Read the full stored bill text
A bill for an act
relating to energy; adding and modifying provisions to support deployment of
energy storage; directing the Public Utilities Commission to issue an order;
requiring utilities to install an energy storage system under certain conditions;
directing public utilities to file a tariff with the Public Utilities Commission;
requiring the Public Utilities Commission to order the installation of energy storage
systems; requiring public utilities to file a plan to install energy storage systems;
establishing an incentive program to install energy storage systems; appropriating
money; amending Minnesota Statutes 2024, sections 216B.1611, by adding a
subdivision; 216B.2422, subdivision 7; proposing coding for new law in Minnesota
Statutes, chapters 216B; 216C.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:
Section 1.
Minnesota Statutes 2024, section 216B.1611, is amended by adding a subdivision
to read:
new text begin
Subd. 5.
new text end
new text begin
Distributed generation capacity; treatment.
new text end
new text begin
(a) No later than November 1,
2026, the commission must issue an order clarifying that for purposes of interconnecting
an on-site customer-owned distributed generation facility, the capacity of the facility must
be measured and expressed as:
new text end
new text begin
(1) export capacity rather than nameplate capacity; and
new text end
new text begin
(2) alternating current capacity.
new text end
new text begin
(b) For purposes of this subdivision, "export capacity" means a distributed generation
facility's nameplate capacity net of any limitations on the amount of power the distributed
generating facility is capable of exporting to a utility's distribution system resulting from
physical equipment that is part of or connected to the generating facility, including but not
limited to an inverter, relay, or energy storage system, as defined in section 216B.2422,
subdivision 1, paragraph (f), as reported to the utility by the owner of the distributed
generation facility.
new text end
new text begin
(c) The owner of a distributed generation facility interconnected to a utility's distribution
system is prohibited from increasing the export capacity of the distributed generation facility
beyond the level that was first interconnected to the utility's distribution system unless the
utility provides written approval. The utility must respond in writing to an owner's notice
of intent to increase export capacity within 90 days of the date the notice is received and
may reject the request only upon determining that approving the request reduces safety or
the reliability of electric service.
new text end
new text begin
EFFECTIVE DATE.
new text end
new text begin
This section is effective the day following final enactment.
new text end
Sec. 2.
new text begin
[216B.1616] FEEDER LINE REPLACEMENT; STORAGE REQUIREMENT.
new text end
new text begin
(a) When replacing a feeder line with a feeder line with a higher capacity, a public utility
must install at the applicable distribution substation an energy storage system that has
sufficient capacity to ensure customer safety and grid reliability.
new text end
new text begin
(b) For purposes of this section:
new text end
new text begin
(1) "energy storage system" has the meaning given in section 216B.2422, subdivision
1, paragraph (f); and
new text end
new text begin
(2) "feeder line" means a powerline (i) that transfers power from a distribution system
substation to distribution transformers, and (ii) whose current flow is the same at the sending
and receiving ends of the powerline.
new text end
new text begin
EFFECTIVE DATE.
new text end
new text begin
This section is effective the day following final enactment.
new text end
Sec. 3.
new text begin
[216B.1617] ENERGY STORAGE; DISTRIBUTED ENERGY RESOURCE
TARIFF.
new text end
new text begin
(a) No later than September 15, 2026, the commission must initiate a docket designed
to result in a commission order requiring public utilities providing electric service to file a
distributed energy resource tariff with the commission, based on guidelines established in
the order, to compensate customer-owners of on-site distributed energy resources for the
discharge of generated or stored energy that is net input to the public utility. The tariff must
account for all value provided by distributed energy resources, including but not limited to
energy, capacity, ancillary services, demand response, temporal value, locational value, and
environmental value.
new text end
new text begin
(b) Within 90 days of the date the commission issues an order under this subdivision, a
public utility must file with the commission for commission approval, disapproval, or
modification a tariff that is consistent with the order.
new text end
new text begin
(c) For purposes of this section, "distributed energy resource" means a resource, located
at a public utility customer's site, with a generation capacity no greater than ten megawatts.
Distributed energy resource includes an energy storage system, as defined in section
216B.2422, subdivision 1.
new text end
new text begin
EFFECTIVE DATE.
new text end
new text begin
This section is effective the day following final enactment.
new text end
Sec. 4.
new text begin
[216B.1697] ENERGY STORAGE SYSTEMS; DEPLOYMENT TARGETS.
new text end
new text begin
Subdivision 1.
new text end
new text begin
Definition.
new text end
new text begin
For purposes of this section, "energy storage system" has the
meaning given in section 216B.2422, subdivision 1.
new text end
new text begin
Subd. 2.
new text end
new text begin
Deployment targets.
new text end
new text begin
(a) A utility required to file a resource plan under section
216B.2422 must deploy energy storage systems with a capacity determined by the
commission under paragraph (b). No later than December 31, 2036, the aggregate statewide
capacity of energy storage systems deployed by all utilities subject to this section must be
at least 3,000 megawatts.
new text end
new text begin
(b) No later than October 1, 2026, the commission must issue an order specifying the
amount of energy storage capacity required of each utility subject to this section to meet
the statewide capacity target and schedule in paragraph (a). The amount of energy storage
capacity required of an individual utility must be calculated by dividing the utility's total
electric retail sales to Minnesota customers in 2025 by the total electric retail sales to
Minnesota customers in 2025 of all utilities subject to this section, and multiplying the
resulting quotient by 3,000 megawatts. The commission may establish interim energy storage
capacity targets that utilities are required to meet before the 2036 target date.
new text end
new text begin
Subd. 3.
new text end
new text begin
Application.
new text end
new text begin
(a) A utility must file an application with the commission before
installing a proposed energy storage system. The application must contain:
new text end
new text begin
(1) the energy storage system's technical specifications, including but not limited to:
new text end
new text begin
(i) the maximum amount of electric output the energy storage system is capable of
providing;
new text end
new text begin
(ii) the length of time the energy storage system is capable of sustaining maximum
output;
new text end
new text begin
(iii) the location of the project within the utility's distribution system and a description
of the analysis conducted to determine the location;
new text end
new text begin
(iv) a description of the utility's electric system needs the proposed energy storage system
addresses;
new text end
new text begin
(v) a description of the services the energy storage system is expected to provide; and
new text end
new text begin
(vi) a description of the technology required to construct, operate, and maintain the
energy storage system, including a data or communication system necessary to operate the
energy storage system;
new text end
new text begin
(2) the estimated cost of the project, including:
new text end
new text begin
(i) capital costs;
new text end
new text begin
(ii) the estimated cost per unit of energy delivered by the energy storage system; and
new text end
new text begin
(iii) an evaluation of the energy storage system's cost-effectiveness;
new text end
new text begin
(3) the energy storage system's estimated benefits to the utility's electric system, including
but not limited to:
new text end
new text begin
(i) deferred investments in generation, transmission, or distribution capacity;
new text end
new text begin
(ii) reduced need for electricity during times of peak demand;
new text end
new text begin
(iii) improved reliability of the utility's transmission or distribution system; and
new text end
new text begin
(iv) improved integration of the utility's renewable energy resources;
new text end
new text begin
(4) a description indicating how the addition of an energy storage system complements
the utility's proposed actions described in the most recent integrated resource plan submitted
under section 216B.2422 to meet expected demand with the least expensive combination
of resources; and
new text end
new text begin
(5) any additional information required by the commission.
new text end
new text begin
(b) A utility must include in the application an evaluation of the potential to store energy
throughout the utility's electric system and must identify geographic areas in the utility's
service area where the deployment of energy storage systems has the greatest potential to
achieve the economic benefits identified in paragraph (a), clause (3).
new text end
new text begin
Subd. 4.
new text end
new text begin
Commission review.
new text end
new text begin
The commission must review each proposal submitted
under this section and may approve, reject, or modify the proposal. The commission must
approve a proposal the commission determines: (1) is in the public interest; and (2) reasonably
balances the value derived from the deployment of an energy storage system for ratepayers
and the utility's operations with the cost to procure, construct, operate, and maintain the
energy storage system.
new text end
new text begin
Subd. 5.
new text end
new text begin
Cost recovery.
new text end
new text begin
A public utility may recover from ratepayers all costs prudently
incurred by the public utility to deploy an energy storage system approved by the commission
under this section, net of any revenues generated by the operation of the energy storage
system.
new text end
new text begin
Subd. 6.
new text end
new text begin
Reporting; compliance.
new text end
new text begin
The commission must establish reporting procedures
for utilities that are sufficient in content and frequency to ensure the commission is informed
regarding compliance with this section.
new text end
new text begin
Subd. 7.
new text end
new text begin
Commission authority; orders.
new text end
new text begin
The commission may issue orders and conduct
proceedings necessary to implement and administer this section.
new text end
new text begin
EFFECTIVE DATE.
new text end
new text begin
This section is effective the day following final enactment.
new text end
Sec. 5.
Minnesota Statutes 2024, section 216B.2422, subdivision 7, is amended to read:
Subd. 7.
Energy storage systems assessment.
(a) Each
deleted text begin
public
deleted text end
utility required to file a
resource plan under subdivision 2 must
new text begin
incorporate in the utility's resource planning the
energy storage targets the utility is required to meet under section 216B.1697 and must
new text end
include in the filing an assessment of energy storage systems that analyzes how the
deployment of energy storage systems contributes to:
(1) meeting identified generation and capacity needs;
deleted text begin
and
deleted text end
new text begin
(2) the factors identified under section 216B.1697, subdivision 3, paragraph (a), clause
(3); and
new text end
deleted text begin
(2)
deleted text end
new text begin
(3)
new text end
evaluating ancillary services.
(b) The assessment must employ appropriate modeling methods to enable the analysis
required in paragraph (a).
Sec. 6.
new text begin
[216C.3771] ENERGY STORAGE INCENTIVE PROGRAM.
new text end
new text begin
(a) The public utility subject to section 116C.779 must develop and operate a program
that provides grants to customers to reduce the cost to purchase and install an on-site energy
storage system, as defined in section 216B.2422, subdivision 1, paragraph (f). No later than
November 1, 2026, the public utility subject to this section must file a plan with the
commissioner to operate the program. The public utility must not operate the program until
the plan is approved by the commissioner. A change to an operating program must be
approved by the commissioner.
new text end
new text begin
(b) To be eligible to receive a grant under this section, a customer's energy storage system
must:
new text end
new text begin
(1) have a capacity no greater than 50 kilowatt-hours; and
new text end
new text begin
(2) be located within the electric service area of the public utility subject to this section.
new text end
new text begin
(c) An owner of an energy storage system is eligible to receive a grant under this section
if:
new text end
new text begin
(1) a solar energy generating system is operating at the same site as the proposed energy
storage system; or
new text end
new text begin
(2) the owner has filed an application with the public utility subject to this section to
interconnect a solar energy generating system at the same site as the proposed energy storage
system.
new text end
new text begin
(d) The amount of a grant awarded under this section must be based on the number of
watt-hours that reflects the duration of the energy storage system at the system's rated
capacity, up to a maximum of $........
new text end
new text begin
(e) The commissioner must annually review and may adjust the amount of grants awarded
under this section, but the commissioner must not increase the amount above the amount
awarded in previous years unless the commissioner demonstrates in writing that an upward
adjustment is warranted due to market conditions.
new text end
new text begin
(f) A customer who receives a grant under this section is eligible to receive financial
assistance under programs operated by the state or the utility for the solar energy generating
system operating in conjunction with the energy storage system.
new text end
new text begin
(g) For purposes of this section, "solar energy generating system" means a set of devices
whose primary purpose is to produce electricity by means of any combination of collecting,
transferring, or converting solar-generated energy.
new text end
new text begin
EFFECTIVE DATE.
new text end
new text begin
This section is effective the day following final enactment.
new text end
Sec. 7.
new text begin
APPROPRIATION.
new text end
new text begin
Notwithstanding Minnesota Statutes, section 116C.779, subdivision 1, paragraph (j),
$....... in fiscal year 2027 is appropriated from the renewable development account established
in Minnesota Statutes, section 116C.779, to the commissioner of commerce to award grants
to install energy storage systems under Minnesota Statutes, section 216C.3771, and to pay
the reasonable costs incurred by the department to administer Minnesota Statutes, section
216C.3771. This appropriation is available until expended. The base for this appropriation
in fiscal year 2028 is $........
new text end