Read the full stored bill text
Florida Senate
-
2026
SB 1646
By
Senator Simon
3-01052B-26 20261646__
1 A bill to be entitled
2 An act relating to educational facilities; amending s.
3 1013.64, F.S.; revising the formula to calculate funds
4 for remodeling, renovation, maintenance, repairs, and
5 site improvement of existing facilities; requiring a
6 board to prioritize a specified amount of funds to
7 correct unsafe, unhealthy, or unsanitary conditions;
8 revising criteria for a district school board to
9 request funds from the Special Facility Construction
10 Account; requiring the Department of Education to
11 participate in a design review process; requiring the
12 department to conduct construction site visits;
13 deleting obsolete language; requiring the department
14 to keep a specified agreement on file; requiring a
15 school district to use a specified process to select
16 an architect and construction manager; authorizing a
17 district school board to enter into a contingency
18 construction contract; prohibiting elected state
19 officials from participating in the selection process;
20 deleting a requirement that certain plans be approved
21 by the district school board as being in compliance
22 with specified safety codes; revising the requirements
23 for a construction project to be exempt from certain
24 cost requirements; amending s. 1013.62, F.S.;
25 conforming a cross-reference; providing an effective
26 date.
27
28 Be It Enacted by the Legislature of the State of Florida:
29
30 Section 1. Subsections (1) and (2) and paragraph (e) of
31 subsection (6) of section 1013.64, Florida Statutes, are amended
32 to read:
33 1013.64 Funds for comprehensive educational plant needs;
34 construction cost maximums for school district capital
35 projects.—Allocations from the Public Education Capital Outlay
36 and Debt Service Trust Fund to the various boards for capital
37 outlay projects shall be determined as follows:
38 (1)(a) Funds for remodeling, renovation, maintenance,
39 repairs, and site improvement for existing satisfactory
40 facilities shall be given priority consideration by the
41 Legislature for appropriations allocated to the boards from the
42 total amount of the Public Education Capital Outlay and Debt
43 Service Trust Fund appropriated. These funds
must
shall
be
44 calculated pursuant to the following basic formula: the building
45 value
multiplied by
times
the building age
and
divided by
over
46 the
most current
sum of the
years’
digits
report
. These
47
calculations assume
assuming
a 50-year building life
span for
48
permanent
. For modular noncombustible
facilities, a 35-year
49
building
life
span for modular noncombustible facilities
shall
50
be used
, and
for relocatable facilities,
a 20-year
building
life
51
span for relocatable facilities
shall be used
.
The
“building
52 value” is calculated by multiplying each building’s total
53 assignable square feet
by
times
the appropriate net-to-gross
54 conversion rate found in state board rules and
multiplying
that
55 product
by
times
the current average new construction cost.
The
56 “building age” is calculated by multiplying the prior year’s
57 building age
by
times
1 minus the prior year’s sum received from
58 this subsection divided by the prior year’s building value
and
59
then adding
.
to the net result
shall be added
the number 1. Each
60 board shall receive the percentage generated by the preceding
61 formula of the total amount appropriated for the purposes of
62 this section.
63 (b) Each board is prohibited from using the funds received
64 pursuant to this section to supplant funds in the current fiscal
65 year approved operating budget, and all budgeted funds
must
66
shall
be expended at a
similar
rate not less than
the amount
67
that
would have been expended had the funds under this section
68 not been received.
69 (c) Each remodeling, renovation, maintenance, repair, or
70 site improvement project will expand or upgrade current
71 educational plants to prolong the useful life of the plant.
72 (d) Each board shall maintain
its
fund accounting in a
73 manner which will permit a detailed audit of the funds expended
74 in this program.
75 (e) Remodeling projects shall be based on the
76 recommendations of a survey pursuant to s. 1013.31.
77 (f)
A board shall prioritize a minimum of
At least
one
78 tenth of
its
a board’s
annual allocation provided under this
79 section
shall be spent
to correct unsafe, unhealthy, or
80 unsanitary conditions in its educational facilities, as required
81 by s. 1013.12, or
a lesser amount sufficient
to correct all
82 deficiencies cited in its annual comprehensive safety inspection
83 reports.
A board may use less than one-tenth of its allocation
84
if that amount satisfies all
This paragraph shall not be
85
construed to limit the amount a board may expend to correct such
86 deficiencies.
87 (g) When an existing educational plant is determined to be
88 unsatisfactory pursuant to the survey conducted under s.
89 1013.31, the board may, by resolution, designate the plant as a
90 historic educational facility and may use funds generated for
91 renovation and remodeling pursuant to this section to restore
92 the facility for use by the board. The board shall agree to pay
93 renovation and remodeling costs in excess of funds which such
94 facility would have generated through the depreciation formula
95 in paragraph (a) had the facility been determined to be
96 satisfactory. The board shall further agree that the plant shall
97 continue to house students. The board may designate a plant as a
98 historic educational facility only if the Division of Historical
99 Resources of the Department of State or the appropriate historic
100 preservation board under chapter 266 certifies that:
101 1. The plant is listed or determined eligible for listing
102 in the National Register of Historic Places pursuant to the
103 National Historic Preservation Act of 1966, as amended, 16
104 U.S.C. s. 470;
105 2. The plant is designated historic within a certified
106 local district pursuant to s. 48(g)(3)(B)(ii) of the Internal
107 Revenue Code; or
108 3. The division or historic preservation board otherwise
109 finds that the plant is historically significant.
110 (h) University boards of trustees may utilize funds
111 appropriated pursuant to this section for replacement of minor
112 facilities. Minor facilities may
not
be replaced from funds
113 provided pursuant to this section
if
unless
the board determines
114 that the cost of repair or renovation is greater than or equal
115 to the cost of replacement.
116 (2)(a) The department shall establish, as a part of the
117 Public Education Capital Outlay and Debt Service Trust Fund, a
118 separate account, in an amount determined by the Legislature, to
119 be known as the “Special Facility Construction Account.” The
120 Special Facility Construction Account shall be used to provide
121 necessary construction funds to school districts which have
122 urgent construction needs but which lack sufficient resources at
123 present, and cannot reasonably anticipate sufficient resources
124 within the period of the next 3 years, for these purposes from
125 currently authorized sources of capital outlay revenue. A school
126 district requesting funding from the Special Facility
127 Construction Account shall submit one specific construction
128 project, not to exceed one complete educational plant, to the
129 Special Facility Construction Committee. A district may not
130 receive funding for more than one approved project in any 3-year
131 period or while any portion of the district’s participation
132 requirement is outstanding. The first year of the 3-year period
133 shall be the first year a district receives an appropriation.
134 The department shall encourage a construction program that
135 reduces the average size of schools in the district. The request
136 must meet the following criteria to be considered by the
137 committee:
138 1. The project must be deemed a critical need and must be
139 recommended for funding by the Special Facility Construction
140 Committee. Before developing construction plans for the proposed
141 facility, the district school board must
submit an application
142
via letter to
request a preapplication review by
the Special
143 Facility Construction Committee
Chair or the Director of
144
Educational Facilities
or a project review subcommittee convened
145
by the chair of the committee to include two representatives of
146
the department and two staff members from school districts not
147
eligible to participate in the program
. A school district may
148
apply
request a preapplication review
at any time; however, if
149 the district school board seeks inclusion in the department’s
150 next annual capital outlay legislative budget request, the
151
district must apply
preapplication review request must be made
152 before February 1. Within 90 days after receiving the
153
application
preapplication review request
, the committee or
154 subcommittee must meet in the school district to review the
155 project proposal and existing facilities.
The committee or
156
subcommittee, convened by the committee chair,
must
include two
157
representatives from the department and two staff members from
158
school districts not eligible to participate in the program.
To
159 determine whether the proposed project is a critical need, the
160 committee or subcommittee shall consider, at a minimum, the
161 capacity of all existing facilities within the district as
162 determined by the Florida Inventory of School Houses; the
163 district’s pattern of student growth; the district’s existing
164 and projected capital outlay full-time equivalent student
165 enrollment as determined by the demographic, revenue, and
166 education estimating conferences established in s. 216.136; the
167 district’s existing satisfactory student stations; the use of
168 all existing district property and facilities; grade level
169 configurations; and any other information that may affect the
170 need for the proposed project.
171 2. The construction project must be recommended in the most
172 recent survey or survey amendment cooperatively prepared by the
173 district and the department, and approved by the department
174 under the rules of the State Board of Education. If a district
175 employs a consultant in the preparation of a survey or survey
176 amendment, the consultant may not be employed by or receive
177 compensation from a third party that designs or constructs a
178 project recommended by the survey.
179
a.
3.
The construction project must appear on the district’s
180 approved project priority list under the rules of the State
181 Board of Education.
182
b.
4.
The district must have selected and
have an
had
183 approved
a
site for the construction project in compliance with
184
s
s
. 1013.33
and 1013.36
s. 1013.36
and the rules of the State
185 Board of Education.
186
c. The district
must
have developed a district school
187
board
-
adopted list of facilities that do not exceed the norm for
188
net square feet occupancy requirements under the State
189
Requirements for Educational Facilities, using all possible
190
programmatic combinations for multiple use
s
of space to obtain
191
maximum daily use of all spaces within the facility under
192
consideration.
193
3.
a.
The department
shall
participate in the design review
194
process in compliance with s
s
. 1013.04 and 1013.41. If at any
195
time during the design phase the Office of Educational
196
Facilities determines a project goes beyond the scope of the
197
original requested project, to include changing site location,
198
and
the request is
not corrected, the project
is
disqualified
199
from the program and
the district must
reapply.
200
b
.
The department
shall
conduct construction site visits
201
throughout the construction process in compliance with s
.
202
1013.04.
203
5.
The district shall have developed a district school
204
board adopted list of facilities that do not exceed the norm for
205
net square feet occupancy requirements under the State
206
Requirements for Educational Facilities, using all possible
207
programmatic combinations for multiple use of space to obtain
208
maximum daily use of all spaces within the facility under
209
consideration.
210
4.
6.
Upon construction, the total cost per student station,
211 including change orders, must not exceed the cost per student
212 station as provided in subsection (6) unless approved by the
213 Special Facility Construction Committee. At the discretion of
214 the committee, costs that exceed the cost per student station
215 for special facilities may include legal and administrative
216 fees, the cost of site improvements or related offsite
217 improvements, the cost of complying with public shelter and
218 hurricane hardening requirements, cost overruns created by a
219 disaster as defined in s. 252.34(2), costs of security
220 enhancements approved by the school safety specialist, and
221 unforeseeable circumstances beyond the district’s control.
222
5.
7.
There shall be an agreement signed by the district
223 school board
and
kept
on file
with
the department
stating
that
224 it will advertise for bids
no later than
within
30 days
after
of
225 receipt of its encumbrance authorization
for design and
226
construction
from the department
.
227
6.
The selection of an architect and construction manager
228
will be as follows:
229
a
.
When selecting an architect and a construction manager
230
through the “Request for Qualifications” or “Request for
231
Proposals,” the district
shall
use the process developed by the
232
department,
including
scoresheets, submittal requirements, and
233
selection process. The department
shall
collect and review all
234
selection documentation and may provide feedback or take action
235
in the selection process, up to and including overriding the
236
board’s selection and making a new selection.
237
b.
District school boards
may
enter into a contingency
238
construction contract for the full construction amount initially
239
requested at the Special Facilities Construction Account
240
Committee meeting or the final
Guaranteed Maximum Price
,
241
whichever is higher. The contract must have a clause stating
242
that subsequent years
are
contingent on funding.
243
c.
A
n
elected
state
o
fficial
may not participate
in the
244
selection process other than approving the selection committee’s
245
recommendation.
246
7.
8.
For construction projects for which Special Facilities
247 Construction Account funding is sought before the 2019-2020
248 fiscal year, the district shall, at the time of the request and
249 for a continuing period necessary to meet the district’s
250 participation requirement, levy the maximum millage against its
251 nonexempt assessed property value as allowed in s. 1011.71(2) or
252 shall raise an equivalent amount of revenue from the school
253 capital outlay surtax authorized under s. 212.055(6). Beginning
254 with construction projects for which Special Facilities
255 Construction Account funding is sought in the 2019-2020 fiscal
256 year
and thereafter
, the district shall, for a minimum of 3
257 years before
applying for a special facilities project
258
submitting the request
and for a continuing period necessary to
259 meet its participation requirement, levy the maximum millage
260 against the district’s nonexempt assessed property value as
261 authorized under s. 1011.71(2) or shall raise an equivalent
262 amount of revenue from the school capital outlay surtax
263 authorized under s. 212.055(6). Any district with a new or
264 active project, funded under the provisions of this subsection,
265 shall be required to budget no more than the value of 1 mill per
266 year to the project until the district’s participation
267 requirement
of its maximum
relating to the
local discretionary
268 capital improvement millage
pursuant to s. 1011.71(2) for
3
269
years
or the equivalent amount of revenue from the school
270 capital outlay surtax is satisfied.
271
8.
9.
If a
construction
contract has not been signed
120
90
272 days after the advertising of bids, the funding for the specific
273 project
must
shall
revert to the Special Facility New
274 Construction Account to be reallocated to other projects on the
275 list. However, an additional
60
90
days may be granted by the
276 commissioner.
277
9.
10.
The department shall certify the inability of the
278 district to fund the survey-recommended project over a
279 continuous 3-year period using projected capital outlay revenue
280 derived from s. 9(d), Art. XII of the State Constitution, as
281 amended, paragraph (3)(a) of this section, and s. 1011.71(2).
282
10.
11.
The district shall have on file with the department
283 an adopted resolution acknowledging its commitment to satisfy
284 its participation requirement, which is equivalent to all
285 unencumbered and future revenue acquired from s. 9(d), Art. XII
286 of the State Constitution, as amended, paragraph (3)(a) of this
287 section, and s. 1011.71(2), in the year of the initial
288 appropriation and for the 2 years immediately following the
289 initial appropriation.
290
11.a.
12.
Phase I plans must be approved by the district
291
school board as being in compliance with the building and life
292
safety codes before June 1 of the year the application is made.
293
(b)
The Special Facility Construction Committee shall be
294 composed of the following: two representatives of the Department
295 of Education, a representative from the Governor’s office, a
296 representative selected annually by the district school boards,
297 and a representative selected annually by the superintendents. A
298 representative of the department shall chair the committee.
299
b.
(c)
The committee shall review the requests submitted
300 from the districts, evaluate the ability of the project to
301 relieve critical needs, and rank the requests in priority order.
302 This statewide priority list for special facilities construction
303 shall be submitted to the Legislature in the commissioner’s
304 annual capital outlay legislative budget request at least 45
305 days prior to the legislative session.
306 (6)
307 (e) Notwithstanding the requirements of this subsection, an
308 unfinished construction project for new construction of
309 educational plant space
which
that
was started on or before July
310 1,
2030
2028
, is exempt from the total cost per student station
311 requirements established in paragraph (b).
312 Section 2. Paragraph (a) of subsection (3) of section
313 1013.62, Florida Statutes, is amended to read:
314 1013.62 Charter schools capital outlay funding.—
315 (3) If the school board levies the discretionary millage
316 authorized in s. 1011.71(2), the department shall use the
317 following calculation methodology to determine the amount of
318 revenue that a school district must distribute to each eligible
319 charter school:
320 (a) Reduce the total discretionary millage revenue by the
321 school district’s annual debt service obligation incurred as of
322 March 1, 2017, which has not been subsequently retired, and any
323 amount of participation requirement pursuant to
s.
324
1013.64(2)(a)
7
.
s. 1013.64(2)(a)8.
that is being satisfied by
325 revenues raised by the discretionary millage.
326
327 By October 1 of each year, each school district shall certify to
328 the department the amount of debt service and participation
329 requirement that complies with the requirement of paragraph (a)
330 and can be reduced from the total discretionary millage revenue.
331 The Auditor General shall verify compliance with the
332 requirements of paragraph (a) and s. 1011.71(2)(e) during
333 scheduled operational audits of school districts.
334 Section 3. This act shall take effect July 1, 2026.