The Honorable Phil Mendelson
Chairman
Co
uncil of the District of Columbia
1350 Pennsylvania Avenue NW, S uite 504
Washington, DC 20004-3003
Dear Chairman Mendelson:
Pursuant to D.C. Official Code § 2-352.02, I have enclosed, for consideration by the Council of the District of Columbia,
the (a) Council Contract Summary for the contract between the District of Columbia Housing Authority (“DCHA”) and
Vigil Contracting Inc., and (b) the Contract Number DJ98-54-2024S with Vigil Contracting, Inc.
DCHA proposes to enter into a contract for the Phase 3 unit renovations at the Greenleaf Family DCHA property with
V
igil Contracting, Inc. for one (1) year with four (4) one-year options. Under the proposed contract, Vigil Contracting,
Inc. will receive up to $4,550,000.00.
As always, I am available to discuss any questions you may have re garding the p roposed contract. I n order to
facilitate a response to any questions concerning this contract, please have your staff contact Hammere Gebreyes,
D
irector of External Affairs & Senior Advisor, at (202) 207-4694.
I look forward to your favorable consideration of this proposed contract.
Sincerely,
Keith Pettigrew
Executive Director, District of Columbia Housing Authority
Enclosures
KP/hg
cc: Nyasha Smith, Secretary to the Council
February 6, 2026
COUNCIL CONTRACT SUMMARY
Pur
suant to D.C. Official Code § 2-352.02(c), as amended, the following is provided:
(1) The name of th e propose d c ont ractor, th e c ontract/loan am ount, an d the t erm of t he
proposed contract:
Contractor: Vigil Contracting, LLC (f/k/a Vigil Contracting, Inc.)
Contract Amount: $25,000.00 - $8,000,000.00
Contract Term(s): One (1) base ye a r with four (4) additional one-year options
Source Selection Method: RFP 54-2024
(2) Description of the Goods and Services to be p rovided:
Pursuant to D.C. Official Code § 2 -352.02(b)(2), as amended, I have enclosed for consideration the
Indefinite-quantity Job Order Contract for general construction, repair, and demolition services.
(3) A d escription of the selection p rocess, including the number of of ferors, the eval uation
criteria, the evaluation results, and the basis for selecting the proposed contractor:
The District of Columbia Housing Authority (DCHA), responsible for providing affordable housing
solutions within the District, initiated a competitive bidding process to procure general construction,
repair, and demolition services. This process was set in motion with the release of a Request for Proposal
(RFP) on August 19, 2024.
To ensure maximum visibility and encourage a wide range of participation, the RFP was advertised
extensively in both print and online media. Prominent publications such as The Washington Post,
Washington Informer, Washington Times, and El Tiempo Latino carried the advertisement, reaching a
diverse audience across the District. Additionally, the RFP Notification was prominently displayed on
the
DCHA website and the RFP posted to the Housing Agency Marketplace, providing easy online
access to potential bidders.
The DCHA received thirty five (35) proposals from vendors in response to the RFP. To ensure a fair
and impartial evaluation, a dedicated review panel was convened. This panel comprised experienced
staff members from DCHA's Capital Construction and Design department, bringing their expertise in
construction projects. The evaluation process was rigorous, focusing not only on the technical
requirements outlined in the RFP but also on the vendors' Section 3 plan. This plan is a key component
of the evaluation, aimed to promote job training and employment opportunities for low-income
residents, aligning with DCHA's commitment to social and economic upliftment within the District.
Based on this comprehensive evaluation, the vendor was identified as having successfully met the
technical requirements and
demonstrating the capability to deliver the general construction, repair, and
demolition services. This vendor was Vigil Contracting LLC.
To ensure compliance with government regulations and maintain the highest standards of integrity,
DCHA staff conducted a further review of the qualified vendors using the System for Award
Management.
This crucial step ensured that none of the vendors were debarred or suspended from doing
business with either the federal or District government, safeguarding the procurement process from
potential legal or ethical complications.
Ul
timately, after careful consideration and thorough evaluation, Vigil Contracting, Inc. emerged as the
propos
ed contractor. Their proposal was evaluated based on the firm's technical capability, capacity,
performance history, and proposed pricing coefficients/factors, which are applied to the Construction
Task Catalog. The selection was based on offering the best value while meeting all technical, social
responsibility, and JOC requirements outlined in the RFP.
The contract is an Indefinite-quantity Job Order Contract (JOC) for general construction, repair, and
demolition services. The contract term is one (1) base year with four (4) one-year options. The base year
runs from May 1, 2025, through April 30, 2026. The minimum total amount that may be ordered under
this Contract is $25,000.00, and the maximum total amount that may be ordered during the base year
shall not exceed $8,000,000.00. Work is initiated only upon issuance of a Job Order and a
corresponding Notice to Proceed. A specific Job Order (DJ98-DC02.01) has been issued for the Phase
3 unit renovations at Greenleaf Family with a value of $4,550,000 and an estimated duration of 270
days.
(
4) Background and qualifications of the proposed contractor:
Vigil Contracting , LLC brings over three decades of comprehensive experience to the general
contracting industry, consistently delivering high-quality construction projects across a diverse
range of
sectors. Their extensive history is built on a foundation of deep industry knowledge, a
commitment to regulator y compliance, and a proven track record of successful project
execution. Throughout their 30-ye ar tenure, they have cultivated a reputation for reliability and
excellence, successfully navigating complex projects while adhering to stringent safety and
environmental standards. They understand the critical importance of integrating regulatory
knowledge with practical construction expertise to ensure project success.
Vigil Contracting , LLC possesses the robust qualifications necessary to effectively mobilize
and manage projects of any scale. Their financial stability is demonstrated through consistently
strong financial statements and recent independent audits, showcasing their capacity to handle project
costs and ensure timely completion. Their team comprises seasoned professionals with extensive
experience in all facets of construction, from planning and design to execution and final
delivery. They maintain rigorous quality control measures and prioritize clear communication
with clients and stakeholders throughout the project lifecycle. This commitment to
excellence, coupled with their deep understanding of regulatory requirements, positions
Vigil Contracting , LLC as a reliable and capable partner for any construction endeavor.
(5) Performance standards and expected outcomes of the proposed contract:
The
expected outcomes of this Job Order Contract (JOC) are the efficient and timely completion of
repair, demolition, and general construction projects for DCHA and its affiliated facilities. The
work performed under individual Job Orders is expected to be executed in strict accordance with the
Contract, which includes the Construction Task Catalog® (CTC), Technical Specifications, and all
applicable Federal and District laws, regulations, and codes. Key performance standards include
adhering to project
schedules, maintaining site safety and preparation, providing quality assurance, and performing all work
with experienced labor and high-quality mate rials.
Performance will be rigorously controlled and monitored by the Authority's designated Project Manager.
The Contractor must furnish all necessary management, documentation, labor, materials, equipment,
and design support to complete each Job Order. Quality is maintained through the requirement for
t
echnical submittals such as safety plans, detailed construction schedules, and shop drawings within five
da
ys of receiving the Job Order/Notice to Proceed. Furthermore, all work must align with the
Modernization Principles and Redevelopment Principles adopted by the DCHA Board of
C
ommissioners.
A critical outcome of this contract is the fulfillment of DCHA's commitment to social responsibility.
T
he Contractor is required to comply with Section 3 requirements, which mandate providing training,
e
mployment, and contracting opportunities to low and very low income reside nts of the District of
Columbia, to the greatest extent feasible. Additionally, the Contractor must adhere to the prevailing
w
age rates set forth in the Davis Bacon wage determinations for the Metropolitan Washington D.C.
area, as applicable to the type of construction and working hours specified in each Job Order.
Further ensuring project integrity and completion, the Contractor is required to provide a 100%
P
erformance Bond and a 100% Payment Bond for any individual Job Order exceeding $150,000. Failure
to
submit these acceptable bonds at the time the Notice to Proceed is issued can result in the cancellation
of
the Job Order and possible termination of the Contract for default. This bonding requirement
guarantees faithful performance and payment for all labor and materials used in the performance of the
Work.
(
6) Description of the funding source for the proposed agreem ent and a certification that th e
proposed agreement is consistent with the District's f inancial plan and budget:
Th
e funding source is the capital funds allocated to DCHA in the Fiscal Year 2025 budget. The
certification that the proposed contract is consistent with the District's financial and budget is attached.
(7)A
certification of legal sufficiency:
The Legal Sufficiency Memorandum is attached.
(8)A
certification that the proposed contractor's/proposed owner is in compliance with District
tax laws:
The District tax law compliance certification is attached.
(9) The
status of the proposed contractor as a certified local, small or disadvantaged business
enterprise.
Vigil Contracting, LLC's subcontractor, Cobra Contracting LLC, is a Certified Business Enterprise
(CBE). This designation reflects Vigil Contracting, LLC's ’s commitment to diversity and inclusion in
business opportunities. Vigil Contracting, LLC meets the District’s criteria for CBE participation in
government contracting.
(10) A s t atement i ndicating w hether the p roposed con tractor i s cu rrently d ebarred from
providing services or good to th e District o r federal government:
DCHA’s Office of Administrative Service has conducted a federal and local search of Vigil Contracting,
LLC
and has found no evidence of federal or District debarment.
(11) Where the contract, if executed, will be m ade available via F OIA request:
The contract will be made available on the DCHA website.
(12) Where the original solicitation, and any amendment or modifications, will be made
available online:
Original solicitation #54-2024 w as published on the DCHA Website. See link:
http://dchousing.org/wordpress/solicitations.
Initial File #: C00005934358
Entity Type: Foreign Business Corporation
GOVERNMENT OF THE DISTRICT OF COLUMBIA
DEPARTMENT OF LICENSING AND CONSUMER PROTECTION
CORPORATIONS DIVISION
C E R T I F I C A T E
THIS IS TO CERTIFY that all applicable provisions of the District of Columbia Business
Organizations Code (Title 29) have been complied with and accordingly, this CERTIFICATE OF
GOOD STANDING is hereby issued to
Vigil Contracting, LLC
WE FURTHER CERTIFY that the qualified foreign entity is registered to do business in the
District; that all fees, and penalties owed to the District for entity filings collected through the Mayor
have been paid and Payment is reflected in the records of the Mayor; The entity's most recent
biennial report required by § 29-102.11 has been delivered for filing to the Mayor; and the entity's
registration has not been terminated. This office does not have any information about the entity’s
business practices and financial standing and this certificate shall not be construed as the entity’s
endorsement
IN TESTIMONY WHEREOF I have hereunto set my hand and caused the seal of this office to be
affixed as of 12/15/2025 12:25 PM
Muriel Bowser
Mayor
Tracking #: C2025CT0001684
Business and Professional Licensing Administration
IGILPOWERED BY ®YNG
CERTIFICATE OF FEDERAL TAXES
DistrictofColumbiaHousingAuthority3007mStreet,SW,10nFloorWashington,DC 20032
1, JJVigitPresidentofVigilContracting ,herebycertifythatVialContractingis
currentwithitsfederaltaxableobligations,orhasworkedoutandiscurrentwitha paymentschedule
approvedbythefederalgovernment.
Title:President
Date:December8—_, 2025
StateofMaryland
CountyofAnneArundel
lherebycertifythatonthis&th_dayofDecembar2025,W Vigil_ personallyappearedbeforemeandacknowledged{he _JisthePresident‘OfVisiContracting,andin{his Jcapacityasthe Presidentofvigiconvacting,[he |]executedthiscertificateasofthedatesetforthabove.
NotarySeal
SHANNONMAZZOGHTNotaryPublic-MarylangBaltimoraCountyMyCammissionExpirosDecember18,2025
ViciPOWERED BY ®BYNG
TheundersignedherebycertifiesthatVigilContractingiscurrentlynot,andwillnotbe,in
violationof Districtof Columbia Code §1-1163.34a, which provides a covered contractorshallnot
contributetoaprohibitedrecipientduringtheprohibitedperiod.
39. ne
ON Vigil
Title:President
NOTARY:
Iherebycertifythaton this_8th___ dayof s«t#2025, _JuVigil personallyappearedand
signedthisdocumentandacknowledgedthathewasthePresidentofVigilContracting
Arann Magyarse
State/County/DistrictofColumbia NotaryPubli
[SEAL] SHANNON MAZZOCHINotaryPublic-MarylanaBaltimoreCountyMy CommissionExpiresDagember18.2025
Vicu.POWERED BY ®YNG
CERTIFICATE OF PENDING LITIGATION
Date:December6, 2025_
DistrictofColumbiaHousingAuthority
3007mStreet,SW, 10nFloor
Washington,DC 20032
1,JUVigil,ProsidentofVigilContracting _herebycerfifythatVigilContractinghas no pending claims againstthe Districtof Columbia or the Districtof Columbia Housing Authority
—Namé?JJVigTitle:PresidentDate!Decembers__,2025
Stateof_Maryland
Countyof AnneArundi
Iherebycertifythaton this_gih_dayofDecember,2025, JJVigil_ personallyappearedbeforeme and
acknowledgedhe JisthePresident OfVigiContecing,andin(his]capacityasthePresident
ofvigtcontracting,[he] executedthiscertificateasofthedatesetforthabove.
NotarySeal
‘SHANNONMAZZOCHTNoteryPublic-MarylandBaltimoraCountyMyCommissionExpirasDacamper18,2026.
IGILPOWERED BY iBYNG
TEAM AFFIDAVITCERTIFICATE
1,UdVigil,PresidentofVigilContracting herebyattestthatall
membersoftheteamwhoarelistedbelowarenotlistedintheListofPartiesExcludedfromFederalProcurementorNon-ProcurementPrograms:
ProjectName: _GreenleafMakeReady
ProjectNumber:_DJ98-DC02.01,
CONSTRUCTION TEAM:
Contractor;VigilContracting
Subcontractor:Cobra Contracting
Subcontractor: Charm CityConstruction
Subcontractor.
|furtherattestthatnoprincipal,majorstockholder,officer,ordirectoroftheconstructionteamisdebarredfromparticipatinginafederalprocurementornon-procurementprogram.
By.28.4)
Name: JJ Vigil
Title:President
Date:December8_, 2025
Stateof __Maryland
Countyof _AnneArundel
\herebycertifythatonthis_8th_dayofDecember2025,JJVigil_ personallyappearedbefore
meandacknowledged[he JsthePresidentOfVigContracting,andin(his] capacityas
the[SignatoryTitle]of[Contractor],[he/she]executedthiscertificateasofthedatesetforth
above.
NotarySeal or dh am Ny yt a
Name: non oChe
"SHANNONMAzZOCHTNotaryPublic-MarylendBaltimoreCountyMyCommissionExpiresDecember18,2026
*
*
* GovernmentoftheDistrictofColumbia
HEE OfficeoftheChietFinancialOfficer 11014!Street,SWHam OfliceofTaxandRevenue Washington,DC20024
DateofNotice:February6,2026 NoticeNumber:0015653493 =
VIGILCONTRACTING,LLC FEIN:**-"0"24472140PRIESTBRIDGECT STE7 CaseID:18868649CROFTONMD 21114-2499
CERTIFICATE OF CLEAN HANDS
AsreportedintheCleanHandssystem,theabovereferencedindividual/entityhasnooutstandingliabilitywiththeDistrictofColumbiaOfficeofTaxandRevenueortheDepartmentofEmploymentServices.Asofthedateabove,theindividual/entityhascompliedwithDCCode§47-2862,thereforethisCertificateofCleanHandsisissued.
TITLE 47. TAXATION, LICENSING, PERMITS, ASSESSMENTS, AND FEES
CHAPTER 28 GENERAL LICENSE
SUBCHAPTER II.CLEAN HANDS BEFORE RECEIVING A LICENSE OR PERMIT
D.C. CODE § 47-2862 (2006)
§47-2862PROHIBITIONAGAINST ISSUANCE OF LICENSEOR PERMIT
AuthorizedBy Melinda Jenkins
Branch Chief,Collectionand Enforcement Administration
Tovalidatethiscertificate,pleasevisitMyTax.DC.gov.OntheMyTaxDC homepage,clickthe“Validate a Certificateof Clean Hands” hyperlink under the Clean Hands section.
11014thStreetSW,SuiteW270,Washington,DC20024/Phone:(202)724-S048/MyTax.DCgov
MEMORANDUM
TO:
FROM:
DATE:
Keith Pettigrew
Executive Director
Andrea Powell
Deputy General Counsel
February 6, 2026
District of Columbia Housing Authority
300 7th Street, SW, 10th Floor, Washington, DC 20024
202-535-1000
Keith Pettigrew, Executive Director
SUBJECT: Proposed Contract for Phase 3 Unit Renovations services at the Greenleaf Family
DCHA project between
District of Columbia Housing Authority (“DCHA”) and Vigil
Contracting, LLC (“Contractor”) to be submitted to the Council for the District of
Columbia for approval pursuant to D.C. Official Code §2-352.02(a)(1), as
amended.
1. Procurement Process
I have enclosed
for consideration by the Council of the District of Columbia, the Council
Contract Summary for a proposed contract, in an amount up to $4,550,000.00 between DCHA
and Vigil Contracting, LLC. This proposed contract is for the Phase 3 unit renovations services at
the Greenleaf Family DCHA project. DCHA issued a Request for Proposal (RFP) Solicitation No.:
54-2024 on August 19, 2024. To ensure maximum visibility and encourage a wide range of
participation, the RFP was advertised extensively in both print and online media. Prominent
publications such as The Washington Post, Washington Informer, Washington Times, and El
Tiempo Latino carried the advertisement, reaching a diverse audience across the District.
Additionally, the RFP Notification was prominently displayed on the DCHA website and the
RFP posted to the
Housing Agency Marketplace, providing easy online to potential bidders.
The DCHA received proposals from vendors in response to the RFP. To ensure a fair and impartial
eval
uation, a dedicated review panel was convened. Based on this comprehensive evaluation, the
vendor was identified as having
successfully met the technical requirements and demonstrating
the capability to deliver the required storm water management service. The vendor was Vigil
Contracting, LLC
2. Description
of Proposed Contract
This
proposed contract
between DCHA and Vigil Contracting, LLC is for the Phase 3 unit renovations
services at
the Greenleaf Family DCHA project. A contract will be entered into with Vigil C ontracting,
Inc.
The length of the Contract will be
a one year contract with four (4) one year options. The scope of
www.dchousing.org
www.dchousing.org
work in the Contract contains sufficient details and plans. DCHA will fund the Contract with
capital funds allocated to DCHA in the Fiscal Year 2025 budget which is in compliance with the
applicable Federal and District of Columbia regulations and DCHA’s policies and procedures.
3. Legal
Review
The DCHA
Office of the General Counsel (OGC) has reviewed the proposed Contract with Vigil
Contracting
, LLC for legal sufficiency. OGC’s review of the Contract indicated that it is legally
sufficient. In
addition, we are not aware of any pending legal claims of Vigil Contracting, LLC.
against the
District of Columbia or DCHA.
APPROVED AS TO
LEGAL SUFFICIENCY:
Andrea Powell
Deputy General Counsel
District of Columbia Housing Authority
CERTIFICATIONS
I hereby certify that the proposed contract between the District of Columbia Housing
Authority ("DCHA") and Vigil Construction LLC to provide Phase Three unit renovations
services for the Greenleaf Family DCHA property in the amount ofup to Four Million Five
Hundred Fifty Thousand Dollars ($4,550,000) from capital funds allocated to DCHA in the
Fiscal Year 2025 budget, is in compliance with the applicable Federal and District law and
DCHA's policies and procedures.
Keith Pettigrew
Executive Director,
DCHA
Dated: February 6, 2026
I have reviewed this proposed action. DCHA will make available to Vigil Construction LLC
up to Four Million Five Hundred Fifty Thousand Dollars ($4,550,000) to provide Phase Three
unit renovations services for the Greenleaf Family DCHA property. This action is within the
appropriated DCHA budget authority for the Fiscal Year 2025 and is consistent with the
financial plan and budget adopted by the District of Columbia and such funds are available
for administration by DCHA in Fiscal Year 2026.
Dated: February 6, 2026
Zewdneh Shiferaw
Deputy Chief Financial Officer
RESOLUTION 25-08
TO AUTHORIZE THE EXECUTION OF MULTIPLE JOB ORDER CONTRACTING
(JOC) CONTRACTS
WHEREAS, District of Columbia Housing Authority (“DCHA”), its instrumentalities
and affiliates require a large capacity of contracts to accomplish various projects for
repair, alteration, modernization, maintenance, rehabilitation, demolition, construction
and environmental services at various properties; and
WHEREAS, on August 18, 2024 , DCHA advertised a Request for Proposals
(“RFP”) in was placed in The Washington Post Sunday Edition , Washington Informer,
Afro American, The Washington Times, El Tiempo Latino and East of the River. Copies
were emailed to LSDBE Vendors Email Blast, Section 3 Vendors Email Blast, all District
Government Certified Business Entity members and all District of Columbia Department
of Housing and Community Development (“DHCD”) Section 3 vendors; and
WHEREAS, on August 19, 2024, Solicitation No. 54 -2024 Job Order Contracting
(JOC) was posted on the DCHA website, and the Agency’s e-procurement system; and
WHEREAS, Solicitation No.’s 54 -2024, 54 -2024A through 54 -2024I for JOC
General Construction, Electrical, Mechanical and Plumbing, and Electrical and Fire Alarm
for the repair, alteration, modernization, maintenanc e, rehabilitation, demolition and
construction of infrastructure, buildings and structures by means of Job Orders issued
under JOC Indefinite Delivery Indefinite Quantity (IDIQ) contracts (“JOC Contract”) was
posted to the Agency’s e-procurement system Bonfire, issued to the Department of Small
and Local Business Development, bidders interested in doing business with DCHA,
posted to the DCHA Website; and
WHEREAS, by November 20, 2024, DCHA received thirty -five (35) proposals for
evaluation; and
WHEREAS, the solicitation stated that DCHA would make an award to the firms
that were deemed technically qualified in accordance with the solicitation requirements
for the repair, alteration, modernization, maintenance, rehabilitation, demolition and
construction of infrastructure, buildings and structures, and in the best interest of DCHA;
and
RESOLUTION 25-08
TO AUTHORIZE THE EXECUTION
OF MULTIPLE JOB ORDER CONTRACTING
(JOC) CONTRACTS
WHEREAS, based on the proposals and the results of the evaluation process,
DCHA determined that A.L. Merton, ARS Design Build, Autumn General Contracting,
LLC, Bennett Group, C & A Electric, Inc, Centennial Contractors Enterprises, Inc.,
Consys Inc., Delkan Group, First Choice Construction, HEP Construction, Irreno
Construction Company, JAP Construction LLC, Landivar and Associates, Metropolitan
Engineering Inc., Micon Construction, Inc, Mo Construction Inc., One-Kare Enterprise
LLC, S-Works Construction Corporation, TMG Construction Corporation, Vigil
Contracting Inc., Walker Construction have met the technical requirements of the RFP
as a qualified firms capable of providing the repair, alteration, modernization,
maintenance, rehabilitation, demolition and construction of infrastructure, buildings and
structures by means of Job Orders issued under JOC Contracts; and
WHEREAS, DCHA performed a review of the Federal Systems Award
Management and the District’s Excluded Parties List on March 10, 2025, and has
determined that A.L. Merton, ARS Design Build, Autumn General Contracting, LLC,
Bennett Group, C & A Electric, Inc, Centennial Contractors Enterprises, Inc., Consys Inc.,
Delkan Group, First Choice Construction, HEP Construction, Irreno Construction
Company, JAP Construction LLC, Landivar and Associates, Metropolitan Engineering
Inc., Micon Construction, Inc, Mo Construction In c., One-Kare Enterprise LLC, S -Works
Construction Corporation, TMG Construction Corporation, Vigil Contracting Inc., Walker
Construction does not appear on that list.
RESOLUTION 25-08
TO AUTHORIZE THE EXECUTION
OF MULTIPLE JOB ORDER CONTRACTING
(JOC) CONTRACTS
NOW, THEREFORE, BE IT RESOLVED , that the Board of Commissioners of
District of Columbia Housing Authority hereby authorizes the Executive Director to
execute twenty -one (21) contracts to provide repair, alteration, modernization,
maintenance, rehabilitation, demolition and construction of infrastructure, buildings and
structures by means of Job Orders issued under JOC Indefinite Delivery Indefinite
Quantity (IDIQ) contracts (“JOC Contract”) at various pro perties owned by or done on
behalf of, the Authority or any of its instrumentalities or affiliates, for a period of five (5)
years consisting of one (1) base year with four (4) one -year options, in the minimum
aggregate amount of Five Hundred Twenty -Five Thousand Dollars ($525,000.00) not to
exceed the maximum aggregate amount of Five Hundred Thirty -Five Million Dollars
($535,000,000.00), subject to the availability of funding.
ADOPTED, by the Board of Commissioners and signed in authentication of its
passage the 9th day of April 2025.
ATTEST: APPROVED:
Keith L. Pettigrew Raymond Skinner
Executive Director/Secretary Chairperson
APPROVED FOR FORM AND LEGAL SUFFICIENCY:
Amy M. Glassman
Senior Vice President & General Counsel
GOVERNMENT OF THE DISTRICT OF COLUMBIA
PROFILE SUMMARY
(CONTRA
CTs TO PURCHASE, SELL, ACQUIRE, TRANSFER, LEASE OF REAL
PROPERTY/ EXCLUSIVE RIGHT AGREEMENTs/LOANs & GRANTs OVER
$1M/INTRA-DISTRICTs)
Contract Agency: District of Columbia Housing Authority
________________________________
Agency Code
________003______
___
Using Age
ncy: District of Columbia Housing
Authority Agency Code
_______________________________ ______003_________
Loan/Grant/Lease Sub-recipient Name: Vigil Contracting, LLC.
Should the D.C. Council have any questions regarding this loan/grant/lease, please contact:
Michael R
eese (202) 439-0007
Program Manager Telephone #
TYPE OF D
OCUMENT SUBMITTED
1. ❒ Loan/Grant/Lease Modification 4. ❒ Unwritten or Informal Contract
2. ❒ Exercise of Grant Option Year (E.O.) 5. ❒ Lease of Real Property
LOAN/GRANT TYPE
1. ❒ Subsidy 4. ❒ Cost Reimbursement
2. ❒ Loan Price 5. ❒ Time and Material
3. X Task Order 6. ❒ Advance Payment
3. ❒ Loan/Grant/Lease Modification: 6. ❒ Other:
Contract for Phase 3 Unit Renovations
at Greenleaf
{0030246 -}
GRANT/LOAN/LEASE INFORMATION
Grant/Loan/Lease No.: DHA21C-FY25-005A Subsidy: $4,550,000.00
Subsidy Amt. Required This FY: $4,550,000.00 Amt. Required Next FY: N/A
Caption: DJ98-DC02.01 Unit Renovations Term: Under 365 days
Does this H
ousing Subsidy Amount exceed $1 million: Yes No
If yes, p
lease attach a copy of the DC Council approval and provide the following information:
Date received: Date approved:
LEASE IN
FORMATION - N/A
Lease No.: Total Cost Location:
Annual Cost Sq. Ft. Leased: Cost Per Sq. Ft.
Total
Bldg. Sq. Ft.: % Sq. Ft. Leased By D.C.
BRIEF DES
CRIPTION OF GRANT/LOAN/LEASE
SOURCE OF FUNDING
1. ☐Appropriated 4. ☐Intra-District
2. ☐Capital 5. ☐Inter-Jurisdictional
3. ☐Grant ( ) 6. ☒Other: (Indicate: ) District Funds
If pro
curement action is funded by grant or other non-capital or non-appropriated funds, will the
District need to expend some portion of its funds prior to receiving funds from the grantor or
other funding source?
Yes No Not a pplicable
If Yes, in
dicate the amount the District will need to expend and the percentage this amount
represents of the total funds required to support the effort. District Funds $
% .
X
X
CONTRACT
JOB ORDER CONTRACT UOC)
THIS CONTRACTmadeandenteredintothisJst_dayof May_,2025by andbetween:Vigil
Contracting,Ine,hereinaftercalledthe“Contractor”and(heDistrictofColumbiaHousingAulhorily
hereinaitercalledthe“DCHA”.
WITNESSETH,thattheContractorandtheDCHA tortheconsiderationslatedhereinmutuallyagreeas
follows:
ARTICLE1:StatementofWorkTheContractorshellfurnishallInbor,materials,tools,equipment,andices,andperformandcompleteallworkrequiredforContractNo.5: natrictaccordancewith
ContractNo,54-20248,anyAddendatherefo,Drawings,ConsituctionTaskCatalogs-Distribution,UsingTheConstmetionTaskCatalog®-Distribution,TechnicalSpecifications~Distribution;JOCREPVolumeiandVolumeLV,andReportsreferencedtherein,whichsaidTechnicalSpecifications,Reports,AddendaandDrawingsareincorporatedhereinbyreferenceandmadeaparthereof,
ARTICLE2:TheComractSumThisContractisanindefinite-quantityJobOrderContractJOC}tortherepair,demolition,and/orconstructionoftheilemsspecified,TheminimumtotalamountthatmaybeorderedunderthisContractis$25,000.00.ThemaximumtotalamountthalmaybeorderedwadetthisContractduringthebaseyearperiodofMay 1,2025throughApril30,2026shallnotexceed.
$8,000,000.00,Thismaximummaybeadjustedinaccordancewithanyapprovedcontractamendments,Thecomtraettormisone(1)baseyearwithfour(4)one-yearoptionperiods,AnyunusedcontractcapacitymayberolledoverutlhediscretionofDCHA.‘NoworkshaltcommenceunderthisContractuntilaJobOrderhasbeenissuedandacorrespondingNoticestoProceedhasbeenprovidedbyDCHA,
DC CouncilApprovalMandate:
InaccordancewithDC Councilmandateanyconttact(s)awardedbyDCHA andmeetthe
requirementslistedbelowrequireYCCouncilApproval.TheCouncilhastwoapprovalworktlows,
(1)Passive-contractisapprovedwithin10daysofsubmittal;and(2)Active-contractmaymake
up1045daysaficrsubmitial,TheproposedcontractunderthisrosolutionissubjecttoDCCouncil
approvalbasedontheaguregatelotalandmulti-yearawardrequestedabove.Forthepurposeof
JOC contracts DCHA is only required to submit Job Orders and ‘ask Orders subject to the
requirementsbelow.
1.Aggregatetotalisequaltoorgreutorthan$1,000,000.00,
2.Multi-yearcontracts[«typicalJobOrderorTaskOrderislessthan12monthshowever,
shouldalimeextensionherequired#2willbeapplicable];3, Or both | and 2.
ARTICLE 3:‘TheContractTermOne(1)baseyearwithFour(4)one-yearoptions.BaseyearMay 1,
2025—April30,2026;4oneyearuptionrenewalatthediscretionofDCHAbasedoncupacityandperfortmance.Inaddition,ContractoruuusedcontractcapacitymayberolledaverperDCH\’sdiscretion.
ARHICLE4:ContractDocument
‘ChisContractshallconsistofthecomponentparts,allafwhichareincorporatedhereinandmadeparthereof:
BidDocuments
1
2,
3#
‘ThisContract
General Conditions of the Contract forConstruction IUD Form 3370
DCHASupplementalConditions
AILRFPDocuments
a.JOCSpecialConditions
b.ConstructionTaskCatalog?-Distribution
c.Drawings
UsingTheConstructionTaskCatalog®~Disiribution
&.TechnicalSpecificationsDistribution
£ JOCREPVolutne1
JOCREPVolumeIV
hyReports
TochnicalSpecifications
je Addenda
MAWBERequirements
Scetion3 Requirements
ApprenticeshipProgeam
AffirmativeAction/ContractComplianceRequirements
WageDecision
ProtestProcedures
Schedule
DCHAModemizationPrinciples
DCHA’ RedevelopmentPrinciples
CowtractForrn(Sample)
PaymentBond(Sample)
PerformanceBond(Sample)
BidSubmissionRequirements
W
18,
19,
20,
21.
22.
23,
24,
25.
26.
BidBondForm(Sample)BidFormStatementofBiddersQualifications,Representations,CertificationsandOtherSlatementsofBidders,IUD FormNon-CollusiveAffidavitPrieneContractor’CertificationofContiamedEligibility‘TaxCertificationAffidavitPaymenttoSubcontractorsandSuppliersCentificateContractorsOptiontoPerformWorkatOtherthanAuthorityOwnedorControlledInstitutionData Form/{nto
27. NoticestoProceed
THIS CONTRACT, logetherwiih Lhe otherdocuments enumotated in Article3 with saidother documents
areasfullyapattoftheJobOrderContactNo54-20248asifattachedheretoorrepeatedherein,fromtheContract.IntheeventthatunypartofthisContractshallbedeclaredunenforceableorinyalid,theprovisionsinArticle3shallgovern,oxoeptasotherwisespecificallystated,Thevariousjwovisionsinthe‘AddendashallbeconstruedinorderofpreferenceofthecomponentpartoftheContractwhicheachmotifies.
ThisContractmayheexecutedbythepartiesinoneormorecounterpatts,eachof whichshallbedeemed.tobeanoriginalhereofandallofwhichcounterpartoriginalsshallbedomedtoconstituteoneandthesamedocument,
NoworkundertheContractshallcommenceuntilaJobOrderhasbeenexecutedandthecontractorisin
receiptofa NoticetoProceedissuedbyDCIIA.
INWITNESSWEEREOS,thepastiestherciohavecausedthisContracttobeexecutedasofthedayandyearfirstabovewritten,
VigilContracting,Ine
“(Contractor
BY__WVigil 28,
~ (Person'sNuh
dedsealy oeved Tite coo
BusinessAddress:
2140 Prios|Bridge Ct,Suite 7
(Sireet)
Crofton,Md 21114
«City)
Witness: DistrictofColumbiaHousingAuthority
ery! Moore
Vile___ ContractingOfficer
BusinessAddress:
3007"StreetSW 10"Floor
(Steet)
Washinglon,D.C,20024
CERTIFICATION:
1, _ddVigil ___ certifythatTamthe coo oftheCorporationnamedasContractorherein;thal__JJVigil chosignedthisContractonbehalfoftheConnuoter,wasthen coo ofsaidConporation,thatsaidContractwasduly
signedforandinbehalfofsaidcorporationbyauthorityofitsgoverningbody,andiswithinthescopeofitscorporatepowers,
By Vigil...Oe fo .
Title_GOO
ADDENDUM
ADDENDUM NO. 1 to Contract No 54-2024S
ISSUED: June 27, 2025
CONTRACT NO.: JOC 54-2024S
Job Order Contracting
Vigil Contracting, Inc , shall acknowledge receipt of this addendum, by returning it. Failure to
acknowledge receipt of this addendum may be cause for rejection of your contract.
Contractor’s are informed that the above-named contract is modified as follows:
The District of Columbia Housing Authority hereby issues Addendum No. 1 is hereby
amended to include the following:
A. Contract Documents, Article 4 Item 17, page 2, Bid Bond Form (Sample) Delete
“Form” and (“Sample”)
B. Payment and Performance Bond Requirements
WHEREAS, in accordance with 2 C.F.R. § 200.326 and the DCHA Procurement and
Contracting Policy § 7203.5(a), DCHA requires Payment and Performance Bonds for
construction contracts exceeding $150,000; and
WHEREAS, DCHA is clarifying its requirements to ensure uniform application and
enforceability across all Job Order Contracts;
NOW, THEREFORE, the following shall apply and be binding on the Contractor as part of its
Contract with DCHA:
1. Performance Bond Requirement
The Contractor shall provide a Performance Bond in the amount of 100% of the Job
Order price prior to commencement of any work authorized by an individual Job Order
issued under this Contract. The Performance Bond shall guarantee the faithful
performance of the work in accordance with the terms and conditions of the Contract.
2. Payment Bond Requirement
The Contractor shall provide a Payment Bond in the amount of 100% of the Job 3.
ATTACHMENT A
Addendum No.
JOC Contract 54-2024S
Job Order Contracting
DCHA Contract 54-2024S Job Order Contracting Page 2 of 2
Order price prior to commencement of any work authorized by an individual Job Order.
The Payment Bond shall guarantee the payment of all labor, materials, supplies, and
services used in the performance of work under the Contract.
3. Bonding Form and Surety Approval
Bonds shall be executed on the standard DCHA bond forms as included in the Contract
Documents (refer to JOC RFP 2024 Volume I) and must be issued by a surety company
authorized to do business in the District of Columbia and acceptable to DCHA.
4. Execution and Delivery
The required Payment and Performance Bonds must be submitted for each Job Order
exceeding $150,000 at the time the Notice to Proceed is issued. Failure to submit
acceptable bonds shall result in the cancellation of the Job Order and may be grounds for
termination of the Contract for default.
5. Modifications and Enforceability
No part of this Addendum shall be deemed to waive or limit any right of DCHA under
the original Contract documents. The Addendum is incorporated into the Contract and
shall have the same force and effect as if originally included therein.
ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED
ADDENDUM
ADDENDUM NO. 1 to Contract No 54-2024S
ISSUED: June 27, 2025
CONTRACT NO.: JOC 54-2024S
Job Order Contracting
Vigil Contracting, Inc , shall acknowledge receipt of this addendum, by returning it. Failure to
acknowledge receipt of this addendum may be cause for rejection of your contract.
Contractor’s are informed that the above-named contract is modified as follows:
The District of Columbia Housing Authority hereby issues Addendum No. 1 is hereby
amended to include the following:
A. Contract Documents, Article 4 Item 17, page 2, Bid Bond Form (Sample) Delete
“Form” and (“Sample”)
B. Payment and Performance Bond Requirements
WHEREAS, in accordance with 2 C.F.R. § 200.326 and the DCHA Procurement and
Contracting Policy § 7203.5(a), DCHA requires Payment and Performance Bonds for
construction contracts exceeding $150,000; and
WHEREAS, DCHA is clarifying its requirements to ensure uniform application and
enforceability across all Job Order Contracts;
NOW, THEREFORE, the following shall apply and be binding on the Contractor as part of its
Contract with DCHA:
1. Performance Bond Requirement
The Contractor shall provide a Performance Bond in the amount of 100% of the Job
Order price prior to commencement of any work authorized by an individual Job Order
issued under this Contract. The Performance Bond shall guarantee the faithful
performance of the work in accordance with the terms and conditions of the Contract.
2. Payment Bond Requirement
The Contractor shall provide a Payment Bond in the amount of 100% of the Job 3.
ATTACHMENT A
Addendum No.
JOC Contract 54-2024S
Job Order Contracting
DCHA Contract 54-2024S Job Order Contracting Page 2 of 2
Order price prior to commencement of any work authorized by an individual Job Order.
The Payment Bond shall guarantee the payment of all labor, materials, supplies, and
services used in the performance of work under the Contract.
3. Bonding Form and Surety Approval
Bonds shall be executed on the standard DCHA bond forms as included in the Contract
Documents (refer to JOC RFP 2024 Volume I) and must be issued by a surety company
authorized to do business in the District of Columbia and acceptable to DCHA.
4. Execution and Delivery
The required Payment and Performance Bonds must be submitted for each Job Order
exceeding $150,000 at the time the Notice to Proceed is issued. Failure to submit
acceptable bonds shall result in the cancellation of the Job Order and may be grounds for
termination of the Contract for default.
5. Modifications and Enforceability
No part of this Addendum shall be deemed to waive or limit any right of DCHA under
the original Contract documents. The Addendum is incorporated into the Contract and
shall have the same force and effect as if originally included therein.
ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED
ADDENDUM
ADDENDUM NO. 2 to Contract No 54-2024S
ISSUED: July 2, 2025
CONTRACT NO.: JOC 54-2024S
Job Order Contracting
Vigil Contracting, Inc, shall acknowledge receipt of this addendum, by returning it. Failure to
acknowledge receipt of this addendum may be cause for rejection of your contract.
Contractor’s are informed that the above-named contract is modified as follows:
The District of Columbia Housing Authority hereby issues Addendum No. 2 is hereby
amended to include the following:
A. Payment and Performance Bond Requirements
WHEREAS, in accordance with 2 C.F.R. § 200.326 and the DCHA Procurement and
Contracting Policy § 7203.5(a), DCHA requires Payment and Performance Bonds for
construction contracts exceeding $150,000; and
WHEREAS, DCHA is clarifying its requirements to ensure uniform application and
enforceability across all Job Order Contracts;
NOW, THEREFORE, the following shall apply and be binding on the Contractor as part of its
Contract with DCHA:
1. Performance Bond Requirement
The Contractor shall provide a Performance Bond in the amount of 100% of the total
Contract price prior to commencement of any work authorized by an individual Job Order
issued under this Contract. The Performance Bond shall guarantee the faithful performance
of the work in accordance with the terms and conditions of the Contract.
2. Payment Bond Requirement
The Contractor shall provide a Payment Bond in the amount of 100% of the total
Contract price prior to commencement of any work authorized by an individual Job
Order. The Payment Bond shall guarantee the payment of all labor, materials, supplies, and
services used in the performance of work under the Contract.
ATTACHMENT A
Addendum No. 2
JOC Contract 54-2024S
Job Order Contracting
DCHA Contract 54-2024S Job Order Contracting Page 2 of 2
3. Bonding Form and Surety Approval
Bonds shall be executed on the standard DCHA bond forms as included in the Contract
Documents (refer to JOC RFP 2024 Volume I) and must be issued by a surety company
authorized to do business in the District of Columbia and acceptable to DCHA.
4. Execution and Delivery
The required Payment and Performance Bonds must be submitted for any contract
exceeding $150,000 at the time the Notice to Proceed is issued. Failure to submit
acceptable bonds shall result in the cancellation of the Job Order and may be grounds for
termination of the Contract for default.
5. Modifications and Enforceability
No part of this Addendum shall be deemed to waive or limit any right of DCHA under the
original Contract documents. The Addendum is incorporated into the Contract and shall
have the same force and effect as if originally included therein.
ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED
Checklistof Documents Included:
Summary Cost Sheet
Notice to Proceed
Wage Determination
ProjectScope of Work
UtilizationCompliance Report
Pre-ConstructionEvaluation
Summary ofCost Project
ID# DJ98-DC62.01
Phase 3 Unit
Renovations at
GreenleafFamily
am # DescriptionofTask value Comments
1 | Phase3UnitRenovationsatGreenteat 84,580,000.0Family
2 | socProgramLicensingFee1.95% $50,000.01
3 | FundingSource DGFY25
4 | PropertyGode e021
TOTAL $84,800,000.00}
Districtof Columbia Housing Authority
Job Order Contracting (JOC) Program
Phase 3 Unit Renovations at Greenleaf Family
ProjectNumber: DJ98-DC02.01
Project Manager: LaTrice Browning
JOCJobOrderPackage-DJ98-DC02.01
DistrictofColumbiaHousingAuthority
Job Order/Notice To Proceed (NTP)
Date: August07,2025, JobOrderNumber,— QJ98-0¢02.01
GontractNumber: Duse-54-20245 PONumber:
ProjectNumber—DJ98-DC02.01
ProjectName:____Phase3UnitRenovationsatGreenleafFamily
ProjectLocation:
C021-Greenleaf
‘Schedule: ProposedNTPDate:Sep29,2025
EstimatedGompletionDate;Jun25,2026
ContractDuration:270Days
|
GriefDescriptionofWork(SeeDetailedScopeofWork&RFPforcontractualrequirements:
Phase3UnitRenovationsatGreenleafFamily
JobOnterValue:$4,550,000.00
ContractorsLocalOffice: Contractor'sHomaOffic:
DGHousingVigilContracting,ine. DCH«sing-VigilGontracting,Ine.ddVigil Veil
2140PriastBridgeCt 2140PriestBridgeCtSts.7 Ste.7Crofton,MD21114 Grotto,MD21114
DCHAAppgavalSignaty
Mee — Br7/2025 ditaee RETESET 08/28/2025ProjectMatagey Date ‘AdministratorBate
KenBose 08/28/225
TOUTSO Bae CaniraaangOFGEr Dae
SantraciarsAcosplanos
ferele} 08/07/25.oo Title Date
Penmits:GantractortoprovideOwnercoplesofallnecessarypermitepriortofieldactivities,
‘ThisJobOrderisbeingissuedinaccordancewithalltermsandconditionsofDCHAContract,1DJ98-54.20248.Ratertosections247ofDCHAJobOrderPackageforrelateddocumants.
Copies:Contractor,DMA,CPAandOFM
JOC JobOrderPackage-DJ98-DC02.01 4obOrderHateToProceed aS
Districtof Columbia Housing Authority
Wage Determination
SSS]
DatsPrepared 72028
ProjectNumber: Dy98-Dc02.01
ProjectName: Phase3UnitRanavationsatGreenleafFamily
ProjectLocation:Greanleaf
ProjectManager: LeTriceBrowning
‘Thewagadeterminationforthisjoborderis:
Residentiat
Explanation,asnacessary’
JOC JobOrderPackageDJ98-DC02.01‘WegeDetermination
DistrictofColumbiaHousingAuthority
3007thStreet,SW |10thFloor
‘Washington,BC20024
(202}585-1000|dehousingorg
KeithL.Pettigres,ExecutiveDirector
ContractsAdministration« ComplianceDivision
WAGE DECISION REQUEST
ContractCompliauceDivision
FROM: BatriceStinson DEPT:CCD DATE: 7/24/2025
INSTRUCTIONS:Pleasecompletethisformbyfirstplacingacheck(v)besideA iftherequestisfora constructioncontractorB iftherequestisfora servicecontract.Then placea check(+)
besidetheappropriateactivityunklertherespectivecategory;andfillinallothercorrespondinginformation,Itisveryimportantthatyoucompletethelastsentenceattheendofthecategory,inorderthatthewagedecisionissuedmaybekeptcurrent.
CONTRACT NO: 0198-54-20245Phase3UnitRenovationsat Greenleaf
FamilyTask#fD198-D002.01
[aJA.constructionContract$2,000plus{}1.Demolitionofstructureslocatedat{}(a)commercialorhigh-riseresidential
4}(b)low-riseresidential
{X}2.Constnction,alteration,repairorremodelingof
{}(@)low-risecesidentialunitslocatedat£)(B)commercialfacilityorhigh-riseresidentialunitslocatedal_£}(@)siteimprovementslocatedat£}(@)sever/waterTinelocatedat
{X}(@)othersPhase3 UnitRenovationsatGreenleatFamily
(1B ServiceContract$2,500plus
{}1.Janitorial,elevatororheating/airconditioningorboiler(s)maintenanceandservicing,moving/storage,transcriber,courierorphotographicservices
locatedat{}2.Others(specify)
1 Thesedeterminations:__D1C20250003__withmodification_2_arecorrectforthiscontractNo_DJ98-DC02.01 :
‘ThesedeterminationsNo: _DJ98-OC02.01tobeusedforthiscontract,butmaybechangeduponrequestforCCD.
Canal, Cave 07/25/25‘LaborComfltanceSpecialist Date
‘WageDeeisionRequestexpirationdate NA
*GeneralDecisionNumberC2025000302/14)2028
SupersededGeneralDecisionNumber0620240003
StateDistriet ofColumbia
GonstructionTypeResidential
CountyDistrictofColumbiaStatewides
RESIDENTIALCONSTRUCTIONPROJECTS(cons/stingofsinglefamilyhomesandapartmentsup toandincluding4stores}$
NoteContraclssubjacttotheDavisBaconActaregenerallyrequiredtopayatleasttheapplicableminimumwagerateTequiredunderExecutiveOrdar14026orExecutiveOrder136585PleasenoteInattheseExecutiveOrdersapplytocoveredcontractsentered|ntobythefedera!governmentthatareSubjecttotheDavis-BaconActilself,butdo notapplytocontractssubjectonlytotheDavis-BaconRelatedActs,includingthosesetforthat29CFR 8$1(a)(1)$
SECC EEEEEKEEEEEECECEEREEEEEEEEEEEEEEECELEEEEEEREEEEEE
Ifthecontractisentered $ ExecutiveOrder14026sintoonorafterJanuary30, generallyappliestothe+2022,orthecontractis contract
(holed Lal Piercing selaayapi tie 1] 1 1 vee vatteri al
Mer aah i UTES ganas |Pevage nl
tb qruci eae atadel neh bap
mitneee daria lous1 det the ‘
ral nates an Phi balicarecetiagal
plead qardteybeer eourelvoilesf lialTet HAUL de pee beer ar te
depliailevaqeuhpittUtah tteeCeceinalinifitishigher)forallhoursspentperforming onthat contract in 2025 §
KEE EEE EEEEE EEE, EEEEEEEEE EERE
TheapplicableExecutiveOrderminimumwageratewillbeadjustedannually$IfthiscontractiscoveredbyoneoftheExecutiveOrdersandaclassificationconsiderednecessaryforperformanceofworkonthecontractdoesnotappearonthiswagsdetermination,thecontractormuststillsubmitaconformancerequestf
Adina linia beran cocaclr aaytema erevotepour bers rrde tksfrvlics Cicer:ingeeiadleadHi Wrve€goldgeriytpi barig
VediliccliceBeater Fiblivatinytee) ULE eisUitditie
2 yews
VEOH AE DIR
tis tinyer
HOES VSEEA TRIANONWUERRL AESEY bile ie
Weis rec ncar.eshingslopeag mecal soaeping,orang begingerePepainptalline sawelded s,ebeli atten car inagbes les chal ley
pec hey yathys
PM VAEUIDNEHee teersby BernCo ertayayFool on vie dcedig ata berGeetre tpVoebegivicyBoythedupallerTartsging aveSusiivesHaypueidedWeeaphyesaacbsdeep faraatceptelenvedoalieshe pedbaliby
TELEVDS CHTWIMANE
fal Prtyes
ELENAEDVEcdRE Sande Sb brat
PAIDUWLIERESPesCeresiter Dey, belenmngs da
rely VrifapalleTh
DeyVeneraBey,IndeperieeefeTartayiagbey,Gripteesthescinitf
:hihi
4 VACATIONS Employer contribu tes 8% of basic hourly rate
forSyearsormoreofservice;6% ofbasichourlyratefor6monthsto5 yearsofserviceasvacationpaycredit
PLLM0005-00808/01/2024
Rates Fringes
PLUMBER...0...ceee si GBB 143610
a PAID1OLIDAYSLaborDay,Veterans:Day,ThanksgivingDayand the day after Thanksgiving, Chris mas Day, New Year: 8
Day, Martin Luther Kin g:sBirthday, Memorial Day and the
FourthofJuly.
PL LMO602-00908/012024
Rates Fringes
PIPEFITTER(1VAGPipe
Instaation )eccseeeeeeeeeee$52.27 23.7944
aPAID1OLIDAYSNewYear:s Day,MartinLutherKing:sBirthday,MemorialDay,IndependenceDay,LaborDay,Veterans:Day,ThanksgivingDayandthedayafterThanksgivingandChristmasDay.
SLDC2008-00405/27/2008
Rates Fringes
BRICKLAYER 2071 ool
CARPEMIER,IncludingDeveeL]
langing . LTA ee 237
CERENDMASGH/CONCRETEPINISIER©. 1812 0 00
DRYWALL.PYNISHER/TAPER 1500#4 0 00
BLECTRICLAY 1993 all
LABORER,CommonorGenerwd 125434 0 00
LABORER,HasonTenderforseictingecatthiagclmaicaoforistingmsary brick,stneandeenntstrucwras(restratimmrh); aledes
pointing,caulkingandaleaningofnaw orreplacenentmasonry,brick,stoneandcement . 1289et
PAIMER.BrushandRolLer 1532#* 315
POINTER,CAILRER,CLEANER,
CueluzespaniingexelkitgClaniegsaenccingweGESbrick,stoneandcementstructures(restoration
vork); oseludespointingcaulking,cleaningofnovorreplaconentWasoury,brick,stoneorcement 18.33
POOPER - 2633 000
SHEETMETALWORKER + 1833 000
WELDERS-Reveiverateprescribedforcraftperformingperaliontowhichweldingis ineidontal
BEBBBEBEOUGBBBBEDSBEOG8SBBBBBEG55S558G8GA0BRAAPRRRRBBEBBBBBBBEBE
veWorkersinthisclassificationmayhaentitledtoa higheruinimumwageunderExecutiveOrder14026 (.1725)or13658(12.80) PlcasesentheNoteatthetopoflhewagedeterainalionforworeinformationPleasealse notethattheminimumvagerequirementsof Hxecutive Ordor14026arenotcerrevtlyteingmtorcelastoanvemlactstsubcotract tMichthesttesalms,luivians,eWississiepi,facludiagtheiragencies,arew party
ote.Executiwdrder(F130, RetahlishiagPaid sickLewforFateraitntractorsepp.iestallemuactssusjat w theDavis-BaconActforshichthecontractisavarded(andanysolicitetiomeissued)oncratterJanuary],20170£ thiscontractLscoveredbytheUO,thecontractormst providecompLoyeastithlacurofpaidsickleaveforevery39 haretheywork,upto6 hoursofpaidsickleaveeachyearEmpLopesmetbapermittadteunepaideiel leaveforthsirwrilleas,injursorohekalth-rostdasre,includingpreventivecare;loassistsfamilymember(orporsaywi is
Lifefamilytotheom iorce)shodsilt,injured,orhasotherkmit-relatenesds,includicgoreeamears:a forrasmsrasultioginooteassistafanilymenber{orperso siaisLikefamilyto theenployee!whois avictimof, domesticviolas,sewslassuutl,orotKagkditiwal ietrotenem tractorequirenntsaudsurkerprotectiwsundsthe £9isavailableat
hetpst‘famdolgos/agencies/ubdjgoveruuent-contracts
UnlistedclassificationsneededforworksotincludedwitkinthescopeoftheclaggilivationsListedaaybeaddedafteravardonlyasprovidedinthelaborstanJardscontactclauses(290FR55 (a)(1)(iid)
ThebodyofeuchwagedeterminationListstheclassificationsandwagetatesthathavebeonfoundtobeprevailingforthelype(s)ofconstructionandaeographicarcacoveredby thewagedeterminationTheclassificationsarelistedinulphubeticalorderanderrateidentificrsindicatingthethertheparticularraleisuunionrate(currentunionnegotiatedrate), a surveyrate,aeightedunionaveragerate,a stateadoptedrate,of4supplementalclassificationtate
UsiouRuteIdentifiers
‘four-letteridentifierbeiaoiugaitheoaracterothe thanese susie? 782,or9809denotesthatauaionratemsprevailingforthatclassificationin the surveyExamplesPLOMOL98-00507/01/2024PLUMis an identifieroftheunionwhosecollectivelyhargainedrateprevailedinthesurveyforthisclassification,shichinthisexauplewuldbePlumvers0198indicatestheLocalunionnumberordistrictcouncilnuaberwhereapplicablo,ic, PlumbersLocal198 Thenextfuaber,003intheexample,isaninternalnumberusedinprocessingthesagedetermastiontbedate,W/M/2M4 in thecramle,ietheaffectivedateoltheuostcorrontnegotiatedrate
TniowprevailingwageratesareupdatadtoreflectallchangesovertimethatarereportedtaSHOin theratesinthecolvectivehargainingagreewent (C04)governingtheclassification
UnionAverageReto Identifiers
TheWW idwtifierindicetethatnosingleratpremiled forhoaclessi fications.sutthat100ofthedetareported fortheclassificationsreflectedunionratesEXANPIUNGOE O61O01OL/202OG indteatesthattherateis ashuedundonaveragerateHindicatastheStateafUbieThenestnumber,0010intheexumple,isan intornalnunheruselioprofuciogtbemgdetardnstiothedat,Oso /2024intheemupLle,indicatesthadatetheagedeteruioatiosm3updatedtoreflectthemostcurreutunionaveragerate
AUAVGratewillbeupdatedonceayear,usuallyinJanuary,torellectaweightedaverageofthecurrentralesinthecollecLivebarguiningagreenontschahichtheruleisbased
SurveyRateIdenfiers
The“"SU"”identifierindinatesthateither@ singlenou-nnion
rateprevailod(asdefinedin29CFR1.2)forthisclassificetiointhesursyorthettheretemsdevindbycomputingaseightedaverageratebasedonalltheratesreportedimthesurtoplerthatelaesiciealon.dsaweightedaveragerateiceludesallretesreportedintiesurse,il myfozledevsbunimuséum-unimestes.BmaplesULIG2:6/27/2024,80indicatestherateisasinglenon union
prevailingrateor9veishtedaverageofsurveydataforthatclassification.FLindicatestheStateofFlorida,2022isthevearofthesurveyonwichtheseClassificationsandratesarebased.The nextnumber,007intheexample,isan internalnunborusedinproducingthewagedetermination.Thedate,6/27/2024intheoxample,indicatesthesurvoxcompletiondalefortheclassificationsandratasunderthatidentifier
PSU?wageratestepicallyreminineffectwotila nexsuxverisconducted.However,theWageandHourDivision(8HD)hastheHiseret£ontoupdutesuchrulesunder29CHR1.Ce} CL)
StateAdoptedRateTdeatiflees
the“°Si""identifierindicatesthattheclassificationsandprevailingwageratessetbyu state(orJocal)governmontwereadoptedunder28.C.FR 1.3(g)-(h}.Example’$aMe2023-0071/09/2024.SAreflectsthattheratesaresuiteadopted.WErefery totheStateofHaine,2023isthayearduriagwhichtheSwtecopletedthesarwrenchichthelistedclassilicetiosandratesarebased,Thenextatober,M7inthecmmle,is aninternalnumberusedinproducingthesavedetermination.Thedate,01/03/2024inthecxample,reflectstheduteouwhichtheclassificationsandratesunderthe?SA?identifiertookeffectunderstatelawinthostatefromwhichlheratesweroadopted.
WAGEDETETATNATIOWAPPEALSPROGESS
} fiastherebeanauinitialdecisioninthomatter?Thiscunbe
3)asurveyunderlyinga wagedeterainuLionunexistingpublishedwagedetersinatien4 oninitial¥MDlettersattingforthapositionona sagedeterminationmattor3 aninitialeonformence(additionalclassificationandrate)deteraination
thauroyrelacelumtters.initielemtct,ineiudingsayaforsumariesofsurveys,ehouldsedirested-otheMD BranchofWageSurveys.Requestscau be subaittedviaemil to
davishaconinfoOdel.govorbymailteh
BranchofFageSurversFageandHourDivisicn0.3.DopartuentofLabor200GonstitutionAvenue,K.Washington,DO20219
Rogardinganyotherwagedeterinationmattersuchasconformancedecisions,reyeslsforinitialdecisionsshouldbeGirectedtbe MBrenchof(msauelion faseDetersinetims
Requestscanbesebnitiedvisemil toDCH Otice@dol. yorabymil Ww
Branchof ConstructionTageDeterwinationsFageandHourDivisionU.S.Department ofLabor200Constitutionavenue,N.F,Fashington,DC 20210
} [faninitialdecisionhasbeenissued,thenanyinterested
party (those affcetedby the action) that disagrses with the
decisioncanrequestreviesandreconsiderationfromtheTageandHourAuaiuistrator(See29CFRPart1.8and29CFRPort7)Requestsforreviewandreconsiderationcanbesubmituedviaemailtodba.reconsiderationfdol,govorbymailtol
FageandHourAdministratorU.§.Department ofLabor20)Constitutionavenuc,NL.¥.Washington,DC 20210
Theveguestsholdbeaccomanietbrafullstatenentoftheinterestedpoe‘)sporitionendanyinincm tis(ve30 pemontdat,projetdscriptia.erspructizemterial,ste.) tattherequestorvousidersrelevanttotheissue.
} [fthedeisiooftheMuinisteurisanfwreble, aninterestodpartymysppaaldirertlytthe MninistretivReviawBoard(formerlytheFageAppealsBoard). rite tol
AdministrativeReviowRardTLS.Departwent ofLahor200Constitutionavenue,NL¥,Fashington,DC 20210.
SHRORGSGSS56000NGEERSSSSESC EEREEEsdGESLRKOEEEEE
AARA6S5656
ENDOPGENERALDECISION”
Districtof Columbia Housing Authority
Detailed Scope of Work
Date: July28,2028Contractor DCHousing-VigitContracting,Inc.ProjectNo. Duge-Dc02.01
ProjectName: Phase3UnitRenovationsatGreenleafFamily
Location: Greenleaf
Final[Jreiminny— []Rone‘DetailedSoapsofWork
Refertotheattacheddocumenttitled:CapitalConstruction& DesignScopeofWorkDJ98-DC02.01«
Phase3UnitRenovationsatGreenleafFamily,Dated:7/24/25,Pages:1-3.UnitListing.
PleasereferencetheRequestforProposalforadditionalInformationregardingthisjoborder.DCHARepresentative:
alsHOE.— anosPrange a
Contractor'sAcceptance:
TheundersignedhasreviewedthisscopeofworkandagreesthatthisdocumentinconjunctionwiththeREP-constitutestheScopeofWarkinisentirety.
Banand coo 98/07/25
Nema Tie Date
JOC JabOrderPackageDJ98-DC02.01 I]DetaledScapeofWor Pagetoftarre0z6
DistrictofColumbiaHousingAuthority
3007thStreet,SW|10thFloor
Washington,0620024
(202)585-000|dchousing.org
KeithL.Pettigrew,ExecutiveDirector
CapitalConstruction& Design
ScopeofWorkDJIB-DCO2.01:Phase3UnitRenovationsatGreenleafFamily
July31,2025
GeneralRequirements:
1.Allworkshallbedoneper DistrictofColumbiacodesandallotherapplicablecodesfollowedandenforcedbytheDistrictofColumbiaineffectatthetimeoftheinstallation
2,AllWorkmustbeexecutedperthegeneraltermsandconditionsofthespecifiedJOC/DIQcontract.a.Contractormustprovideconstructionscheduleforapprovalpriortopreconstructionmeeting,forDCLIA-PMapproval
b._Thecontactormustprovideconstructionscheduleofvaluesafconstructionstart.3.Allsystemsshallbeoperableandfunctionatthecompletionofthiscontract.4, Thecontractormustsecuretheunit/workingareaafalltimesduringcontracvactiveworkingperioduntilowneracceptance,anydamageorstolenequipmentormaterialsshallbetheresponsibilityofthecontractottorepairorreplace.DCHA willnotbeheldresponsibleforanylossotdamagedmaterials,orequipmentleftonthesite.ProvidesubmittalsforallnewequipmentforDCHAapprovalpriortoequipmentprocurement.Allequipmentshallbeinstalledpermanufacturer'sinstallationdocumentsorapplicablecodesiftheytakeprecedence.Contractor(oprovidetrainingofbothDCH staffandoutsidevendorsassociated
Contractormustprovidethefollowingnotifications6 DCHA-PMforcoordination:a.MaterialDeliveries:48hrnoticepriortodeliveryforelevator/siteaccesscoordination.‘UtilityShutdown:48hrnoticepriorteshutdownofutilitiesthataffectoccupiedunits.S. Allworkshallbecompletedwiththeleastpossibledisturbanceandutilityinterruptiontothedevelopmentresidents.TheContractorshallnotifytheDCHAPropertyManagerandtheDCH PMO contactofanyinterruptionsinwilityservicestotheresidentsatleastseventy-two(72)hoursbeforetheinterruption,Interruptionsshallonlyoccurallet‘writtenvonsentfromthePropertyManagerandshallbecoordinatedtoavoidrepeatedinterruptions.Allinterruptionsshalloccurduringoff-peakhoursandshallbelimitedtoamaximumoftwo(2)hoursperinterruptionoratthediscretionofthePropertyManager.10,TheContractorshallprotecttheexistingstructurefromanydamageduringthiscontract'sexecution,AnydamageincurredshallbetheresponsibilityofthecontractorandmustbereportedtotheDCHAPMO contactandtheRegionalMaintenanceSupervisorimmediately.Thedamage(s)mustbepromptlyrepaired(oinsurethecontinuedcffeetiveoperationofthesystematnocosttoDCHA.AlldamagethatoccursfothepropertyduetotheContractor’snegligenceshallberepairedatnocosttoDCHA andallrepairsmustbeacceptabletotheDCHAPMO contactorRegionalMaintenanceSupervisor.11,TheContractoratfinalwalkthroughshalldemonstratetheoperationandthepropereffectivefunctionoftheinstalleditemsandmaterialspriortoacceptancebytheDCHAPMO contact.TheContractorshallalsoprovidewarrantiesasrequiredforsuchequipment.12.Thecontractorshallprovide$55,983.65allowancetobeusedunforeseenconditionsasdirectedbyDCHA.
ral
Page1of3
DetailedScopeofWork
GeneralScope
‘Thecontractorshallprovidealllabor,materials,equipment,andsupervisionnecessarytoperformrenovationsandelectricalupgradestotheidentifiedunits.Workincludesbutisnotlimitedtothefollowingtrades:
‘orkBreakdownbyDivision
Division61 — General Conditions
+ Projectmanagement,coordination,andadministrationTemporaryfacilitiesandcontrols«Site safety,security,andcleanliness
Division02—Demolition
+ Removalofexistinginteriorfinishes,fixtures,cabinetry,andMUPcomponentsasneeded+ Properdisposalofllconstructiondebrisinaccordancewithenvironmentalregulations
Division06-CarpentryandMillwork
+ Repairorreplacementofcabinetry,countertops,trim,andotherwoodwork+ Installationofnewshelvingandotherstoragefeatureswherespecified
Division08—DoorsandWindows
ReplacementofdamagedorobsoleteinteriordoorsandhardwareInstallationofnewunitentrydoors(asapplicable)
+ Pumishandinstallglassdoorswithblackhorizontalandverticalaluminummullionsanddooroperators.
Division09—Finishes
+ Newflooring(VCY,tie,orotherapprovedmaterials)+ Wallandceilingrepairsincludingnewpain{inishes
+ Replacementofbaseboards,thresholds,andotherfinishelements
Division10~Specialties
‘+Installationofbathroomaccessories,includingtowelbars,toiletpaperholders,andmirrors
Division11—Appliances
+ Removalandreplacementofkitchenappliancesperunit(ranges,refrigerators,etc.)
Division15 — Mechanical (HVAC and Plumbing)
+ Replacementand/orupgradeofplumbingfixturesincludingLoilets,sinks,faucets,andbathtubs+ Repairstopipinganddrainsystemsasneeded
Division16—Blectricat
+ Upgradestounitelectricalsystemsincluding:
© Newreceptacles,switches,andcoverplates
Page2of3
0 Replacementorinstallationoflightingfixtures(kitchen,bathroom,ceiling-mounted,cte,)
Electricalpanelreplacementandcircuitlabeling(whererequired)o Smokeandcarbonmonoxidedetectorinstallation
Division17—Communtcations/LifeSafety
Replaceobsoletesmokedetectorswithnewsmokedetectorsandintegratethemwithexistingfirealarmsystems.
FurnishandinstallacompleteClosed-CireuitTelevision(CCTV)system,includingcameras,networkvideorecorders(NYRs),cabling,powersupplies,andallaccessoriesnecessaryforafullyoperationalsystem.
‘Workmustcomplywithapplicablecodes(NFPA,NEC,andlocaljurisdictionalrequirements)andalignwithDCHAsecuritystandards,Allinstalledequipmentshallbenew,UL-listed,andsourcedfromapprovedmanufacturers.Providefixeddomeand/orbulletcameraswithhigh-definitionresolution(minimum1080p,preferably4Kinhigh-traffic/commonareas).
Camerasshallhavenight-visiow/infraredcapability,widedynamicrange(WDR),andweatherproofhousingsforexteriorTocations.
Installcamerasatdesignatedentrances,corridors,stairwells,commonspaces.andotherareasidentifiedinprojectdrawings.NVRs shallprovidecentralizedrecording.playback,andremoteaccessviasecurelogin,withstoragecapacitysufficientfor
aminimumof30 daysofcontinuousrecording,
‘Systemshallsupporlmotiondetectionandevent-basedalerts,
ProvideCat6networkcabling(orequivalent)forallIPcameras.Ensurecablingisconcealedwithinwalls,ceilings,orconduittomaintaina“newconstruction”appearance.Providenecessarypower-over-Ethernct(Pak)switches,patchpanels,andrackstosupporttheCCT network.
IntegrateCCTVsystemwithexistingbuildingsecurityinfrastructure,includingacecsscontrolandtirealarmsystems,ifapplicable.EnsurecompatibilitywithremotemonitoringplatfonnsusedbyDCHA securitystaff.
Providesecurenetworkconfiguration,includingVLAN segmentationforCCTVtraffic.
Perfonncompletesystemtesting,includingvideoqualityverification,motiondetection,recording,andremoteuccess.Conductfinalwalk-throughwithDCIIArepresentativestocondirmcameraplacement,coverage,andunctionality.Providetrainingfordesignatedstaffonsystemoperation,playback,andmaintenance
Page3of3
54 UnitsforGreenleaf
102,115,118,119,206,207,208,210,211,244,215,217,218,223,302,304,305,306,308,312,313,
316,320,321,322,401,402,403,404,405,406,407,408,409,413,416,418,419,420,421,501,502,
503,505,506,$07,508,$09,$10,513,517,£20,522,523
Districtof Columbia Housing Authority
Contractor'sPriceProposalSummary-CSI
JobOrderNumbar— 0198-0002.01
Tite: Phase3UnitRenovationsatGreenleafFamily
Contractor: DCHousing-VigilContracting,Ino.
ContractNumber:0/88-5420245ProposalValue: $4,550,000.00
ProposalName: Phase3UnitRenovationsatGreenleafFamily
Location: GreenleatBriefScope:
To:_LaTileaBrowning,ProjectManager From:
01-GeneralRequirements: $.2,022,07.56
96-Wood,Plastic,andComposites: $854717.21
08-Openings: $133,748.66
09-Finishes: $590,544.13
410-Specialties: $1,048.40
41Equipments $130,001.34
42-Furnishings: $72,680.56
22.Plumbing: 5153,88961
23-Heating,Ventlating,AndAie-Concitioning(HVAC: $235446.56,
28Electrical: $219,560.21
28-ElectronicSafetyAndSecurity: $299,875.66
‘WorkOrderProposalTotal '$4,550,000.00
‘TawononterotaeteresentscorelforthepopesAnycrepancybeeennet,‘b-tlsandbepoortalsdvtoundngoeineaeandabe.
ThePercentofNPPonthisProposal 45%
fi994 a/07125Vigil, Date
JOCobOrderPackageDIGE-DCOZOT ©
ComactrsPicsProposalSummaryCS agetofrans
DistrictofColumbiaHousingAuthority
Contractor'sPriceProposalDetail-CSI
JobOrderNumber:
Tite:
Contractor:
ContractNumber:
ProposalValue:
PropesalName:
Dug8-D002.01
Phase3UnitRenovationsatGreenleafFamily
DCHousing-VigilContracting,Inc,
98.54.20248
$4,580,000.00
Phase3UnitRangvationsatGreanteafFamily
Location: GreenleafGardens
281Mommer Meds WOM_ enero LineTotal
1Requirements
T ‘Dra21600-0002 EA RaimbureableeesReimbutsableFeesvillbapakiteecorlactrar 325,085.68‘ligtcostsasdirectabyOve.Insertthespproprstequantityaaus‘theasecostthesctuslRemburesbeFeeIrtierearemuleReimbursableFess,staaconesepartalyandaddsexmmantinthe“nol”blocktoidenlytheRemburanbaFeaeg,adelclosure,read‘a,venouspetits,exendedwaranty.sepeditedshippingcuts,ele).Acopyofeachveep,inves,oFpretofpaymentshelbosubmitedwiththePriceProposal
‘Guatity TaiPee Farraat seaasesx 5100 x 1.0000=
Catogonyt:NoCatagoryInput Catouonya
7 Hane THR "GarpenterFororkanctindiwiedinheGansnactonTaskCatalogard 82a2892.27tiretedbyowneront“Saari Tate Farlastaaton 329500x $5088x aso= semenaz7
UserNote:labortoinstallnewbulkheadsfornewvasenupmert(0hoursparbulked)
Gategoryt:NoCategoryinput Category:
3 01741900-4018 EA 800Dumpster(Ton)CcnstructonDebria'incudesdeliveryf $41,205.88“lumpsterrefalceat,pileupcoat,hauling,anddpa fe,Nomhazerdousmaleam ‘Untrt“ Fae rrleaden 5400 x seeasax susan=
Category’;NoCategoryInput Ccatogoryés
a rasaBOOTH ER FinaGieanRosinaUnt-ThreeBedroomUnit Seasao
‘Guantiy Trace ~Ineaaton S400 x 108848 x 4.1800=
Categaryl:NoCategoryIncut Catagoryé:
3 1S 07OOO ‘SF RadertGating,includingProperCianoaal,PerSFofFlooravea 336078.00
Gani Tite Fac —
Category:NoCategoryInput
Installation4000.00x 058 suaso0.=
Getegorys
JOCJobOrderPackageDJ98-D002.04
‘Contact'sPieProposatDati-CS
10
Pagotfteran
Contractor'sPriceProposalDetail-CS!Continued.
JobOrdarNumber;— DJ98-DC02.04
Title: Phase3UnitRenovationsatGreenleafFamily
(051Murer oa, VOM _beserpton ieTotat
[D1-GeneralRequirements }
a ‘oreso806-0008 LF RaplaceGauntrTop-Laminateincluesbacksplashandendsplash $51,388.99dedperleboseaconsknetion,‘uantiy UniPrice Factor TaInstallatione800 x wees x asap= $51.308.98
Gategoryt:No Categoryinput
7 (4850800-0010, ER GultutForSinksAndtavatoos seme
Guanity Unite Faw jaaInston nA x 17940 x s.aso0= seasret
Catagory:NoCategoryinput Category:
3 tS 06-9008 TA Banosnetaoar1aThick,18Gauge,Fuck,(Fant) sageiess
‘Completelnludeshinges,bumpare,brassrshpeepele,bratsneck.‘esdbatackeesweathering.hesheldsweep,primerandvoces:
__sang.~Guay Una Fake ‘TaarInstaloton soo x siser2x 800 * 90756°91Demoton e400x saea2x 300 ssezse
Category:NoCatagaryInput Category
a 0198800-0002 ore EA orGearWilhSpringHinges,Aad — ‘38621
uanity UritPce Face etalInetaaon ton x sasasx s00= 556.21
sorote:
Gategoryt:NaCategoryInput Caterer
bseoRaD0m FA IneoaodDeer,308Thick,6PanelSaidGore,PantGradabooren, $169,250.52
— ‘Gusniiy— inPi Faeee——rrInstaoten seo x s2t0gsx susan= 5145,79609Dermaiten sean x sa38 ‘Asoo= saa.49
Gatagoryt:NoCategoryInput Categont:
1 oraB08coo BA DoorViewerPoapHates 82,718.98
arent i Bice" rrInstallationsionx e780 x ‘4800 seom40eration shox gear x 11500= $095.55
Category:NoCategoryinput Categorys:
12019508 00-06 EA EnlyLan(MasterKeyed)FalconGrEqual 7 $10,176.86
vn aay ORF Fae ~ TadInston san x 50516 x aso « soana4Demon sionx sar. x 4.400 sae
NoCategoryInput Category:
7 oravew0RTe ‘SE RasldortelSerCastPasir,1Goat BaaTED
~ Goantiy iti Far aaInstaatonssso0000x sure sas + 5204,79280
Gatageryt:NoCategoryInput Gategorya:
JOCJobOrderPackage0J98-DC02.01 0
Contain’PloProposeDetl-CS Poe20f11arrzces
Contractor'sPriceProposalDetall-G81Continued.
JobOrderNumber;098-D002.01
Title:c5imumper od,
Phase3 UnitRenovationsatGreenleafFamily
uo Deertption LineTotat
[01-GeneralRequirements J
Te oresosoncers Sr PanteneReserUnGari darvalsnoir, 526754800lichenet, telusproperstonPerSFeforsesCombinatione-clossadeggsha.Taaspentoronecatpineedo satacan Tatas Face 18——ian stom. we 11500= sani100
Gatagoryt:NoCategoryput Category
1B ovaswaweeaTsGareGGF PorBscPainaCont,a #192080Coan Tra aaa TaalIain sa0900x ery 14500 se2050User:
Category:NoCategoryinput cater
1 oaseevecoa SF Reploe1x VET,rca lngcompo 33857026‘Guaniity ‘UntPre Factor” Tete
Instatonsoso eer x 11800= 01997025
CcatagorytsNoCategoryput Category
Gres1o0n-0008 EA ResidentledineCabinettsMier 7 52148071
~ cuane THRPREF ar raatItaton sox some x 180 0126Seen oD soo 1500= s1.n4s
atogoryt:NoCategoryput Categoryear ooo GH RevitBthSacoPociagncoonTroGSPToraaa soirSoapbuh,Tor PaperHtAnd StatensSel(Oe)Stonerfediy uitPre Far yolason sm x wer x 14600= tnsooiesBeieten Ho est 11600 ‘9030
catagory:NoCatogoyput Catagory
owas ee08s ER BFSasSirdarSonFrosiardngRarer saan- oumey ee Fair Taration HOD nk BIASHOS 1.1500 sso.Sermon woe saz x tio series
CcategorytsNoCategoryInput Category
vrsean0-0%8 ER BlessSeiateowlhanSiahSingUneFacsnse 3785038hens coco mipinnndts,than ae ~-rat‘otton oo x stots 14800* 0037Benetton foo 782 x 11800 seisoa7e
Category:NoCategorympd Category
sean EA _Tua/ShowarFavetinShowereadnchesdoore,do or $e000878cd. P,snandsoukSaat TmPrce Fa TaInaton 400 x soot x 11500= 50.0645Ceneton so seer 1500 #890830
atagoryt:NoCategoryput Category
JOOJobOrderPackageDJG8-DC02.0% 70ComactarsPosPrepoetBoil) Pane30f11riao2s
Contractor'sPriceProposalDatail.CS!Continued..
JobOrderNumber;—DJ98-D002.01
Phase3UnitRenovationsatGreenleafFamily
S1Nambee Mod WOM _deserintion LineTetst
Requirements
Oreszz0D0078 EA Tub’showerEnlosure4Stee,©HeightnauangBackerBoars(Wander 35842058Boat},CeramieTiertGro —i nn a aeInctallaton son x sipaT x 4.4800 6.20073Deion 5400x sees x 13800= siazip8s
Categoryt:No GategaryInput Gategory4:
Bunge z20n0m FA RejlateGasSlop!Guta SEsi838
uanity iates Fase TeaInston sao seer x 11600= 35.1638
Category:NeCategoryInput ‘atogory
wwe zRODOE FA WierGoss2Place,RaundFrontWhiteAmericanStandardGekwont §407280.88[Champin2527-012(Goad267,016,Tek42720TOKNCIIGESseaansing,eacutenoun,supplyvansandIne.
any “WaaPree Fa TatIeaacon e500x siardax 13600 ‘00.8040Demlton seo0x sO x 1800 s9g0048
Categaryt:NoCatagoryInpat Gategarys
rT "EA BathiShawerTrim,AmericanStandard776.502PolishedGhiomelndues $10,208.65‘uhverterspoutvalveleverhandle,showeramandshawarhaa,a rn asInetain sto x gimme x 4.4800= sa21564Demin 5400x sg? x 11800= sa.nssot
categoryt:NoCategoryinput Category:
Subtotalfor01-GeneralRequirements: '$2,022,907.56
[os- Wood, Plastic,andComposites
Ba Tesco00a ‘SF ThickPlywoodUnderlaymentBCGrade Ferrey
Guin RCS Fear raatsatiationez000 x sex ‘.as00 sennabation ysz000x, pas x soo seot.08
Gatogory’:NoCategorytnpid Catagorys:
06202800-0002 UF 12WideWoodSheningForResientlClotels 1282800
Goan Faster “Tarloin samo 2600 x 44800= sura32Demin ano x sete 1.1500 ‘1890.58
Category:NoCategoryput Category:
BBB Tee TF U2a2 ne PineCoveMoring ‘58568500
aRPree Tea -tngenston 1590000+ sa2t x sas0o0 se9.780.38amation 1590000x wr x 11500 515,506.58
Categony!:NoCelegoryInput
JOCJobOrderPackageDJ98-DC02.01 70
eaeC82 PageoF
‘aoe
Contractor'sPriceProposalDetail-CSIContinuet
vobOrderNumber, -088.0002.01
Tite: Phase3UnitRenovationsatGreenleafFamily
csNember ig UOM_Deacription LineTotal
06-Wood,Plastic,andComposites
aaaTeODOTeT ry "Wo,35°Highs22-34"Daop,SingleDroveranaSifeDoar,Sad 385,176.36akFaceFrame,DorandOrawerFront,BaseCabinetGuana UnitPcs TaInstallaton120 x sea7s x sao seo.snt2eDernaten 16209x suas x 4800 488604
Category?NaGategaryInput Gategory4:
wea sense BA Se"Wide,35Highx230°Deep,SingleDrawerandDoubleDoar,Sal 3586520{akFaceFrame,DoorandDrawerFront,BaseCabinet“Guantiy ~UniPiee TasInsalaton stonx suet x 29,208.08Demotlen 5400x yo0e7x soarraa
Category:NaCategoryInput Category:
Hogar aaenee EA afWide,3 High12" Daap,SloglaDoor,SoldOakFaceFrameand 72,895.60
oO “ URPre reaInatallatonrw x sossezx 1800 508.30837Dematen ws x faa x 800= 34.5560
Categoryt:NoCategoryInput Catogorysi
teatooness EA a1Whe,35Highx2-3"Deep,SingleDraverandSingleDoorSal 37432459‘eedFaceFrame,ThannofalDoorandDrawerFron,Se8eCabinet.uray ree Fecar Te .Insaiaton yw200x so7758x s.asoo= sro.senasDemon wean x 288 s.4so0= $3.90456
ategonyt:NoCategoryInput category:
= 81 1300-050 EA 18°Wide,95"Highx23-34"Deep,ThreeDrewerBave,SolidWoodFace $65,008.39= FromeandTherafolDrawerFronts,BateCabinet“deer UntPie Faer TeaInstat we200x sume7 x ‘1100= 2.10272Demin sez $1628 411500= 248.8
Category:NoCelegoryInput Category
EECELECTIOC) EAE Was,3highcZ"DeepSinsDoor,SakWendFaceFramed $6758806_ “ThammatatlGoey,WalCabinetURE Fae TagInston ss200x suigs x 1.1500 seos00.08emotion se200x wuge x 14800 wase4s6
Category:NoCategoryInput ‘Categorys:
35 (98941900-0001 EA 26"Wide,20"High12"Deep,DoubleDoers,SolidWoodFaceFrameand $94,197.39‘ToemtalDoors,WalCabinet7any TatPi Fae —TearIretalloton18209x gesaesx 14800= 9730877Deenion 1820 x S667 x 13500= seaniee
Category:NoCategoryInput Gotegorya:
CearaWOH EA 15°Wide,sorFighx12"Deep,SingleDoor.SoldWeodFaceFrameand SaratDecorateLemmeVeneerDoor,WalCabinet no‘auaniy UnaPaes Far romInstalaton 16209x sear x sco = se4e714Domaiicn 18200x 31820x sco = s28t688
category:NoCatagoryInput category:
Subtotalfor06-Wood,Plastic,andComposites: $654,717.21
JOCJobOrderPackageDJ98-DC0201 10
Contactor’PriceProposalDatil-C8! PageSoft
anaes
Contractor'sPriceProposalDetail-CSIContinued.
JobOrderNumber: Duge-DC02.01
Title: Phase3UnitRenovationsatGreenleafFamily
CBINumbee Mod, WOM _Descriation LineTotal
[08- Openings
a 083813-0170 ‘SF UpTa2SFFerWindor3/4"InsulstedGlazingForSectionalOveriead $51,624.85DoorsAdditionslcostforfactayeupaiad‘Guana Sa ss Fa) TasInstaaton e000 x sean x 44800 351,62485
Gategoryt:NoCategoryInput Cateyorys:
« 06422939-000 ER GoncesledPerOfOaoreSangDoorDperstor,UpT2950LBPanelFor $44,006.48newstecetrontorexistingconcasledoperetarinstastione. .it Faia TearInstaiation sox S702 x 1.1500© ‘$40,504.60amation sok yo0904x as00= $8,50198
sorNote:storefrontdoors
Catogoryt:NoCategoryInput Categorya:
BeasTawa-DeG SF @'HighWithHorizontalulion,27x4-127Frama,VerticalMullonsOn $29,310.05_Gener,AusinumStorsontFaringAseemy‘Oxantty Trt ce Faeie TeInstaltion yooanx yam x 4.800 ‘$23.506.20Demolition 7a00 x SUNT x 14500 s5ir708s
UserNote:storefronttion
Gategoryt:|NoCategoryInput Categorys:
a 08431900.0040 20 ——«SF‘FarBlackColorCtass|AnetzedFeish,Add $2,604.55,
unt ‘UnitPies Factor ToaInetaation 7000 x st x 1.1800= $2864.58
UserNote:
Category:NoCategoryInput Sategony4:
" (08724200-0208 UF 4°Wath,6/8"Height,PlainMarbleTwreshola ~ $6142.83,
— Tush UnitPre Fate Tat -Instaiavon 21800 aia 1.1800* sastses
emetion 2600 x wo 1.1500= 3150728
Categonyt:NoCategoryInput Catoganys:
Subtotalfor06-Opening $133,748.66
loo- Fi
a ‘SF 250TOS00$F,CutAndPateHolsInPastorToMatchEsty $260,820.00,
— aan UnePae Facer TaalAatatiion wro0000x sao x +1609 $280,800.00
Catogoryt:NoCalegoryinput Catagonya:
ad 5301800.0908 ‘SF__ LacsThan”xa",Mausied,CeramicFoorTeelneludeeglazedporcelain, $21,761.90Uunglazespereolinandglazedcaramécts,Teemountedremhack,siteorfromin12"x12%,2"28 ofsitarsizedshostsCuan “UnitFre Fae - TerInstaaion 745.00x sox 1.1500 518,091.00emefion 76.00 sah x aso = ss98e.0
Category?NoCategoryInput Cotegoryd:
JOCJobOrderPackageDJ98-DC02.01
Contac’PiesPropoeaDet3
10
Pagocftteras
Contractor'sPriceProposalDetail-CSIContinued...
Job OrderNumber: (DV98-DC02.01
Tie: Phaea3UnitRenovationsatGreenigtFamilycintet e___UOMDestin tineTt
jnshesFDOT OS EE FeUpTOR Tanay Tae rar ‘eatater 00x Hat ticoo* eneVeer
Cngory:NoGetegeryet eteporytoBonne) Da aFFortigaoaLowacaiFiSronghCisRearEvan soresSos rymy Tats Fa Taitten sco es 19500" erasert
coegeryt:NoCatagoryInput Catagoyteee oneT OFF Anaageone wr WalVohalesGap, 31660380tnasaglpectsndgreevisu _ay ane _ -——aiataten beanx 0 iso* simaames0ooeaion ceo a ‘eno aazra0
categeryt:NoCategoryneat eaegerye:easeower oF paseo or‘Cuantity Unit Price Factor Total
estton 100)x a Theo* siaeae
Category:NoCategoryut Category“a0 TROpWG7 0h FargibdLowa HiSeongCri Rea 325500Gonna -Sew Tae a]rattan so) wae comaeet
catagory:NoCategoryret categoa aero 2k BasPanBahRarWa,Paao WedSoaBanBo aany Tas Fear—~ rarutter tue x Moe Teo= worstCategory:NoCtegerypu etapawww 2k eaPanBac Wa,BoFanPaneWo Dar TaARD
ittaten . sass ‘800 sengonzaCaragory:HoCategorytut Category:
Subtotalfor08= Fries $690,54439,
JOGJobOrderPackage0198-D602.01
(ContacorPricePreposaDeti-
40
PageTeenamraces
Contractor'sPriceProposalDetall-CS!Continued.
dJobOrderNumbsr;— 0498-0002.04
Title: Phase4UnitRenovationsatGreenleafFamily
25Number Mod. __UOM_Desorinion LinoTotat
10Speciation ]
102820120081 EAT CopperPine,HepgerHanger $1,848.10
- Co Tait Far Taal‘nett vwsayx ganz x vasa7 v9.28Demin vosanx wer x 1.1600 sassat
Gategoryt:NoCategoryinput Catogorys:
Subtotalfor10-Spactaties: $1,840.10
14—Equipment ]
a3 42-0000 EA 0"Non-DuctedRangeHood(Been«1000), $16,208.08
aan TanPe Faster Taesnsstton 5400 x poag7 x sea srgse3.28Demalon sion 9728 x 1.4800 wai7
Category:NoCategoryinput Categery4:
11307812-0089 "ER _-920T022CFTepFreeserRefigernt - $90,048.73
Guan — ‘UniPree Facto Tal -Inston e400 x 102520x 600 ‘e.g0992emotion sioo x 52855x 1.1500 siscar
Catagory’:NeCategoryInput Catogorys:
me naoTsTepe ‘SF __SariaoeSteelRangaSplaohFat 32624368
ua Tne Facer TataInstallations1acdx men x 4.1500 $29,008.97Dermaton aio x Bias +1500 s1essce
Gategeryt:NaCategoryInput Catagorya:
Subtotalfor11-Equipment: $130,591.34
12 Furnishings:
8 ARFTBaz0000 SF 1"Shs,VingHorizontalLauernds $72,890.58
Cuaniy— Taito Facer "TaalInetalatonsasoaox $025 x 3500* soa.ge100Demian au000 x goss 114500 350958
Cetegoryt:NoCategoryInput Catogorys:
Subtotalfor12 Furnishings: $72,880.56
(22Pmnbing
3 221418000878 FT HardDrawnTypeLCopperTubeipa 82081218
7 ee rae "etnaan assoonx, 1078 sssea> 91870508emits 1960.00x wen x 1.1500 saa7azsGatogonrt:No Catagoryinput Gategory#:
JOCJobOrderPackageDJ98-DCO2.01 a0]
‘Contactor’PreeProposalDetal- ge 817
errenas
Contractor'sPricePropasalDetallCSIContinued...
dobOrderNumber;—-D498-DC02.01
Tie: Phase3UnitRenovationsatGreenleafFamily
8iumber Mod UoM _Deeeration LineTotal
[a2-Plurabing ]
oat Teoues ER 1°00DegreeCopperEsow SEIASO2
Saari TaiPiEs Far TeToetteion zea x sox s.aso0 519.9888Darelion piBcox s00z3x s.3so0.= 7500.13
Category’:NoCategoryInput ategory4
@ wyseenass ms CapperConrng
a a a - ~Inetaiaton 2iBod 55048x s.s00 s12.50823Demon >is00x soz x s.asea $7500.33
Gategoryt:NaCategoryInput Catogorys
BA wna FA WateCopperAaepiar $20ReT
Caan" - Fade TearInetalaton 2180 x x 4.800" saaotsemotion 28x x 44800= ‘5.85010
Gategeryt:NoCategoryInput Catagory:
Ba wane EA 1 CutAndPrepareExstngInPlaceCopperPhe 3270202
Rae iiIrstallaton x Hix +800= se78202
Gategeryt:NoCategoryInput Catagory
maT 9anae EA #WashingMachaneOweox,Paws,Two12”SupplyValve 316965.30
Tasha TAPE Factor anInealagon stanx semen x s.as00= 1495607Demaen sis0x sia49x 800 = 31,140.28
Gatogoryt:NaCatagoryinput Catogory4:
@ marzova0 EA HPinsultedGarbageDisporal ~ 32440718
a a aeInetalaion secox ssss76x s.00 522,001.48Demon shoox sm778x 14600 s.ats7s
Gategoryt:NoCategoryinput Category
@ amas EX ax 16GatedbateVailTopWahItagrtodBachaplaanAndSri PADS
Tuan Tare Factor TaalInetalanon secox sores x sagen $23,27870Demon S00 x S987 x 44800= $3.906.83
Category:NaCatagoryinput Category
Subtotalfor22-Plumbing $163,883.81
[23-Heating,Ventiating,AndAir-Conditioning(HVAC)
Be aatizso0au2 A 34%{08STxTwended)RewiengAdaptorForCorugatedSanless 3280SStelTubing(CSST},FlexibleGasFipe(uantty Units Facer “TellInstallationsano ser x 4.4800 se.n8448
Category:NaCategoryInput catagoryt:
JOCJobOrderPackageDJ98-D002.01 10
Contact’PlsProposalOatl-C81 Pageoortt
2025
Contractor'sPriceProposalDetail-C$!Continued.
JobOrderNumber;— DU98-DC02.01
Tithe: Phase3UnitRenovationsatGreenleafFamily
csiNumor od, UO Description UneTetat
[23-Heating,Ventilating,AndAir-Conditioning(HVAC)
ZT eSUNONE ER THandlo,175PS)ForgedBrace,QuatorTurn,GasBalValve(Legend SAMSIeueTop7-2004102-535)any Ta Pre Far TearInetaliatensao x se08 x s.as00= si208.28Demeon HA x ge 1.1500 sri788
Category:NoCategoryInput Category:
manecose SF GaugeStainlessStealRadateeCover 106577.04
Inston x 4.400 sts091252Deion x saso0= $5603.52
Cotegoryt:NaCatagoryInput ateryt:
a7 gaanecn-ons ‘SF PrimedAndPainted,GalvanizedSteelRadiatorShit 361,094.88
ne TeaInetataion ‘yoaconx saasax sasoo= -ys5,268.38emestion sioso0ox we x 14800= 5665.52
Category:NoCatagoryInput category:
‘Subtotalfor28-Heating,Ventilating,AndAir-Conditioning(HVAC) $298,446.86
[26-Electrical
@% 2ez7z000-0018 EA 20Amporee.125Vol1Phase,NEMAS20,DuplexRecepade $88228,17
Tear Te ad TataInatataion aasoonx wags x 4.400= s.360.38Demian es000 x sate x 44800= 919865:73
category’:NaCategoryInput Catagorys:
teamoonese 'B___1Gang,802StanissBiolWithBatnFishSrichWalPlioe SRT
oma WaPre Far ~ ToaInstaeton 41990.00x sear sage0= ‘9496.30emalton ie80.00x moe x T4800= maria
Gategoryt:NoCategoryInput atogorys:
7 26781619-0000 FA 4PolaGFi.16To30Ampevs,720/240VetULListed30mAExapmant $25,407.87_ ProtacienClonSreshe,10,000AngersInlemuptingCapac‘Guenity Tatas Fane YaarInstallationoso x siers2x +500= 20.88866emailer 0am x 08s x 800 = sasi31
ategonrt:NoCategoryInput Categorya:
Ti ae veonon2 rr ¢angiPensedLEDStfaigntFotvte(Cidanie2) Fras
TREE ora TeaInstallation * sa287 x 4.4800= saazaoDemoton ssostx 11600= 34.8063
Gaegeryt:NoCategoryInput Category
JOCJobOrderPackageDJ98-DC02.01 70
Cantor'sPrisePropatalDotCS Pege100618
anraezs
Contractor'sPriceProposalDetall-C8iContinued.
JohOrdarNumber;—_DU98-DC02.04
Title: Phase3UnitRenovationsatGreenleafFamilycsimumper Mod. OM Desorption LineTotal
28-Electrical l
72 26811900-0106, "5"Dlameter,7-100Lumar,LowProfleSurfaceMountLEDPure(RP 381,608.23Lphing#380}Guaniy UniPrice Feetor TalalInstaition sam x pietotx 4.4800= 571.85595Deraton s7e00x e269 x 11600© 9580.28
Category:NoCatagoryInput Catagarya:
‘Subtotalfor28-Electrical: $212,553.21
[28-ElectronieSafetyAndSecurity ]
73280000 0.0001 is cen $220.548,20
rete Susy TakPie Fear Teal‘neta 120 x $22054820x ‘0000= eaages.20
Category’:NoCatagoryInput categont:
7% sereTion-0ee ER HandieapiPushToOpen,PushButionConkle,Exo StandAte 31TesS-AcoassGontalaGonvolsauntna#Selgengeleccalhor,Erchdesclecticalbox.‘usr oniPrice FacerInetataion sox gre7s x 11500= souraz0Demon 50x sosa x soo = s1st00
Category’:NaCategoryinput Category:
eee eae ER GombinatonFeeAraGODetector(SintKrightSKFIRE-CO} $116,268.93
‘oantiy Tare pa TaInstatationvam x seans9x 4.1800 $107616.20,Daron zs x 5426 x 4.4800 1089773
Gatayoryt:NaCategoryInput Category
‘Subtotalfor28-ElectronicSafetyAndSecurity: $330,876.88
WorkOrderProposalTotal $4,560,000.00
Thiswerknarproposaltotalrepresentsthesoredtoaforthepropotal.Anydiscrepancywasnfinettl,sub-ctalsandthproposotafsdueteauralofhetetalsauruttt
ThePercentofNPPonthisProposal: 485%
JOGJobOrderPackage0J98:0002.01 10
Contnsar®PesPrepareDetCS Pageitof11
era
Date: 87772026
From: J VigilDCHousing-VigilContracting,in.
2140PrigstBridgeCt
Project:Phase3UnitRenovationsatGreenleafFamily
Projact#: DU98-D602.01
ProposalAmour $4560,000.00
NameofContractor wars| toue Contteations)| __ Planned]96 Actual%
obraContacting,LLG Deiat| Irsalaion 0 sistsocone|96rd e200]omCounsDEHowing-VigContracting, ateanrjat Na szarca004esaes] save)oombe cvaragement TotalSa5s000nc0‘000% somo0am
ContractorReporing Planned Retwal
NYA Contracting: 64.99% 0.00%
CBEContracting 2601% 200K
TotalManHours FromProposal| Prarined”| Actual
TotalProjectManHours 22.020 recoo0s| aco
Seaton3ReportingSection325%Goal Planned| Aaual
Seaton$ManHours azaz.30 seoo00| 000
NewSection3ManFires NA 000 200
oe. thsimire PO YY ig
1te__GOO. DemerSianeg_OTAuguacsrumercapantevane__BSHit Concare
‘Arana__2140ritBridget.Sto.7,Groen,MD21114
TelephoneNumber
JOCJobOrderPackage-0J98-DC02.01 2
DCHA
CONTRACT NUMBER: 54-2024-S CONTRACT MODIFICATION
District of Columbia Housing Authority CONTRACT DATE:
May 1, 2025
FUNDING SOURCE (BUDGET AND ACCOUNT) CONTRACTOR:
Vigil Contracting Inc
2140 Priest Bridge Court, Suite 7
Crofton, MD 21114
DCHA SITE & PROJECT NUMBER: DATE OF THIS CONTRACT MODIFICATION:
December 18, 2025
PROJECT MANAGER APPROVAL DESCRIPTION OF WORK UNDER CONTRACT:
Job Order Contracting CONTRACT MODIFICATION #1
WILL PROJECT BUDGET BE EXCEEDED BY APPROVAL OF THIS MODIFICATION? YES X NO
HAS THE HUD OBLIGATION DEADLINE PASSED FOR THE APPROVED FUNDS? YES X NO
NOTE: CONTRACT MODIFICATION CAN NOT BE APPROVED IF HUD OBLIGATION DEADLINE HAS EXPIRED
1. ORIGINAL CONTRACT AMOUNT NOT APPLICABLE
2. DOLLAR AMOUNT OF ALL PREVIOUS MODIFICATIONS NOT APPLICABLE
3. CONTRACT AMOUNT INCLUDING ALL PREVIOUS MODIFICATIONS ( 1 + 2) NOT APPLICABLE
4. PERCENTAGE CHANGE FROM ORIGINAL CONTACT AMOUNT (3 1 x 100) NOT APPLICABLE
5. DOLLAR AMOUNT OF THIS MODIFICATION NOT APPLICABLE
6. ADJUSTED CONTRACT AMOUNT INCLUDING THIS AMOUNT (3 + 5) NOT APPLICABLE
7. PERCENTAGE CHANGE FROM ORIGINAL CONTRACT AMOUNT (6 1x 100) ~
SOURCE OF ADDITIONAL FUNDS NEEDED FOR THIS MODIFICATION
LATEST APPROVED COMPLETION DATE
ADDITIONAL TIME REQUIRED
REVISED COMPLETION DATE
JUSTIFICATION FOR THIS CONTRACT MODIFICATION (Attach additional pages as necessary):
In accordance with Contract No. 54-2024-S; DCHA hereby issues this Administrative Contract Modification to
reflect the Contractor’s new legal name change from Vigil Inc. to Vigil LLC.
ALL OTHER TERMS AND CONDITIONS REMAINS UNCHANGED
Accepted for CONTRACTOR Approved for DCHA (Owner)
SIGNATURE SIGNATURE
NAME and TITLE: NAME and TITLE:
Cheryl Moore
Contracting Officer
DATE: DATE:
2/03/2026