Read the full stored bill text
89(R) HB 3970 - Engrossed version - Bill Text
By: Darby
H.B. No. 3970
A BILL TO BE ENTITLED
AN ACT
relating to the interconnection and operation of large loads.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
SECTION 1. Subchapter D, Chapter 39, Utilities Code, is
amended by adding Section 39.169 to read as follows:
Sec.
39.169.
LARGE LOAD INTERCONNECTION. (a) In this
section:
(1)
"Behind-the-meter generation" means a generation
facility on the retail customer's side of the meter capable of
serving the full load requirement of the retail customer.
(2)
"Flexible load" means a large load operated by a
retail customer who is obligated by contract or agreement in the
ERCOT market to reduce the load or power the load exclusively with
back-up generation:
(A)
at the direction of the independent
organization certified under Section 39.151 for the ERCOT power
region; or
(B)
as required to protect the integrity of the
ERCOT grid.
(b)
The commission by rule shall establish a program to
provide an expedited process for the interconnection of large
loads.
The program must require the interconnecting electric
cooperative, municipally owned utility, or transmission and
distribution utility and the independent organization certified
under Section 39.151 for the ERCOT power region to give priority in
the interconnection queue to a large load for which a retail
customer has received approval for expedited processing over any
other large loads that have not entered into a contractual
agreement with the electric utility, electric cooperative, or
municipally owned utility regarding the provision of electric
service.
If applicable, the generation interconnection
application for a generation facility associated with the large
load must be processed in parallel with the large load.
(c)
The program must require a large load to qualify for
expedited interconnection processing by bringing in-service, not
later than the 180th day after the interconnection date,
behind-the-meter generation that is:
(1)
registered with the independent organization
certified under Section 39.151 for the ERCOT power region; and
(2)
capable of serving the full load requirement of
the customer.
(d)
As an alternative to the requirements of Subsection (c),
a large load may qualify for expedited interconnection processing,
if the load is a facility with an aggregated peak demand at a single
site of more than 75 megawatts, by:
(1)
providing to the interconnecting electric
cooperative, municipally owned utility, or transmission and
distribution utility all data regarding, and posting all required
financial security for, the load; and
(2)
being subject to a binding commitment with the
independent organization certified under Section 39.151 for the
ERCOT power region to establish the load as a flexible load for a
minimum period established by the commission, which must be at
least 10 years.
(e)
A large load that qualifies for expedited
interconnection processing may choose:
(1)
if authorized by the independent organization
certified under Section 39.151 for the ERCOT power region and the
relevant electric cooperative, municipally owned utility, or
transmission and distribution utility, to contract with a vendor
approved by the relevant electric cooperative, municipally owned
utility, or transmission and distribution utility or by the
independent organization to perform all studies required by the
relevant electric cooperative, municipally owned utility, or
transmission and distribution utility before the approval of the
interconnection application; and
(2)
if authorized by the relevant electric
cooperative, municipally owned utility, or transmission and
distribution utility:
(A)
to procure equipment required for the
interconnection in accordance with technical specifications
provided by the relevant electric cooperative, municipally owned
utility, or transmission and distribution utility; and
(B)
to construct interconnection facilities in
accordance with technical and other requirements of the relevant
electric cooperative, municipally owned utility, or transmission
and distribution utility.
(f)
The program may provide that studies required by an
electric cooperative, municipally owned utility, or transmission
and distribution utility before the approval of an interconnection
application for a flexible load may evaluate the load as non-firm.
(g)
Demand reductions from flexible loads that receive
expedited processing and are removed from the system through the
utilization of behind-the-meter generation during an energy
emergency alert must be counted toward any obligation of the
electric cooperative, municipally owned utility, or transmission
and distribution utility to shed load.
(h)
The independent organization certified under Section
39.151 for the ERCOT power region shall consider action taken under
this section as a reliability deployment when calculating any price
adjustments for reliability deployments.
(i)
The commission shall establish financial penalties the
commission may impose on an owner or operator of a large load that
is approved for expedited interconnection processing but fails to
reduce the load or power the load with back-up generation as
directed by the independent organization certified under Section
39.151 for the ERCOT power region.
SECTION 2. This Act takes effect September 1, 2025.