Segment of U.S. Highway 169 four-lane highway expansion appropriation and previous appropriation cancellation provision

Segment of U.S. Highway 169 four-lane highway expansion appropriation and previous appropriation cancellation provision

Budget
Passed Legislature

This bill passed both chambers and reached final enrollment, even if later executive action is not shown here.

Sponsor
Farnsworth, Green, Heintzeman
Last action
2026-02-26
Official status
Introduction and first reading
Effective date
Not listed

Plain English Breakdown

The plain English breakdown is still being put together. The official documents below are already here.

Bill History

  1. 2026-02-26 House

    Introduction and first reading

Official Summary Text

Segment of U.S. Highway 169 four-lane highway expansion appropriation and previous appropriation cancellation provision

Current Bill Text

Read the full stored bill text
A bill for an act

relating to transportation; canceling previous appropriation; appropriating money

for expansion of a segment of U.S. Highway 169 to a four-lane highway.

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:

Section 1.
new text begin
CANCELLATION; PASSENGER RAIL PROJECT.
new text end

new text begin

$117,000,000 of the appropriation in Laws 2023, chapter 68, article 1, section 2,

subdivision 2, paragraph (d), for capital improvements and betterments for the

Minneapolis-Duluth Northern Lights Express intercity passenger rail project is canceled on

the effective date of this section.

new text end

new text begin

EFFECTIVE DATE.

new text end

new text begin

This section is effective the day following final enactment.

new text end

Sec. 2.
new text begin
U.S. HIGHWAY 169 EXPANSION; APPROPRIATION.
new text end

new text begin

$117,000,000 in fiscal year 2026 is appropriated from the general fund to the

commissioner of transportation for predesign; design; engineering; environmental analysis

and remediation; property acquisition, including easements; and construction of an expansion

of marked U.S. Highway 169 from a two-lane to a four-lane divided highway between

Taconite and Pengilly. This is a onetime appropriation and is available until June 30, 2029.

new text end

new text begin

EFFECTIVE DATE.

new text end

new text begin

This section is effective the day following final enactment.

new text end