Back to Iowa

HF2580 • 2026

A bill for an act relating to the siting and operation of renewable electric power generating facilities.(Formerly HSB 692 .)

A bill for an act relating to the siting and operation of renewable electric power generating facilities.(Formerly HSB 692 .)

Passed Legislature

This bill passed both chambers and reached final enrollment, even if later executive action is not shown here.

Sponsor
COMMITTEE ON COMMERCE
Last action
2026-04-27
Official status
Amendment H-8403 filed. H.J. 1012 .
Effective date
Not listed

Plain English Breakdown

Using official source text because the generated explanation was unavailable or could not be confirmed against the official bill text.

A bill for an act relating to the siting and operation of renewable electric power generating facilities.(Formerly HSB 692 .)

A bill for an act relating to the siting and operation of renewable electric power generating facilities.(Formerly HSB 692 .)

What This Bill Does

  • A bill for an act relating to the siting and operation of renewable electric power generating facilities.(Formerly HSB 692 .)

Limits and Unknowns

  • This entry is temporarily using official source text because the generated explanation could not be confirmed against the official bill text during the last sync.

Bill History

  1. 2026-04-27 Iowa Legislature

    Amendment H-8403 filed. H.J. 1012 .

  2. 2026-03-19 Iowa Legislature

    Placed on calendar under unfinished business. H.J. 691 .

  3. 2026-03-17 Iowa Legislature

    Amendments H-8225 , H-8226 , H-8227 and H-8228 filed. H.J. 684 .

  4. 2026-02-18 Iowa Legislature

    Introduced, placed on calendar. H.J. 330 .

Official Summary Text

A bill for an act relating to the siting and operation of renewable electric power generating facilities.(Formerly HSB 692 .)

Current Bill Text

Read the full stored bill text
House

File

2580

-

Introduced

HOUSE

FILE

2580

BY

COMMITTEE

ON

COMMERCE

(SUCCESSOR

TO

HSB

692)

A

BILL

FOR

An

Act

relating

to

the

siting

and

operation

of

renewable

1

electric

power

generating

facilities.

2

BE

IT

ENACTED

BY

THE

GENERAL

ASSEMBLY

OF

THE

STATE

OF

IOWA:

3

TLSB

5997HV

(2)

91

sb/js

H.F.

2580

Section

1.

Section

6A.22,

Code

2026,

is

amended

by

adding

1

the

following

new

subsection:

2

NEW

SUBSECTION

.

3.

Notwithstanding

any

other

provision

of

3

law,

a

person

shall

not

exercise

the

power

of

eminent

domain

to

4

acquire

right-of-way

for,

construct,

or

operate

any

renewable

5

electric

power

generation

facility,

as

defined

in

section

6

476.53B.

7

Sec.

2.

NEW

SECTION

.

476.53B

Local

authority

standards

——

8

renewable

electric

power

generation.

9

1.

The

standards

in

this

section

shall

apply

to

the

approval

10

by

local

authorities

of

all

renewable

electric

power

generation

11

facilities

proposed

after

January

1,

2026.

12

2.

For

purposes

of

this

section,

unless

the

context

13

otherwise

requires:

14

a.

“Abutting

dwelling”

means

an

occupied

building

or

15

structure

used

primarily

for

human

habitation

that

is

located

16

on

nonparticipating

property.

17

b.

“Battery

energy

storage

system”

means

an

electrochemical

18

device

that

charges,

or

collects,

energy

from

the

grid

or

a

19

generation

facility,

stores

that

energy,

and

then

discharges

20

that

energy

at

a

later

time

to

provide

electricity

or

other

21

grid

services.

22

c.

“Community

building”

means

any

one

or

more

of

the

23

following

buildings

that

is

existing

and

occupied

on

the

date

24

that

the

application

for

approval,

rezoning,

or

a

special

or

25

conditional

use

permit

is

filed

with

the

county:

a

school,

a

26

place

of

worship,

a

day

care

facility,

a

public

library,

or

a

27

community

center.

28

d.

“Local

authority”

means

a

city

as

defined

in

section

29

362.2

or

a

county

as

provided

in

chapter

331.

30

e.

“Nonparticipating

property”

means

any

real

property

owned

31

by

a

person

who

has

not

granted

written

permission,

consent,

32

an

easement,

or

other

similar

agreement

pertaining

to

a

wind

33

energy

conversion

facility

on

such

property.

34

f.

“Public

road

right-of-way”

means

the

same

as

defined

in

35

-1-

LSB

5997HV

(2)

91

sb/js

1/

12

H.F.

2580

section

306.3.

1

g.

“Railroad

right-of-way”

means

the

same

as

defined

in

2

section

476.27.

3

h.

“Renewable

electric

power

generation

facility”

means

4

a

battery

energy

storage

system,

a

solar

energy

conversion

5

facility,

or

a

wind

energy

conversion

facility.

6

i.

“Renewable

electric

power

generation

moratorium”

means

a

7

regulation

that

explicitly

or

implicitly

disallows

a

renewable

8

electric

power

generation

facility

from

being

developed

9

or

operated

in

any

district

zoned

to

allow

agricultural

or

10

industrial

use.

11

j.

“Repowering”

means

the

same

as

defined

in

section

476.53.

12

k.

“Solar

energy

conversion

facility”

means

a

solar

energy

13

conversion

facility,

as

defined

in

section

476C.1,

that

has

14

a

nameplate

generating

capacity

greater

than

one

hundred

15

kilowatts.

16

l.

“Unoccupied

structure”

means

a

building

or

structure

that

17

is

not

occupied

or

used

primarily

for

human

habitation

at

the

18

time

of

siting.

19

m.

“Wind

energy

conversion

facility”

or

“facility”

means

a

20

wind

energy

conversion

facility,

as

defined

in

section

476C.1,

21

or

a

wind

turbine

that

is

part

of

a

wind

energy

conversion

22

system,

that

has

a

nameplate

generating

capacity

greater

than

23

one

hundred

kilowatts.

24

3.

a.

A

local

authority

may

determine

setback

standards

25

for

wind

energy

conversion

facilities

that,

notwithstanding

any

26

statute

or

regulation

to

the

contrary,

shall

be

no

greater

than

27

and

shall

not

include

any

setback

requirements

beyond

those

in

28

this

subsection:

29

(1)

The

facility

shall

be

sited

two

times

the

total

height

30

of

a

wind

energy

conversion

facility

to

be

constructed

on

31

a

proposed

facility

from

any

existing

abutting

dwelling

or

32

community

building.

33

(2)

The

facility

shall

be

sited

one

and

one-tenth

times

34

the

total

height

of

a

wind

energy

conversion

facility

to

35

-2-

LSB

5997HV

(2)

91

sb/js

2/

12

H.F.

2580

be

constructed

on

a

proposed

facility

from

any

existing

1

nonparticipating

property.

2

(3)

The

facility

shall

be

sited

one

and

one-tenth

times

3

the

total

height

of

a

wind

energy

conversion

facility

to

be

4

constructed

on

a

proposed

facility

from

any

existing

overhead

5

utility

line,

electric

substation,

public

road

right-of-way,

6

railroad

right-of-way,

or

unoccupied

structure.

7

(4)

Each

wind

turbine

shall

not

exceed

the

height

allowed

8

under

the

determination

of

no

hazard

for

that

turbine

from

the

9

federal

aviation

administration

obstruction

evaluation

under

10

14

C.F.R.

pt.

77.

Nothing

in

this

section

shall

be

construed

11

as

prohibiting

an

airport,

aviation

authority,

or

municipality

12

from

administering

and

enforcing

airport

zoning

pursuant

to

13

the

provisions

of

chapter

329

for

the

protection

of

navigable

14

airspace.

15

b.

For

purposes

of

this

subsection,

the

facility

site

16

distance

shall

be

measured

from

the

center

of

the

wind

energy

17

conversion

facility

foundation

to

the

nearest

point

of

the

18

abutting

dwelling,

community

building,

nonparticipating

19

property,

overhead

utility

line,

electric

substation,

public

20

road

right-of-way,

railroad

right-of-way,

or

unoccupied

21

structure.

22

c.

For

purposes

of

this

subsection,

the

total

height

of

23

a

wind

energy

conversion

facility

shall

be

measured

as

the

24

distance

from

ground

level

to

the

tip

of

the

wind

energy

25

conversion

facility’s

blade

at

its

highest

vertical

point.

26

4.

A

local

authority

may

determine

setback

standards

27

for

solar

energy

conversion

facilities.

For

purposes

of

28

this

subsection,

distance

shall

be

measured

from

the

nearest

29

aboveground

point

of

a

solar

facility,

not

including

any

30

fencing,

to

the

nearest

point

of

the

abutting

dwelling,

31

overhead

utility

line,

electric

substation,

nonparticipating

32

property

line,

public

road

right-of-way,

railroad

right-of-way,

33

or

unoccupied

structure.

The

standards

shall

be

no

greater

34

than:

35

-3-

LSB

5997HV

(2)

91

sb/js

3/

12

H.F.

2580

a.

Fifty

feet

from

the

near

edge

of

any

existing

1

nonparticipating

property

line

or

one

hundred

feet

from

any

2

existing

abutting

dwelling

or

community

building,

whichever

is

3

greater.

4

b.

Fifty

feet

from

any

existing

overhead

utility

line,

5

substation,

public

road

right-of-way,

or

railroad

right-of-way.

6

5.

A

local

authority

may

determine

setback

standards

7

for

battery

energy

storage

systems.

For

purposes

of

this

8

subsection,

distance

shall

be

measured

from

the

nearest

storage

9

container

edge

to

the

nearest

point

of

the

abutting

dwelling,

10

overhead

utility

line,

electric

substation,

nonparticipating

11

property

line,

public

road

right-of-way,

railroad

right-of-way,

12

or

unoccupied

structure.

The

standards

shall

be

no

greater

13

than:

14

a.

Fifty

feet

from

any

existing

participating

property

line.

15

b.

One

hundred

feet

from

any

existing

nonparticipating

16

property

line

or

any

existing

abutting

dwelling

or

community

17

building.

18

c.

Fifty

feet

from

any

existing

nonassociated

transmission,

19

substation,

or

distribution

lines.

20

d.

Fifty

feet

from

any

public

road

right-of-way

or

railroad

21

right-of-way.

22

6.

A

local

authority

may

only

implement

the

following

23

additional

standards

and

only

to

the

extent

specified

in

this

24

subsection:

25

a.

A

shadow

flicker

standard

that

is

no

more

restrictive

26

than

thirty

hours

per

year

under

planned

operating

conditions

27

as

indicated

by

industry

standard

computer

modeling

measured

28

from

an

abutting

dwelling

or

community

building.

29

b.

A

sound

limitation

that

is

no

more

restrictive

than

30

a

maximum

forty-seven

decibel

sound

from

the

wind

energy

31

conversion

facility

as

measured

at

an

existing

abutting

32

dwelling

or

community

building.

Decibel

modeling

shall

use

the

33

A-weighted

scale

as

designed

by

the

American

national

standards

34

institute.

Sound

modeling

shall

be

completed

by

a

professional

35

-4-

LSB

5997HV

(2)

91

sb/js

4/

12

H.F.

2580

board-certified

by

the

institute

of

noise

control

engineering,

1

or

an

appropriately

licensed

professional

engineer.

2

c.

A

requirement

that

the

applicant

of

a

proposed

wind

3

energy

conversion

facility

shall

agree

to

repair

or

replace

any

4

damaged

drainage

infrastructure

if

directly

attributable

to

the

5

construction

or

operation

of

the

facility.

6

d.

A

requirement

that

renewable

electric

power

generation

7

facilities

meet

all

applicable

national

electric

safety

code

8

and

international

building

code

requirements.

9

e.

A

requirement

that

renewable

electric

power

generation

10

facilities

meet

all

applicable

provisions

of

national

fire

11

protection

association

standard

855.

12

f.

A

requirement

that

renewable

electric

power

generation

13

facilities

for

fencing

are

no

more

restrictive

than

the

14

requirement

issued

by

the

national

electric

safety

code.

15

g.

A

requirement

for

solar

energy

conversion

facilities

16

to

maintain

appropriate

ground

cover

within

the

solar

energy

17

conversion

facility’s

fence

line

throughout

the

life

of

the

18

facility

to

minimize

erosion.

19

h.

A

height

requirement

for

solar

energy

conversion

20

facilities

for

a

minimum

one

and

one-half

feet

panel

height

21

from

the

ground,

exclusive

of

supporting

infrastructure,

with

22

no

additional

or

higher

minimum

height

requirements

for

the

23

solar

energy

conversion

facility.

24

7.

A

local

authority

must

provide

a

process

for

the

owner

of

25

any

abutting

dwelling,

nonparticipating

property,

or

community

26

building

to

waive

the

standards

in

this

section

or

those

27

adopted

by

a

local

authority.

28

8.

A

local

authority

must

use

reasonable

estimates

of

the

29

cost

of

approving

an

application

for

a

facility,

which

shall

30

not

exceed

one

thousand

dollars

per

wind

energy

conversion

31

system,

solar

energy

conversion

system,

or

battery

energy

32

storage

system.

A

local

authority

may

not

require

the

facility

33

owner

to

pay

costs,

fees,

or

charges

for

administrative

or

road

34

work

that

is

not

specifically

and

uniquely

attributable

to

the

35

-5-

LSB

5997HV

(2)

91

sb/js

5/

12

H.F.

2580

approval

and

construction

of

the

facility.

1

9.

A

local

authority

shall

not

prohibit

or

regulate

testing

2

activities

undertaken

by

a

wind

energy

conversion

facility

3

owner

for

purposes

of

determining

the

suitability

of

the

4

placement

of

a

wind

energy

conversion

facility.

5

10.

Ordinances,

limitations,

or

other

requirements

imposed

6

after

an

application

for

approval,

rezoning,

or

a

special

7

or

conditional

use

permit

for

a

renewable

electric

power

8

generation

facility

has

been

submitted

or

previously

approved

9

shall

not

be

construed

to

limit

or

impair

the

construction,

10

operation,

or

maintenance

of

the

renewable

electric

power

11

generation

facility.

12

11.

A

local

authority

shall

not

prohibit

an

affected

13

landowner

or

other

entity

from

waiving

any

requirements

under

14

this

section

by

the

conveyance

of

an

easement

or

other

property

15

interest.

16

12.

a.

A

local

authority

may

require

the

owner

of

the

17

proposed

renewable

electric

power

generation

facility

to

file

18

with

the

county

recorder

of

the

county

or

counties

in

which

19

the

proposed

facility

will

be

located

a

decommissioning

plan

20

outlining

measures

that

will

be

taken

to

return

the

land

to

21

a

reasonably

similar

state

to

the

condition

that

existed

22

before

construction

of

the

renewable

electric

power

generation

23

facility.

Removal

requirements

of

underground

project

24

infrastructure

may

not

exceed

a

maximum

depth

of

four

feet.

A

25

local

authority

shall

not

require

a

revision

or

amendment

of

26

a

decommissioning

plan.

27

b.

A

local

authority

may

require

the

owner

to

provide

28

in

the

decommissioning

plan

proof

of

financial

assurance

to

29

fund

decommissioning

efforts,

which

assurance

is

calculated

30

by

an

independent

third

party

as

the

estimated

costs

of

31

decommissioning,

inclusive

of

net

salvage

value,

no

earlier

32

than

the

following

schedule:

33

(1)

Five

percent

of

determined

decommissioning

costs

34

committed

by

the

initial

commercial

operation

date.

35

-6-

LSB

5997HV

(2)

91

sb/js

6/

12

H.F.

2580

(2)

One

hundred

percent

of

determined

decommissioning

costs

1

committed

by

the

fifteenth

year

of

commercial

operation.

2

c.

After

the

fifteenth

year

of

commercial

operation,

the

3

owner

of

the

renewable

electric

power

generation

facility

4

may

reestimate

the

cost

of

decommissioning,

inclusive

of

net

5

salvage

value,

using

an

independent

third

party

for

the

purpose

6

of

redetermining

the

amount

required

for

financial

assurance.

7

d.

Evidence

of

financial

security

may

be

in

the

form

of

a

8

surety

bond,

collateral

bond,

parent

guaranty,

cash,

cashier’s

9

check,

certificate

of

deposit,

bank

joint

custody

receipt,

or

10

other

approved

negotiable

instrument.

11

e.

This

subsection

shall

not

apply

to

a

renewable

electric

12

power

generation

facility

owned

or

operated

by

a

public

utility

13

regulated

by

the

Iowa

utilities

commission.

14

13.

a.

This

section

shall

not

apply

to

a

wind

energy

15

conversion

facility

that

has

a

nameplate

capacity

of

16

twenty-five

or

more

megawatts

on

any

single

gathering

line

17

and

if

the

facility

has

applied

for

certification

pursuant

to

18

chapter

476A.

19

b.

This

section

shall

not

apply

to

a

renewable

electric

20

power

generation

facility

that

is

operating

or

has

submitted

21

an

application

for

the

issuance

of

permits

on

or

before

the

22

effective

date

of

this

Act.

23

c.

This

section

shall

not

apply

to

the

repowering

of

a

wind

24

energy

conversion

facility

existing

on

or

before

January

1,

25

2025.

26

d.

This

section

shall

not

apply

to

the

repowering

of

a

27

renewable

electric

power

generation

facility,

which

is

not

28

already

excluded

under

paragraph

“c”

,

existing

on

or

before

29

January

1,

2026,

provided

that

the

repowering

does

not

require

30

the

issuance

of

any

new

permits,

or

amendments

to

existing

31

permits,

from

a

local

authority.

This

section

shall

apply

32

to

the

repowering

of

a

renewable

electric

power

generation

33

facility

existing

on

or

before

January

1,

2026,

when

such

34

repowering

requires

the

issuance

of

any

new

permits,

or

35

-7-

LSB

5997HV

(2)

91

sb/js

7/

12

H.F.

2580

amendments

to

existing

permits,

from

a

local

authority.

1

14.

a.

A

local

authority

shall

not

adopt

regulations

2

that

explicitly

or

implicitly

disallow

a

renewable

electric

3

power

generation

facility

from

being

developed

or

operated

4

in

any

district

zoned

to

allow

agricultural

or

industrial

5

use.

A

local

authority

may

not

prohibit

or

otherwise

limit

6

renewable

electric

power

generation

facility

development

7

based

on

corn

suitability

rating

as

calculated

using

the

8

methodology

recognized

by

the

Iowa

state

university

of

science

9

and

technology.

A

local

authority

may

not

limit

the

size

of

10

any

specific

project

or

create

caps

on

projects

based

on

total

11

land

mass

within

the

local

jurisdiction.

12

b.

A

local

authority

may

place

one

temporary

moratorium

13

for

up

to

six

months

on

the

installation

of

a

wind

energy

14

conversion

facility

for

the

purpose

of

adopting

new

regulations

15

that

are

consistent

with

this

section.

All

new,

revised,

16

or

amended

ordinances

or

regulations

pertaining

to

solar

or

17

solar

energy

conversion

facilities

shall

only

be

prospectively

18

applied.

19

c.

Nothing

in

this

section

requires

a

local

authority

20

to

adopt

standards

for

approval

of

renewable

electric

power

21

generation

facilities.

22

15.

a.

Any

requirement

for

renewable

electric

power

23

generation

siting,

compliance,

and

operation

pursuant

to

24

subsections

3

through

14

may

be

waived

by

the

local

authority

25

if

the

local

authority

fulfills

the

requirements

under

26

paragraph

“b”

.

27

b.

If

on

the

effective

date

of

this

Act

a

local

authority

28

has

in

effect

a

renewable

electric

power

generation

moratorium

29

or

standards

not

in

compliance

with

subsections

3

through

14,

30

the

local

authority

must

do

all

of

the

following

by

January

1,

31

2028,

and

a

local

authority

enacting

a

renewable

electric

power

32

generation

moratorium

or

not

in

compliance

with

subsections

3

33

through

14

must

do

all

of

the

following

before

the

enactment

34

of

the

moratorium

or

standards:

35

-8-

LSB

5997HV

(2)

91

sb/js

8/

12

H.F.

2580

(1)

Send

notice

to

all

persons

under

the

local

authority’s

1

jurisdiction

required

to

pay

property

tax

to

the

local

2

authority.

If

the

local

authority

operates

an

internet

3

site,

the

local

authority

shall

post

notice

on

the

local

4

authority’s

internet

site.

The

notice

shall

include

the

amount

5

of

estimated

property

tax

revenue

that

has

not

been

received

6

by

the

local

authority

based

on

any

renewable

electric

power

7

generation

moratorium

or

standards

not

in

compliance

with

8

the

requirements

of

subsections

3

through

14.

If

the

local

9

authority

is

unable

to

determine

the

tax

revenue

amount,

the

10

local

authority

must

review

another

local

authority

with

a

11

similarly

sized

population

that

has

not

adopted

a

renewable

12

electric

power

generation

moratorium

and

is

in

compliance

13

with

the

standards

of

this

section

and

determine

the

amount

14

generated

annually

in

property

tax

revenue

from

renewable

15

electric

power

generation

facilities

by

the

other

local

16

authority.

17

(2)

Hold

a

public

hearing

discussing

reasons

for

the

18

renewable

electric

generation

moratorium

or

standards

not

19

in

compliance

with

subsections

3

through

14,

including

a

20

demonstration

showing

the

renewable

electric

generation

21

moratorium

or

the

noncompliant

standards

are

necessary

to

22

prevent

an

adverse

impact

on

the

health

or

safety

of

the

local

23

authority’s

residents

or

public

facilities.

24

Sec.

3.

COMPLIANCE

BY

LOCAL

AUTHORITIES.

If

any

local

25

authority

has

a

standard

in

effect

on

or

after

the

effective

26

date

of

this

Act

that

does

not

comply

with

the

provisions

27

in

this

Act,

the

local

authority

must

amend

the

standard

to

28

comply

with

this

Act

by

December

31,

2026,

or

follow

procedures

29

described

in

section

476.53B,

subsection

15,

as

enacted

by

this

30

Act.

31

EXPLANATION

32

The

inclusion

of

this

explanation

does

not

constitute

agreement

with

33

the

explanation’s

substance

by

the

members

of

the

general

assembly.

34

This

bill

relates

to

siting

and

operation

of

certain

35

-9-

LSB

5997HV

(2)

91

sb/js

9/

12

H.F.

2580

renewable

electric

power

generation

facilities.

1

The

bill

prohibits

exercising

the

power

of

eminent

domain

2

for

acquiring

right-of-way

for,

constructing,

or

operating

any

3

renewable

electric

power

generation

facility

(facility).

4

The

bill

creates

standard-making

ability

for

local

5

authorities

approving

a

facility

proposed

after

January

1,

6

2026.

7

The

bill

sets

guidelines

for

a

local

authority

to

implement

8

a

facility

setback

standard,

which

shall

include

a

facility’s

9

distance

from

specified

existing

buildings

based

on

the

10

facility’s

height.

The

local

authority

must

include

a

process

11

for

an

owner

of

an

abutting

dwelling,

nonparticipating

12

property,

or

community

building

to

waive

the

setback

standards.

13

The

bill

includes

additional

standards

a

local

authority

14

may

implement

including

shadow

flicker

standards,

sound

15

limitations,

a

requirement

that

an

applicant

for

a

proposed

16

facility

shall

agree

to

repair

any

damages

caused

by

the

17

facility,

wind

turbine

height

limitations,

electric

code

18

and

building

code

standards,

fire

protection

standards,

19

fencing

limitations,

ground

cover

standards,

and

solar

energy

20

conversion

facility

panel

height

requirements.

21

The

bill

requires

a

local

authority

to

utilize

reasonable

22

estimates

for

application

approval

costs

and

prohibits

the

23

local

authority

from

requiring

the

facility

owner

to

pay

for

24

administration

or

road

work

that

is

not

directly

attributable

25

to

the

approval

and

construction

of

the

facility.

A

local

26

authority

shall

not

prohibit

or

regulate

a

facility

testing

the

27

suitability

of

a

facility

placement.

Any

regulations

enacted

28

after

the

application

for

a

facility

permit

shall

not

limit

the

29

construction,

operation,

or

maintenance

of

that

facility.

A

30

local

authority

shall

not

prohibit

an

affected

landowner

or

31

other

entity

from

waiving

requirements

by

conveyance

of

an

32

easement.

33

The

bill

provides

that

a

local

authority

may

require

a

34

facility

that

is

not

owned

or

operated

by

a

public

utility

35

-10-

LSB

5997HV

(2)

91

sb/js

10/

12

H.F.

2580

regulated

by

the

Iowa

utilities

commission

to

file

a

1

decommissioning

plan

including

certain

measures.

The

local

2

authority

is

prohibited

from

requiring

a

facility

to

provide

a

3

revision

or

amendment

of

a

decommissioning

plan.

4

The

bill

shall

not

apply

to

a

wind

energy

conversion

facility

5

with

a

nameplate

capacity

of

25

or

more

megawatts

and

that

has

6

applied

for

certification

under

Code

chapter

476A,

a

facility

7

that

is

currently

operating

or

has

applied

for

certification

8

before

the

enactment

of

the

bill,

or

the

repowering

of

a

9

facility

existing

on

or

before

January

1,

2026,

subject

to

10

certain

conditions.

11

The

bill

allows

a

local

authority

to

place

one

temporary

12

moratorium

for

up

to

six

months

on

the

installation

of

a

13

wind

energy

conversion

facility

for

the

purpose

of

adopting

14

new

regulations

that

are

consistent

with

the

bill.

The

bill

15

provides

that

all

new,

revised,

or

amended

ordinances

or

16

regulations

pertaining

to

solar

or

solar

energy

conversion

17

facilities

shall

only

be

prospectively

applied.

18

The

bill

authorizes

a

local

authority

to

waive

any

19

requirement

for

renewable

electric

power

generation

under

20

the

bill

if

the

local

authority

complies

with

additional

21

requirements

established

in

the

bill.

22

The

bill

provides

that

if,

on

the

effective

date

of

the

23

bill,

a

local

authority

has

in

effect

a

moratorium

on

renewable

24

electric

power

generation

or

has

adopted

standards

that

do

25

not

comply

with

standards

in

the

bill,

the

local

authority

26

must

complete

specified

actions

by

January

1,

2028.

The

bill

27

further

provides

that

a

local

authority

that

enacts

a

renewable

28

electric

power

generation

moratorium

or

adopts

noncompliant

29

standards

must

complete

the

same

actions

prior

to

enactment

of

30

the

moratorium

or

standards.

31

The

bill

requires

the

local

authority

to

provide

notice

to

32

all

persons

within

its

jurisdiction

who

are

required

to

pay

33

property

tax

to

the

local

authority

and

to

post

the

notice

34

on

the

local

authority’s

internet

site,

if

applicable.

The

35

-11-

LSB

5997HV

(2)

91

sb/js

11/

12

H.F.

2580

notice

must

include

an

estimate

of

the

amount

of

property

tax

1

revenue

not

received

by

the

local

authority

as

a

result

of

the

2

moratorium

or

noncompliance

with

standards

in

the

bill.

If

the

3

local

authority

is

unable

to

determine

the

amount

of

property

4

tax

revenue,

the

bill

requires

the

local

authority

to

compare

5

itself

to

another

local

authority

with

a

similar

population

6

that

has

not

adopted

a

renewable

electric

power

generation

7

moratorium

and

that

complies

with

the

standards

in

the

bill,

8

and

to

determine

the

amount

of

property

tax

revenue

generated

9

annually

by

facilities

in

that

comparable

jurisdiction.

10

The

bill

also

requires

the

local

authority

to

hold

a

public

11

hearing

to

discuss

the

reasons

for

the

renewable

electric

power

12

generation

moratorium

or

noncompliant

standards.

The

public

13

hearing

must

include

a

demonstration

that

the

moratorium

or

14

noncompliant

standards

are

necessary

to

prevent

an

adverse

15

impact

on

the

health

or

safety

of

the

local

authority’s

16

residents

or

public

facilities.

17

The

bill

expounds

that

a

local

authority

is

not

required

18

to

adopt

standards

for

approval

of

renewable

electric

power

19

generation

facilities;

however,

a

local

authority

with

existing

20

siting

standards

in

effect

on

or

after

the

effective

date

21

of

the

bill

that

do

not

comply

with

the

bill

must

amend

the

22

standards

to

comply

with

the

bill

by

December

31,

2026,

or

23

follow

the

noncompliance

procedures

described

in

the

bill.

24

-12-

LSB

5997HV

(2)

91

sb/js

12/

12