Read the full stored bill text
89(R) HB 3712 - House Committee Report version - Bill Text
89R26827 SCR-F
By: Guillen
H.B. No. 3712
Substitute the following for H.B. No. 3712:
By: Button
C.S.H.B. No. 3712
A BILL TO BE ENTITLED
AN ACT
relating to funds reserved or retained for certain construction
materials.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
SECTION 1. Section 2252.032, Government Code, is amended by
amending Subsection (e) and adding Subsection (e-1) to read as
follows:
(e) A governmental entity may not withhold retainage:
(1) after completion of the work required to be
performed under the contract by the prime contractor, including
during the warranty period; [
or
]
(2) for the purpose of requiring the prime contractor,
after completion of the work required to be performed under the
contract, to perform work on manufactured goods or systems that
were:
(A) specified by the designer of record; and
(B) properly installed by the contractor
; or
(3) for specially fabricated material that:
(A)
has been delivered by a subcontractor and
accepted by the governmental entity and the prime contractor at the
site or off-site; and
(B) is covered by a manufacturer's warranty:
(i)
under a contract with the governmental
entity; or
(ii)
assigned to the governmental entity by
the prime contractor
.
(e-1)
Subsection (e)(3) does not apply to funds for the
value of the installation of the specially fabricated material by a
subcontractor.
SECTION 2. Section 53.101, Property Code, is amended by
amending Subsection (a) and adding Subsections (a-1) and (a-2) to
read as follows:
(a)
Except as provided by Subsection (a-1), during
[
During
]
the progress of work under an original contract for which a
mechanic's lien may be claimed and for 30 days after the work under
the contract is completed, the owner shall reserve:
(1) 10 percent of the contract price of the work to the
owner; or
(2) 10 percent of the value of the work, measured by
the proportion that the work done bears to the work to be done,
using the contract price or, if there is no contract price, using
the reasonable value of the completed work.
(a-1)
An owner is not required to reserve under this section
and may not retain under a contract funds for specially fabricated
material that:
(1)
has been delivered by a subcontractor and accepted
by the owner or a contractor or subcontractor at the site or
off-site; and
(2)
is covered by a manufacturer's warranty under a
contract with the owner or a contractor or subcontractor.
(a-2)
Subsection (a-1) does not apply to funds for the value
of the installation of specially fabricated material by a
subcontractor.
SECTION 3. The changes in law made by this Act apply only to
an original contract that is entered into on or after the effective
date of this Act. An original contract entered into before the
effective date of this Act is governed by the law as it existed
immediately before the effective date of this Act, and the former
law is continued in effect for that purpose.
SECTION 4. This Act takes effect September 1, 2025.