Back to Wyoming
Wyoming2025Enacted

SF0154

Industrial and Renewable Energy Project Deadlines

Last scannedAug 25, 2026, 2:25 AM

In one sentence

This law changes deadlines for reviewing applications related to industrial, wind, and solar projects.

What it does

  • Extends the deadline for counties to hold a hearing on wind or solar project applications from sixty days to ninety days after determining completeness.
  • Increases the time for counties to make decisions on permit applications for wind or solar projects from forty-five days to sixty days after completing the hearing.
  • Gives industrial project applicants more time to provide additional information before review, extending it from thirty days to forty-five days.
  • Lengthens the deadline for a hearing on industrial siting permit applications from ninety days to one hundred twenty days after receiving an application.

Who it affects

  • Counties and the Industrial Siting Council responsible for reviewing project applications
  • Applicants seeking permits for industrial, wind, and solar projects

Limits and unknowns

  • This act only affects applications submitted on and after January 1, 2026.
  • It does not specify what happens if an application is incomplete beyond the new deadlines.

Plain language

Terms to know

Industrial siting permit
A type of permit required for certain large-scale industrial projects.
Application deadline
The date by which a task or action must be completed according to the law.

Official record

Sources

Validated

Official summary

Bill Summary - 25LSO-0379 Bill No.: SF0154 Effective: 1/1/2026 LSO No.: 25LSO-0379 Enrolled Act No.: SEA No. 0046 Chapter No.: 78 Prime Sponsor: Boner Catch Title: Industrial, wind and solar projects-hearing deadline. Has Report: No Subject: Amending deadlines for reviewing industrial, wind, and solar projects. Summary/Major Elements: Current law establishes a process by which counties and the Industrial Siting Council review applications for permits for siting industrial projects, wind projects, and solar projects. The law specifies deadlines by which the governmental entities must complete various steps of the application and review process. This act amends those deadlines. For counties, the deadline by which the county must hold a hearing on the application for a wind or solar facility is extended from sixty (60) days to ninety (90) days after determining that the application is complete. The deadline for counties to render a decision on a permit application is extended from forty‑five (45) days to sixty (60) days after completion of the hearing. For industrial projects under the jurisdiction of the Industrial Siting Council, the deadline for an applicant to provide additional information before review is extended from thirty (30) days to forty‑five (45) days. For a hearing on industrial projects, the deadline is extended from ninety (90) days to one hundred twenty (120) days after receiving a permit application. The act applies to all permit applications submitted on and after January 1, 2026. The above summary is not an official publication of the Wyoming Legislature and is not an official statement of legislative intent. While the Legislative Service Office endeavored to provide accurate information in this summary, it should not be relied upon as a comprehensive abstract of the bill.

Public statements

Why lawmakers voted

Last checked Aug 5, 8:07 AM

Brian Boner

R · S02

Voted Yes

Why they voted this way

The lawmaker supports the bill because it balances industry interests with those of the Industrial Siting Council by splitting the difference on cure periods and deadlines.

Public statementFloor statement at 8:15 Watch the statement

If a lawmaker is not listed, we couldn't find a published reason.

Wyoming roll calls

Recorded votes

5 roll calls

S Concur:Passed 30-1-0-0-02025-02-26 · Senate30 yes 1 no
H 3rd Reading:Passed 36-23-3-0-02025-02-26 · House36 yes 23 no
H09 - Minerals:Recommend Amend and Do Pass 8-0-1-0-02025-02-21 · House8 yes 0 no
S 3rd Reading:Passed 26-4-1-0-02025-02-10 · Senate26 yes 4 no
S09 - Minerals:Recommend Do Pass 5-0-0-0-02025-02-05 · Senate5 yes 0 no

Official activity

Bill history

  1. Assigned Chapter Number 78LSO
  2. Governor Signed SEA No. 0046 Governor
  3. H Speaker Signed SEA No. 0046House
  4. S President Signed SEA No. 0046Senate
  5. Assigned Number SEA No. 0046LSO
  6. S Concur:Passed 30-1-0-0-0Senate
  7. S Received for ConcurrenceSenate
  8. H 3rd Reading:Passed 36-23-3-0-0House
  9. H 2nd Reading:PassedHouse
  10. H COW:PassedHouse
  11. H Placed on General FileHouse
  12. H09 - Minerals:Recommend Amend and Do Pass 8-0-1-0-0House
  13. H Introduced and Referred to H09 - MineralsHouse
  14. H Received for IntroductionHouse
  15. S 3rd Reading:Passed 26-4-1-0-0Senate
  16. S 2nd Reading:PassedSenate
  17. S COW:PassedSenate
  18. S Placed on General FileSenate
  19. S09 - Minerals:Recommend Do Pass 5-0-0-0-0Senate
  20. S Introduced and Referred to S09 - MineralsSenate

Changes

Amendments

1 stored

SF0154HS001

The amendment changes the deadline for the director of the department of environmental quality to hold a hearing on industrial siting permit applications from sixty days to forty-five days.