require an alternate approval process for an operation that extracts materials by the use of explosives.

require an alternate approval process for an operation that extracts materials by the use of explosives.

Energy
Active

The official status still shows this bill as active or still awaiting another formal step.

Sponsor
Carley
Last action
2026-02-17
Official status
Do Pass
Effective date
Not listed

Plain English Breakdown

Using official source text because the generated explanation was unavailable or could not be confirmed against the official bill text.

require an alternate approval process for an operation that extracts materials by the use of explosives.

require an alternate approval process for an operation that extracts materials by the use of explosives.

What This Bill Does

  • require an alternate approval process for an operation that extracts materials by the use of explosives.
  • Official keyword topics: Administrative Procedure Licensure Mining, Oil and Gas Official sponsor note: Representatives <a rel="noopener" href="https://sdlegislature.gov/Legislators/Profile/4772/Detail">Jorgenson</a> (prime) and <a rel="noopener" href="https://sdlegislature.gov/Legislators/Profile/4824/Detail">Uhre-Balk</a> and Senator <a rel="noopener" href="https://sdlegislature.gov/Legislators/Profile/4740/Detail">Carley</a> (prime)

Limits and Unknowns

  • This entry is temporarily using official source text because the generated explanation could not be confirmed against the official bill text during the last sync.

Bill History

  1. 2026-02-17 House of Representatives

    Do Pass

  2. 2026-02-12 House Agriculture and Natural Resources

    Do Pass

  3. 2026-02-12 House Agriculture and Natural Resources

    Scheduled for hearing

  4. 2026-02-04 House of Representatives

    First read in House and referred to House Agriculture and Natural Resources

Official Summary Text

require an alternate approval process for an operation that extracts materials by the use of explosives.
Official keyword topics:
Administrative Procedure
Licensure
Mining, Oil and Gas
Official sponsor note: Representatives <a rel="noopener" href="https://sdlegislature.gov/Legislators/Profile/4772/Detail">Jorgenson</a> (prime) and <a rel="noopener" href="https://sdlegislature.gov/Legislators/Profile/4824/Detail">Uhre-Balk</a> and Senator <a rel="noopener" href="https://sdlegislature.gov/Legislators/Profile/4740/Detail">Carley</a> (prime)

Current Bill Text

Read the full stored bill text
26.466.12 101st Legislative Session 1287

2026 South Dakota Legislature
House Bill 1287

Introduced by: Representative Jorgenson

Underscores indicate new language.
Overstrikes indicate deleted language.
An Act to require an alternate approval process for an operation that extracts 1
materials by the use of explosives. 2
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF SOUTH DAKOTA: 3
Section 1. That § 45-6-65 be AMENDED: 4
45-6-65. An operator shall obtain a license to mine any of the following materials, 5
provided they are extracted by means that do not include the use of explosives: 6
(1) Sand; 7
(2) Gravel; 8
(3) Rock to be crushed and used in construction; 9
(4) Pegmatite minerals; 10
(5) Limestone; and 11
(6) Iron ore, gypsum, shale, pozzolan, and other materials used in the process of 12
making cement or lime. 13
The operator shall comply with the requirements of §§ 45-6-68, 45-6-69, 45-6-71, 14
and 45-6-72, for each site to be mined. Failure to comply with these requirements for 15
each site mined constitutes mining without a license. 16
The fee for the license is one hundred dollars annually, for each mine site 17
authorized under the license. The department shall forward any fees collected under this 18
section to the state treasurer for deposit in the environment and natural resources fee 19
fund established in § 1-41-23. 20
Section 2. That a NEW SECTION be added to chapter 45-6: 21
Any operator that uses explosives in its mining operation must report its use of 22
explosives to the department within ninety days of the date this Act becomes effective. 23
Use of explosives by any contractor, subcontractor, or agent of the operator is 24
considered use by the operator for purposes of this section. 25
26.466.12 2 1287
Underscores indicate new language.
Overstrikes indicate deleted language.
In order to mine any of the materials listed in this section with the use of 1
explosives, on or after July 1, 2026, the operator of any new or expanding mining 2
operation shall obtain a permit under chapter 45-6B. Any operator that fails to obtain the 3
required permit is subject to the penalties provided in chapter 45-6B. 4
If, for good cause, an operator is unable to obtain a permit by July 1, 2026, the 5
operator may request that the department grant a six -month extension of the license 6
while the operator is applying for a permit. 7
Operators who mine with the use of explosives under permits granted under 8
chapter 45-6 must obtain permits under chapter 45-6B. The department shall implement 9
a schedule for operators to transition to permits under chapter 45-6B starting July 1, 10
2026. The schedule may allow twenty percent of the operators in each of the consecutive 11
five years from the date this Act becomes effective to transition to the new permits. 12
Section 3. That § 45-6B-3 be AMENDED: 13
45-6B-3. Terms used in this chapter mean: 14
(1) "Abandoned mined lands," lands that were mined for noncoal minerals and 15
materials and for which there is no continuing reclamation responsibility or 16
responsibility for other remedial action under state or federal laws; 17
(2) "Affected land," land from which overburden is to be or has been removed and land 18
upon which overburden, waste rock, mine spoil, or mill tailings is to be or has been 19
deposited; land which is disturbed by the building of access roads, railroad loops, 20
warehouses, storage areas, or other support facilities for the purpose of mining or 21
milling; and land affected by surface subsidence, unstable slopes, and other 22
surface effects caused by underground mine workings; 23
(3) "Aquifer," a water -bearing bed or stratum of permeable rock, sand, or gravel 24
capable of yielding usable quantities of water to wells or springs; 25
(4) "Black Hills," Lawrence County south of Interstate Highway 90, Meade County west 26
and south of Interstate Highway 90 and Pennington and Custer Counties west of 27
South Dakota Highway 79; 28
(5) "Board," the Board of Minerals and Environment; 29
(6) "Department," the Department of Environment Agriculture and Natural Resources; 30
(7) "Development," the work performed in relation to a deposit, following the 31
exploration required to prove minerals are in existence in commercial quantities 32
but before production activities, aimed at preparing the site for mining, defining 33
26.466.12 3 1287
Underscores indicate new language.
Overstrikes indicate deleted language.
further the ore deposit by drilling or other means, conducting pilot plant operations, 1
constructing roads or ancillary facilities; 2
(8) "Life of the mine permit," a permit to conduct a mining operation which is in effect 3
if: 4
(a) An operator continues to engage in the extraction of minerals and complies 5
with the provisions of this chapter; 6
(b) Mineral reserves are shown by the operator to remain in the mining 7
operation and the operator plans to, or does, temporarily cease production 8
for one hundred eighty days or more if the operator files a notice thereof 9
with the board stating the reasons for nonproduction, a plan for ceasing 10
production for one hundred eighty days or more if the operator files a notice 11
thereof with the board stating the reasons for nonproduction, a plan for the 12
resumption of production, and the measures taken to comply with 13
reclamation and other necessary activities as established by the board to 14
maintain the mine in a nonproducing state. The requirement of a notice of 15
temporary cessation does not apply to operators who resume operating 16
within one year and have included, in their permit applications, a statement 17
following the exploration required to prove minerals are in existence in that 18
the affected lands are to be used for less than one hundred eighty days per 19
year; 20
(c) Production is resumed within five years of the date production ended, or 21
the operator files a report requesting an extension of the period of 22
temporary cessation of production with the board stating the reasons for 23
the continuation of nonproduction and those factors necessary to, and the 24
operator's plans for, resumption of production. A temporary cessation of 25
production may not be continued for more than ten years without 26
terminating the operation and fully complying with the reclamation 27
requirements of this chapter. 28
A life of the mine permit includes that period of time after cessation of production 29
necessary to complete reclamation of affected lands, until the board 30
releases, in writing, the operator from further reclamation obligations 31
regarding the affected land, declares the mining operation terminated, and 32
releases the surety thereon; 33
(9) "Milling," the beneficiation of a mined material from its natural occurrence in ore; 34
26.466.12 4 1287
Underscores indicate new language.
Overstrikes indicate deleted language.
(10) "Mineral," a substance with economic value, whether organic or inorganic, that can 1
be extracted from the earth, other than the following: water, oil, gas, sand, gravel, 2
or rock to be crushed and used in construction, pegmatite minerals, or limestone, 3
but excluding the following materials if extracted by methods that do not include 4
the use of explosives: 5
(a) Water; 6
(b) Oil; 7
(c) Gas; 8
(d) Sand; 9
(e) Gravel; 10
(f) Rock to be crushed and used in construction; 11
(g) Pegmatite minerals; and 12
(h) Limestone, sand, gypsum, shale, or iron ore used in the process of making 13
cement; 14
(11) "Mining operation," the development or extraction of a mineral from its natural 15
occurrence on affected land. The term includes surface mining and surface 16
operation, in situ mining, the reprocessing of tailings piles, the disposal of refuse 17
from underground mining, milling and processing located on the land described in 18
the application for a mining permit, and stand-alone milling and processing facilities 19
utilizing chemical or biological leaching agents , and the extraction of any material 20
by the use of explosives. The term does not include extraction of sand, gravel, or 21
rock to be crushed and used in construction, exploration activities, bulk sampling, 22
the exploration and extraction of natural petroleum in a liquid or gaseous state by 23
means of wells or pipe, borrow excavation for embankments, or the extraction of 24
geothermal resources; 25
(12) "Operator," any person, firm, partnership, limited liability company, association, or 26
corporation or any department, division or agency of federal, state, county, or 27
municipal government engaged in or controlling a mining operation; 28
(13) "Overburden," all of the earth and other materials which are disturbed or removed, 29
in the original state, or as it exists after removal from its natural state in the 30
process of surface mining; 31
(14) "Reclamation," the employment during and after a mining operation of procedures 32
reasonably designed to minimize as much as practicable the disruption from the 33
mining operation and to provide for the rehabilitation of affected land through the 34
26.466.12 5 1287
Underscores indicate new language.
Overstrikes indicate deleted language.
rehabilitation of plant cover, soil stability, water resources, or other measures 1
appropriate to the subsequent beneficial use of such mined and reclaimed lands; 2
(15) "Surface mining," the mining of minerals by removing the overburden lying above 3
such deposits and mining directly from the deposits thereby exposed. The term 4
includes mining directly from such deposits where there is no overburden and such 5
practices as open cut mining, open pit mining, strip mining, placer mining, 6
quarrying, and dredging; 7
(16) "Surface mining disturbed land," land from which overburden has been removed, 8
land upon which overburden, waste rock, mine spoil, or mill tailings have been 9
deposited, land mined which has no overburden, heap leach pads, and process 10
ponds; 11
(17) "Tailings," the discharged valueless product of a beneficiation process. 12