$84,794,307.00
$84,794,307.00
$84,154,494
$84,154,494
$87,495,111
$87,495,111
xk * xk
REVISED EMPLOYMENT PLAN
B.JUSTIFICATIONSHEET:PleaseprovideadetailedexplanationofwhytheEmployerwillnothaveanynewhiresontheproject.
SmootDCisafull-serviceConstructionManagement,DesignBuildandGeneralContracting
firm.Asamanagingcontractor,SmootDCemploysprojectmanagers,projectsuperintendents
andprojectengineers.Wedonotemployapprenticeabletradesandwedonothireskilledor
unskilledlaborasthesepositionsareemployedhistoricallyatthetradesubcontractorlevel.
Inresponsetothisprojectsolicitation,we haveidentifiedkeystaffresponsibleforexecutingthe
work andhavecommittedthestaffforthedurationoftheproject.Thisparticularprojectrequires
specificexpertisethatexistswithinourcurrentstaffand additionalstaffisnotneededinorderto
fulfilltheprojectrequirements.
Forthesereasons,SmootDCdoesnotanticipateneedinganynewhiresonthisprojectatthis
time.Intheeventthatadditionalprojectmanagement staffisrequired,we willwork withDOES
andtheFirstSourceProgramtoidentifyqualifiedapplicantsformanagement-levelpositions.

ThispagetobecompletedbyEmployer

*
*
*
+
*
+
GOVERNMENTOF THEDISTRICTOFCOLUMBIA
REVISEDEMPLOYMENTPLAN
C. EMPLOYMENT PROJECTIONS.
Aprojectionofthetotalnumberofhourstobeworkedbyfull-timeandpart-timehourlywageemployeesonanannualbasisbyjobcategoryandthetotalnumberofhourstobeworkedbyfull-timeandpart-timehourlywageemployeeswhoareDistrictresidents;
Notapplicable.SmootDCdoesnotemploytradelabor.
Aprojectionofthetotalnumberoffull-timeandparttimesalariedemployeeonanannualbasisbyjobcategoryandthetotalnumberoffull-timeandpart-timesalariedemployeesthatwillbeDistrictresidents;
Notapplicable.SmootDCdoesnotemploytradelabor.
Atimetableoutliningthetotalhoursworkedbyfull-timeandpart-timehourlywageemployeesbyjobcategoryandthetotalnumberoffull-timeandpart-timesalariedemployeesbyjobcategoryoverthedurationofthelifeofthe51%hiringrequirementsset.and_anassociatehiringschedulewhichwillpredictswhenspecificjobopeningswillbeavailable.
Notapplicable.SmootDCdoesnotemploytradelabor.
Providedescriptionsoftheskillrequirementsbyjobttleorpostion,includingindustry-recognizedcertificationsrequiredforthedifferentpositions.SmootDCemploysprojectmanagers,projectsuperintendents,and projectengineers.We requireata minimuma college
degree,plusuptosevenyearsconstructionexperiencedependingontheposition.
Provideastrategytofillthe51%hiringofDistrictresidentsrequirement,includingacomponentoncommunicatingtheserequirementstocontractorsandsubcontractorsandacomponentonpotentialcommunityoutreachpartnershipswiththeUniversityoftheDistrictofColumbia,theUniversityoftheDistrictofColumbiaCommunityCollege,theDepartmentofEmploymentServices,JointlyFundedApprenticeshipPrograms,theDistrictofColumbiaWorkforceIntermediary,orothergovernment-approved,community-basedjobtrainingproviders,
Notapplicable.SmootDCdoesnotemploytradelabor.

ThispagetobecompletedbyEmployer

**—GOVERNMENTOFTHEDISTRICTOFCOLUMBIA —
REVISEDEMPLOYMENTPLAN
+
*
+
*
C. EMPLOYMENT PROJECTIONS (Continued)
VI. Thisstrategyshouldincludearemediationstrategytoameliorateanyproblemsassociatedwithmeetingthese51%HiringofDistrictResidentrequirements,includinganyproblemsencounteredwithcontractorsandsubcontractors.
As FirstSourcecomplianceisa subcontractrequirement,SmootDC monitorsDC resident
workhoursuponsubmissionofpayrequisitionbysubcontractors.Complianceconcerns
arebroughttotheattentionofthespecificsubcontractorandaremediationplanis
requested.TheplanisreviewedwithDOEStoresolveworkhourcomplianceissueswith
subcontractors.
Vil.‘Thedesignationofa seniorofficialfromtheEmployerwhowillberesponsibleforimplementingthehiringandreportingrequirements.
DevonCarlin,ProjectControlsManager,isresponsibleforFirstSourceCompliance.
VIII.ProvidedescriptionsofthehealthandretirementbenefitsthatwillbeprovidedtoDistrictresidentsworkingontheprojectorcontract.
SmootDCprovidescomprehensivehealthandretirementbenefitstoitsfull-timeemployees.
IX. ProvideastrategytoensurethatDistrictresidentswhoworkontheprojectorcontractreceiveongoingemploymentandtrainingopportunitiesaftertheycompleteworkonthejobforwhichtheywereinitiallyhiredandareviewofpastpracticesincontinuingtoemployDistrictresidentsfromoneprojectorcontracttothenext.
Not applicable.SmootDC does not employ tradelabor.
ThispagetobecompletedbyEmployer x NS;ployerInitials

= ‘GOVERNMENTOF THEDISTRICTOFCOLUMBIA=
c
xh,
xi.
+
*
*
*
REVISEDEMPLOYMENTPLAN
EMPLOYMENT PROJECTIONS(continued)
Providea strategytohiregraduatesofDistrictofColumbiaPublicSchools,DistrictofColumbiaPublicCharterSchools,community-basedjobtrainingproviders,andhard-to-employresidents.
SmootDCworkswithavarietyofworkforcedevelopmentorganizationstorecruitandreferDC residentsforcareersinconstruction.We havea longstandingpartnershipwithACE
Mentoringwhichprovidesmentoringand scholarshipstohighschoolstudentspursuing
degreesinarchitecture,constructionand engineering.Also,we supporttheDC
InfrastructureAcademyby linkingstudentstojobswithoursubcontractors.We workwithorganizationslikeSkylandWorkforceCenterandCSOSAtodevelopapoolofDC residentsforreferraltoourtradesubcontractors,
PleasedisclosepastcompliancewiththeFirstSourceEmploymentAgreementActof1984ortheWorkforceIntermediaryEstablishmentandReformofFirstSourceAmendmentActof2011andtheDavis-BaconAct,whereapplicable,andthebidderorofferor'sgeneralDistrict-residenthiringpracticesonprojectsorcontractscompletedwithinthelasttwo(2)years.
SmootDCcompletedconstructionprojectsforDGSschoolsandrecreationcentershaveconsistentlymetthelocalworkforcegoalsincompliancewithFirstSource.
PleasenotethatEMPLOYERSwithconstructionprojectsmustmakepayrollandpersonnelrecordsavailableuponrequestatjobsitestothecontractingDistrictofColumbiaagency.
SmootDCregistersitsDC fundedprojectswithLCPTracker,theonlinecertifiedpayrollreportingsoftwareusedbyDOES.

ThispagetobecompletedbyEmployer
EmployerInitials
9/29/2025
9/29/2025
9/29/2025
10-09-2025
Signature Department of Employment Services
g and Specifications
Exhibit H
Capital Non-Eligible Items

Brent Elementary School - Capital Eligibility Scrub
Description Manufacturer Quantity Unit Cost Subtotal Capital FY26 Non-Capital FY27 Non-Capital
$ 13,810,874.27 $ - $ 1,367,447.88
Description Manufacturer Quantity Unit Cost Subtotal Capital FY26 Non-Capital FY27 Non-Capital
Visual Display Units
TB-01 - TACK BOARD 5 X 4 FORBO 5 $ 162.40 $ 812.00 $ 812.00
TB-01 - TACK BOARD 6 X 4 FORBO 35 $ 204.77 $ 7,166.95 $ 7,166.95
TB-01 - TACK BOARD 9 X 4 FORBO 1 $ 397.58 $ 397.58 $ 397.58
TB-01 - TACK BOARD 12 X 3.5 FORBO 5 $ 462.02 $ 2,310.10 $ 2,310.10
TB-01 - TACK BOARD 14 X 3.5 FORBO 12 $ 522.38 $ 6,268.56 $ 6,268.56
TB-01 - TACK BOARD 16 X 3.5 FORBO 8 $ 614.77 $ 4,918.16 $ 4,918.16
TB-01 - TACK BOARD 54" X 34" FORBO 1 $ 205.55 $ 205.55 $ 205.55
TB-01 - TACK BOARD 33" X 34" FORBO 6 $ 120.20 $ 721.20 $ 721.20
TB-01 - TACK BOARD 42" X 34" FORBO 7 $ 120.20 $ 841.40 $ 841.40
TB-01 - TACK BOARD 57" X 34" FORBO 10 $ 202.55 $ 2,025.50 $ 2,025.50
TB-02 - TACK BOARD 6 X 4 FORBO 38 $ 256.45 $ 9,745.10 $ 9,745.10
TB-03 - TACK RAIL W/ INSERT FORBO 643 $ 21.33 $ 13,715.19 $ 13,715.19
TB-03 - 1" MAP RAIL, CLIPS FORBO 324 $ 1.00 $ 324.00 $ 324.00
MB-01 - MARKER BOARD 6 X 4 Multiple 33 $ 296.45 $ 9,782.85 $ 9,782.85
MB-01 - MARKER BOARD 8 X 4 Multiple 5 $ 390.38 $ 1,951.90 $ 1,951.90
MB-02 - MARKER BOARD 6 X 4 Multiple 51 $ 275.96 $ 14,073.96 $ 14,073.96
75,260.00$ 75,260.00$ - $ -$
Div 10 Accessories
Toilet Partitions Multiple 1 $ 55,900.00 $ 55,900.00 $ 55,900.00
Display Cases Multiple 3 $ 4,633.33 $ 13,900.00 $ 13,900.00
Metal Lockers Multiple 1 $ 4,500.00 $ 4,500.00 $ 4,500.00
Bicycle Racks (Indoor) Multiple 1 $ 1,843.00 $ 1,843.00 $ 1,843.00
Fire extinguisher cabinets recessed - fire rated stainless teel Larsens 12 $ 275.50 $ 3,306.00 $ 3,306.00
Fire extinguisher - 10 lb Amerax 12 $ 66.25 $ 795.00 795.00$
Shower seat Bobrick 2 $ 250.00 $ 500.00 $ 500.00
Toilet paper holder Bobrick 57 $ 125.00 $ 7,125.00 $ 7,125.00
Towel Dispenser Kimberly Clark 41 $ 79.00 $ 3,239.00 $ 3,239.00
Mirror 24" x 36" frameless Lenoir 61 $ 66.00 $ 4,026.00 $ 4,026.00
Soap Dispenser Impact ClearVu 45 $ 37.00 $ 1,665.00 $ 1,665.00
18" Grab Bar Bobrick 33 $ 26.00 $ 858.00 $ 858.00
36" Grab Bar Bobrick 33 $ 28.00 $ 924.00 $ 924.00
42" Grab Bar Bobrick 33 $ 32.00 $ 1,056.00 $ 1,056.00
Hand Dryer Dyson 16 $ 1,011.00 $ 16,176.00 $ 16,176.00
Robe Hook Gamco 57 $ 14.00 $ 798.00 $ 798.00
Shower Curtain Rod Bobrick 2 $ 44.00 $ 88.00 $ 88.00
Shower Curtain Rod Bobrick 2 $ 42.00 $ 84.00 $ 84.00
Shower Curtain Hooks Gamco 100 $ 2.00 $ 200.00 $ 200.00
Mop and Broom Holder & Shelf Bobrick 8 $ 13.00 $ 104.00 $ 104.00
Utility Shelf Bobrick 8 $ 55.00 $ 440.00 $ 440.00
Delivery/Freight Multiple 1 $ 14,200.00 $ 15,492.00 $ 15,492.00
$ 133,019.00 $ 130,926.00 $ - $ 2,093.00
Equipment (Division 10000)
Div 10 Accessories (Division 10000) Totals
Visual Display Units (Division 10000) Totals
Page 1 of 10
Brent Elementary School - Capital Eligibility Scrub
Flagpoles
Flagpole and associated base Multiple 1 $ 7,694.00 $ 7,694.00 $ 7,694.00
7,694.00$ 7,694.00$ - $ -$
Walk In Cooler/Freezer w/ refrigeration Bally 1 $69,337.00 $ 69,337.00 $ 69,337.00
Dunnage Rack Metro 2 $336.00 $ 672.00 672.00$
Quick Ship - MetroMax® i Shelf Metro 16 $650.00 $ 10,400.00 $ 10,400.00
Rack New Age 4 $1,067.00 $ 4,268.00 $ 4,268.00
Utility Cart Steril-Sil 4 $1,730.00 $ 6,920.00 6,920.00$
Dunnage Rack Metro 1 $381.00 $ 381.00 $ 381.00
Quick Ship - MetroMax® Q Shelf Metro 15 $455.33 $ 6,830.00 $ 6,830.00
Pro-Bowl Hand Sink John Boos 4 $1,030.00 $ 4,120.00 $ 4,120.00
Prep Sink KEYCUSTO 1 $4,722.00 $ 4,722.00 $ 4,722.00
Work Table KEYCUSTO 2 $3,189.50 $ 6,379.00 $ 6,379.00
Work Table KEYCUSTO 2 $2,547.00 $ 5,094.00 $ 5,094.00
Retractable Cord Reel APC 2 $487.00 $ 974.00 974.00$
Blixer® Commercial Blender/Mixer Robot Coupe 1 $1,856.00 $ 1,856.00 1,856.00$
Combination Food Processor Robot Coupe 1 $5,020.00 $ 5,020.00 5,020.00$
Condensate Hood Captive-Aire 1 $12,668.00 $ 12,668.00 $ 12,668.00
(QUICK SHIP) Two Connected Evolution™ Boilerless AccuTemp 1 $22,379.00 $ 22,379.00 $ 22,379.00
(QUICK-SHIP) Platinum Double Convection Oven Southbend (Middleby) 2 $13,344.00 $ 26,688.00 $ 26,688.00
Designer Line Refrigerator Continental Refrigerator 1 $12,184.00 $ 12,184.00 $ 12,184.00
Designer Line Heated Cabinet Continental Refrigerator 2 $14,780.00 $ 29,560.00 $ 29,560.00
Designer Line Refrigerator Continental Refrigerator 1 $14,200.00 $ 14,200.00 $ 14,200.00
Work Counter KEYCUSTO 1 $2,700.00 $ 2,700.00 $ 2,700.00
Milk Cooler Continental Refrigerator 1 $6,072.00 $ 6,072.00 $ 6,072.00
Five wekk HFC Delfield 1 $16,864.00 $ 16,864.00 $ 16,864.00
Flexible Shield Delfield 1 $6,489.00 $ 6,489.00 $ 6,489.00
Cold Food Counter Delfield 1 $3,255.00 $ 3,255.00 $ 3,255.00
All Purpose Counter Delfield 1 $11,803.00 $ 11,803.00 $ 11,803.00
Two Tier Display Delfield 1 $7,255.00 $ 7,255.00 $ 7,255.00
All Purpose Counter Delfield 1 $5,302.00 $ 5,302.00 $ 5,302.00
Pot Washing Sink KEYCUSTO 1 $7,764.00 $ 7,764.00 $ 7,764.00
Soiled Dish Table KEYCUSTO 1 $3,973.00 $ 3,973.00 $ 3,973.00
SS-200™ Complete Disposer Package InSinkErator 1 $4,527.00 $ 4,527.00 $ 4,527.00
Ventless Dishwashing Machine Hobart 1 $34,704.00 $ 34,704.00 $ 34,704.00
Clean Dish Table KEYCUSTO 1 $1,955.00 $ 1,955.00 $ 1,955.00
Quick Ship - MetroMax® i Shelf Metro 8 $268.50 $ 2,148.00 $ 2,148.00
ProSave® BRUTE® Container Rubbermaid 2 $137.00 $ 274.00 274.00$
Quick Ship - MetroMax® Q Shelf Metro 5 $103.00 $ 515.00 $ 515.00
Slim Jim® Container Rubbermaid 8 $61.00 $ 488.00 488.00$
Freight/Management/Installation Multiple 1 $138,909.00 $ 138,909.00 $ 138,909.00
$ 499,649.00 $ 483,445.00 $ - $ 16,204.00
Stage Curtains Multiple 1 41,231.25$ $ 41,231.25 41,231.25$
Rigging Systems Multiple 1 53,142.75$ $ 51,027.75 51,027.75$
Foodservice Equipment Total
Theater Equipment
Flagpoles (Division 10000) Totals
Foodservice Equipment
Page 2 of 10
Brent Elementary School - Capital Eligibility Scrub
$ 92,259.00 $ 92,259.00 $ - $ -
Backstops Porter 6 $ 10,778.33 $ 64,669.98 64,669.98$
Wall pads Porter 114 $ 249.13 $ 28,400.82 28,400.82$
Archery Net Porter 1 $ 23,250.00 $ 23,250.00 23,250.00$
Curtain Porter 1 $ 16,000.00 $ 16,000.00 16,000.00$
Vball Sleeves (permanent) Porter 2 $ 1,675.00 $ 3,350.00 3,350.00$
Vball package (Volleyball Powr Line Competition packages with poles, net, pads, cart) Porter 1 $ 7,220.00 $ 7,220.00 7,220.00$
Scoreboard Daktronics 1 $ 16,940.00 $ 16,940.00 16,940.00$
Rock Wall 11 panels 4x8 Everlast 11 $ 2,036.36 $ 22,399.96 22,399.96$
Freight/Management/Installation Multiple 1 $ 16,669.24 $ 16,669.24 16,669.24$
$ 198,900.00 $ 191,680.00 $ - $ 7,220.00
2-5 Play Area
Mud Kitchen Nature's Instruments 1 $ 1,986.13 $ 1,986.13 1,986.13$
Water Channel Kompan 1 $ 22,203.36 $ 22,203.36 22,203.36$
Kopman Embankment Slide Kompan 1 $ 12,326.00 $ 12,326.00 12,326.00$
Kompan Communication Panel Kompan 1 $ 7,045.52 $ 7,045.52 7,045.52$
Flexipave Multiple 1 $ 9,223.00 $ 9,223.00 9,223.00$
Synthetic Turf Multiple 1 $ 101,900.00 $ 101,900.00 101,900.00$
Chalkboard Nature's Instruments 1 $ 13,798.00 $ 13,798.00 13,798.00$
Willow Hut Multiple 1 $ 15,015.00 $ 15,015.00 15,015.00$
Outdoor Chalkboard Nature's Instruments 1 $ 7,588.00 $ 7,588.00 7,588.00$
Permeable resin bound aggregate Multiple 1 $ 9,083.00 $ 9,083.00 9,083.00$
5-12 Play Area
Kompan Butterfly Kompan 1 $ 159,883.00 $ 159,883.00 159,883.00$
Kompan Maxite Climber Kompan 1 $ 204,415.40 $ 204,415.40 204,415.40$
Kompan Rock-It Kompan 1 $ 9,887.76 $ 9,887.76 9,887.76$
Kopman Freestanding Slide Kompan 1 $ 38,028.60 $ 38,028.60 38,028.60$
Kompan Multi Goal & Moveable Goal Kompan 1 $ 16,614.00 $ 16,614.00 16,614.00$
Poured in Place Play Surface Multiple 1 $ 181,363.00 $ 181,363.00 181,363.00$
Freight/Management/Installation Multiple 1 $ 85,199.23 $ 85,199.23 85,199.23$
$ 895,559.00 $ 895,559.00 $ - $ -
Medical Curtain & Track Inpro 3 $1,735.00 $5,205.00 $5,205.00
Undercounter Refrigerator Zephyr 1 $1,458.00 $1,458.00 $1,458.00
36"W x 12"D Metal Shelving Starter Unit Parent 6 $117.00 $702.00 $702.00
36"W x 12"D Metal Shelving Adder Unit Parent 16 $113.00 $1,808.00 $1,808.00
36"W x 24"D Metal Shelving Unit Parent 69 $182.00 $12,558.00 $12,558.00
36"W x 18"D Metal Shelving Unit Parent 67 $163.00 $10,921.00 $10,921.00
Medicine Cabinet with Double Key Locks Global Industrial 1 $199.00 $199.00 $199.00
Instrument Storage Cabinet; Straight Grille Doors Wenger 2 $2,297.00 $4,594.00 $4,594.00
Instrument Storage Cabinet, Large- Adjustable Shelves; Straight Grille Doors Wenger 1 $2,200.00 $2,200.00 $2,200.00
Instrument Storage Cabinet - Adjustable Shelves; Straight Grille Doors Wenger 2 $2,981.00 $5,962.00 $5,962.00
Playground Equipment
Playground Equipment
Furnishings (12000)
Theater Equipment Total
Athletic Equipment
Athletic Equipment Total
Page 3 of 10
Brent Elementary School - Capital Eligibility Scrub
Instrument Storage Cabinet, Small; Straight Grille Doors Wenger 1 $2,425.00 $2,425.00 $2,425.00
Sheet Music Storage - Folio Cabinet Wenger 1 $1,445.00 $1,445.00 $1,445.00
Cantilever Student Chair - 13" Seat Height KI, Inc. 272 $92.00 $25,024.00 $25,024.00
Cantilever Student Chair - 15" Seat Height KI, Inc. 338 $93.00 $31,434.00 $31,434.00
Cantilever Student Chair - 18" Seat Height KI, Inc. 231 $94.00 $21,714.00 $21,714.00
Sled Base High Density Stack Chair KI, Inc. 542 $93.00 $50,406.00 $50,406.00
4-Leg Stack Chair with Upholstered Seat KI, Inc. 6 $227.00 $1,362.00 $1,362.00
Nesting Training Table, 24" x 30" x 29" H KI, Inc. 6 $497.00 $2,982.00 $2,982.00
Rectangular Activity Table - 30" x 60" KI, Inc. 68 $292.00 $19,856.00 $19,856.00
Nesting Rectangular Training Table - 24" x 42" KI, Inc. 5 $629.00 $3,145.00 $3,145.00
Teacher Workstation with Mobile Pedestal File KI, Inc. 45 $1,231.00 $55,395.00 $55,395.00
Teacher Task Chair with Arms KI, Inc. 45 $359.00 $16,155.00 $16,155.00
Teacher Armless Task Chair KI, Inc. 34 $343.00 $11,662.00 $11,662.00
Round Lounge Seat, 18" x 18" x 14" H KI, Inc. 106 $442.00 $46,852.00 $46,852.00
Crescent Lounge Seat, 26" Dia., Concealed Glides; 14" H KI, Inc. 2 $537.00 $1,074.00 $1,074.00
Round Lounge Seat, 26" Dia., Concealed Glides; 18" H KI, Inc. 4 $575.00 $2,300.00 $2,300.00
4-Drawer Lateral File KI, Inc. 62 $942.00 $58,404.00 $58,404.00
Fireproof File - Vertical FireKing 8 $2,580.00 $20,640.00 $20,640.00
36" W x 24" D x 36" H Double-Face Bookcase Unit, Mobile KI, Inc. 29 $698.00 $20,242.00 $20,242.00
36" W x 24" D x 42" H Double Faced Wood Shelving-Starter; Casters Russwood 12 $1,032.00 $12,384.00 $12,384.00
36" W x 24" D x 42" H Double Faced Wood Shelving-Adder; Casters Russwood 18 $880.00 $15,840.00 $15,840.00
Casegoods Wardrobe Unit, 24" W x 20" D x 72" H KI, Inc. 41 $989.00 $40,549.00 $40,549.00
18" W x 18" D x 65" H Steel Wardrobe Cabinet KI, Inc. 7 $685.00 $4,795.00 $4,795.00
30" x 18" x 65" H Tall Storage Cabinet KI, Inc. 9 $845.00 $7,605.00 $7,605.00
Adjustable Height Cantilever Desk with Book Basket KI, Inc. 422 $235.00 $99,170.00 $99,170.00
36" W x 12" D x 28.5" H Steel Bookshelf KI, Inc. 77 $376.00 $28,952.00 $28,952.00
36" W x 12" D x 54" H Steel Bookshelf KI, Inc. 23 $563.00 $12,949.00 $12,949.00
Casegoods Bookshelf, 36" W x 14" D x 72" H KI, Inc. 1 $648.00 $648.00 $648.00
Office Workstation with WS Supporting File - 60" W x 24" D KI, Inc. 4 $1,096.00 $4,384.00 $4,384.00
Office Workstation with WS Supporting File - 66" W x 30" D KI, Inc. 17 $1,262.00 $21,454.00 $21,454.00
Principal Desk & Return with Pedestal File - Casegoods KI, Inc. 1 $1,315.00 $1,315.00 $1,315.00
Office Desk Shell -54" W x 24" D KI, Inc. 2 $639.00 $1,278.00 $1,278.00
30" Round Table KI, Inc. 5 $463.00 $2,315.00 $2,315.00
36" Round Table KI, Inc. 10 $513.00 $5,130.00 $5,130.00
Cubed Side Table KI, Inc. 4 $846.00 $3,384.00 $3,384.00
Nesting Training Table, 24" x 36" x 29" H KI, Inc. 1 $618.00 $618.00 $618.00
Square Table -36" x 36" KI, Inc. 2 $494.00 $988.00 $988.00
Personal Worksurface, Cantilever Base KI, Inc. 15 $307.00 $4,605.00 $4,605.00
Non-powered Computer Table with Grommet- 24" D x 36" W x 29" H KI, Inc. 5 $618.00 $3,090.00 $3,090.00
Administrative Task Chair with Arms KI, Inc. 48 $399.00 $19,152.00 $19,152.00
Music Rug Joy Carpets 1 $379.00 $379.00 $379.00
Rectangular Training Table, 24" x 36" x 29" H KI, Inc. 3 $434.00 $1,302.00 $1,302.00
Lounge Chair with Arms KI, Inc. 23 $1,596.00 $36,708.00 $36,708.00
Inside Curve 45 Degree Lounge Seat with Back, 18" Seat Height KI, Inc. 4 $1,223.00 $4,892.00 $4,892.00
30 Degree Lounge Seat, No Back; 18" H KI, Inc. 10 $668.00 $6,680.00 $6,680.00
CZ Rectangular Conference Table - 35.5" x 95.5" KI, Inc. 1 $1,098.00 $1,098.00 $1,098.00
Square Table -36" x 36" KI, Inc. 6 $479.00 $2,874.00 $2,874.00
Casegoods Round Table - 42" Diameter KI, Inc. 1 $565.00 $565.00 $565.00
Four-Leg Work Table -60" Diameter KI, Inc. 1 $722.00 $722.00 $722.00
Executive Task Chair with Arms KI, Inc. 19 $736.00 $13,984.00 $13,984.00
Nesting Rectangular Training Table, 24" x 36" KI, Inc. 28 $616.00 $17,248.00 $17,248.00
Nesting Rectangular Table with Collaborative Base - 24" x 60" KI, Inc. 2 $696.00 $1,392.00 $1,392.00
Height Adjustable Diamond Shape Activity Table KI, Inc. 34 $415.00 $14,110.00 $14,110.00
Page 4 of 10
Brent Elementary School - Capital Eligibility Scrub
Fireproof Safe FireKing/ Global Industrial 2 $894.00 $1,788.00 $1,788.00
Treatment Table with Shelves Clinton Industries, Inc. 1 $651.00 $651.00 $651.00
Adjustable Height Backless Medical Stool KI, Inc. 1 $319.00 $319.00 $319.00
Top-Freezer Refrigerator with Icemaker Frigidaire 2 $1,002.00 $2,004.00 $2,004.00
Top-Freezer Refrigerator with Icemaker with Lock Frigidaire & WILNORY 1 $1,132.00 $1,132.00 $1,132.00
Recovery Cot Clinton Industries, Inc. 2 $498.00 $996.00 $996.00
Fixed Top Rectangular Training Table - 24" x 60" KI, Inc. 5 $510.00 $2,550.00 $2,550.00
Square Table - 36" x 36" x 29" H KI, Inc. 1 $479.00 $479.00 $479.00
Standing Choral Risers - Section Wenger 4 $2,870.00 $11,480.00 $11,480.00
Risers Storage Unit Wenger 1 $1,610.00 $1,610.00 $1,610.00
FlipForm Riser Unit Wenger 4 $1,456.00 $5,824.00 $5,824.00
CZ Rectangular Conference Table - 35.5" x 95.5" KI, Inc. 1 $1,089.00 $1,089.00 $1,089.00
CZ Rectangular Conference Table - 47.5" x 119.5" KI, Inc. 1 $1,443.00 $1,443.00 $1,443.00
Student Music Chair - 17.5" Seat Height Wenger 30 $106.00 $3,180.00 $3,180.00
Music Chair Storage Unit Wenger 1 $576.00 $576.00 $576.00
Conductor's System Wenger 1 $3,597.00 $3,597.00 $3,597.00
Podium KI, Inc. 1 $543.00 $543.00 $543.00
Digital Upright Piano Roland 1 $3,658.00 $3,658.00 $3,658.00
Sloped Shelf Book Truck Demco 2 $659.00 $1,318.00 $1,318.00
Ball Storage Cart Uline 2 $408.00 $816.00 $816.00
3 Tier Ball Locker Trigon 2 $337.00 $674.00 $674.00
Flammable Cabinet Global Industrial 1 $1,390.00 $1,390.00 $1,390.00
60" W Portable Ballet Barre Vita Vibe 3 $199.00 $597.00 $597.00
Round Cafeteria Table with Benches, 81" KI, Inc. 11 $2,356.00 $25,916.00 $25,916.00
Round Cafeteria Table - Wheelchair Accessible, 72" Dia. KI, Inc. 2 $1,314.00 $2,628.00 $2,628.00
Nesting Rectangular Training Table - 30" x 60" KI, Inc. 7 $720.00 $5,040.00 $5,040.00
Dolly for Stack Chairs KI, Inc. 13 $308.00 $4,004.00 $4,004.00
Drying Storage Unit - 50 Shelves Sax 4 $550.00 $2,200.00 $2,200.00
Top Loading Kiln, EnviroVent, + Furniture Kit Skutt 1 $8,920.00 $8,920.00 $8,920.00
Drying Cabinet Debcor 2 $2,891.00 $5,782.00 $5,782.00
10' Fiberglass Step Ladder Global Industrial 1 $357.00 $357.00 $357.00
Music Stand Wenger 30 $74.00 $2,220.00 $2,220.00
Music Stand Storage Wenger 1 $685.00 $685.00 $685.00
Mobile Markerboard - 48" W x 16" D x 66" H KI, Inc. 4 $727.00 $2,908.00 $2,908.00
Cafe Height Work Table - 36" x 72" x 42" H KI, Inc. 1 $2,264.00 $2,264.00 $2,264.00
Polypropylene Cafe Height 4 Leg Stool, 30" H KI, Inc. 4 $202.00 $808.00 $808.00
Mobile Work Table; Height Adjustable, 30" D x 60" W KI, Inc. 28 $936.00 $26,208.00 $26,208.00
Multimedia Storage Unit Uline 44 $420.00 $18,480.00 $18,480.00
Microwave Cafe 4 $995.00 $3,980.00 $3,980.00
Undercounter Refrigerator Zephyr 3 $1,458.00 $4,374.00 $4,374.00
Industrial Stool with Back - 19"-27" H Worthington Direct 46 $110.00 $5,060.00 $5,060.00
Adjustable Height Table; Plastic Laminate Top, 24" D x 60" W KI, Inc. 15 $761.00 $11,415.00 $11,415.00
Adjustable Height Table; Butcher Block Top, 24" D x 60" W KI, Inc. 8 $1,219.00 $9,752.00 $9,752.00
Kidney Shaped Activity Table KI, Inc. 28 $485.00 $13,580.00 $13,580.00
4-Drawer Lateral File KI, Inc. 4 $998.00 $3,992.00 $3,992.00
Rotary Literature Rack Safco 2 $226.00 $452.00 $452.00
Laundry Hamper Global Industrial 1 $338.00 $338.00 $338.00
Residential Washer Electrolux 1 $1,175.00 $1,175.00 $1,175.00
Residential Dryer Electrolux 1 $1,175.00 $1,175.00 $1,175.00
Paper Storage Center Wood Designs 28 $880.00 $24,640.00 $24,640.00
Wiggle Stool; 12" height KI, Inc. 28 $97.00 $2,716.00 $2,716.00
Wiggle Stool; 14" height KI, Inc. 16 $101.00 $1,616.00 $1,616.00
Wiggle Stool; 18" height KI, Inc. 12 $109.00 $1,308.00 $1,308.00
Page 5 of 10
Brent Elementary School - Capital Eligibility Scrub
Sensory Wrap & Frame Autism Community Store 3 $1,037.00 $3,111.00 $3,111.00
Wall Hook Global Industrial 2 $35.00 $70.00 $70.00
Meditation Chair malu 2 $133.00 $266.00 $266.00
Under Counter Book Return Cart Kingsley 1 $1,740.00 $1,740.00 $1,740.00
Book Return Cart - Locking, Full Height Kingsley 1 $2,230.00 $2,230.00 $2,230.00
First Aid Station Global Industrial 1 $322.00 $322.00 $322.00
Pedal Controlled Waste Bin with Lid Global Industrial 1 $281.00 $281.00 $281.00
Outdoor Picnic Table & Benches Landscape Forms 5 $8,096.00 $40,480.00 $40,480.00
Outdoor Square Lounge Maglin Site Furniture 6 $1,541.00 $9,246.00 $9,246.00
Outdoor Picnic Table and Benches Landscape Forms 8 $3,392.00 $27,136.00 $27,136.00
Bean Bag Lakeshore 56 $135.00 $7,560.00 $7,560.00
9' x 12' Themed Classroom Carpet Lakeshore 15 $532.00 $7,980.00 $7,980.00
12' x 7'6" Solid Rectangular Classroom Carpet Joy Carpets 14 $162.00 $2,268.00 $2,268.00
Fixed Leg Backless Stool; 14" H Lakeshore 66 $123.00 $8,118.00 $8,118.00
Fixed Leg Backless Stool; 18" H Lakeshore 18 $138.00 $2,484.00 $2,484.00
Low Bookcase, 35"w x 12"d x 25"h Lakeshore 28 $495.00 $13,860.00 $13,860.00
Storage Unit Lakeshore 65 $608.00 $39,520.00 $39,520.00
Mobile Listening Center Lakeshore 14 $719.00 $10,066.00 $10,066.00
Hardwood Easel + Newsprint Lakeshore 28 $267.00 $7,476.00 $7,476.00
Wood Bookstand Lakeshore 14 $319.00 $4,466.00 $4,466.00
Hardwood Kitchen Set Lakeshore 13 $1,300.00 $16,900.00 $16,900.00
Pretend & Play Table & Chair Set Lakeshore 13 $739.00 $9,607.00 $9,607.00
Manipulative Storage Bins - Set of 6 Lakeshore 13 $39.00 $507.00 $507.00
Indoor/Outdoor Chair Cubes (Set of 4) Lakeshore 14 $399.00 $5,586.00 $5,586.00
4' x 6' Solid Classroom Rug Joy Carpets 28 $61.00 $1,708.00 $1,708.00
Clear Storage Box & Lid - Set of 20 Lakeshore 13 $15.00 $195.00 $195.00
Sensory Table (Water Play) Lakeshore 13 $470.00 $6,110.00 $6,110.00
Dramatic Play Center Lakeshore 11 $646.00 $7,106.00 $7,106.00
Freight/Management/Installation Multiple 1 $370,758.00 $ 370,758.00 $370,758.00
1,679,547.00$ $ 1,444,653.00 $ - $ 234,894.00
Manual Roller Shades Draper 269 $309.76 $ 83,325.44 83,325.44$
Motorized Roller Shades 14 $1,435.71 $ 20,099.94 20,099.94$
Freight/Management/Installation Multiple 1 $24,983.62 $ 24,983.62 $24,983.62
128,409.00$ 45,083.56$ - $ 83,325.44$
Distribution Equipment ABB 1 $ 265,425.00 $ 265,425.00 265,425.00$
Switchgear (Part of Distribution Equipment)
Panelboards (Part of Distribution Equipment)
Lighting Multiple 1 625,000.00 $ $ 625,000.00 625,000.00$
Light Fixtures (Part of Lighting)
Lighting Controls (Part of Lighting)
Theater Lighting (Part of Lighting)
Fire Alarm Equipment and Devices Notifier 1 80,000.00$ $ 80,000.00 80,000.00$
Generator and ATS Switches Generac 1 142,250.00$ $ 142,250.00 142,250.00$
Freight/Management/Installation Multiple 1 $ 6,892,079.00 $ 6,892,079.00 6,892,079.00$
Classroom / Library / Gym/ Cafeteria AV
Audia Visual Harness Cables to Go 41 $765.00 $31,365.00 $31,365.00
Furnishings (12000) Totals
Window Treatments (12240)
Window Treatments (12240) Totals
Electrical & Low Voltage (26000 - 28000)
Page 6 of 10
Brent Elementary School - Capital Eligibility Scrub
Cables 2 Go TruLink USB 2.0 Superbooster Wall Plate Transmitter and Dongle Receiver Kit Cables to Go 41 $1,294.55 $53,076.55 53,076.55$
LED Display 49" NEC 2 $951.64 $1,903.28 $1,903.28
LED Display 65" NEC 2 $1,102.88 $2,205.76 $2,205.76
Gymnasium Intercom Shunt Biamp 1 $701.82 $701.82 $701.82
Gymnasium A/V Receiver Extron 1 $4,483.64 $4,483.64 $4,483.64
Gymnasium A/V Transmitter/Reciever Extron 1 $709.09 $709.09 $709.09
Gymnasium A/V Cables Extron 1 $1,200.00 $1,200.00 $1,200.00
Gymnasium Controller Extron 1 $2,258.18 $2,258.18 $2,258.18
Gymnasium System Controller Extron 1 $2,007.27 $2,007.27 $2,007.27
Gymnasium Mixer/DSP Biamp 1 $2,901.82 $2,901.82 $2,901.82
Gymnasium CD Player Denon 1 $518.18 $518.18 $518.18
Gymnasium Power Conditioner Surge 1 $1,625.45 $1,625.45 $1,625.45
Gymnasium UPS SurgeX 1 $2,470.91 $2,470.91 $2,470.91
Cafeteria Intercom Shunt Biamp 1 $701.82 $701.82 $701.82
Cafeteria Mixer/DSP Biamp 1 $2,901.82 $2,901.82 $2,901.82
Cafeteria CD Player Denon 1 $518.18 $518.18 $518.18
Cafeteria Power Conditioner Surge 1 $1,625.45 $1,625.45 $1,625.45
Cafeteria UPS SurgeX 1 $2,470.91 $2,470.91 $2,470.91
Audio Input Devices
Gymnasium Mic Level Input Neutrik 3 $45.45 $136.35 $136.35
Gymnasium Line Level Input Neutrik 4 $45.45 $181.80 $181.80
Gymnasium Stereo Input Neutrik 1 $45.45 $45.45 $45.45
Gymnasium Bluetooth Audio Input Symetrix 1 $45.45 $45.45 $45.45
Cafeteria Mic Level Input Neutrik 2 $45.45 $90.90 $90.90
Cafeteria Line Level Input Neutrik 3 $45.45 $136.35 $136.35
Cafeteria Stereo Input Neutrik 1 $45.45 $45.45 $45.45
Cafeteria Bluetooth Audio Input Smetrix 1 $45.45 $45.45 $45.45
Audio Amplification and Loudspeakers
Gymnasium Wired Microphone Shure 2 $167.27 $334.54 $334.54
Gymnasium Microphone stands Atlas 4 $90.91 $363.64 $363.64
Gymnasium Wireless Microphone Equipment Shure 2 $1,763.64 $3,527.28 $3,527.28
Cafeteria Wired Microphone Shure 2 $236.36 $472.72 $472.72
Cafeteria Microphone Stands Atlas 4 $90.91 $363.64 $363.64
Gymnasium Loudspeakers Electro-Voice 2 $1,318.18 $2,636.36 $2,636.36
Cafeteria Loudspeakers Electro-Voice 2 $1,318.18 $2,636.36 $2,636.36
Cafeteria Amplifier QSC 1 $2,487.27 $2,487.27 $2,487.27
Gymnasium Amplifier QSC 1 $2,487.27 $2,487.27 $2,487.27
Video
Gymnasium Projection Screen Da-Lite 1 $16,666.37 $16,666.37 $16,666.37
Gymnasium Projector Epson 1 $23,118.33 $23,118.33 $23,118.33
Library Projection Screen Da-Lite 1 $7,594.12 $7,594.12 $7,594.12
Lirbary Projector Sony 1 $12,475.85 $12,475.85 $12,475.85
Assistive Lisetning System
Gymnasium Assisted Listening Equipment Liten Technologies 2 $2,550.00 $5,100.00 $5,100.00
Cafeteria Assistive Listening Equipment Listen Technologies 2 $2,550.00 $5,100.00 $5,100.00
PA
Bogen Nyquest System Bogen 3 $9,350.00 $28,050.00 $28,050.00
Master Clock w Antenna Bogen 1 $2,390.15 $2,390.15 $2,390.15
Wireless Clocks Bogen 17 $212.88 $3,618.96 $3,618.96
Call Switch Bogen 75 $25.00 $1,875.00 $1,875.00
2X2 Drop Ceiling Speaker Bogen 164 $295.00 $48,380.00 $48,380.00
Paging Horn Speakers Bogen 7 $223.33 $1,563.31 $1,563.31
Page 7 of 10
Brent Elementary School - Capital Eligibility Scrub
Admin Phone Bogen 2 $571.00 $1,142.00 $1,142.00
CCTV Surveillance
Exterior fixed cameras Axis 17 $2,841.67 $48,308.39 $48,308.39
Central Power Supply Cisco 1 $3,600.00 $3,600.00 3,600.00$
Interior Cameras Axis 76 $1,258.33 $95,633.08 $95,633.08
Monitors GE 2 $800.00 $1,600.00 $1,600.00
Vision security soltutions (VSS) hybrid II appliance servers w/ VSS Alloy Intel 1 $105,600.00 $105,600.00 105,600.00$
Access Control/Security
Trove2 Enclosure8 Door Kit with power supply and controller Altronix 2 $1,866.00 $3,732.00 3,732.00$
Access Control Card Reader, SE RP40 Schlage 23 $375.00 $8,625.00 8,625.00$
5MP IR Compact Network Video Intercom Axis 2 $1,530.00 $3,060.00 $3,060.00
EP1502 Controller Mercury-RS2 2 $1,350.00 $2,700.00 $2,700.00
Schlage AD 300 Locks Schlage 13 $2,450.00 $31,850.00 $31,850.00
Linq8ACM Board Altronix 2 $430.00 $860.00 $860.00
MR52 Board Mercury-RS2 8 $850.00 $6,800.00 $6,800.00
Elite Desktop Collaboration Device with Bluetooth Headset Yealink 1 $483.33 $483.33 $483.33
Intrusion Alarm Panel DMP 1 $856.67 $856.67 $856.67
Keypad DMP 1 $135.00 $135.00 $135.00
16 Zone Expander DMP 2 $269.67 $539.34 $539.34
Motion Detector/Glass Break DMP 42 $108.32 $4,549.44 $4,549.44
Panic Button DMP 10 $48.00 $480.00 $480.00
Control
Cafeteria Network PoE+ Switch Netgear 1 $1,570.00 $1,570.00 $1,570.00
Gymnasium Network PoE+ Switch Netgear 1 $1,570.00 $1,570.00 $1,570.00
Equipment Rack and Miscellaneous
Security Equipment Racks Hubbel 1 $708.33 $708.33 $708.33
Equipment Cabinet Otronics 1 $6,256.67 $6,256.67 $6,256.67
Gymnasium Equipment Cabinet Middel Atlantic 1 $4,721.67 $4,721.67 $4,721.67
Cafeteria equipment Cabinet Middle Atlantic 1 $4,721.67 $4,721.67 $4,721.67
Cafeteria Equipment Drawer Lowell 1 $291.67 $291.67 $291.67
Gymnasium Equipment Drawer Lowell 1 $291.67 $291.67 $291.67
Freight/Management/Installation Multiple 1 1,999,700.57$ 1,990,700.57$ 1,990,700.57$
$ 10,623,754.00 $ 10,374,137.71 $ - $ 249,616.29
Bike Rack Victor Stanley 32 $1,750.00 $56,000.00 $56,000.00
Pixel Block Movable Seats Maglin 10 $1,300.00 $13,000.00 $13,000.00
Take-out Table with triple seating Landscape Forms 5 $4,500.00 $22,500.00 $22,500.00
Take-out Table with left triple seating Landscape Forms 1 $4,300.00 $4,300.00 $4,300.00
Take-out Table with right triple seating Landscape Forms 1 $4,300.00 $4,300.00 $4,300.00
Harvest Round Table 47.25" Landscape Forms 1 $3,500.00 $3,500.00 $3,500.00
Dumor Wooden Benches (Installed on concrete seatwalls) Dumor 1 $174,110.00 $174,110.00 $174,110.00
Dumor 474-32VS-BT 32-gallon receptacle BT Dumor 3 $3,715.00 $11,145.00 $11,145.00
Dumor 287-32SH-SO 32-gallon receptacle, side opening with shield Dumor 3 $3,715.00 $11,145.00 $11,145.00
$300,000.00 $ 56,000.00 $0.00 $244,000.00
Compact Auto Floor Scrubber 20" Uline 1 $7,480.88 $7,480.88 $7,480.88
Advance Floor Cleaning/Polishing Machine - 20" Uline 1 $1,575.98 $1,575.98 $1,575.98
3M Floor Stripping Pad 20" Uline 2 $59.35 $118.70 $118.70
Site Furnishings (Division 32)
Site Furnishings (Division 32) Totals
Custodial Equipment
Low Voltage (28000) Totals
Page 8 of 10
Brent Elementary School - Capital Eligibility Scrub
3M Floor Cleaning Pad 20" Uline 2 $58.50 $117.00 $117.00
3M Floor Buffing Pad 20" Uline 2 $51.15 $102.30 $102.30
3M Floor Polishing Pad 20" Uline 2 $57.79 $115.58 $115.58
Industrial upright Vacuum Uline 2 $478.94 $957.88 $957.88
Industrial upright Vacuum replacement bags Uline 5 $5.47 $27.35 $27.35
Idustrial Backpack Vacuum - 10Qt Uline 2 $570.67 $1,141.34 $1,141.34
Replacment bags for 10 Qt. backpack vacuum Uline 5 $16.76 $83.80 $83.80
Squeegee Vacuum Uline 2 $200.00 $400.00 $400.00
Standard Janitor Cart Uline 2 $260.32 $520.64 $520.64
LEAF BLOWER ELECTRIC includes battery and charger Grainger 1 $103.72 $103.72 $103.72
LEAF BLOWER BACKPACK GAS 32CC, includes battery and charger Grainger 1 $354.40 $354.40 $354.40
WEED WACKER includes battery and charger Grainger 1 $359.61 $359.61 $359.61
Genie Man Lift Industrial Products 1 $14,177.00 $14,177.00 $14,177.00
Snow Shovels Uline 2 $24.17 $48.34 $48.34
Electric Power Washer Uline 1 $426.52 $426.52 $426.52
Extension Hose for H-8942 Light Duty Electric Pressure Washer Uline 1 $0.00 $0.00 $0.00
Industrial Plus Garden Hose - 5⁄8" Uline 1 $42.02 $42.02 $42.02
CABINET WALL MOUNT 36x14x27 Uline 6 $407.00 $2,442.00 $2,442.00
32 oz spray bottles with triggers Uline 60 $1.74 $104.40 $104.40
Heavy Duty Microfiber Wet Mop Head - 24 oz, Blue Uline 6 $29.31 $175.86 $175.86
Gate-Style Fiberglass Mop Handle - 60", Blue Uline 6 $18.44 $110.64 $110.64
Microfiber Deluxe Dust Mop Kit - 60" Uline 6 $84.70 $508.20 $508.20
MOP BUCKET & SIDE PRESS WRINGER 35QT YELLOW WAVEBRAKE 1EA Uline 6 $121.52 $729.12 $729.12
BUCKET DIRTY WATER RED WAVEBRAKE COMBOS Uline 6 $33.00 $198.00 $198.00
Uline Microfiber General Purpose Towels - Blue Uline 6 $13.50 $81.00 $81.00
Uline Microfiber General Purpose Towels - Green Uline 6 $13.50 $81.00 $81.00
Uline Microfiber Glass and Mirror Towels - Yellow Uline 6 $13.50 $81.00 $81.00
Uline Microfiber General Purpose Towels - Red Uline 6 $13.50 $81.00 $81.00
Plastic Pail - 5 Gallon, Blue Uline 6 $66.67 $400.02 $400.02
Plastic Pail - 5 Gallon, Green Uline 6 $66.67 $400.02 $400.02
Plastic Pail - 5 Gallon, Yellow Uline 6 $66.67 $400.02 $400.02
Plastic Pail - 5 Gallon, Red Uline 6 $66.67 $400.02 $400.02
GRAFFITI WIPES 40/PK 6PK/CS Uline 6 $98.33 $589.98 $589.98
SQUEEGEE COMPLETE ERGOTECH 10" Uline 6 $27.83 $166.98 $166.98
TELEPOLE ERGO 8FT Uline 6 $69.27 $415.62 $415.62
18" Push Broom Uline 6 $25.04 $150.24 $150.24
BROOM LOBBY FLAGGED BRISTLES Uline 6 $9.36 $56.16 $56.16
DUST PAN UPRIGHT LOBBY BLACK Uline 6 $8.42 $50.52 $50.52
DOLLY BLACK FITS 20, 32, 44 & 55 GAL CANS Uline 8 $53.91 $431.28 $431.28
TOILET PLUNGER 6" BELL CUP 18" WOOD HANDLE Uline 6 $4.96 $29.76 $29.76
FLOOR SIGN 2-SIDE "CAUTION WET FLOOR Uline 6 $16.43 $98.58 $98.58
TRASHCAN 55GAL GRAY VENTED Uline 4 $115.77 $463.08 $463.08
Uline Industrial Trash Liners - 55-60 Gallon, 2 Mil, Black Uline 1 $43.97 $43.97 $43.97
Uline Industrial Trash Liners - 55-60 Gallon, 2 Mil, Clear Uline 1 $43.97 $43.97 $43.97
Uline Industrial Trash Liners - 8-10 Gallon, 1.2 Mil, Black Uline 4 $25.86 $103.44 $103.44
Uline Industrial Trash Liners - 23 Gallon, 1.5 Mil, Black Uline 4 $31.26 $125.04 $125.04
Uline Industrial Trash Liners - 23 Gallon, 1.5 Mil, Clear Uline 4 $27.17 $108.68 $108.68
Uline Industrial Trash Liners - 33 Gallon, 1.5 Mil, Black Uline 4 $44.78 $179.12 $179.12
Uline Industrial Trash Liners - 33 Gallon, 1.5 Mil, Clear Uline 4 $37.69 $150.76 $150.76
BioTuf Compostable Liners - 33 Gallon Uline 1 $110.23 $110.23 $110.23
Uline Economy Coreless Trash Liners - .23 Mil, 4 Gallon Uline 1 $26.68 $26.68 $26.68
Uline Antibacterial Foaming Soap - 1 Gallon Uline 40 $92.29 $3,691.60 $3,691.60
Uline Deluxe Multi-Fold Towels Uline 30 $41.12 $1,233.60 $1,233.60
Page 9 of 10
Brent Elementary School - Capital Eligibility Scrub
Uline Jumbo Bath Tissue - 2-ply Uline 30 $55.25 $1,657.50 $1,657.50
$ 44,272.15 $ 14,177.00 $0.00 $30,095.15
Public Art Allowance 1 500,000.00$ $ 500,000.00 500,000.00$
500,000.00$ $ - $ - $ 500,000.00
Grand Totals $15,178,322.15 $13,810,874.27 $0.00 $1,367,447.88
**Note: The above is based on the current GMP and subcontractor identified in the bid summary. As subcontract agreements are negotiated and executed, the above is subject to change.
Custodial Equipment
Public Art Allowance
Public Art Allowance
Page 10 of 10
g and Specifications
Exhibit I
Capital Eligibility Guildline

1
General Restrictions for Capital Financing Eligibility
To be eligible for
funding in the capital budget, a project must result in a District owned asset,
and be of sufficient value (minimum $250,000) to be carried on the books as such and
depreciated over the life of the project, which is five or more years.
In general, to be capital elig
ible the project must also result in one of the following;
x A new District owned asset,
x Increase the value of an existing District owned asset,
x Increase the life of a District owned asset by at least 2 years.
I. Eligible Projects/Activities
The following are examples of categories of projects elig
ible for capital financing:
ƒ Construction or acquisition of a public facility to be owned, o ccupied, and for use by the District
for the useful life of the asset.
ƒ Large-scale replacement and rehabilitation of existing public facilities
ƒ Improvements to economic development projects owned by the District
ƒ Design work relating to an individual capital project (if the project is implemented/constructed).
ƒ Land purchased for building sites, recreation, rights-of-way, and other public purposes owned by
the District and with access and use by the general population.
ƒ Replacement or rehabilitation of major mechanical systems (such as HVAC, Electrical or entire
lighting systems) or structural components of existing public (District owned) facilities
ƒ Alteration of an existing public facility to make it more funct ional for a new use, including
temporary relocation costs of an existing use
ƒ Light fixtures, shelving, the opening day collections (inventor y) of library books for a public
library (but not for a school facility!)
ƒ Furniture, fixtures and equipment associated with construction or substantial rehabilitation of a
public facility (not to exceed 10 percent of project’s total budget). The items must support the
primary function of the facility but are not necessarily attached as a part of the structure.
ƒ Specific to school modernizations-
ƒ Tables, chairs, desks, etc in a classroom to make it functional are eligible (but not
eligible are erasers, trash cans, chalks, toys, miscellaneous supplies)
ƒ For a fitness room, equipment such as bikes, treadmills, large equipment is eligible
but not free weights, balls, bats, gloves mats and the like (these are not eligible).
ƒ For labs, the equipment and supplies for the lab is ineligible (microscopes, test tubes
etc.). Items in the pre-k room such as play kitchens and other toys would not be
eligible. Because the DC Department of Health oversees/runs hea lth suites, FF&E
in a school health room is ineligible. Music equipment (with 1 exception), table
top items in a kitchen such as blenders/mixers/meat slicers etc, telephones, various
art/pictures, certain clocks, certain speakers, microphones, pl astic/cloth stack cots
in pre-k rooms, etc are many of the ineligible items. Eligible FF&E for Small Caps
projects would include HVAC systems (attached to the facility), playground
equipment (installed)
2

ƒ Construction and rehabilitation of rights of way and public inf rastructure (roads and bridges),
including storm water management systems)
ƒ For Short Term Family Housing (STFH) complete renovations/major renovations are eli– includes
the beds, dresser, nightstand, refrigerator, couches etc. Does not include soft goods such as pillows,
bed linen, comforters, etc.
ƒ Major information technology projects (with a 5 year minimum useful life and $250,000 cost)
ƒ Hazardous materials remediation costs, e.g., asbestos removal a nd abatement, landfill clean-up,
etc.
ƒ Grading and site preparation work
ƒ Lead/Other Toxins testing or assessment costs are eligible only during the construction period
ƒ Trees planted on property owned by the District
ƒ Significant information technology investments, including hard wiring of a facility, hardware, and
software purchases including the manufacturer’s standard term of warranty
ƒ Pieces of artwork in excess of $250,000 per unit (see further discussion in item III e)
ƒ Roof membrane sealing - often referred to as a GacoRoof or ‘cool roof’. Use of this process on a
roof that is due to be replaced and is otherwise structurally s ound, precludes the need to remove
any part of the old roof structure, while essentially replacing the roof with a new guarantee against
leakage. See Item III h. below for further explanation on conditions for eligibility.
ƒ Solar Panels which must; be the exclusive property of the Distr ict, be installed on District owned
assets, have an estimated economic life of more than 25 years, and have a positive return on the
investment (measurable lowered energy costs from the project – identified as an operating impact
of capital)
ƒ Cloud-based software – must include a clear contractual agreement that the District’s data remains
an asset, includes the development/cleansing of the data for conversion and integration. Ongoing
licensing is not eligible (see item i in section III below)
ƒ Small Cap project items must have a unit cost of $5,000 or more with a minimum useful life of 3
years. Specific items which are ineligible include security cameras, fencing, etc.
ƒ Swing space required during a capital project, but not any overhead costs such as electricity, water,
security at the swing space location.
ƒ Labor costs within a DCRA MOU for pulling permits, and the cost of the permits.
ƒ Cost of builders’ risk insurance.
ƒ Facility Condition Assessments for an approved capital project in the current approved 6 year CIP.

II. Not Eligible

The following are examples of categories of projects/activities NOT eligible for capital financing:
ƒ Project does not result in as asset that will be owned by the District for the useful life of the asset.
ƒ Project (or the work being performed) does not increase the val ue of an already existing District
asset.
ƒ Project (or work being performed) does not increase the useful life of an existing District asset by
a minimum of two years.
ƒ Improvements to private property, including District owned property used for private purposes.
ƒ Improvements made by the District to federally owned property.
3

ƒ Items that are not of a permanent nature, such as window air co nditioners, computers, window
coverings, speakers, telephones, etc. Security cameras are ineligible even if attached to a District
facility and to include an associated hardware such as monitors, servers, keyboards, etc. Only the
installation that requires wiring in the walls (and then associated PM costs are also eligible).
ƒ Items that are not permanently affixed to a public facility suc h that removal of the item would
cause damage to the public facility.
ƒ Items involving recurring maintenance of facility or systems and/or frequent repairs
ƒ Items that occupy floor space but require no permanent connecti on to utilities (hard-wired to
electrical or gas supply) or the structure
ƒ Items not requiring floor space but that sit on top of other eq uipment and will require special
outlets.
ƒ Artwork which has less than $250,000 unit cost.

Specific examples of items NOT eligible for capital financing include:

x Real property purchased for re-sale in the immediate or short term to a private entity or
developer.
x Moving expenses (contact the Office of Budget and Planning if you have further
questions on this item).
x Daily maintenance
x Scheduled maintenance
x Items that may meet the unit cost minimum, but will not be installed into a permanent
structure (ex. Costs for the setup and take down of Inauguration Stands are not capital
eligible, but some materials for the stands may be eligible and should be funded with
Paygo)
x Facility Condition Assessments for facilities NOT in the current approved 6 year CIP.
For example, if you are doing a condition assessment for windows of every building
managed by DGS, to see if windows need to be replaced, but you don’t have a capital
project approved and set up to fund say window replacement in Reeves building (1 of the
projects where assessments are being done), and you now want to replace windows at
Reeves, given the assessment, then the FCA must be funded under operating. If a window
replacement project for Reeves comes into existence and approved for funding during the
year of the FCA, then the expenditures can be moved to the approved capital project for
Reeves window replacement if the capital project has funding available.
x Extended warranties
x Replacement furniture, painting, carpeting
x Replacement modular furniture
x Grounds maintenance
x Replacement books for public libraries
x Library books or school text books purchased as part of a DCPS facility
Modernization/Renovation
x Capital or Finance leases or improvements on leased property where the District does not
gain or have an opportunity to gain ownership to the asset at the end of the lease period or
if the lease period does not cover 75 percent of the life of the facility. If no ownership,
the lease should be classified as an operating lease, using operating budget.
4

x Technology refreshes (except for major version upgrades). The software version number
is the indicator of the extent of an upgrade. Going from version 3.0.2 to version 3.0.3 is
not considered a major upgrade. Moving from 3.0.5 to 4.0 is a major upgrade – as can
be seen from the first number to the left of the decimal place.
x Ineligible FF&E. Audio-visual equipment including, TVs, receivers, security cameras,
speakers (PA and/or pure audio), monitors, other equipment with a per unit cost of less
than $5,000
Exception: white boards of >$5,000 each for school modernization, including the
PC necessary to utilize the white board
x Mechanical and HVAC system maintenance, except for replacement of component parts
that extend the useful life of the asset, such as a motor or air handler
x Self Contained Breathing apparatus as the per unit cost is generally not at least $5,000
x Personal computers, laptops, pads, tablets, peripheral computer equipment, including
printers, and telephones
x Moveable partitions (not affixed to the floor such that removal causes damage to the
facility)
x Window guards (security bars)
x Window mounted air conditioners
x Help Desk staffing costs
x Daily COVID testing for employees at worksites
x Recurring backhaul costs for IT (the backhaul portion of the network comprises the
intermediate links between the core network, or backbone network and the small sub-
networks at the "edge" of the entire hierarchical network
x Service and maintenance agreements on equipment
x IT training (exception: travel expenses for the trainers – not those being trained - is
eligible)
x IT cloud-based services – See Item III g. below.
Exception: development of interface applications with District owned IT assets is
eligible

III. Specific Examples of ‘Questionable’ Project/Expense Types

a. FTE’s:
b. Community gardens built on District owned property (These cannot be booked
as assets since the gardens do not add value to the asset or extend the life of the
asset. Individual components - as presented in the request of September 2013 -
the fences, tool sheds, and the watering systems, can be booked individually as
assets since they meet the $5,000 asset value threshold. The remainder of the
items proposed as part of the ‘gardens’ do not qualify individually and would thus
have to be operating expenses).

c. Facilities Assessments. Performing facilities assessments are not normally
eligible for capital budget funding, except in the case where there already exists
an approved capital project to fund the intended work, but an assessment is
needed to flesh out all needed activity.
5

d. Costs for Pre-Development Activities occurring prior to purchase such as
environmental study, Geotech study, ALTA survey and appraisal are eligible IF
the purchase occurs and which point the costs can be charged to the capital project
and are part of the expenses of the acquisition of the asset.

e. Feasibility studies and strategic plans. Conducting feasibility studies on a
possible capital project does not qualify since it does not result in a new district
asset (Initially, feasibility studies must be charged as operating expenses.)
i. Resulting in the implementation of an eligible capital project? (If a
study/charrette result ultimately gets incorporated into the design of a
capital project, then the expenditure can be reversed from operating and be
charged to capital – as a part of the book value of the asset.)
ii. Not resulting in the implementation of an eligible capital project? (These
would remain operating expenses.)

f. Costs associated with build-out of leased space by a District agency as “tenant”
i. Minimum lease term? (It must be a District ‘capital’ lease, and the term
must be a minimum of 10 years.)
1. A capital lease is defined by the following;
a. Ownership transfers at end of the lease term,
b. Present Value of minimum lease payments must be >90%
of fair value of the asset,
c. There is no ‘bargain purchase’ arrangement in the lease
and,
d. The lease term is greater or equal to 75% of the economic
life of the asset.
ii. Minimum cost threshold? Like all capital projects – it must be a minimum
of $250,000 in the agreed-to lease. As a reminder, FF&E expenditures are
only allowable if their removal would result in damage to the asset being
leased e.g. the building. Additionally, the changes must be permanent in
nature (even after our lease expires) and, must be for the benefit of the
District during the lease term.

g. Capital budget subsidies for affordable housing units in private developments
(Since these costs do not result in a District owned asset they cannot be charged to
capital. We recognize there is a benefit to the District but, we cannot book and
depreciate that benefit.) The ineligible subsidies include those:
i. for persons with cognitive challenges,
ii. for persons earning 0-70 percent of Area Median Income,
iii. for real property purchased for re-sale to a private developer.

h. Signage
Building Signage - that is part of a new building's construction or renovation and
intended to be permanently attached is considered to be included as part of the
6

total building project and capitalized if the total project cost is $250,000 or
greater.
i. Signage is considered permanently attached when removal of the signage
would cause structural damage to the building, defacement to the property,
damage to the sign and/or would require professional removal, such as the
removal by a professional electrician.
ii. Examples of signage in new building construction or renovations that
could be permanently attached include:
1. Major building identification signs placed inside the building
structure at each major entrance which list departments, offices and
floors; Wall-mounted directional signage which reinforces
circulation within the building; Exit and restroom signage; and
scoreboards that are permanently attached to the building structure.
Land Improvements Signage - that is outside and not permanently attached to a
building is considered a land improvement. Signage that is part of a land
improvement project should be included in the total project cost and capitalized if
the project cost is $250,000 or greater.
i. Examples of signage that could be considered land improvements include
the following permanently affixed signage:
1. Identification signage which introduces and welcomes visitors to
your facility.
2. Directional signage which offer motorists and pedestrians the
direction and information they need to make their way around your
facility and grounds.
3. Signage located outdoors and not permanently attached to a
building which identifies a building or locations on your facility
campus.
Signage that is not permanently attached to a building or permanently affixed
outside of a building should be capitalized as equipment if the sign has an
acquisition value of at least $5,000 and a useful life expectancy of five years or
greater.

i. Arts Projects - Arts projects are eligible only if they create a single capital asset
with a minimum cost of $250,000 and the useful life is 5 years or more or in
limited cases where removal of the artwork causes major damage to the facility
(murals are considered part of the structure/facility; sculptures are not since they
can be uninstalled and relocated). Art work costing less than $250,000 cannot be
capitalized as a District asset and must be paid for with operating budget.

j. Cloud Based Software Licensing – and Services (versus Hosted Services)
i. When a cloud computing arrangement does not include a software license,
the arrangement will be treated as a service contract and expensed with
operating budget as the services are received.
ii. When a cloud computing arrangement includes license(s) of software
7

District policy allows for “software which is commercially available either
by license or outright purchase and modified using more than minimal
incremental effort” e.g.
1. Does our IT department - assuming they have the expertise - have
the right to go in and change the code (different from
configuration) to meet our needs?
2. Do we have the contractual right to take possession of the software
at any time during the hosting period without significant penalty?
If we can, then we own an asset, and the fee attributable to the software
license portion of the arrangement should be capitalized. If not, we don’t
own the asset and the costs should be expensed using operating budget.
iii. Further, is the use of the license dependent on the maintenance agreement?
If so, the software is not capital eligible since we’re essentially just being
allowed to use someone else’s product.
iv. If capital eligible, before being put into operation, the expenditures will be
classified based on the three phases of internally generated software.

k. Mini Parks – A plan was presented to design and construct a minimum of four
(4) mini parks, and locate each in a standard on-street parking space to provide
recreational amenities in underserved areas of the District. The creation of these
“mini parks” do not generate a new district owned asset, further is not in nature
therefore the parks as units are not capital eligible. Permanent fixtures and wiring
with unit cost in excess of $5,000 may qualify as individual capital assets.

l. Cool, Green / Solar Roofs - Design and construct new sustainable roofs on
selected DGS portfolio buildings. Replacing roofs, by themselves, does not
increase the value or the expected life of the District asset/building and therefore
are not eligible as capital. However, replacement of an existing roof that has
reached the end of its useful life is an eligible capital expenditure.

m. Living Building Design/Construct – (see feasibility studies above).

n. The following specific projects have also been determined by the CFO to be
ineligible for capital budget: (this list is reference for the types of projects that
cannot be capitalized).

OWNER AGENCY PROJECT PROJECT TITLE
AM0 - DEPARTMENT OF GENERAL SERVICES BC401C HILL E RELOCATION OF GOV'T FAC. & FUNCTION
BD0 - OFFICE OF MUNICIPAL PLANNING PLN37C DISTRICT PUBLIC PLANS & STUDIES
BX0 - COMMISSION ON ARTS & HUMANITIES AH7GPC ARTS & HUMANITIES GRANTS & PROJECTS
DB0 - DEPT. OF HOUSING AND COMM.
DEVELOPMENT 04002C PROPERTY ACQUISITION & DISPOSITION
EB0 - DEPUTY MAYOR FOR ECONOMIC
DEVELOPMENT EB402C PENNSYLVANIA AVENUE SE PROPERTIES &
BUSINESS GRANTS
EB0 - DEPUTY MAYOR FOR ECONOMIC
DEVELOPMENT EB343C GEORGIA AVENUE GREAT STREETS & BUSINESS
GRANTS
8

RM0 - DEPARTMENT OF BEHAVIORAL HEALTH HX403C HOUSING INITIATIVES
KA0 - DEPARTMENT OF TRANSPORTATION PM302C PARKING - PLANNING
KA0 - DEPARTMENT OF TRANSPORTATION PM303C PLANNING AND DESIGN REVIEW
KA0 - DEPARTMENT OF TRANSPORTATION PM304C ADVANCED DESIGN AND PLANNING
KA0 - DEPARTMENT OF TRANSPORTATION PP690C PERFORMANCE PARKING ENHANCEMENTS
KT0 - DEPARTMENT OF PUBLIC WORKS SWS13C,
SWS12C SECURITY CAMERA UPGRADE
FL0 - DEPARTMENT OF CORRECTIONS CR008C UPGRADES CENTRAL SECURITY CAMERAS
FL0 - DEPARTMENT OF CORRECTIONS CR004C GEN RENOVAT UPGRD CNTRL SECURITY COMD
CT
JZ0 – DEPARTMENT OF YOUTH REHABILITATION
SERVICES SH732C DYRS -- MISCELLANEOS CAMPUS UPGRADES
KA0 - DEPARTMENT OF TRANSPORTATION CIT15C PAVEMENT MARKING
EB0 - DEPUTY MAYOR FOR ECONOMIC
DEVELOPMENT EB423C POPLAR POINT ENVIRONEMENT ASSESSMENT
FB0 - FIRE AND EMERGENCY MEDICAL SERVICES NEW SELF CONTAINED BREATHING APPARATUS
JZ0 – DEPARTMENT OF YOUTH REHABILITATION
SERVICES NEW IMPROVEMENTS TO INFRASTRUCTURE ON
HOUSING UNITS
JZ0 – DEPARTMENT OF YOUTH REHABILITATION
SERVICES NEW CONTROL CENTER UPGRADE
FA0 - METROPOLITAN POLICE DEPARTMENT NEW BODY/VEHICLE CAMERAS

IV. Short-Term Bonds (formerly Master Equipment Lease/Purchase Financing)

Currently we are transitioning away from what we had called the Master Equipment Lease/Purchase to
finance some projects, which have a useful life of less than 25 years (the duration of our long term bonds).
This was actually a purchase arrangement through a financing co mpany. Starting in the latter part of FY
2016 we will finance assets with a useful life of 5-10 years (fleet, equipment, and IT types of assets) using
short-term bond financing.

Please contact the Office of Budget and Planning to discuss any questions you may have regarding
specific eligibility for this new financing.

To qualify for short-term bond financing, equipment items must have an individual unit value of at least
$5,000 and a useful life of at least five years.

The following are examples of items eligible for Short-Term Bond capital financing:
ƒ Modular buildings in use for five or more years
ƒ Office furniture, including modular furniture – only as a part of overall building renovations (See bullet
under “eligible projects” for additional information).
ƒ Solar panels, energy projects, and energy management systems – with economic life of between 5-10 years.
ƒ Parking meters
ƒ Information technology investments, including hard wiring of a facility, hardware, and software
purchases (including upgrade of version, e.g., from version 1.0 to version 2.0) including the
manufacturer’s standard term of warranty
ƒ Software (if it meets certain parameters e.g. cost, upgrade of version, etc.)
ƒ Street sweepers, road maintenance, and snow removal equipment
9

ƒ Fleet vehicles, including first responder vehicles and school t ransportation vehicles including
buses and vans
ƒ Traffic lights and crosswalk signals
ƒ Scoreboards and field or stadium lighting
ƒ Playground equipment and outdoor fixed-in-place adult exercise equipment
ƒ Voting machines
ƒ Homeland security and surveillance equipment systems – not including the cameras
ƒ Laboratory equipment (with individual values in excess of $5K)
ƒ Broadcast and video equipment
ƒ Electronic White Boards for schools modernization including the PCs necessary to run them
ƒ Security Fencing and lighting, if permanently mounted
ƒ Building access equipment and security screening equipment (but not cameras)
ƒ Signage – see III e. above for eligibility
ƒ Electronic Signage – see III e. above.
ƒ Building entrance canopies
ƒ Trailers/’Demountable’ Units – must be planned for use of 5 years or longer.
x Purchasing trailers – eligible
x Installation of trailers purchased or rented – eligible
x Installation of lines/connections etc to trailers – eligible
x FF&E – ineligible (only furniture being bought and then placed inside the school/modernization is
eligible, if the trailers are for swing space etc for modernization)
x Construction work to existing trailers – ineligible
x Construction work to rental trailers – ineligible

More on capital leases:
Classifying leases
If a company’s lease meets any of the criteria below, it will be required to record its lease as a finance
lease under the new standard:
1. Transfer of ownership: The lease transfers ownership of the underlying asset to the lessee by the end
of the lease term.
2. Bargain purchase option: The lease grants the lessee an option to purchase the underlying asset that
the lessee is reasonably certain to exercise.
3. Lease term: The lease term is for a major part of the remaining economic life of the underlying asset,
which includes renewal periods reasonably expected to be exercised.
4. Present value: The present value of the sum of the lease payments, and any residual value guaranteed
by the lessee that is not otherwise included in the lease payments, represents substantially all of the fair
value of the underlying asset.
5. Specialized nature: The underlying asset is of such a specialized nature that it is expected to have no
alternative use to the lessor at the end of the lease term.
Balance sheets
10

Once a lease is classified, both types go onto the balance sheet anyway. The difference lies in how the
resulting expenses are classified in a company’s income statement.
For operating leases, the expense is recognized as a rent expense and is recorded in the financial
statements under cost of sales/operating expenses.
For a finance lease, though, the resulting expenses are found in two different areas of the income
statement. First, the right of use asset is amortized straight-line and is recorded as an amortization expense
over the shorter of the related asset’s economic life, or the term of the lease. The second component
relates to the interest expense on the associated lease liability.

g and Specifications
Exhibit J
List of Additive Alternates or Deductive

DESCRIPTION ADD ALT: APPROX. VALUE DEDUCT ALT: APPROX VALUEEXPIRATION DATE
1. ADA Peer Review by CORE Group
$ 15,000 120 dys
2. Insurance waiver approved for the Final
Cleaning bid package (15,000)$ 120 dys
3. Insurance waiver approved for the Overhead
Doors bid package ($75) 120 dys
4. Insurance waiver approved for the Resinous
Flooring bid package ($38,010) 120 dys
5. Insurance waiver approved for the Asphalt
Paving bid package ($109,892) 120 dys
06: Provide a portable stage, portable stair and
portable ramp 28,306$ 120 dys
Brent Elementary School Guaranteed Maximum Price (GMP)
GMP - List of Alternates
Updated Wednesday, October 8th, 2025