Back to Massachusetts

H3334 • 2025

An Act relative to timely public payments for work not included in original construction contracts

An Act relative to timely public payments for work not included in original construction contracts

Active

The official status still shows this bill as active or still awaiting another formal step.

Sponsor
William C. Galvin
Last action
2025-12-11
Official status
Referred to House Committee on Ways and Means
Effective date
Not listed

Plain English Breakdown

Using official source text because the generated explanation was unavailable or could not be confirmed against the official bill text.

An Act relative to timely public payments for work not included in original construction contracts

An Act relative to timely public payments for work not included in original construction contracts By Representative Galvin of Canton, a petition (accompanied by bill, House, No.

What This Bill Does

  • An Act relative to timely public payments for work not included in original construction contracts By Representative Galvin of Canton, a petition (accompanied by bill, House, No.
  • 3334) of William C.
  • Galvin relative to timely payments for work not included in public construction contracts.
  • State Administration and Regulatory Oversight.

Limits and Unknowns

  • This entry is temporarily using official source text because the generated explanation could not be confirmed against the official bill text during the last sync.

Bill History

  1. 2025-12-11 House

    Bill reported favorably by committee and referred to the committee on House Ways and Means

  2. 2025-10-08 Joint

    Hearing rescheduled to 10/08/2025 from 01:00 PM-01:55 PM in 222 and Virtual Hearing updated to New End Time

  3. 2025-09-25 Joint

    Hearing rescheduled to 10/08/2025 from 01:00 PM-05:00 PM in 222 and Virtual Hearing location changed

  4. 2025-09-24 Joint

    Hearing scheduled for 10/01/2025 from 10:00 AM-01:00 PM in A-1

  5. 2025-02-27 House

    Referred to the committee on State Administration and Regulatory Oversight

  6. 2025-02-27 Senate

    Senate concurred

Official Summary Text

An Act relative to timely public payments for work not included in original construction contracts
By Representative Galvin of Canton, a petition (accompanied by bill, House, No. 3334) of William C. Galvin relative to timely payments for work not included in public construction contracts. State Administration and Regulatory Oversight.
Status:
Referred to House Committee on Ways and Means

Current Bill Text

Read the full stored bill text
×

Bill H.3334

SECTION 1. Section 39G of chapter 30 of the General Laws, as appearing in the 2022 Official Edition, is hereby amended by inserting after the eighth paragraph the following paragraph:

Every contract subject to section 44A of chapter 149 or subject to section 39M of chapter 30 or subject to chapter 149A, and every subcontract or trade contract as applicable, shall provide a reasonable time period within which a written request submitted by a person seeking an increase in the contract price shall be approved or rejected, whether in whole or in part. The time period shall not exceed 30 days after the later of commencement of the performance of the work on which the request is based or submission of the written request; provided, however, that the time period, as applicable to approval or rejection by the person at each tier of contract below the owner of the project, may be extended by 7 days more than the time period applicable to the person at the tier of contract above the person. A request which is neither approved nor rejected within such time period shall be deemed to be approved and may be submitted for payment within the next application for a periodic progress payment, unless it is rejected before the date payment if due. A rejection of a request, whether in whole or in part, shall be made in writing, shall include an explanation of the factual and contractual basis for the rejection and shall be certified as made in good faith. A rejection of a request shall be subject to the applicable dispute resolution procedure. A provision in the contract which requires a party to delay commencement of the procedure until a date later than 60 days after the rejection shall be void and unenforceable.

The information contained in this website is for general information purposes only. The General Court provides this information as a public service and while we endeavor to keep the data accurate and current to the best of our ability, we make no representations or warranties of any kind, express or implied, about the completeness, accuracy, reliability, suitability or availability with respect to the website or the information contained on the website for any purpose. Any reliance you place on such information is therefore strictly at your own risk.

Close