Back to Wyoming
Wyoming2026Enacted

SF0102

Wyoming Energy Transmission Study

Last scannedAug 25, 2026, 2:25 AM

In one sentence

This law requires the Wyoming Energy Authority to study how energy is transmitted across Wyoming and report their findings.

What it does

  • Requires the Wyoming Energy Authority to complete a two-phase transmission planning study about Wyoming's current system and future needs.
  • Phase one analyzes three potential growth scenarios for electricity demand, including advanced technologies and storage solutions.
  • Phase two creates a summary of public utilities' involvement in regional energy networks.
  • Establishes an advisory working group with representatives from various utility companies and government agencies to provide input on the study.
  • Requires reports to be given to specific committees by November 1, 2027 (phase one) and September 1, 2028 (phase two).

Who it affects

  • The Wyoming Energy Authority
  • Public utilities in Wyoming
  • Government agencies like the Public Service Commission and Office of Consumer Advocate

Limits and unknowns

  • The bill does not specify funding for the study.
  • It is unclear what specific recommendations will come from the advisory working group.

Plain language

Terms to know

Transmission planning study
A detailed examination of how electricity is moved from power plants to consumers, including future needs.
Load growth scenarios
Different predictions about how much more or less electricity might be needed in the future.

Official record

Sources

Validated

Official summary

Bill Summary - 26LSO-0322 Bill No.: SF0102 Effective: Immediately LSO No.: 26LSO-0322 Enrolled Act No.: SEA No. 0050 Chapter No.: 58 Prime Sponsor: Boner Catch Title: Wyoming energy transmission study. Has Report: Yes Subject: Requiring the Energy Authority to study energy transmission in Wyoming. Summary/Major Elements: This act requires the Wyoming Energy Authority to complete a transmission planning study concerning Wyoming's transmission system and the potential growth of that system. The act requires the Energy Authority to complete the study in two (2) phases. Phase one (1) must analyze the impacts of three potential load-growth scenarios on Wyoming's current system, including a model of Wyoming's transmission needs and the consideration of advanced transmission technologies and electricity storage to meet the need for expanded transmission. Phase two (2) requires the Energy Authority to develop a qualitative summary of Wyoming public utilities' participation, if any, in regional transmission organizations. The act requires the Wyoming Energy Authority to report twice to the Joint Corporations, Elections, and Political Subdivisions Interim Committee and the Joint Minerals, Business, and Economic Development Interim Committee on the results of each phase of the study. The act requires the Energy Authority to establish an advisory working group to provide input on the required study. The working group must be comprised of, at a minimum, the Public Service Commission, the Office of Consumer Advocate, and representatives from investor-owned public utilities, municipal utilities, and rural electric cooperatives. Comments: This act is effective immediately. This act requires two (2) reports from the Wyoming Energy Authority to the Joint Corporations, Elections, and Political Subdivisions Interim Committee and the Joint Minerals, Business, and Economic Development Interim Committee. The first report (for phase one (1) of the study) is due by November 1, 2027; the second report (for phase two) is due by September 1, 2028. The above summary is not an official publication of the Wyoming Legislature and is not an official statement of legislative intent. While the Legislative Service Office endeavored to provide accurate information in this summary, it should not be relied upon as a comprehensive abstract of the bill.

Public statements

Why lawmakers voted

Last checked Aug 7, 12:48 PM

Brian Boner

R · S02

Voted Yes

Why they voted this way

The sponsor argues the bill is necessary to gather information and provide legislative direction on future energy transmission policy decisions as regional organizations expand.

Public statementFloor statement at 42:56 Watch the statement

If a lawmaker is not listed, we couldn't find a published reason.

Wyoming roll calls

Recorded votes

5 roll calls

H 3rd Reading:Passed 58-2-2-0-02026-03-04 · House58 yes 2 no
H09 - Minerals:Recommend Do Pass 9-0-0-0-02026-02-27 · House9 yes 0 no
S 3rd Reading:Passed 31-0-0-0-02026-02-24 · Senate31 yes 0 no
S07 - Corporations:Recommend Amend and Do Pass 5-0-0-0-02026-02-18 · Senate5 yes 0 no
S Introduced and Referred to S07 - Corporations 29-2-0-0-02026-02-12 · Senate29 yes 2 no

Official activity

Bill history

  1. Assigned Chapter Number 58LSO
  2. Governor Signed SEA No. 0050 Governor
  3. H Speaker Signed SEA No. 0050House
  4. S President Signed SEA No. 0050Senate
  5. Assigned Number SEA No. 0050LSO
  6. H 3rd Reading:Passed 58-2-2-0-0House
  7. H 2nd Reading:PassedHouse
  8. H COW:PassedHouse
  9. H Placed on General FileHouse
  10. H09 - Minerals:Recommend Do Pass 9-0-0-0-0House
  11. H Introduced and Referred to H09 - MineralsHouse
  12. H Received for IntroductionHouse
  13. S 3rd Reading:Passed 31-0-0-0-0Senate
  14. S 2nd Reading:PassedSenate
  15. S COW:PassedSenate
  16. S Placed on General FileSenate
  17. S07 - Corporations:Recommend Amend and Do Pass 5-0-0-0-0Senate
  18. S Introduced and Referred to S07 - Corporations 29-2-0-0-0Senate
  19. S Received for IntroductionSenate
  20. Bill Number AssignedLSO

Changes

Amendments

1 stored

SF0102SS001

Adopted Standing Committee by Senate Corporations, Elections & Political Subdivisions Committee