SENATE FILE NO. SF0105
Nuclear power generation and storage-amendments-2.
Sponsored by: Senator(s) Anderson, Dockstader, Gierau, Nethercott and Wasserburger
A BILL
for
AN ACT relating to environmental quality; amending and repealing requirements and conditions for legislative approval of the siting of high-level radioactive waste storage facilities as specified; amending provisions for small modular nuclear reactors to apply to advanced nuclear reactors; specifying duties and requirements for advanced nuclear reactors; defining terms; amending definitions, requirements and exemptions related to cost recovery for specified electric generation facilities; amending exemptions for the nuclear electricity production tax; making conforming amendments; repealing nuclear reactor requirements as specified; requiring rulemaking; and providing for an effective date.
Be It Enacted by the Legislature of the State of Wyoming:
Section 1
.
W.S. 35
‑
11
‑
1506(e)(i) and by creating new paragraphs (vi) and (vii), 35
‑
11
‑
2101(b),
(d)(iii)(intro), (e) and by creating new subsections (f) and (g), 37
‑
2
‑
133 by creating a new subsection (j), 37
‑
2
‑
134(a)(ii)
, 37
‑
3
‑
117 by creating a new subsection (f) and 39
‑
23
‑
105(c) are amended to read:
35
‑
11
‑
1506.
Legislative approval of the siting of high
‑
level radioactive waste storage facilities; conditions.
(e)
The legislature hereby authorizes the siting of temporary high
‑
level radioactive waste storage facilities within this state subject to the following:
(i)
A facility
shall only be
is
authorized if
:
(A)
I
t is operated on the site of and to store the
high
‑
level radioactive
waste
or spent nuclear fuel
produced by a nuclear power generation facility operating within the state;
(B)
The facility has received a license to construct and operate from the United States nuclear regulatory commission;
(C)
The report required under paragraph (vi) of this subsection has been submitted; and
(D)
The operator of the facility is in compliance with paragraph (vii) of this subsection.
(vi)
Not later than thirty (30) days before construction of a nuclear electric generation facility commences, the operator of the facility shall submit a report to the department that includes:
(A)
The number of jobs that will be created in the planning, permitting, licensing, site analysis and preparation, purchasing, construction, transportation, operation and decommissioning of the facility;
(B)
Local and state taxes that are estimated to be generated by all aspects of the
construction, operation and decommissioning of the facility;
(C)
All benefits and impacts that will accrue to the state and the local community where the facility will be located, including benefits from job training, education, communication systems, monitoring and security systems.
(vii)
The operator of each facility shall send to the department copies of all publicly available reports, notifications and violations sent to or from the United States nuclear regulatory commission or the operator of the facility not later than fifteen (15) days after the operator sends or receives the report.
ARTICLE 21
ADVANCED NUCLEAR REACTORS
35
‑
11
‑
2101.
Advanced nuclear reactors; requirements.
(b)
Any person operating
a small modular
an advanced
nuclear reactor in the state of Wyoming
in accordance with
this section
shall not store spent nuclear fuel or high
‑
level radioactive waste from the
small modular
advanced
nuclear reactor on the site of the
small modular
advanced
nuclear reactor without first meeting all of the requirements of the United States Nuclear Regulatory Commission.
(d)
As used in this section:
(iii)
"
Small modular
Advanced
nuclear reactor" means a nuclear reactor
, including any necessary ancillary facilities or structures,
that
:
is an improvement over nuclear reactors placed in service before January 1, 2021 and has a license issued by the United States nuclear regulatory commission;
(e)
The provisions of the Industrial Development Information and Siting Act, W.S. 35
‑
12
‑
101 through 35
‑
12
‑
119, shall
:
(i)
A
pply
only
to the extent that those provisions do not interfere with, contradict or duplicate
any requirements of the United States Nuclear Regulatory Commission
;
(ii)
Not apply to any adjacent or ancillary facility that is necessary for the production of electricity at the advanced nuclear reactor
.
(f)
Not less than thirty (30) days before construction of an advanced nuclear reactor commences and if no report is required to be submitted under W.S. 35
‑
11
‑
1506(e)(vi), the operator of the advanced nuclear reactor shall submit a report to the department that includes:
(i)
The number of jobs that will be created in the planning, licensing, site analysis, preparation, purchasing, construction, transportation, operation and decommissioning of the advanced nuclear reactor;
(ii)
Local and state taxes that are estimated to be generated by all aspects of the construction, operation and decommissioning of the advanced nuclear reactor;
(iii)
All benefits and impacts that will accrue to the state and local community where the advanced nuclear reactor will be located, including benefits from job training, education, communications systems, monitoring and security systems.
(g)
The operator of each advanced nuclear reactor shall send to the department copies of all publicly available reports, notifications and violations sent to or from the United States nuclear regulatory commission or the operator of the advanced nuclear reactor not later than fifteen (15) days after the operator sends or receives the report.
37
‑
2
‑
133.
Exemption for purchase of coal
‑
fired generation facilities that would otherwise have been retired; public utility purchase requirements; conditions for exemption.
(j)
The requirements of this section shall not apply to an advanced nuclear reactor that is operated in the state of Wyoming in accordance with W.S. 35
‑
11
‑
2101.
37
‑
2
‑
134.
Electric generation facility closures; presumption; commission review.
(a)
As used in this section:
(ii)
"Retirement" or "retired" means the closure of or the complete and permanent cessation of operations at an electric generation facility. "Retirement" or "retired" shall not include
:
(A)
An electric generation facility that is closed in order to facilitate a conversion to an advanced nuclear reactor that is operated in accordance with W.S. 35
‑
11
‑
2101;
(B)
A
ny closure mandated by federal law
;
or
(C)
A
ny closure resulting from federal environmental requirements to where it is no longer cost effective for the facility to continue operating
.
;
37
‑
3
‑
117.
Limitation for recovery of costs associated with electric generation built to replace retiring coal
‑
fired generation facility; exemption.
(f)
The requirements of this section shall not apply to an advanced nuclear reactor that is operated in the state of Wyoming in accordance with W.S. 35
‑
11
‑
2101.
39
‑
23
‑
105.
Exemptions.
(c)
No tax shall be imposed on any
test or demonstration small modular
advanced
nuclear reactor
licensed and
operated in accordance with W.S.
35
‑
11
‑
2101(b) and 35
‑
11
‑
431 through 35
‑
11
‑
433
35
‑
11
‑
2101
.
Section 2.
W.S. 35
‑
11
‑
1506(e)(ii) through (v) and 35
‑
11
‑
2101(a) and (d)(iii)(A) through (C) are repealed.
Section 3
.
The department of environmental quality and environmental quality council shall promulgate all rules necessary to implement the provisions of this act.
Section 4.
This act is effective
immediately upon completion of all acts necessary for a bill to become law as provided by Article 4, Section 8 of the Wyoming Constitution.
(END)