LD810 • 2025
An Act Regarding the Approval of Transmission Lines
An Act Regarding the Approval of Transmission Lines
Energy
Technology
Enacted
This bill passed the Legislature and reached final enactment based on the latest official action.
- Sponsor
- Representative Christopher Kessler
- Last action
- 2025-06-17
- Official status
- Signed by the Governor
- Effective date
- Not listed
Plain English Breakdown
Using official source text because the generated explanation was unavailable or could not be confirmed against the official bill text.
An Act Regarding the Approval of Transmission Lines
An Act Regarding the Approval of Transmission Lines
Sponsor:
Representative Christopher Kessler
Reference committee:
Energy, Utilities and Technology
Governor action:
Signed by the Governor
What This Bill Does
- An Act Regarding the Approval of Transmission Lines
Sponsor:
Representative Christopher Kessler
Reference committee:
Energy, Utilities and Technology
Governor action:
Signed by the Governor
Limits and Unknowns
- This entry is temporarily using official source text because the generated explanation could not be confirmed against the official bill text during the last sync.
Amendments
These notes stay tied to the official amendment files and metadata from the legislature.
Adopted by House & Senate
Plain English: Page 1 - 132LR2391(02)
COMMITTEE AMENDMENT
1 L.D.
- Page 1 - 132LR2391(02)
COMMITTEE AMENDMENT
1 L.D.
- 810
2 Date: (Filing No.
- H- )
3ENERGY, UTILITIES AND TECHNOLOGY
4 Reproduced and distributed under the direction of the Clerk of the House.
- 5STATE OF MAINE
6HOUSE OF REPRESENTATIVES
7132ND LEGISLATURE
8FIRST SPECIAL SESSION
9 COMMITTEE AMENDMENT “ ” to H.P.
Bill History
-
2025-06-17
Governor
Signed by the Governor
-
2025-06-11
Senate
PASSED TO BE ENACTED , in concurrence.
-
2025-06-10
House
RELEASED .
-
2025-06-02
Committee
Reported Out; OTP-AM/ONTP
-
2025-04-15
Committee
Work Session Held
-
2025-04-15
Committee
Voted; Divided Report
-
2025-04-03
Committee
Work Session Held; TABLED
-
2025-03-25
Committee
Work Session Held; TABLED
-
2025-02-27
Committee
Referred to Committee on Energy, Utilities and Technology.
Official Summary Text
An Act Regarding the Approval of Transmission Lines
Sponsor:
Representative Christopher Kessler
Reference committee:
Energy, Utilities and Technology
Governor action:
Signed by the Governor
Current Bill Text
Read the full stored bill text
Page 1 - 132LR2391(03)
STATE OF MAINE
_____
IN THE YEAR OF OUR LORD
TWO THOUSAND TWENTY-FIVE
_____
H.P. 517 - L.D. 810
An Act Regarding the Approval of Transmission Lines
Be it enacted by the People of the State of Maine as follows:
Sec. 1. 35-A MRSA §3132, sub-§6-C, as amended by PL 2023, c. 644, §2, is
further amended by enacting at the end a new blocked paragraph to read:
For the purposes of this subsection, a high-impact electric transmission line is deemed to
have received the majority legislative approval required by this subsection if the high-
impact electric transmission line is approved for a contract after a competitive procurement
conducted by the commission or a state agency pursuant to statutory authority granted
under this Title.
APPROVED
JUNE 17, 2025
BY GOVERNOR
CHAPTER
340
PUBLIC LAW